Site Visit Minutes FINAL (1).pdf

PDF 136 KB Posted

Attached to
Construct 145th Security Forces Building
Solicitation number
W50S87-26-B-A002
Issued by

About this file

This is a Memorandum for Record documenting the minutes from a pre-bid conference and site visit for solicitation W50S87-26-B-A002, a construction project for the 145th Airlift Wing. The conference was held on June 2, 2026, at 9:00 AM EST and lasted one hour. Government representatives included MSGT Sarah Marshall (Contract Specialist) and Mr. Hansen Pedersen (Base Civil Engineer/COR). The contract period is 360 calendar days, including all work, cleanup, and punch list activities, with anticipated award in mid-September 2026. Following receipt and approval of bonds, the Government will hold a pre-construction conference and issue a Notice to Proceed (NTP).

All interested offerors must be registered in SAM (System for Award Management) at https://www.sam.gov/portal/public/SAM/. Written technical questions must be submitted via email to scott.thomas.53@us.af.mil and sarah.marshall.6@us.af.mil; contractors are prohibited from contacting design or government engineers directly. All contractor questions, answers, amendments, and correspondence will be posted to SAM.gov. The memorandum clarifies that an incorrect answer was provided during the conference regarding award determination. The correct answer is governed by DFARS 252.236-7007 (Additive or Deductive Items), which specifies that the low offeror is determined by offering the lowest aggregate amount for the base bid plus additive or deductive items (in priority order) that provide the most features within available Government funds. The Contracting Officer may award any combination of items if it is in the Government's best interest, funds are available, and the low offeror's price is less than any other responsive, responsible offeror.

View the file

Other files

File Type Posted
Bid Opening Sign-in Sheet.pdf PDF
Construct Security Forces Bldg Abstract.pdf PDF
Solicitation Amendment W50S8726BA0020006 SF 30.pdf PDF
Attachment 15 - NC ANG SF_Addendum03_07-30-2026.pdf PDF
Solicitation Amendment W50S8726BA0020005 SF 30.pdf PDF
Attachment 14 - Questions and Answers - Final.pdf PDF
Attachment 13 - NC ANG SF_Addendum02_07-10-2026.pdf PDF
Solicitation Amendment W50S8726BA0020003 SF 30.pdf PDF
Attachment 14 - Questions and Answers - Final.pdf PDF
Solicitation Amendment W50S8726BA0020004 SF 30.pdf PDF
Attachment 12 - NC ANG SF_Addendum01_07-01-2026.pdf PDF
Solicitation Amendment W50S8726BA0020002 SF 30.pdf PDF
Sign-in sheets.pdf PDF
PreBidSlides_W50S87-26-B-A002 Construct SFS Building.pdf PDF
Solicitation Amendment W50S8726BA0020001 SF 30.pdf PDF
Attachment 11 - Submittal Register.pdf PDF
Attachment 2 - FJRP229030 B-3 Rev Proj Spec Manual vol1.pdf PDF
Attachment 4 - FJRP229030 B-3 Rev Drawings.pdf PDF
Attachment 8 - Brand name justification-Interior and exterior finishes.pdf PDF
Solicitation - W50S8726BA002 Final 22 May 26.pdf PDF
Attachment 1 - FJRP229030 - SOW CNS SFS Admin.pdf PDF
Attachment 3 - FJRP229030 B-3 Rev Proj Spec Manual vol2.pdf PDF
Attachment 7 - Limited Competition Justification Door Hardware - KO signed.pdf PDF
Attachment 9 -Limited Competition Justification Monaco - KO signed.pdf PDF
Attachment 5 Visitor Request Worksheet.pdf PDF
Attachment 6 - Limited Competition Justification Alerton -KO signed.pdf PDF
Attachment 10 - Wage Determination.pdf PDF
Show all 27

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

MEMORANDUM FOR RECORD

SUBJECT: MINUTES OF PRE-BID CONFERENCE AND SITE VISIT, SOLICITATION W50S87-26-

B-A002, CONSTRUCT SECURITY FORCES BUILDING – 145th AIRLIFT WING

2 June 2026/9:00 AM EST/ 1 hour

1. The list of contractors attending the meeting are shown on the attached sign-in sheet.

The following Government representatives attended the subject meeting:

MSGT SARAH MARSHALL – CONTRACT SPECIALIST

MR. HANSEN PEDERSEN – BASE CIVIL ENGINEER (COR)

2. The following items were discussed during the Pre-proposal Conference:

a. The Contract period is 360 calendar days. This includes all work to include cleanup and punch list. We anticipate award of the contract in mid-September.

Following receipt and approval of bonds we will hold a pre-construction conference and issue NTP.

b. Interested offerors must be registered in SAM. To register go to:

https://www.sam.gov/portal/public/SAM/.

3. A power point slide presentation on the project specifics and the selection process was provided to all attendees. (Attached)

4. Questions must be submitted in writing via email, especially technical questions to:

scott.thomas.53@us.af.mil AND sarah.marshall.6@us.af.mil

DO NOT CONTACT the Design Engineers or the Government Engineers. All questions must be routed through the Contracting Office. All Contractor questions when answered will be posted to the SAM.gov website. If a question arises that will result in a change to the plans or specifications, an official amendment will be issued. All correspondence, questions and answers, amendments etc. will be issued or posted at SAM.gov.

5. All attendees were taken to the site to show where the new building will be constructed.

6. Question: Will the contract be awarded based on the total amount of all of the

CLINs?

Answer: The INCORRECT answer was given at the time of the pre-bid conference.

The correct answer is:

mailto:scott.thomas.53@us.af.mil mailto:sarah.marshall.6@us.af.mil

DFARS 252.236-7007 ADDITIVE OR DEDUCTIVE ITEMS (DEC 1991)

(a) The low offeror and the items to be awarded shall be determined as follows—

(1) Prior to the opening of bids, the Government will determine the amount of funds available for the project.

(2) The low offeror shall be the Offeror that—

(i) Is otherwise eligible for award; and

(ii) Offers the lowest aggregate amount for the first or base bid item, plus or minus (in the order stated in the list of priorities in the bid schedule) those additive or deductive items that provide the most features within the funds determined available.

(3) The Contracting Officer shall evaluate all bids on the basis of the same additive or deductive items.

(i) If adding another item from the bid schedule list of priorities would make the award exceed the available funds for all offerors, the Contracting Officer will skip that item and go to the next item from the bid schedule of priorities; and

(ii) Add that next item if an award may be made that includes that item and is within the available funds.

(b) The Contracting Officer will use the list of priorities in the bid schedule only to determine the low offeror. After determining the low offeror, an award may be made on any combination of items if—

(1) It is in the best interest of the Government;

(2) Funds are available at the time of award; and

(3) The low offeror's price for the combination to be awarded is less than the price offered by any other responsive, responsible offeror.

(c) Example¡ The amount available is $100,000. Offeror A's base bid and four additives (in the order stated in the list of priorities in the bid Schedule) are $85,000, $10,000, $8,000, $6,000, and $4,000. Offeror B's base bid and four additives are $80,000, $16,000, $9,000, $7,000, and $4,000. Offeror A is the low offeror. The aggregate amount of offeror A's bid for purposes of award would be $99,000, which includes a base bid plus the first and fourth additives. The second and third additives were skipped because each of them would cause the aggregate bid to exceed $100,000.

7. The pre-bid conference and site visit concluded at 1000 hours.

SCOTT R. THOMAS

CONTRACTING OFFICER

Attachments

Sign-in Sheet

Power Point Slides

2026-06-02T18:04:29-0400
THOMAS.SCOTT.RANDALL.1387777764

File details come from the government source that posted it. Updated .