Attachment 2 - FJRP229030 B-3 Rev Proj Spec Manual vol1.pdf

PDF 6 MB Posted

Attached to
Construct 145th Security Forces Building
Solicitation number
W50S87-26-B-A002
Issued by

About this file

This file is a Project Specification Manual (Volume 1) serving as a technical attachment to an Invitation for Bid (IFB) for construction of a 145th Security Forces Building by the Department of the Army North Carolina Army National Guard.

The solicitation (W50S87-26-B-A002) is a sealed-bid construction contract with the following key dates: site visit on June 2 at 9:00 AM EST (passes due May 28 by 10:00 AM); questions due June 12 by 10:00 AM; bid opening passes due July 2 by 10:00 AM. Bidders must submit complete bid packages including a signed SF 1442 offer form, priced Section 00 10 00 Bid Schedule, SF 24 bid bond, and completed Section 00 45 00 Representations and Certifications. Electronic bid submission is not permitted; facsimile transmission is prohibited. All potential offerors must be registered in the GSA System for Award Management (SAM) database and maintain current representations and certifications. The bid bond requirement is mandatory and must comply with FAR standards. Electronic signatures and mechanically-applied or printed dates are acceptable per DoD Deviation 2020-O0016. All solicitation updates, changes, and amendments will be posted on SAM.gov. The specific technical requirements and project specifications are detailed in the attachment referenced as the Project Specification Manual Volume 1.

View the file

Other files

File Type Posted
Construct Security Forces Bldg Abstract.pdf PDF
Bid Opening Sign-in Sheet.pdf PDF
Solicitation Amendment W50S8726BA0020006 SF 30.pdf PDF
Attachment 15 - NC ANG SF_Addendum03_07-30-2026.pdf PDF
Solicitation Amendment W50S8726BA0020005 SF 30.pdf PDF
Attachment 14 - Questions and Answers - Final.pdf PDF
Solicitation Amendment W50S8726BA0020003 SF 30.pdf PDF
Attachment 14 - Questions and Answers - Final.pdf PDF
Solicitation Amendment W50S8726BA0020004 SF 30.pdf PDF
Attachment 13 - NC ANG SF_Addendum02_07-10-2026.pdf PDF
Attachment 12 - NC ANG SF_Addendum01_07-01-2026.pdf PDF
Solicitation Amendment W50S8726BA0020002 SF 30.pdf PDF
PreBidSlides_W50S87-26-B-A002 Construct SFS Building.pdf PDF
Site Visit Minutes FINAL (1).pdf PDF
Sign-in sheets.pdf PDF
Solicitation Amendment W50S8726BA0020001 SF 30.pdf PDF
Attachment 11 - Submittal Register.pdf PDF
Attachment 3 - FJRP229030 B-3 Rev Proj Spec Manual vol2.pdf PDF
Attachment 5 Visitor Request Worksheet.pdf PDF
Attachment 8 - Brand name justification-Interior and exterior finishes.pdf PDF
Attachment 10 - Wage Determination.pdf PDF
Attachment 4 - FJRP229030 B-3 Rev Drawings.pdf PDF
Attachment 6 - Limited Competition Justification Alerton -KO signed.pdf PDF
Attachment 9 -Limited Competition Justification Monaco - KO signed.pdf PDF
Solicitation - W50S8726BA002 Final 22 May 26.pdf PDF
Attachment 1 - FJRP229030 - SOW CNS SFS Admin.pdf PDF
Attachment 7 - Limited Competition Justification Door Hardware - KO signed.pdf PDF
Show all 27

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Project Manual

North Carolina Air National Guard, 145th Airlift Wing Charlotte Air National Guard Base Construct Security Forces Building

Project No.: FJRP229030

B-3 Submittal - Final May 30, 2025

Volume 1: Divisions 00-21

Charlotte Air National Guard Base Project No.: FJRP229030

PROJECT TABLE OF CONTENTS

DIVISION 00 - PROCUREMENT AND CONTRACTING REQUIREMENTS

00 01 15 LIST OF DRAWINGS

DIVISION 01 - GENERAL REQUIREMENTS

01 11 00 SUMMARY OF WORK

01 14 00 WORK RESTRICTIONS

01 30 00 ADMINISTRATIVE REQUIREMENTS

01 32 01.00 10 PROJECT SCHEDULE

01 33 00 SUBMITTAL PROCEDURES

01 33 29 SUSTAINABILITY REQUIREMENTS AND REPORTING

01 35 13 SPECIAL PROJECT PROCEDURES

01 35 26 GOVERNMENTAL SAFETY REQUIREMENTS

01 42 00 SOURCES FOR REFERENCE PUBLICATIONS

01 45 00 QUALITY CONTROL

01 45 35 SPECIAL INSPECTIONS

01 50 00 TEMPORARY CONSTRUCTION FACILITIES AND CONTROLS

01 57 19 TEMPORARY ENVIRONMENTAL CONTROLS

01 74 19 CONSTRUCTION WASTE MANAGEMENT AND DISPOSAL

01 78 00 CLOSEOUT SUBMITTALS

01 78 23 OPERATION AND MAINTENANCE DATA

01 91 00.15 10 TOTAL BUILDING COMMISSIONING

DIVISION 02 - Not Used

DIVISION 03 - CONCRETE

03 30 00 CAST-IN-PLACE CONCRETE

03 62 16 METALLIC NON-SHRINK GROUTING

DIVISION 04 - MASONRY

04 20 00 UNIT MASONRY

DIVISION 05 - METALS

05 05 20 POST-INSTALLED CONCRETE AND MASONRY ANCHORS

05 05 23.16 STRUCTURAL WELDING

05 12 00 STRUCTURAL STEEL

05 21 00 STEEL JOIST FRAMING

05 30 00 STEEL DECKS

05 40 00 COLD-FORMED METAL FRAMING

05 50 13 MISCELLANEOUS METAL FABRICATIONS

05 51 00 METAL STAIRS

05 51 33 METAL LADDERS

05 52 00 METAL RAILINGS

DIVISION 06 - WOOD, PLASTICS, AND COMPOSITES

06 10 00 ROUGH CARPENTRY

06 41 16.00 10 PLASTIC-LAMINATE-CLAD ARCHITECTURAL CABINETS

06 61 16 SOLID SURFACING FABRICATIONS

DIVISION 07 - THERMAL AND MOISTURE PROTECTION

07 13 53 ELASTOMERIC SHEET WATERPROOFING

PROJECT TABLE OF CONTENTS Page 1

07 21 13 BOARD AND BLOCK INSULATION

07 21 16 MINERAL FIBER BLANKET INSULATION

07 27 10 BUILDING AIR BARRIER SYSTEM

07 27 19.01 SELF-ADHERING AIR BARRIERS

07 42 13 METAL WALL PANELS

07 54 19 POLYVINYL-CHLORIDE ROOFING

07 60 00 FLASHING AND SHEET METAL

07 84 00 FIRESTOPPING

07 92 00 JOINT SEALANTS

DIVISION 08 - OPENINGS

08 11 13 STEEL DOORS AND FRAMES

08 14 00 WOOD DOORS

08 31 00 ACCESS DOORS AND PANELS

08 34 59 VAULT DOORS AND DAY GATES

08 41 13 ALUMINUM-FRAMED ENTRANCES AND STOREFRONTS

08 51 13 ALUMINUM WINDOWS

08 56 63 DETENTION AND SECURITY WINDOWS

08 71 00 DOOR HARDWARE

08 81 00 GLAZING

08 91 00 METAL WALL LOUVERS

DIVISION 09 - FINISHES

09 22 00 SUPPORTS FOR PLASTER AND GYPSUM BOARD

09 29 00 GYPSUM BOARD

09 30 10 CERAMIC, QUARRY, AND GLASS TILING

09 51 00 ACOUSTICAL CEILINGS

09 65 00 RESILIENT FLOORING

09 68 00 CARPETING

09 90 00 PAINTS AND COATINGS

09 96 00 HIGH-PERFORMANCE COATINGS

DIVISION 10 - SPECIALTIES

10 11 00 VISUAL DISPLAY UNITS

10 14 00.10 EXTERIOR SIGNAGE

10 14 00.20 INTERIOR SIGNAGE

10 21 13 TOILET COMPARTMENTS

10 22 39 FOLDING PANEL PARTITIONS

10 26 00 WALL AND DOOR PROTECTION

10 28 13 TOILET ACCESSORIES

10 44 16 FIRE EXTINGUISHERS

10 51 13 METAL LOCKERS

10 73 20 MANUFACTURED CANOPY

DIVISION 11 - EQUIPMENT

11 81 29 FACILITY FALL PROTECTION

DIVISION 12 - FURNISHINGS

12 21 00 WINDOW BLINDS

DIVISION 13 - SPECIAL CONSTRUCTION

13 48 73 SEISMIC CONTROL FOR MISCELLANEOUS EQUIPMENT

PROJECT TABLE OF CONTENTS Page 2

DIVISION 14 - CONVEYING EQUIPMENT

14 21 23 ELECTRIC TRACTION PASSENGER ELEVATORS

DIVISION 21 - FIRE SUPPRESSION

21 13 13 WET PIPE SPRINKLER SYSTEMS, FIRE PROTECTION

DIVISION 22 - PLUMBING

22 00 00 PLUMBING, GENERAL PURPOSE

22 05 48.00 20 MECHANICAL SOUND, VIBRATION, AND SEISMIC CONTROL

22 07 19.00 40 PLUMBING PIPING INSULATION

22 14 29.00 40 SUMP PUMPS

DIVISION 23 - HEATING, VENTILATING, AND AIR CONDITIONING (HVAC)

23 03 00.00 20 BASIC MECHANICAL MATERIALS AND METHODS

23 05 48.00 40 VIBRATION AND SEISMIC CONTROLS FOR HVAC PIPING AND

EQUIPMENT

23 05 48.19 SEISMIC BRACING FOR HVAC

23 05 93 TESTING, ADJUSTING, AND BALANCING FOR HVAC

23 07 00 THERMAL INSULATION FOR MECHANICAL SYSTEMS

23 08 00.00 20 COMMISSIONING OF MECHANICAL AND PLUMBING SYSTEMS

23 09 00 INSTRUMENTATION AND CONTROL FOR HVAC

23 09 13 INSTRUMENTATION AND CONTROL DEVICES FOR HVAC

23 09 23.02 BACNET DIRECT DIGITAL CONTROL FOR HVAC AND OTHER BUILDING

CONTROL SYSTEMS

23 23 00 REFRIGERANT PIPING

23 31 13.00 40 METAL DUCTS

23 34 23.00 40 HVAC POWER VENTILATORS

23 36 00.00 40 AIR TERMINAL UNITS

23 37 13.00 40 DIFFUSERS, REGISTERS, AND GRILLES

23 74 33.00 40 PACKAGED, OUTDOOR, HEATING AND COOLING MAKEUP

AIR-CONDITIONERS

23 81 29 DUCTLESS SPLIT AIR CONDITIONERS

23 83 00.00 20 ELECTRIC SPACE HEATING EQUIPMENT

DIVISION 25 - INTEGRATED AUTOMATION

25 05 11.01 CYBERSECURITY FOR MECH-HVAC FACILITY-RELATED CONTROL

SYSTEMS

25 05 11.02 CYBERSECURITY FOR FLS FACILITY-RELATED CONTROL SYSTEMS

DIVISION 26 - ELECTRICAL

26 05 00.00 40 COMMON WORK RESULTS FOR ELECTRICAL

26 05 13.00 40 MEDIUM-VOLTAGE CABLES

26 05 26.00 40 GROUNDING AND BONDING FOR ELECTRICAL SYSTEMS

26 05 71.00 40 LOW VOLTAGE OVERCURRENT PROTECTIVE DEVICES

26 09 23.00 40 LIGHTING CONTROL DEVICES

26 20 00 INTERIOR DISTRIBUTION SYSTEM

26 24 16.00 40 PANELBOARDS

26 32 15.00 ENGINE-GENERATOR SET STATIONARY 15-2500 KW, WITH

AUXILIARIES

26 41 00 LIGHTNING PROTECTION SYSTEM

26 51 00 INTERIOR LIGHTING

26 52 00.00 40 EMERGENCY LIGHTING

26 53 00.00 40 EXIT SIGNS

PROJECT TABLE OF CONTENTS Page 3

26 55 53.00 40 SECURITY LIGHTING

DIVISION 27 - COMMUNICATIONS

27 05 13.43 TELEVISION DISTRIBUTION SYSTEM

27 05 28.36 40 CABLE TRAYS FOR COMMUNICATIONS SYSTEMS

27 10 00 BUILDING TELECOMMUNICATIONS CABLING SYSTEM

27 13 23.00 40 COMMUNICATIONS OPTICAL BACKBONE CABLING

DIVISION 28 - ELECTRONIC SAFETY AND SECURITY

28 31 76 INTERIOR FIRE ALARM AND MASS NOTIFICATION SYSTEM,

ADDRESSABLE

DIVISION 31 - EARTHWORK

31 00 00 EARTHWORK

31 23 00.00 20 EXCAVATION AND FILL

DIVISION 32 - EXTERIOR IMPROVEMENTS

32 12 16.16 ROAD-MIX ASPHALT PAVING

32 13 13.06 PORTLAND CEMENT CONCRETE PAVEMENT FOR ROADS AND SITE

FACILITIES

32 16 19 CONCRETE CURBS, GUTTERS AND SIDEWALKS

32 17 23 PAVEMENT MARKINGS

32 34 13 FABRICATED PEDESTRIAN BRIDGES

32 92 19 SEEDING

DIVISION 33 - UTILITIES

33 11 00 WATER UTILITY DISTRIBUTION PIPING

33 30 00 SANITARY SEWERAGE

33 40 00 STORMWATER UTILITIES

33 46 13 FOUNDATION DRAINAGE

33 46 16 SUBDRAINAGE PIPING

DIVISION 34 - Not Used

DIVISION 35 - Not Used

DIVISION 40 - Not Used

DIVISION 41 - Not Used

DIVISION 42 - Not Used

DIVISION 43 - Not Used

DIVISION 44 - Not Used

DIVISION 45 - Not Used

DIVISION 46 - Not Used

DIVISION 48 - Not Used

-- End of Project Table of Contents --

PROJECT TABLE OF CONTENTS Page 4

SECTION TABLE OF CONTENTS

DIVISION 00 - PROCUREMENT AND CONTRACTING REQUIREMENTS

DOCUMENT 00 01 15

LIST OF DRAWINGS

PART 1 GENERAL

1.1 SUMMARY

1.2 CONTRACT DRAWINGS

-- End of Section Table of Contents --

DOCUMENT 00 01 15 Page 1

DOCUMENT 00 01 15

LIST OF DRAWINGS

PART 1 GENERAL

1.1 SUMMARY

This section lists the drawings for the project pursuant to contract clause "DFARS 252.236-7001, Contract Drawings, Maps and Specifications."

1.2 CONTRACT DRAWINGS

Contract drawings are as follows:

DRAWING NO. TITLE

GENERAL

G000 G001 G002 G101

COVER SHEET

ABBREVIATIONS, LEGENDS, & SHEET INDEX

CODE INFORMATION

LIFE-SAFETY PLANS

CIVIL

C001 C002 C003 C101 C102 C201 C301 C501 C502

DEMOLITION PLAN

EROSION CONTROL PLAN

SESC DETAILD

SITE LAYOUT PLAN

LANDSCAPE PLAN

UTILITY PLAN

GRADING AND DRAINAGE PLAN

DETAILS

DETAILS

DOCUMENT 00 01 15 Page 2

DRAWING NO. TITLE

STRUCTURE

S001 S002 S003 S007 S008 S009 S010 S011 S101 S102 S103 S200 S201 S300 S301 S302 S303 S304 S305

ABBREVIATIONS, LEGENDS, & SYMBOLS

GENERAL NOTES

GENERAL NOTES

TYPICAL DETAILS

TYPICAL DETAILS

TYPICAL DETAILS

TYPICAL DETAILS

TYPICAL DETAILS

STRUCTURAL FOUNDATION PLAN

STRUCTURAL SECOND FLOOR FRAMING PLAN

STRUCTURAL ROOF FRAMING PLAN

STRUCTURAL ELEVATIONS

STRUCTURAL ELEVATIONS

STRUCTURAL DETAILS

STRUCTURAL DETAILS

STRUCTURAL DETAILS

STRUCTURAL DETAILS

STRUCTURAL DETAILS

STRUCTURAL DETAILS

DOCUMENT 00 01 15 Page 3

DRAWING NO. TITLE

ARCHITECTURE

A101 A102 A103 A150 A151 A200 A201 A220 A240 A300 A320 A321 A400 A420 A500 A501 A502 A520 A521 A530 A600 A601 A602 A610 A611 A630 A640 A670 A680 A700 A701 A702 A800 A900

FLOOR PLAN - LEVEL 1

FLOOR PLAN - LEVEL 2

ROOF PLAN

REFLECTED CEILING PLAN - LEVEL 1

REFLECTED CEILING PLAN - LEVEL 2

EXTERIOR PERSPECTIVES

EXTERIOR ELEVATIONS

ENLARGED EXTERIOR ELEVATIONS

CURTAINWALL / WINDOW ELEVATIONS

BUILDING SECTIONS

WALL SECTIONS

WALL SECTIONS

ENLARGED FLOOR PLANS

ENLARGED REFLECTED CEILING PLANS

EXTERIOR PLAN DETAILS

EXTERIOR PLAN DETAILS

EXTERIOR PLAN DETAILS

EXTERIOR SECTION DETAILS

EXTERIOR SECTION DETAILS

ROOF DETAILS

TYPICAL MOUNTING HEIGHTS

INTERIOR ELEVATIONS

INTERIOR ELEVATIONS

SIGNAGE

SIGNAGE

INTERIOR CEILING DETAILS

INTERIOR MILLWORK ELEVATIONS AND DETAILS

PARTITION TYPE SCHEDULE, NOTES AND DETAILS

DOOR SCHEDULE

ENLARGED STAIR PLANS AND SECTIONS - STAIR 01

ENLARGED ELEVATOR PLANS WALL SECTIONS - ELEV 01

TYPICAL STAIR DETAILS

FINISH LEGENDS AND SCHEDULES

OLI #1 - PEDESTRIAN BRIDGE

FIRE PROTECTION

FA001

FA101

FA201

FA501

FA502

FA503

FX001

FX101

FX201

FX501

FX801

FIRE ALARM SYMBOLS, LEGEND, ABBREVIATIONS AND NOTES

FIRST FLOOR PLAN - FIRE ALARM

SECOND FLOOR PLAN - FIRE ALARM

FIRE ALARM DETAILS

FIRE ALARM DETAILS

FIRE ALARM DETAILS

FIRE SUPPRESSION SYMBOLS, LEGEND, ABBREVIATIONS AND NOTES

FIRST FLOOR PLAN - FIRE SUPPRESSION

SECOND FLOOR PLAN - FIRE SUPPRESSION

FIRE SUPPRESSION DETAILS

FIRE EXTINGUISHER LAYOUT

DOCUMENT 00 01 15 Page 4

DRAWING NO. TITLE

PLUMBING

P001 P100 P101 P102 P103 P301 P601 P602 P701 P801 P802

GENERAL INFO - PLUMBING

UNDERGROUND PLUMBING PLAN

FIRST FLOOR PLUMBING PLAN

SECOND FLOOR PLUMBING PLAN

ROOF PLUMBING PLAN

PLUMBING ENLARGED PLANS

PLUMBING DETAILS

PLUMBING DETAILS

PLUMBING SCHEDULES

PLUMBING STACK DIAGRAM

DOMESTIC RISER DIAGRAM

MECHANICAL

M001 M002 M101 M102 M401 M601 M602 M701 M801 M802

GENERAL INFORMATION - HVAC

HVAC ZONING PLANS

FIRST FLOOR HVAC DUCTWORK PLAN

SECOND FLOOR HVAC DUCTWORK PLAN

HVAC SECTIONS

HVAC DETAILS

HVAC DETAILS

HVAC SCHEDULES

HVAC SEQUENCE OF OPERATIONS

HVAC SEQUENCE OF OPERATIONS

ELECTRICAL

E001 E090 E100 E101 E102 E201 E202 E501 E502 E503 E601 E701 E702

ABBREVIATIONS, LEGENDS & GENERAL NOTES

GROUNDING AND LIGHTNING PROTECTION PLANS

ELECTRICAL SITE PLAN

POWER PLAN - LEVEL 1

POWER PLAN - LEVEL 2

LIGHTING PLAN - LEVEL 1

LIGHTING PLAN - LEVEL 2

ELECTRICAL DETAILS

ELECTRICAL DETAILS

ELECTRICAL DETAILS

ELECTRICAL ONE-LINE DIAGRAM

ELECTRICAL SCHEDULES

ELECTRICAL PANEL SCHEDULES

TELECOM

T001 T101 T102 T201 T301 T501 T502 T601

TELECOMMUNICATIONS LEGEND. ABBREVIATIONS AND SYMBOLS

TELECOMMUNICATIONS FIRST FLOOR PLAN

TELECOMMUNICATIONS SECOND FLOOR PLAN

TELECOMMUNICATIONS SITE PLAN

ENLARGED COMMUNICATIONS ROOM FLOOR PLAN

TELECOMMUNICATIONS DETAILS

TELECOMMUNICATIONS DETAILS

TECHNOLOGY RISER DIAGRAMS

-- End of Document --

DOCUMENT 00 01 15 Page 5

SECTION TABLE OF CONTENTS

DIVISION 01 - GENERAL REQUIREMENTS

SECTION 01 11 00

SUMMARY OF WORK

PART 1 GENERAL

1.1 WORK COVERED BY CONTRACT DOCUMENTS

1.1.1 Project Description

1.2 USE OF SITE

1.3 EXISTING WORK

1.4 LOCATION OF UNDERGROUND UTILITIES

1.4.1 Notification Prior to Excavation

1.5 GOVERNMENT-FURNISHED MATERIAL AND EQUIPMENT

1.5.1 Delivery Schedule

1.5.2 Delivery Location

PART 2 PRODUCTS

PART 3 EXECUTION

SECTION 01 11 00 Page 1

SECTION 01 11 00

SUMMARY OF WORK

PART 1 GENERAL

1.1 WORK COVERED BY CONTRACT DOCUMENTS

1.1.1 Project Description

The work includes construction of a new, 2-story, 9,530 square foot Security Forces Building for the North Carolina Air National Guard (NC ANG) 145th Airlift Wing and incidental related work.

1.2 USE OF SITE

Before work is started, arrange with the Contracting Officer a sequence of procedure, means of access, space for storage of materials and equipment, and use of approaches, walkways , and stairways.

1.3 EXISTING WORK

Comply with FAR 52.236-9 Protection of Existing Vegetation, Structures, Equipment, Utilities, and Improvements .

1.4 LOCATION OF UNDERGROUND UTILITIES

No digging permits required unless required by NCDEQ. Notify CO prior to start of excavation. Comply with Installation requirements for locating and marking underground utilities. Contact local utility locating service a minimum of 48 hours prior to excavating, to mark utilities, and within sufficient time required if work occurs on a Monday or after a Holiday.

Verify existing utility locations indicated on contract drawings, within area of work.

Identify and mark all other utilities not managed and located by the local utility companies. Scan the construction site with Ground Penetrating Radar (GPR), electromagnetic, or sonic equipment, and mark the surface of the ground or paved surface where existing underground utilities are discovered. Verify the elevations of existing piping, utilities,and any type of underground obstruction not indicated, or specified to be removed, that is indicated or discovered during scanning, in locations to be traversed by piping, ducts, and other work to be conducted or installed.

Verify elevations before installing new work closer than nearest manhole or other structure at which an adjustment in grade can be made.

1.4.1 Notification Prior to Excavation

Notify the Contracting Officer at least 4 days prior to starting excavation work.

1.5 GOVERNMENT-FURNISHED MATERIAL AND EQUIPMENT

Pursuant to Contract Clause FAR 52.245-1 Government Property, the Government will furnish materials and equipment for installation by the Contractor as indicated in the Drawings and Specifications. This includes, SECTION 01 11 00 Page 2 but is not limited to:

PR-1 PROJECTOR SCREEN

PS-1 PROJECTION SCREEN, CEILING MOUNTED

TV-1 LARGE WALL MOUNTED TELEVISION

TV-2 SMALL WALL MOUNTED TELEVISION

WB-1 WHITEBOARD

T-2 HAND TOWEL ROLL DISPENSER

T-4 SOAP DISPENSER

It is the intention of the Government to furnish all quantities of the items required to complete the work as specified.

1.5.1 Delivery Schedule

Notify the Contracting Officer in writing at least 21 calendar days in advance of the date on which the materials and equipment are required.

Pick up materials and equipment no later than 30 calendar days after such date.

1.5.2 Delivery Location

The materials and equipment are located within 1 mile of the jobsite.

PART 2 PRODUCTS

Not used.

PART 3 EXECUTION

Not used.

-- End of Section --

SECTION 01 11 00 Page 3

SECTION TABLE OF CONTENTS

DIVISION 01 - GENERAL REQUIREMENTS

SECTION 01 14 00

WORK RESTRICTIONS

PART 1 GENERAL

1.1 SUBMITTALS

1.2 SPECIAL SCHEDULING REQUIREMENTS

1.3 CONTRACTOR ACCESS AND USE OF PREMISES

1.3.1 Activity Regulations

1.3.1.1 Subcontractors and Personnel Contacts

1.3.1.2 No Smoking Policy

1.3.2 Working Hours

1.3.3 Work Outside Regular Hours

1.3.4 Utility Cutovers and Interruptions

1.4 SECURITY REQUIREMENTS

PART 2 PRODUCTS

PART 3 EXECUTION

SECTION 01 14 00 Page 1

SECTION 01 14 00

WORK RESTRICTIONS

PART 1 GENERAL

1.1 SUBMITTALS

Government approval is required for submittals with a "G" or "S" classification. Submittals not having a "G" or "S" classification are for Contractor Quality Control approval. Submit the following in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:

SD-01 Preconstruction Submittals

List of Contact Personnel

1.2 SPECIAL SCHEDULING REQUIREMENTS

There are no special scheduling requirements apart from the typical Mon-Fri 0730-1600 work hours. The Contractor is permitted to work on Government holidays with prior approval. The only items that need to be in place prior to starting is temporary erosion controls and concrete washouts before related work is started.

1.3 CONTRACTOR ACCESS AND USE OF PREMISES

1.3.1 Activity Regulations

Ensure that Contractor personnel employed on the Activity become familiar with and obey Activity regulations including safety, fire, traffic and security regulations. Keep within the limits of the work and avenues of ingress and egress. Wear appropriate personal protective equipment (PPE) in designated areas. Do not enter any restricted areas unless required to do so and until cleared for such entry. Ensure all Contractor equipment, include delivery vehicles, are clearly identified with their company name.

1.3.1.1 Subcontractors and Personnel Contacts

Provide a list of contact personnel of the Contractor and subcontractors including addresses and telephone numbers for use in the event of an emergency. As changes occur and additional information becomes available, correct and change the information contained in previous lists.

1.3.1.2 No Smoking Policy

Smoking is prohibited within and outside of all buildings on installation, except in designated smoking areas. This applies to existing buildings, buildings under construction and buildings under renovation. Discarding tobacco materials other than into designated tobacco receptacles is considered littering and is subject to fines. The Contracting Officer will identify designated smoking areas.

1.3.2 Working Hours

Regular working hours will consist of an 8 1/2 hour period, between 7 a.m.

SECTION 01 14 00 Page 2 and 3:30 p.m., Monday through Friday, excluding Government holidays.

1.3.3 Work Outside Regular Hours

Work outside regular working hours requires Contracting Officer approval.

Make application 15 calendar days prior to such work to allow arrangements to be made by the Government for inspecting the work in progress, giving the specific dates, hours, location, type of work to be performed, contract number and project title. Based on the justification provided, the Contracting Officer may approve work outside regular hours. During periods of darkness, the different parts of the work must be lighted in a manner approved by the Contracting Officer.

1.3.4 Utility Cutovers and Interruptions

a. Make utility cutovers and interruptions after normal working hours or on Saturdays, Sundays, and Government holidays. Conform to procedures required in paragraph WORK OUTSIDE REGULAR HOURS.

b. Ensure that new utility lines are complete, except for the connection, before interrupting existing service.

c. Interruption to water, sanitary sewer, storm sewer, telephone service, electric service, air conditioning, heating, fire alarm, compressed air, and natural gas are considered utility cutovers pursuant to the paragraph WORK OUTSIDE REGULAR HOURS.

1.4 SECURITY REQUIREMENTS

Contractor's employees are required to provide a Real ID during the badging and background check process.

PART 2 PRODUCTS

Not Used

PART 3 EXECUTION

Not Used

SECTION 01 14 00 Page 3

SECTION TABLE OF CONTENTS

DIVISION 01 - GENERAL REQUIREMENTS

SECTION 01 30 00

ADMINISTRATIVE REQUIREMENTS

PART 1 GENERAL

1.1 REFERENCES

1.2 SUBMITTALS

1.3 COLOR BOARDS FOR AIR FORCE PROJECTS

1.4 VIEW LOCATION MAP

1.5 PROGRESS AND COMPLETION PICTURES

1.6 MINIMUM INSURANCE REQUIREMENTS

1.7 SUPERVISION

1.7.1 Superintendent Qualifications

1.7.2 Minimum Communication Requirements

1.7.3 Duties

1.7.4 Non-Compliance Actions

1.8 PRECONSTRUCTION

1.8.1 Attendees

1.9 FACILITY TURNOVER PLANNING MEETINGS (Red Zone Meetings)

1.9.1 Red Zone Checklist

1.9.2 Meetings

1.10 PARTNERING

1.10.1 Team-Led (Informal) Partnering

PART 2 PRODUCTS

PART 3 EXECUTION

SECTION 01 30 00 Page 1

SECTION 01 30 00

ADMINISTRATIVE REQUIREMENTS

PART 1 GENERAL

1.1 REFERENCES

The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.

U.S. ARMY CORPS OF ENGINEERS (USACE)

EM 385-1-1 (2014) Safety -- Safety and Health Requirements Manual

1.2 SUBMITTALS

Government approval is required for submittals with a "G" or "S" classification. Submittals not having a "G" or "S" classification are for Contractor Quality Control approval. Submit the following in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:

SD-01 Preconstruction Submittals

View Location Map

Progress and Completion Pictures

SD-04 Samples

Color Boards ; G

1.3 COLOR BOARDS FOR AIR FORCE PROJECTS

Submit five sets of color boards within 90 calendar days after Contract Award. Each set of boards must include samples of colors and finishes of interior surfaces, such as walls, floors, and ceilings. Present the samples on 8 by 10-1/2 inches boards (modules) with a maximum spread of 24 by 31-1/2 inches for foldouts. Design modules to fit in a standard loose-leaf, three-ring binder. Where special finishes such as architectural concrete, carpet, or prefinished textured metal panels are required, submit samples not less than 12 inches square with the board.

If more space is needed, more than one board per set may be submitted.

Certify that the color samples have been reviewed in detail, and that the color samples are in strict accordance with contract drawings and specifications, except as may be otherwise explicitly stated. Submittal of color samples does not relieve the Contractor of the responsibility to submit samples required elsewhere herein.

1.4 VIEW LOCATION MAP

Submit, prior to or with the first digital photograph submittals, a sketch or drawing indicating the required photographic locations. Update as required if the locations are moved.

SECTION 01 30 00 Page 2

1.5 PROGRESS AND COMPLETION PICTURES

Photographically document site conditions prior to start of construction operations. Provide monthly, and within one month of the completion of work, digital photographs, 1600x1200x24 bit true color minimum resolution in JPEG file format showing the sequence and progress of work. Take a minimum of 20 digital photographs each week throughout the entire project from a minimum of ten different viewpoints selected by the Contractor unless otherwise directed by the Contracting Officer. Submit with the monthly invoice two sets of digital photographs, each set on a separate compact disc (CD) or data versatile disc (DVD), cumulative of all photos to date. Indicate photographs demonstrating environmental procedures.

Provide photographs for each month in a separate monthly directory and name each file to indicate its location on the view location sketch. Also provide the view location sketch on the CD or DVD as a digital file.

Include a date designator in file names. Photographs provided are for unrestricted use by the Government.

1.6 MINIMUM INSURANCE REQUIREMENTS

Provide the minimum insurance coverage required by FAR 28.307-2 Liability, during the entire period of performance under this contract. Provide other insurance coverage as required by State law.

1.7 SUPERVISION

1.7.1 Superintendent Qualifications

Provide project superintendent with a minimum of 10 years experience in construction with at least 5 of those years as a superintendent on projects similar in size and complexity. The individual must be familiar with the requirements of EM 385-1-1 and have experience in the areas of hazard identification and safety compliance. The individual must be capable of interpreting a critical path schedule and construction drawings. The qualification requirements for the alternate superintendent are the same as for the project superintendent. The Contracting Officer may request proof of the superintendent's qualifications at any point in the project if the performance of the superintendent is in question.

For projects where the superintendent is permitted to also serve as the Quality Control (QC) Manager as established in Section QUALITY CONTROL, the superintendent must have qualifications in accordance with that section.

1.7.2 Minimum Communication Requirements

Have at least one qualified superintendent, or competent alternate, capable of reading, writing, and conversing fluently in the English language, on the job-site at all times during the performance of Contract work.In addition, if a Quality Control (QC) representative is required on the Contract, then that individual must also have fluent English communication skills.

1.7.3 Duties

The project superintendent is primarily responsible for managing subcontractors and coordinating day-to-day production and schedule adherence on the project. The superintendent is required to attend Red

SECTION 01 30 00 Page 3

Zone meetings, partnering meetings, and quality control meetings. The superintendent or qualified alternative must be on-site at all times during the performance of this contract until the work is completed and accepted.

1.7.4 Non-Compliance Actions

The Project Superintendent is subject to removal by the Contracting Officer for non-compliance with requirements specified in the contract and for failure to manage the project to ensure timely completion.

Furthermore, the Contracting Officer may issue an order stopping all or part of the work until satisfactory corrective action has been taken. No part of the time lost due to such stop orders is acceptable as the subject of claim for extension of time for excess costs or damages by the Contractor.

1.8 PRECONSTRUCTION

Immediately after award , prior to commencing any work at the site, coordinate with the Contracting Officer a time and place to meet for the Preconstruction Meeting . The meeting must take place within 14 calendar days after award of the contract, but prior to commencement of any work at the site. The purpose of this is to discuss and develop a mutual understanding of the administrative requirements of the Contract including but not limited to: daily reporting, invoicing, value engineering, safety, base-access, outage requests, hot work permits, schedule requirements, quality control, schedule of prices or earned value report, shop drawings, submittals, cybersecurity, prosecution of the work, government acceptance, final inspections and contract close-out. Contractor must present and discuss their basic approach to scheduling the construction work and any required phasing.

1.8.1 Attendees

Contractor attendees must include the Project Manager, Superintendent, Site Safety and Health Officer (SSHO), Quality Control Manager and major subcontractors.

1.9 FACILITY TURNOVER PLANNING MEETINGS (Red Zone Meetings)

Meet with the Government to identify strategies to ensure the project is carried to expeditious closure and turnover to the Client. Start planning the turnover process at the Pre-Construction Conference meeting with a discussion of the Red Zone process and convene at regularly scheduled NRZ Meetings beginning at approximately 75 percent of project completion.

Include the following in the facility Turnover effort:

1.9.1 Red Zone Checklist

a. Contracting Officer's Technical Representative (COTR) will provide the Contractor a copy of the Red Zone Checklist template.

b. Prior to 75 percent completion, modify the Red Zone Checklist template by adding or deleting critical activities applicable to the project and assign planned completion dates for each activity. Submit the modified Red Zone Checklist to the Contracting Officer. The Contracting Officer may request additional activities be added to the Red Zone Checklist at any time as necessary.

SECTION 01 30 00 Page 4

1.9.2 Meetings

a. Conduct regular Red Zone Meetings beginning at approximately 75 percent project completion, or three to six months prior to Beneficial Occupancy Date (BOD), whichever comes first.

b. The Contracting Officer will establish the frequency of the meetings, which is expected to increase as the project completion draws nearer.

At the beginning, Red Zone meetings may be every two weeks then increase to weekly towards the final month of the project.

c. Using the Red Zone Checklist as a Plan of Action and Milestones (POAM) and basis for discussion, review upcoming critical activities and strategies to ensure work is completed on time.

d. During the Red Zone Meetings discuss with the COTR any upcoming activities that require Government involvement.

e. Maintain the Red Zone Checklist by documenting the actual completion dates as work is completed and update the Red Zone Checklist with revised planned completion dates as necessary to match progress.

Distribute copies of the current Red Zone Checklist to attendees at each Red Zone Meeting.

1.10 PARTNERING

To most effectively accomplish this Contract, the Contractor and Government must form a cohesive partnership with the common goal of drawing on the strength of each organization in an effort to achieve a successful project without safety mishaps, conforming to the Contract, within budget and on schedule. The partnering team must consist of personnel from both the Government and Contractor including project level and corporate level leadership positions. Key Personnel from the supported command, end user, Contractor, key subcontractors and the Designer of Record are required to participate in the Partnering process.

1.10.1 Team-Led (Informal) Partnering

a. The Contracting Officer will coordinate the initial Team-Led (Informal) Partnering Session with key personnel of the project team, including Contractor and Government personnel. The Partnering Session will be co-led by the Government Construction Manager and Contractor's Project Manager.

b. The Initial Team-led Partnering session may be held concurrently with the Pre-Construction meeting. Partnering sessions will be held at a location mutually agreed to by the Contracting Officer and the Contractor, typically at a conference room on-base or at the Contractor's temporary trailer.

c. The Initial Team-Led Partnering Session will be conducted and facilitated using electronic media (a video and accompanying forms) provided by Contracting Officer.

d. The Partners will determine the frequency of the follow-on sessions.

e. Participants will bear their own costs for meals, lodging and transportation associated with Partnering.

SECTION 01 30 00 Page 5

PART 2 PRODUCTS

Not Used

PART 3 EXECUTION

Not Used

SECTION 01 30 00 Page 6

SECTION TABLE OF CONTENTS

DIVISION 01 - GENERAL REQUIREMENTS

SECTION 01 32 01.00 10

PROJECT SCHEDULE

PART 1 GENERAL

1.1 REFERENCES

1.2 SUBMITTALS

1.3 PROJECT SCHEDULER QUALIFICATIONS

PART 2 PRODUCTS

2.1 SOFTWARE

2.1.1 Government Default Software

2.1.2 Contractor Software

2.1.2.1 Primavera

2.1.2.2 Other Than Primavera

PART 3 EXECUTION

3.1 GENERAL REQUIREMENTS

3.2 BASIS FOR PAYMENT AND COST LOADING

3.2.1 Activity Cost Loading

3.2.2 Withholdings / Payment Rejection

3.3 PROJECT SCHEDULE DETAILED REQUIREMENTS

3.3.1 Level of Detail Required

3.3.2 Activity Durations

3.3.3 Procurement Activities

3.3.4 Mandatory Tasks

3.3.5 Government Activities

3.3.6 Standard Activity Coding Dictionary

3.3.6.1 Workers Per Day (WRKP)

3.3.6.2 Responsible Party Coding (RESP)

3.3.6.3 Area of Work Coding (AREA)

3.3.6.4 Modification Number (MODF)

3.3.6.5 Bid Item Coding (BIDI)

3.3.6.6 Phase of Work Coding (PHAS)

3.3.6.7 Category of Work Coding (CATW)

3.3.6.8 Feature of Work Coding (FOW)

3.3.7 Contract Milestones and Constraints

3.3.7.1 Project Start Date Milestone and Constraint

3.3.7.2 End Project Finish Milestone and Constraint

3.3.7.3 Interim Completion Dates and Constraints

3.3.7.3.1 Start Phase

3.3.7.3.2 End Phase

3.3.8 Calendars

3.3.9 Open Ended Logic

3.3.10 Default Progress Data Disallowed

3.3.11 Out-of-Sequence Progress

3.3.12 Added and Deleted Activities

SECTION 01 32 01.00 10 Page 1

3.3.13 Original Durations

3.3.14 Leads, Lags, and Start to Finish Relationships

3.3.15 Retained Logic

3.3.16 Percent Complete

3.3.17 Remaining Duration

3.3.18 Cost Loading of Closeout Activities

3.3.18.1 As-Built Drawings

3.3.18.2 O & M Manuals

3.3.19 Early Completion Schedule and the Right to Finish Early

3.4 PROJECT SCHEDULE SUBMISSIONS

3.4.1 Preliminary Project Schedule Submission

3.4.2 Initial Project Schedule Submission

3.4.3 Periodic Schedule Updates

3.5 SUBMISSION REQUIREMENTS

3.5.1 Data CD/DVDs

3.5.2 Narrative Report

3.5.3 Schedule Reports

3.5.3.1 Activity Report

3.5.3.2 Logic Report

3.5.3.3 Total Float Report

3.5.3.4 Earnings Report by CLIN

3.5.3.5 Schedule Log

3.5.4 Network Diagram

3.5.4.1 Continuous Flow

3.5.4.2 Project Milestone Dates

3.5.4.3 Critical Path

3.5.4.4 Banding

3.5.4.5 Cash Flow / Schedule Variance Control (SVC) Diagram

3.6 PERIODIC SCHEDULE UPDATE

3.6.1 Periodic Schedule Update Meetings

3.6.2 Update Submission Following Progress Meeting

3.7 WEEKLY PROGRESS MEETINGS

3.8 REQUESTS FOR TIME EXTENSIONS

3.8.1 Justification of Delay

3.8.2 Weather Delays

3.8.3 Time Impact Analysis (Prospective Analysis)

3.8.4 Forensic Schedule Analysis (Retrospective Analysis)

3.8.5 Fragmentary Network (Fragnet)

3.8.6 Time Extension

3.8.7 Impact to Early Completion Schedule

3.9 FAILURE TO ACHIEVE PROGRESS

3.9.1 Artificially Improving Progress

3.9.2 Failure to Perform

3.9.3 Recovery Schedule

3.10 OWNERSHIP OF FLOAT

3.11 TRANSFER OF SCHEDULE DATA INTO RMS/QCS

3.12 PRIMAVERA P6 MANDATORY REQUIREMENTS

SECTION 01 32 01.00 10 Page 2

SECTION 01 32 01.00 10

PROJECT SCHEDULE

PART 1 GENERAL

1.1 REFERENCES

The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.

AACE INTERNATIONAL (AACE)

AACE 29R-03 (2011) Forensic Schedule Analysis

AACE 52R-06 (2006) Time Impact Analysis - As Applied in Construction

U.S. ARMY CORPS OF ENGINEERS (USACE)

ER 1-1-11 (2017) Administration -- Project Schedules

1.2 SUBMITTALS

Government approval is required for submittals with a "G" or "S" classification. Submittals not having a "G" or "S" classification are for Contractor Quality Control approval. Submit the following in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:

SD-01 Preconstruction Submittals

Project Scheduler Qualifications ; G

Preliminary Project Schedule ; G

Initial Project Schedule ; G

Periodic Schedule Update ; G

1.3 PROJECT SCHEDULER QUALIFICATIONS

Designate an authorized representative to be responsible for the preparation of the schedule and all required updating and production of reports. The authorized representative must have a minimum of 2-years experience scheduling construction projects similar in size and nature to this project with scheduling software that meets the requirements of this specification. Representative must have a comprehensive knowledge of CPM scheduling principles and application.

PART 2 PRODUCTS

2.1 SOFTWARE

The scheduling software utilized to produce and update the schedules required herein must be capable of meeting all requirements of this

SECTION 01 32 01.00 10 Page 3 specification.

2.1.1 Government Default Software

The Government intends to use Primavera P6.

2.1.2 Contractor Software

Scheduling software used by the contractor must be commercially available from the software vendor for purchase with vendor software support agreements available. The software routine used to create the required sdef file must be created and supported by the software manufacturer.

2.1.2.1 Primavera

If Primavera P6 is selected for use, provide the "xer" export file in a version of P6 importable by the Government system.

2.1.2.2 Other Than Primavera

If the contractor chooses software other than Primavera P6, that is compliant with this specification, provide for the Government's use two licenses, two computers, and training for two Government employees in the use of the software. These computers will be stand-alone and not connected to Government network. Computers and licenses will be returned at project completion.

PART 3 EXECUTION

3.1 GENERAL REQUIREMENTS

Prepare for approval a Project Schedule, as specified herein, pursuant to FAR Clause 52.236-15 Schedules for Construction Contracts. Show in the schedule the proposed sequence to perform the work and dates contemplated for starting and completing all schedule activities. The scheduling of the entire project is required. The scheduling of construction is the responsibility of the Contractor. Contractor management personnel must actively participate in its development. Subcontractors and suppliers working on the project must also contribute in developing and maintaining an accurate Project Schedule. Provide a schedule that is a forward planning as well as a project monitoring tool. Use the Critical Path Method (CPM) of network calculation to generate all Project Schedules.

Prepare each Project Schedule using the Precedence Diagram Method (PDM).

3.2 BASIS FOR PAYMENT AND COST LOADING

The schedule is the basis for determining contract earnings during each update period and therefore the amount of each progress payment. The aggregate value of all activities coded to a contract CLIN must equal the value of the CLIN.

3.2.1 Activity Cost Loading

Activity cost loading must be reasonable and without front-end loading.

Provide additional documentation to demonstrate reasonableness if requested by the Contracting Officer.

SECTION 01 32 01.00 10 Page 4

3.2.2 Withholdings / Payment Rejection

Failure to meet the requirements of this specification may result in the disapproval of the preliminary, initial or periodic schedule updates and subsequent rejection of payment requests until compliance is met.

In the event that the Contracting Officer directs schedule revisions and those revisions have not been included in subsequent Project Schedule revisions or updates, the Contracting Officer may withhold 10 percent of pay request amount from each payment period until such revisions to the project schedule have been made.

3.3 PROJECT SCHEDULE DETAILED REQUIREMENTS

3.3.1 Level of Detail Required

Develop the Project Schedule to the appropriate level of detail to address major milestones and to allow for satisfactory project planning and execution. Failure to develop the Project Schedule to an appropriate level of detail will result in its disapproval. The Contracting Officer will consider, but is not limited to, the following characteristics and requirements to determine appropriate level of detail:

3.3.2 Activity Durations

Reasonable activity durations are those that allow the progress of ongoing activities to be accurately determined between update periods.

Less than 2 percent of all non-procurement activities may have Original Durations (OD) greater than 20 work days or 30 calendar days.

3.3.3 Procurement Activities

Include activities associated with the critical submittals and their approvals, procurement, fabrication, and delivery of long lead materials, equipment, fabricated assemblies, and supplies. Long lead procurement activities are those with an anticipated procurement sequence of over 90 calendar days.

3.3.4 Mandatory Tasks

Include the following activities/tasks in the initial project schedule and all updates.

a. Submission, review and acceptance of SD-01 Preconstruction Submittals (individual activity for each).

b. Submission, review and acceptance of features require design completion

c. Submission of mechanical/electrical/information systems layout drawings.

d. Long procurement activities

e. Submission and approval of O & M manuals.

f. Submission and approval of as-built drawings.

g. Submission and approval of DD1354 data and installed equipment lists.

SECTION 01 32 01.00 10 Page 5

h. Submission and approval of testing and air balance (TAB).

i. Submission of TAB specialist design review report.

j. Submission and approval of fire protection specialist.

k. Submission and approval of Building Commissioning Plan, test data, and reports: Develop the schedule logic associated with testing and commissioning of mechanical systems to a level of detail consistent with the contract commissioning requirements. All tasks associated with all building testing and commissioning will be completed prior to submission of building commissioning report and subsequent contract completion.

l. Air and water balancing.

m. Building commissioning - Functional Performance Testing.

n. Controls testing plan submission.

o. Controls testing.

p. Performance Verification testing.

q. Other systems testing, if required.

r. Contractor's pre-final inspection.

s. Correction of punch list from Contractor's pre-final inspection.

t. Government's pre-final inspection.

u. Correction of punch list from Government's pre-final inspection.

v. Final inspection.

3.3.5 Government Activities

Show Government and other agency activities that could impact progress.

These activities include, but are not limited to: approvals, environmental permit approvals by State regulators, inspections, utility tie-in, Government Furnished Equipment (GFE) and Notice to Proceed (NTP) for phasing requirements.

3.3.6 Standard Activity Coding Dictionary

Use the activity coding structure defined in the Standard Data Exchange Format (SDEF) in ER 1-1-11 . This exact structure is mandatory. Develop and assign all Activity Codes to activities as detailed herein. A template SDEF compatible schedule backup file is available on the QCS web site: http://rms.usace.army.mil .

The SDEF format is as follows:

SECTION 01 32 01.00 10 Page 6

Field Activity Code Length Description

1 WRKP 3 Workers per day

2 RESP 4 Responsible party

3 AREA 4 Area of work

4 MODF 6 Modification Number

5 BIDI 6 Bid Item (CLIN)

6 PHAS 2 Phase of work

7 CATW 1 Category of work

8 FOW 20 Feature of work*

*Some systems require that FEATURE OF WORK values be placed in several activity code fields. The notation shown is for Primavera P6. Refer to the specific software guidelines with respect to the FEATURE OF WORK field requirements.

3.3.6.1 Workers Per Day (WRKP)

Assign Workers per Day for all field construction or direct work activities, if directed by the Contracting Officer. Workers per day is based on the average number of workers expected each day to perform a task for the duration of that activity.

3.3.6.2 Responsible Party Coding (RESP)

Assign responsibility code for all activities to the Prime Contractor, Subcontractor(s) or Government agency(ies) responsible for performing the activity.

a. Activities coded with a Government Responsibility code include, but are not limited to: Government approvals, Government design reviews, environmental permit approvals by State regulators, Government Furnished Property/Equipment (GFP) and Notice to Proceed (NTP) for phasing requirements.

b. Activities cannot have more than one Responsibility Code. Examples of acceptable activity code values are: DOR (for the designer of record);

ELEC (for the electrical subcontractor); MECH (for the mechanical subcontractor); and GOVT (for USACE).

3.3.6.3 Area of Work Coding (AREA)

Assign Work Area code to activities based upon the work area in which the activity occurs. Define work areas based on resource constraints or space constraints that would preclude a resource, such as a particular trade or craft work crew from working in more than one work area at a time due to restraints on resources or space. Examples of Work Area Coding include different areas within a floor of a building, different floors within a building, and different buildings within a complex of buildings.

SECTION 01 32 01.00 10 Page 7

Activities cannot have more than one Work Area Code.

Not all activities are required to be Work Area coded. A lack of Work Area coding indicates the activity is not resource or space constrained.

3.3.6.4 Modification Number (MODF)

Assign a Modification Number Code to any activity or sequence of activities added to the schedule as a result of a Contract Modification, when approved by Contracting Officer. Key all Code values to the Government's modification numbering system. An activity can have only one Modification Number Code.

3.3.6.5 Bid Item Coding (BIDI)

Assign a Bid Item Code to all activities using the Contract Line Item Schedule (CLIN) to which the activity belongs, even when an activity is not cost loaded. An activity can have only one BIDI Code.

3.3.6.6 Phase of Work Coding (PHAS)

Assign Phase of Work Code to all activities. Examples of phase of work are procurement phase and construction phase. Each activity can have only one Phase of Work code.

a. Code proposed fast track design and construction phases proposed to allow filtering and organizing the schedule by fast track design and construction packages.

b. If the contract specifies phasing with separately defined performance periods, identify a Phase Code to allow filtering and organizing the schedule accordingly.

3.3.6.7 Category of Work Coding (CATW)

Assign a Category of Work Code to all activities. Category of Work Codes include, but are not limited to construction submittal, procurement, fabrication, weather sensitive installation, non-weather sensitive installation, start-up, and testing activities. Each activity can have no more than one Category of Work Code.

3.3.6.8 Feature of Work Coding (FOW)

Assign a Feature of Work Code to appropriate activities based on the Definable Feature of Work to which the activity belongs based on the approved QC plan.

Definable Feature of Work is defined in Section 01 45 00 QUALITY CONTROL.

An activity can have only one Feature of Work Code.

3.3.7 Contract Milestones and Constraints

Milestone activities are to be used for significant project events including, but not limited to, project phasing, project start and end activities, or interim completion dates. The use of artificial float constraints such as "zero free float" or "zero total float" are prohibited.

Mandatory constraints that ignore or effect network logic are prohibited.

SECTION 01 32 01.00 10 Page 8

No constrained dates are allowed in the schedule other than those specified herein. Submit additional constraints to the Contracting Officer for approval on a case by case basis.

3.3.7.1 Project Start Date Milestone and Constraint

The first activity in the project schedule must be a start milestone titled "NTP Acknowledged," which must have a "Start On" constraint date equal to the date that the NTP is acknowledged.

3.3.7.2 End Project Finish Milestone and Constraint

The last activity in the schedule must be a finish milestone titled "End Project."

Constrain the project schedule to the Contract Completion Date in such a way that if the schedule calculates an early finish, then the float calculation for "End Project" milestone reflects positive float on the longest path. If the project schedule calculates a late finish, then the "End Project" milestone float calculation reflects negative float on the longest path. The Government is under no obligation to accelerate Government activities to support a Contractor's early completion.

3.3.7.3 Interim Completion Dates and Constraints

Constrain contractually specified interim completion dates to show negative float when the calculated late finish date of the last activity in that phase is later than the specified interim completion date.

3.3.7.3.1 Start Phase

Use a start milestone as the first activity for a project phase. Call the start milestone "Start Phase X" where "X" refers to the phase of work.

3.3.7.3.2 End Phase

Use a finish milestone as the last activity for a project phase. Call the finish milestone "End Phase X" where "X" refers to the phase of work.

3.3.8 Calendars

Schedule activities on a Calendar to which the activity logically belongs. Develop calendars to accommodate any contract defined work period such as a 7-day calendar for Government Acceptance activities, concrete cure times, etc. Develop the default Calendar to match the physical work plan with non-work periods identified including weekends and holidays. Develop a Seasonal Calendar(s) and assign to seasonally affected activities as applicable.

If an activity is weather sensitive it should be assigned to a calendar showing non-work days on a monthly basis, with the non-work days selected at random across the weeks of the calendar, using the anticipated adverse weather delay work days provided in the Special Contract Requirements .

Assign non-work days over a seven-day week as weather records are compiled on seven-day weeks, which may cause some of the weather related non-work days to fall on weekends .

SECTION 01 32 01.00 10 Page 9

3.3.9 Open Ended Logic

Only two open ended activities are allowed: the first activity "NTP Acknowledged" may have no predecessor logic, and the last activity -"End Project" may have no successor logic.

Predecessor open ended logic may be allowed in a time impact analyses upon the Contracting Officer's approval.

3.3.10 Default Progress Data Disallowed

Actual Start and Finish dates must not automatically update with default mechanisms included in the scheduling software. Updating of the percent complete and the remaining duration of any activity must be independent functions. Disable program features that calculate one of these parameters from the other. Activity Actual Start (AS) and Actual Finish (AF) dates assigned during the updating process must match those dates provided in the Contractor Quality Control Reports. Failure to document the AS and AF dates in the Daily Quality Control report will result in disapproval of the Contractor's schedule.

3.3.11 Out-of-Sequence Progress

Activities that have progressed before all preceding logic has been satisfied (Out-of-Sequence Progress) will be allowed only on a case-by-case basis subject to approval by the Contracting Officer.

Propose logic corrections to eliminate out of sequence progress or justify not changing the sequencing for approval prior to submitting an updated project schedule. Address out of sequence progress or logic changes in the Narrative Report and in the periodic schedule update meetings.

3.3.12 Added and Deleted Activities

Do not delete activities from the project schedule or add new activities to the schedule without approval from the Contracting Officer. Activity ID and description changes are considered new activities and cannot be changed without Contracting Officer approval.

3.3.13 Original Durations

Activity Original Durations (OD) must be reasonable to perform the work item. OD changes are prohibited unless justification is provided and approved by the Contracting Officer.

3.3.14 Leads, Lags, and Start to Finish Relationships

Lags must be reasonable as determined by the Government and not used in place of realistic original durations, must not be in place to artificially absorb float, or to replace proper schedule logic.

a. Leads (negative lags) are prohibited.

b. Start to Finish (SF) relationships are prohibited.

3.3.15 Retained Logic

Schedule calculations must retain the logic between predecessors and successors ("retained logic" mode) even when the successor activity(s) starts and the predecessor activity(s) has not finished (out-of-sequence

SECTION 01 32 01.00 10 Page 10 progress). Software features that in effect sever the tie between predecessor and successor activities when the successor has started and the predecessor logic is not satisfied ("progress override") are not be allowed.

3.3.16 Percent Complete

Update the percent complete for each activity started, based on the realistic assessment of earned value. Activities which are complete but for remaining minor punch list work and which do not restrain the initiation of successor activities may be declared 100 percent complete to allow for proper schedule management.

3.3.17 Remaining Duration

Update the remaining duration for each activity…