This document is a comprehensive project manual for the Volusia County Tax Collectors Office interior renovation project located in DeLand, Florida. The project manual consists of multiple specification sections covering architectural, mechanical, electrical, and finishing work, with Volume 1 detailing general requirements, existing conditions, concrete, masonry, metals, wood, thermal and moisture protection, openings, finishes, specialties, equipment, and furnishings. The project involves selective demolition and renovation of the existing Tax Collectors Office within the Thomas C. Kelley Administration Center, with new work including interior finishes, ceilings, doors, mechanical, electrical, plumbing, and sprinkler systems. The project will be constructed under a lump sum single prime contract, with work to be performed during normal business hours while maintaining minimal disruption to the county's ongoing operations.

The project specifications indicate a comprehensive approach to renovation, with detailed requirements for materials, installation methods, and quality standards. The contract appears to be funded by Volusia County, with the work to be completed under a fixed-price arrangement. The project manual includes extensive technical specifications for each building system, emphasizing quality control, material compatibility, and adherence to current building codes and standards. Specific attention is given to coordination between trades, sustainable design considerations, and ensuring minimal disruption to the existing county operations during the renovation process. The specifications suggest a thorough and methodical approach to the renovation, with significant emphasis on precise execution, material quality, and maintaining the functional integrity of the Tax Collectors Office during the construction period.

View the file

Other files

File Type Posted
Tax_Collector_Interior_Renovations_and_Restoration_(Addendum_#3_Revision).pdf PDF
M1.101_-_FIRST_LEVEL_PLAN_AND_SCHEDULES_MECHANICAL.pdf PDF
E1.102_-_FIRST_LEVEL_PLAN_LIGHTING.pdf PDF
E1.101_-_FIRST_LEVEL_PLAN_POWER.pdf PDF
E0.001_-_ELECTRICAL_LEGEND_NOTES_ABBREVIATIONS.pdf PDF
Attachment_E_-_Additional_Renderings.pdf PDF
Attachment_D_-_Fire_Alarm_Panel.pdf PDF
Tax_Collector_Interior_Renovations_and_Restoration.pdf PDF
MASTER_Construction_Contract.pdf PDF
Attachment_C_-_Staging_2.png PNG image
Attachment_B_-_Staging_1.png PNG image
Attachment_A_-_Parking.png PNG image
COV_Division_27,_IT_Systems_Design_and_Installation_Guidelines_for_A-E.pdf PDF
Sales_Tax_Exemption_Procedure.pdf PDF
PRIME-SUB_FORM.xls XLS spreadsheet
VC_Tax_Collector_DeLand_Office_Project_Manuals_5.15.2025.pdf PDF
VC_Tax_Collector_DeLand_Office_Renovation_Bid_Set_5.15.2025.pdf PDF
Payment_and_Performance_Bond.pdf PDF
Basic_Insurance_Requirements.pdf PDF
Special_Conditions.pdf PDF
Bid_Documents.pdf PDF
VCTCO_Architectural.pdf PDF
VCTCO_Volume_2_specs.pdf PDF
Mechanical.pdf PDF
Fire_Protection.pdf PDF
Electrical.pdf PDF
2025-05-15_-_BID_&_PERMIT_SET_-_Telecommunications.pdf PDF
VOLUSIA_COUNTY_TC_Form_C402.pdf PDF
Plumbing.pdf PDF
staging_(1).png PNG image
Pre-Bid_Meeting_Invitee_Listing.docx DOCX document
Staging.png PNG image
Parking.png PNG image
PRIME-SUB_FORM_for_Contractors_rev._01.15.2025_(lock_before_publishing)_(1).xls XLS spreadsheet
SPECIAL_CONDITIONS_FOR_BIDDERS.docx DOCX document
Show all 35

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Volusia County Tax Collector�s Office

Deland, Florida

Project Manual Volume 1 of 2

May 15, 2025

VOLUSIA COUNTY

TAX COLLECTOR�S OFFICE

TABLE OF CONTENTS

VOLUSIA COUNTY TAX COLLECTOR�S OFFICE

DeLand, FL

TABLE OF CONTENTS OF PROJECT SPECIFICATIONS - Volume 1

DIVISION 1 - GENERAL REQUIREMENTS

01 10 00 Summary of Work 01 25 00 Substitution Procedures 01 26 00 Contract Modification Procedures 01 29 00 Payment Procedures 01 31 00 Project Management & Coordination 01 32 00 Construction Progress Documentation 01 33 00 Submittal Procedures 01 40 00 Quality Requirements 01 42 00 References 01 50 00 Temporary Facilities and Controls 01 60 00 Product Requirements 01 73 00 Execution 01 77 00 Closeout Procedures 01 78 23 Operation & Maintenance Data 01 78 39 Project Record Documents 01 79 00 Demonstration & Training

DIVISION 2 � EXISTING CONDITIONS

02 41 21 Cutting and Patching

DIVISION 3 � CONCRETE

DIVISION 4 � MASONRY

DIVISION 5 � METALS

DIVISION 6 � WOOD, PLASTICS, AND COMPOSITES

06 41 16 Plastic Laminate Clad Architectural Cabinet

DIVISION 7 � THERMAL AND MOISTURE PROTECTION

TABLE OF CONTENTS

DIVISION 8 � OPENINGS

08 11 13 Hollow Metal Doors and Frames 08 14 16 Flush Wood Doors 08 41 13 Aluminum-Framed Entrances and Storefronts 08 71 00 Door Hardware 08 80 00 Glazing

DIVISION 9 � FINISHES

09 22 16 Non-structural Metal Framing 09 29 00 Gypsum Board 09 30 13 Ceramic Tiling 09 51 13 Acoustical Panel Ceilings 09 65 13 Resilient Base and Accessories 09 65 19 Resilient Flooring 09 68 13 Tile Carpeting 09 91 00 Painting and Coatings

DIVISION 10 � SPECIALTIES

10 00 00 Miscellaneous Specialties 10 44 13 Fire Protection Cabinets 10 44 16 Fire Extinguishers 10 51 23 Plastic Lockers 10 56 13 Metal Storage Shelving

DIVISION 11 � EQUIPMENT

11 30 13 Residential Appliances

DIVISION 12 � FURNISHINGS

12 24 13 Roller Window Shades 12 36 61 Solid surfacing Countertops

DIVISION 14 � CONVEYING EQUIPMENT

END OF VOLUME 1

SUMMARY 011000 - 1/3

SECTION 011000 - SUMMARY

PART 1 - GENERAL

1.1 SUMMARY

A. Section Includes:

1. Project information.

2. Work covered by Contract Documents.

3. Access to site.

4. Coordination with occupants.

5. Work restrictions.

6. Specification and drawing conventions.

7. Miscellaneous provisions.

1.2 PROJECT INFORMATION

A. Project Identification: Volusia County Tax Collector�s Office.

1. Project Location: Deland, Florida.

B. Owner: Volusia County.

C. Architect: Silling Associates, Inc.

1.3 WORK COVERED BY CONTRACT DOCUMENTS

A. The Work of Project is defined by the Contract Documents dated May 1, 2025, and consists of the following:

1. The project involves selective demolition and renovation of the existing Volusia County Tax Collector�s Office located in the Thomas C. Kelley Administration Center. New work includes, but not limited to: interior finishes, ceilings, doors, mechanical, electrical, plumbing, and sprinkler work. Work is described on the drawings and in the Project Manual.

B. Type of Contract:

1. Project will be constructed under a lump sum single prime.

1.4 ACCESS TO SITE

A. General: Contractor shall have full use of Project site for construction operations.

B. Use of Site: Limit use of Project site to work in areas to receive work. Do not disturb portions of Project site beyond areas in which the Work is indicated.

SUMMARY 011000 - 2/3

1. Limits: Confine construction operations to areas shown to receive work.

2. Driveways, Walkways and Entrances: Keep driveways loading areas, and entrances serving adjacent building clear and available to Owner, Owner's employees, and emergency vehicles at all times. Do not use these areas for parking or storage of materials.

a. Schedule deliveries to minimize use of driveways and entrances by construction operations.

b. Schedule deliveries to minimize space and time requirements for storage of materials and equipment on-site.

1.5 WORK RESTRICTIONS

A. Work Restrictions, General: Comply with restrictions on construction operations.

1. Comply with limitations on use of public streets and with other requirements of authorities having jurisdiction.

B. On-Site Work Hours:

1. Construction and demolition allowed during normal business hours.

2. Large-scale activities and disturbances must be coordinated around County's existing scheduled council days.

3. Working in an active and occupied County building requires minimizing disruption.

4. Excessive noise, debris, or disruptive construction activity will not be permitted.

5. Contractor may be asked to stop work immediately if disruptions occur and continue after business hours.

C. Controlled Substances: Use of controlled substances on Project site is not permitted.

1.6 SPECIFICATION AND DRAWING CONVENTIONS

A. Specification Content: The Specifications use certain conventions for the style of language and the intended meaning of certain terms, words, and phrases when used in particular situations. These conventions are as follows:

1. Imperative mood and streamlined language are generally used in the Specifications. The words "shall," "shall be," or "shall comply with," depending on the context, are implied where a colon (:) is used within a sentence or phrase.

2. Specification requirements are to be performed by Contractor unless specifically stated otherwise.

B. Division 01 General Requirements: Requirements of Sections in Division 01 apply to the Work of all Sections in the Specifications.

C. Drawing Coordination: Requirements for materials and products identified on Drawings are described in detail in the Specifications. One or more of the following are used on Drawings to identify materials and products:

SUMMARY 011000 - 3/3

1. Terminology: Materials and products are identified by the typical generic terms used in the individual Specifications Sections.

2. Abbreviations: Materials and products are identified by abbreviations published as part of the U.S. National CAD Standard and scheduled on Drawings.

3. Keynoting: Materials and products are identified by reference keynotes referencing Specification Section numbers found in this Project Manual.

PART 2 - PRODUCTS (Not Used)

PART 3 - EXECUTION (Not Used)

END OF SECTION 011000

SUBSTITUTION

PROCEDURES

012500 - 1/4

SECTION 012500 - SUBSTITUTION PROCEDURES

PART 1 - GENERAL

1.1 SUMMARY

A. Section includes administrative and procedural requirements for substitutions.

1.2 DEFINITIONS

A. Substitutions: Changes in products, materials, equipment, and methods of construction from those required by the Contract Documents and proposed by Contractor.

1. Substitutions for Cause: Changes proposed by Contractor that are required due to changed Project conditions, such as unavailability of product, regulatory changes, or unavailability of required warranty terms.

2. Substitutions for Convenience: Changes proposed by Contractor or Owner that are not required to meet other Project requirements but may offer advantage to Contractor or Owner.

1.3 ACTION SUBMITTALS

A. Substitution Requests: Submit one PDF electronic copy of each request for consideration.

Identify product or fabrication or installation method to be replaced. Include Specification Section number and title and Drawing numbers and titles.

1. Substitution Request Form: Use CSI Form 13.1A.

2. Documentation: Show compliance with requirements for substitutions and the following, as applicable:

a. Statement indicating why specified products or fabrication or installation cannot be provided, if applicable.

b. Coordination information, including a list of changes or revisions needed to other parts of the Work and to construction performed by Owner and separate contractors, that will be necessary to accommodate proposed substitution.

c. Detailed comparison of significant qualities of proposed substitution with those of the Work specified. Include annotated copy of the applicable Specification Section. Significant qualities may include attributes such as performance, weight, size, durability, visual effect, sustainable design characteristics, warranties, and specific features and requirements indicated.

Indicate deviations, if any, from the Work specified.

d. Product Data, including drawings and descriptions of products and fabrication and installation procedures.

e. Samples, where applicable or requested.

SUBSTITUTION

PROCEDURES

012500 - 2/4

f. Certificates and qualification data, where applicable or requested.

g. List of similar installations for completed projects with project names and addresses and names and addresses of architects and owners.

h. Material test reports from a qualified testing agency indicating and interpreting test results for compliance with requirements indicated.

i. Research reports evidencing compliance with building code in effect for

Project, from ICC-ES.

j. Detailed comparison of Contractor's construction schedule using proposed substitution with products specified for the Work, including effect on the overall Contract Time. If specified product or method of construction cannot be provided within the Contract Time, include letter from manufacturer, on manufacturer's letterhead, stating date of receipt of purchase order, lack of availability, or delays in delivery.

k. Cost information, including a proposal of change, if any, in the Contract Sum.

l. Contractor's certification that proposed substitution complies with requirements in the Contract Documents except as indicated in substitution request, is compatible with related materials, and is appropriate for applications indicated.

m. Contractor's waiver of rights to additional payment or time that may subsequently become necessary because of failure of proposed substitution to produce indicated results.

3. Architect's Action: If necessary, Architect will request additional information or documentation for evaluation within seven days of receipt of a request for substitution. Architect will notify Contractor of acceptance or rejection of proposed substitution within 15 days of receipt of request, or seven days of receipt of additional information or documentation, whichever is later.

a. Forms of Acceptance: Change Order, Construction Change Directive, or Architect's Supplemental Instructions for minor changes in the Work.

b. Use product specified if Architect does not issue a decision on use of a proposed substitution within time allocated.

1.4 QUALITY ASSURANCE

A. Compatibility of Substitutions: Investigate and document compatibility of proposed substitution with related products and materials. Engage a qualified testing agency to perform compatibility tests recommended by manufacturers.

1.5 PROCEDURES

A. Coordination: Revise or adjust affected work as necessary to integrate work of the approved substitutions.

SUBSTITUTION

PROCEDURES

012500 - 3/4

PART 2 - PRODUCTS

2.1 SUBSTITUTIONS

A. Substitutions for Cause: Submit requests for substitution immediately on discovery of need for change, but not later than 15 days prior to time required for preparation and review of related submittals.

1. Conditions: Architect will consider Contractor's request for substitution when the following conditions are satisfied. If the following conditions are not satisfied, Architect will return requests without action, except to record noncompliance with these requirements:

a. Requested substitution is consistent with the Contract Documents and will produce indicated results.

b. Substitution request is fully documented and properly submitted.

c. Requested substitution will not adversely affect Contractor's construction schedule.

d. Requested substitution has received necessary approvals of authorities having jurisdiction.

e. Requested substitution is compatible with other portions of the Work.

f. Requested substitution has been coordinated with other portions of the Work.

g. Requested substitution provides specified warranty.

h. If requested substitution involves more than one contractor, requested substitution has been coordinated with other portions of the Work, is uniform and consistent, is compatible with other products, and is acceptable to all contractors involved.

B. Substitutions for Convenience: Architect will consider requests for substitution if received within 60 days after the Notice to Proceed. Requests received after that time may be considered or rejected at discretion of Architect. Requests prior to award of the Bid will not be reviewed.

1. Conditions: Architect will consider Contractor's request for substitution when the following conditions are satisfied. If the following conditions are not satisfied, Architect will return requests without action, except to record noncompliance with these requirements:

a. Requested substitution offers Owner a substantial advantage in cost, time, energy conservation, or other considerations, after deducting additional responsibilities Owner must assume. Owner's additional responsibilities may include compensation to Architect for redesign and evaluation services, increased cost of other construction by Owner, and similar considerations.

b. Requested substitution does not require extensive revisions to the Contract Documents.

c. Requested substitution is consistent with the Contract Documents and will produce indicated results.

d. Substitution request is fully documented and properly submitted.

SUBSTITUTION

PROCEDURES

012500 - 4/4

e. Requested substitution will not adversely affect Contractor's construction schedule.

f. Requested substitution has received necessary approvals of authorities having jurisdiction.

g. Requested substitution is compatible with other portions of the Work.

h. Requested substitution has been coordinated with other portions of the Work.

i. Requested substitution provides specified warranty.

j. If requested substitution involves more than one contractor, requested substitution has been coordinated with other portions of the Work, is uniform and consistent, is compatible with other products, and is acceptable to all contractors involved.

END OF SECTION 012500

CONTRACT MODIFICATION

PROCEDURES

012600 - 1/2

SECTION 012600 - CONTRACT MODIFICATION PROCEDURES

PART 1 - GENERAL

1.1 SUMMARY

A. Section includes administrative and procedural requirements for handling and processing Contract modifications.

1.2 MINOR CHANGES IN THE WORK

A. Architect will issue supplemental instructions authorizing minor changes in the Work, not involving adjustment to the Contract Sum or the Contract Time, on AIA Document G710, "Architect's Supplemental Instructions."

1.3 PROPOSAL REQUESTS

A. Owner-Initiated Proposal Requests: Architect will issue a detailed description of proposed changes in the Work that may require adjustment to the Contract Sum or the Contract Time. If necessary, the description will include supplemental or revised Drawings and Specifications.

1. Work Change Proposal Requests issued by Architect are not instructions either to stop work in progress or to execute the proposed change.

2. Within time specified in Proposal Request after receipt of Proposal Request, submit a quotation estimating cost adjustments to the Contract Sum and the Contract Time necessary to execute the change.

a. Include a list of quantities of products required or eliminated and unit costs, with total amount of purchases and credits to be made. If requested, furnish survey data to substantiate quantities.

b. Indicate applicable taxes, delivery charges, equipment rental, and amounts of trade discounts.

c. Include costs of labor and supervision directly attributable to the change.

d. Include an updated Contractor's construction schedule that indicates the effect of the change, including, but not limited to, changes in activity duration, start and finish times, and activity relationship. Use available total float before requesting an extension of the Contract Time.

e. Quotation Form: Use forms acceptable to Architect.

B. Contractor-Initiated Proposals: If latent or changed conditions require modifications to the Contract, Contractor may initiate a claim by submitting a request for a change to Architect.

CONTRACT MODIFICATION

PROCEDURES

012600 - 2/2

1. Include a statement outlining reasons for the change and the effect of the change on the Work. Provide a complete description of the proposed change. Indicate the effect of the proposed change on the Contract Sum and the Contract Time.

2. Include a list of quantities of products required or eliminated and unit costs, with total amount of purchases and credits to be made. If requested, furnish survey data to substantiate quantities.

3. Indicate applicable taxes, delivery charges, equipment rental, and amounts of trade discounts.

4. Include costs of labor and supervision directly attributable to the change.

5. Include an updated Contractor's construction schedule that indicates the effect of the change, including, but not limited to, changes in activity duration, start and finish times, and activity relationship. Use available total float before requesting an extension of the Contract Time.

6. Comply with requirements in Section 012500 "Substitution Procedures" if the proposed change requires substitution of one product or system for product or system specified.

7. Proposal Request Form: Use form acceptable to Architect.

1.4 CHANGE ORDER PROCEDURES

A. On Owner's approval of a Work Changes Proposal Request, Architect will issue a Change Order for signatures of Owner and Contractor on AIA Document G701.

1.5 CONSTRUCTION CHANGE DIRECTIVE

A. Construction Change Directive: Architect may issue a Construction Change Directive on AIA Document G714. Construction Change Directive instructs Contractor to proceed with a change in the Work, for subsequent inclusion in a Change Order.

1. Construction Change Directive contains a complete description of change in the Work. It also designates method to be followed to determine change in the Contract Sum or the Contract Time.

B. Documentation: Maintain detailed records on a time and material basis of work required by the Construction Change Directive.

1. After completion of change, submit an itemized account and supporting data necessary to substantiate cost and time adjustments to the Contract.

PART 2 - PRODUCTS (Not Used)

END OF SECTION 012600

PAYMENT PROCEDURES 012900 - 1/5

SECTION 012900 - PAYMENT PROCEDURES

PART 1 - GENERAL

1.1 SUMMARY

A. Section includes administrative and procedural requirements necessary to prepare and process Applications for Payment.

1.2 DEFINITIONS

A. Schedule of Values: A statement furnished by Contractor allocating portions of the Contract Sum to various portions of the Work and used as the basis for reviewing Contractor's Applications for Payment.

1.3 SCHEDULE OF VALUES

A. Coordination: Coordinate preparation of the schedule of values with preparation of Contractor's construction schedule.

1. Coordinate line items in the schedule of values with other required administrative forms and schedules, including the following:

a. Application for Payment forms with continuation sheets.

b. Submittal schedule.

c. Items required to be indicated as separate activities in Contractor's construction schedule.

2. Submit the schedule of values to Architect at earliest possible date, but no later than seven days before the date scheduled for submittal of initial Applications for Payment.

B. Format and Content: Use Project Manual table of contents as a guide to establish line items for the schedule of values. Provide at least one line item for each Specification Section.

1. Identification: Include the following Project identification on the schedule of values:

a. Project name and location.

b. Name of Architect.

c. Contractor's name and address.

d. Date of submittal.

2. Arrange schedule of values consistent with format of AIA Document G703.

PAYMENT PROCEDURES 012900 - 2/5

3. Arrange the schedule of values in tabular form with separate columns to indicate the following for each item listed:

a. Description of the Work.

b. Change Orders (numbers) that affect value.

c. Dollar value of the following, as a percentage of the Contract Sum to nearest one-hundredth percent, adjusted to total 100 percent.

1) Labor.

2) Materials.

3) Equipment.

4. Provide a breakdown of the Contract Sum in enough detail to facilitate continued evaluation of Applications for Payment and progress reports. Coordinate with Project Manual table of contents. Provide multiple line items for principal subcontract amounts in excess of five percent of the Contract Sum.

a. Include separate line items under Contractor and principal subcontracts for Project closeout requirements in an amount totaling five percent of the Contract Sum and subcontract amount.

5. Round amounts to nearest whole dollar; total shall equal the Contract Sum.

6. Provide a separate line item in the schedule of values for each part of the Work where Applications for Payment may include materials or equipment purchased or fabricated and stored, but not yet installed.

a. Differentiate between items stored on-site and items stored off-site. If required, include evidence of insurance.

7. Provide separate line items in the schedule of values for initial cost of materials, for each subsequent stage of completion, and for total installed value of that part of the Work.

8. Purchase Contracts: Provide a separate line item in the schedule of values for each purchase contract. Show line-item value of purchase contract. Indicate owner payments or deposits, if any, and balance to be paid by Contractor.

9. Each item in the schedule of values and Applications for Payment shall be complete. Include total cost and proportionate share of general overhead and profit for each item.

a. Temporary facilities and other major cost items that are not direct cost of actual work-in-place may be shown either as separate line items in the schedule of values or distributed as general overhead expense, at Contractor's option.

10. Schedule Updating: Update and resubmit the schedule of values before the next Applications for Payment when Change Orders or Construction Change Directives result in a change in the Contract Sum.

PAYMENT PROCEDURES 012900 - 3/5

1.4 APPLICATIONS FOR PAYMENT

A. Each Application for Payment following the initial Application for Payment shall be consistent with previous applications and payments as certified by Architect and paid for by Owner.

1. Initial Application for Payment, Application for Payment at time of Substantial Completion, and final Application for Payment involve additional requirements.

B. Payment Application Times: The date for each progress payment is indicated in the Agreement between Owner and Contractor. The period of construction work covered by each Application for Payment is the period indicated in the Agreement.

C. Application for Payment Forms: Use AIA Document G702 and AIA Document G703 as form for Applications for Payment.

D. Application Preparation: Complete every entry on form. Notarize and execute by a person authorized to sign legal documents on behalf of Contractor. Architect will return incomplete applications without action.

1. Entries shall match data on the schedule of values and Contractor's construction schedule. Use updated schedules if revisions were made.

2. Include amounts for work completed following previous Application for Payment, whether or not payment has been received. Include only amounts for work completed at time of Application for Payment.

3. Include amounts of Change Orders and Construction Change Directives issued before last day of construction period covered by application.

4. Indicate separate amounts for work being carried out under Owner-requested project acceleration.

E. Stored Materials: Include in Application for Payment amounts applied for materials or equipment purchased or fabricated and stored, but not yet installed. Differentiate between items stored on-site and items stored off-site.

1. Provide certificate of insurance, evidence of transfer of title to Owner, and consent of surety to payment, for stored materials.

2. Provide supporting documentation that verifies amount requested, such as paid invoices. Match amount requested with amounts indicated on documentation; do not include overhead and profit on stored materials.

3. Provide summary documentation for stored materials indicating the following:

a. Value of materials previously stored and remaining stored as of date of previous Applications for Payment.

b. Value of previously stored materials put in place after date of previous Application for Payment and on or before date of current Application for Payment.

c. Value of materials stored since date of previous Application for Payment and remaining stored as of date of current Application for Payment.

PAYMENT PROCEDURES 012900 - 4/5

F. Transmittal: Submit three signed and notarized original copies of each Application for Payment to Architect by a method ensuring receipt within 24 hours. One copy shall include waivers of lien and similar attachments if required.

1. Transmit each copy with a transmittal form listing attachments and recording appropriate information about application.

G. Waivers of Mechanic's Lien: With each Application for Payment, submit waivers of mechanic's lien from entities lawfully entitled to file a mechanic's lien arising out of the Contract and related to the Work covered by the payment.

1. Submit partial waivers on each item for amount requested in previous application, after deduction for retainage, on each item.

2. When an application shows completion of an item, submit conditional final or full waivers.

3. Owner reserves the right to designate which entities involved in the Work must submit waivers.

4. Waiver Forms: Submit executed waivers of lien on forms acceptable to Owner.

H. Initial Application for Payment: Administrative actions and submittals that must precede or coincide with submittal of first Application for Payment include the following:

1. List of subcontractors.

2. Schedule of values.

3. Contractor's construction schedule (preliminary if not final).

4. Schedule of unit prices.

5. Submittal schedule (preliminary if not final).

6. List of Contractor's staff assignments.

7. List of Contractor's principal consultants.

8. Copies of building permits.

9. Copies of authorizations and licenses from authorities having jurisdiction for performance of the Work.

10. Report of preconstruction conference.

11. Certificates of insurance and insurance policies.

12. Performance and payment bonds.

I. Application for Payment at Substantial Completion: After Architect issues the Certificate of Substantial Completion, submit an Application for Payment showing 100 percent completion for portion of the Work claimed as substantially complete.

1. Include documentation supporting claim that the Work is substantially complete and a statement showing an accounting of changes to the Contract Sum.

2. This application shall reflect Certificate(s) of Substantial Completion issued previously for Owner occupancy of designated portions of the Work.

J. Final Payment Application: After completing Project closeout requirements, submit final Application for Payment with releases and supporting documentation not previously submitted and accepted, including, but not limited, to the following:

1. Evidence of completion of Project closeout requirements.

PAYMENT PROCEDURES 012900 - 5/5

2. Insurance certificates for products and completed operations where required and proof that taxes, fees, and similar obligations were paid.

3. Updated final statement, accounting for final changes to the Contract Sum.

4. AIA Document G706, "Contractor's Affidavit of Payment of Debts and Claims."

5. AIA Document G706A, "Contractor's Affidavit of Release of Liens."

6. AIA Document G707, "Consent of Surety to Final Payment."

7. Final meter readings for utilities, a measured record of stored fuel, and similar data as of date of Substantial Completion or when Owner took possession of and assumed responsibility for corresponding elements of the Work.

PART 2 - PRODUCTS (Not Used)

END OF SECTION 012900

PROJECT MANAGEMENT

AND COORDINATION

013100 - 1/10

SECTION 013100 - PROJECT MANAGEMENT AND COORDINATION

PART 1 - GENERAL

1.1 SUMMARY

A. Section includes administrative provisions for coordinating construction operations on Project including, but not limited to, the following:

1. General coordination procedures.

2. Requests for Information (RFIs).

3. Project meetings.

4. Coordination Drawings.

B. Each contractor shall participate in coordination requirements. Certain areas of responsibility are assigned to a specific contractor.

1.2 DEFINITIONS

A. RFI: Request from Owner, Architect, or Contractor seeking information required by or clarifications of the Contract Documents.

1.3 INFORMATIONAL SUBMITTALS

A. Subcontract List: Prepare a written summary identifying individuals or firms proposed for each portion of the Work, including those who are to furnish products or equipment fabricated to a special design. Include the following information in tabular form:

1. Name, address, and telephone number of entity performing subcontract or supplying products.

2. Number and title of related Specification Section(s) covered by subcontract.

3. Drawing number and detail references, as appropriate, covered by subcontract.

B. Key Personnel Names: Within 15 days of starting construction operations, submit a list of key personnel assignments, including superintendent and other personnel in attendance at Project site. Identify individuals and their duties and responsibilities; list addresses and telephone numbers, including home, office, and cellular telephone numbers and e-mail addresses. Provide names, addresses, and telephone numbers of individuals assigned as alternates in the absence of individuals assigned to Project.

1. Post copies of list in project meeting room, in temporary field office, and by each temporary telephone. Keep list current at all times.

PROJECT MANAGEMENT

AND COORDINATION

013100 - 2/10

1.4 GENERAL COORDINATION PROCEDURES

A. Coordination: Coordinate construction operations included in different Sections of the Specifications to ensure efficient and orderly installation of each part of the Work.

Coordinate construction operations, included in different Sections, that depend on each other for proper installation, connection, and operation.

1. Schedule construction operations in sequence required to obtain the best results where installation of one part of the Work depends on installation of other components, before or after its own installation.

2. Coordinate installation of different components to ensure maximum performance and accessibility for required maintenance, service, and repair.

3. Make adequate provisions to accommodate items scheduled for later installation.

B. Prepare memoranda for distribution to each party involved, outlining special procedures required for coordination. Include such items as required notices, reports, and list of attendees at meetings.

1. Prepare similar memoranda for Owner and separate contractors if coordination of their Work is required.

C. Administrative Procedures: Coordinate scheduling and timing of required administrative procedures with other construction activities to avoid conflicts and to ensure orderly progress of the Work. Such administrative activities include, but are not limited to, the following:

1. Preparation of Contractor's construction schedule.

2. Preparation of the schedule of values.

3. Installation and removal of temporary facilities and controls.

4. Delivery and processing of submittals.

5. Progress meetings.

6. Preinstallation conferences.

7. Project closeout activities.

8. Startup and adjustment of systems.

D. Conservation: Coordinate construction activities to ensure that operations are carried out with consideration given to conservation of energy, water, and materials. Coordinate use of temporary utilities to minimize waste.

1. Salvage materials and equipment involved in performance of, but not actually incorporated into, the Work. See other Sections for disposition of salvaged materials that are designated as Owner's property.

1.5 REQUESTS FOR INFORMATION (RFIs)

A. General: Immediately on discovery of the need for additional information or interpretation of the Contract Documents, Contractor shall prepare and submit an RFI in the form specified.

1. Architect will return RFIs submitted to Architect by other entities controlled by Contractor with no response.

PROJECT MANAGEMENT

AND COORDINATION

013100 - 3/10

2. Coordinate and submit RFIs in a prompt manner so as to avoid delays in Contractor's work or work of subcontractors.

B. Content of the RFI: Include a detailed, legible description of item needing information or interpretation and the following:

1. Project name.

2. Project number.

3. Date.

4. Name of Contractor.

5. Name of Architect.

6. RFI number, numbered sequentially.

7. RFI subject.

8. Specification Section number and title and related paragraphs, as appropriate.

9. Drawing number and detail references, as appropriate.

10. Field dimensions and conditions, as appropriate.

11. Contractor's suggested resolution. If Contractor's suggested resolution impacts the

Contract Time or the Contract Sum, Contractor shall state impact in the RFI.

12. Contractor's signature.

13. Attachments: Include sketches, descriptions, measurements, photos, Product Data, Shop Drawings, coordination drawings, and other information necessary to fully describe items needing interpretation.

a. Include dimensions, thicknesses, structural grid references, and details of affected materials, assemblies, and attachments on attached sketches.

C. RFI Forms: Software-generated form with substantially the same content as indicated above, acceptable to Architect.

1. Attachments shall be electronic files in Adobe Acrobat PDF format.

D. Architect's Action: Architect will review each RFI, determine action required, and respond.

Allow seven working days for Architect's response for each RFI. RFIs received by Architect after 1:00 p.m. will be considered as received the following working day.

1. The following Contractor-generated RFIs will be returned without action:

a. Requests for approval of submittals.

b. Requests for approval of substitutions.

c. Requests for approval of Contractor's means and methods.

d. Requests for coordination information already indicated in the Contract

Documents.

e. Requests for adjustments in the Contract Time or the Contract Sum.

f. Requests for interpretation of Architect's actions on submittals.

g. Incomplete RFIs or inaccurately prepared RFIs.

2. Architect's action may include a request for additional information, in which case Architect's time for response will date from time of receipt of additional information.

PROJECT MANAGEMENT

AND COORDINATION

013100 - 4/10

3. Architect's action on RFIs that may result in a change to the Contract Time or the Contract Sum may be eligible for Contractor to submit Change Proposal according to Section 012600 "Contract Modification Procedures."

a. If Contractor believes the RFI response warrants change in the Contract Time or the Contract Sum, notify Architect in writing within 10 days of receipt of the RFI response.

E. RFI Log: Prepare, maintain, and submit a tabular log of RFIs organized by the RFI number.

Submit log at each job meeting. Software log with not less than the following:

1. Project name.

2. Name and address of Contractor.

3. Name and address of Architect.

4. RFI number including RFIs that were returned without action or withdrawn.

5. RFI description.

6. Date the RFI was submitted.

7. Date Architect�s response was received.

F. On receipt of Architect's action, update the RFI log and immediately distribute the RFI response to affected parties. Review response and notify Architect within seven days if Contractor disagrees with response.

1. Identification of related Minor Change in the Work, Construction Change Directive, and Proposal Request, as appropriate.

2. Identification of related Field Order, Work Change Directive, and Proposal Request, as appropriate.

1.6 PROJECT MEETINGS

A. General: Schedule and conduct meetings and conferences at Project site unless otherwise indicated.

1. Attendees: Inform participants and others involved, and individuals whose presence is required, of date and time of each meeting. Notify Owner and Architect of scheduled meeting dates and times.

2. Agenda: Prepare the meeting agenda. Distribute the agenda to all invited attendees.

3. Minutes: Entity responsible for conducting meeting will record significant discussions and agreements achieved. Distribute the meeting minutes to everyone concerned, including Owner and Architect, within three days of the meeting.

B. Preconstruction Conference: Schedule and conduct a preconstruction conference before starting construction, at a time convenient to Owner and Architect, but no later than 15 days after execution of the Agreement.

1. Conduct the conference to review responsibilities and personnel assignments.

2. Attendees: Authorized representatives of Owner, Owner's Commissioning Authority, Architect, and their consultants; Contractor and its superintendent;

PROJECT MANAGEMENT

AND COORDINATION

013100 - 5/10 major subcontractors; suppliers; and other concerned parties shall attend the conference. Participants at the conference shall be familiar with Project and authorized to conclude matters relating to the Work.

3. Agenda: Discuss items of significance that could affect progress, including the following:

a. Tentative construction schedule.

b. Phasing.

c. Critical work sequencing and long-lead items.

d. Designation of key personnel and their duties.

e. Lines of communications.

f. Procedures for processing field decisions and Change Orders.

g. Procedures for RFIs.

h. Procedures for testing and inspecting.

i. Procedures for processing Applications for Payment.

j. Submittal procedures.

k. Preparation of record documents.

l. Use of the premises and existing building.

m. Work restrictions.

n. Working hours.

o. Owner's occupancy requirements.

p. Responsibility for temporary facilities and controls.

q. Procedures for moisture and mold control.

r. Procedures for disruptions and shutdowns.

s. Parking availability.

t. Office, work, and storage areas.

u. Equipment deliveries and priorities.

v. First aid.

w. Security.

x. Progress cleaning.

4. Minutes: Entity responsible for conducting meeting will record and distribute meeting minutes.

C. Pre-Installation Conferences: Conduct a pre-installation conference at Project site before each construction activity that requires coordination with other construction.

1. Attendees: Installer and representatives of manufacturers and fabricators involved in or affected by the installation and its coordination or integration with other materials and installations that have preceded or will follow, shall attend the meeting. Advise Architect, and Owner's Commissioning Authority of scheduled meeting dates.

2. Agenda: Review progress of other construction activities and preparations for the particular activity under consideration, including requirements for the following:

a. Manufacturer's written instructions.

b. Warranty requirements.

c. Compatibility of materials.

d. Acceptability of substrates.

e. Temporary facilities and controls.

f. Space and access limitations.

PROJECT MANAGEMENT

AND COORDINATION

013100 - 6/10

g. Regulations of authorities having jurisdiction.

h. Testing and inspecting requirements.

i. Installation procedures.

j. Coordination with other work.

k. Required performance results.

l. Protection of adjacent work.

m. Protection of construction and personnel.

3. Record significant conference discussions, agreements, and disagreements, including required corrective measures and actions.

4. Reporting: Distribute minutes of the meeting to each party present and to other parties requiring information.

5. Do not proceed with installation if the conference cannot be successfully concluded.

Initiate whatever actions are necessary to resolve impediments to performance of the Work and reconvene the conference at earliest feasible date.

D. Project Closeout Conference: Schedule and conduct a project closeout conference, at a time convenient to Owner and Architect, but no later than 90 days prior to the scheduled date of Substantial Completion.

1. Conduct the conference to review requirements and responsibilities related to Project closeout.

2. Attendees: Authorized representatives of Owner, Owner's Commissioning Authority, Architect, and their consultants; Contractor and its superintendent; major subcontractors; suppliers; and other concerned parties shall attend the meeting.

Participants at the meeting shall be familiar with Project and authorized to conclude matters relating to the Work.

3. Agenda: Discuss items of significance that could affect or delay Project closeout, including the following:

a. Preparation of record documents.

b. Procedures required prior to inspection for Substantial Completion and for final inspection for acceptance.

c. Submittal of written warranties.

d. Requirements for preparing operations and maintenance data.

e. Requirements for delivery of material samples, attic stock, and spare parts.

f. Requirements for demonstration and training.

g. Preparation of Contractor's punch list.

h. Procedures for processing Applications for Payment at Substantial Completion and for final payment.

i. Submittal procedures.

j. Installation of Owner's furniture, fixtures, and equipment.

k. Responsibility for removing temporary facilities and controls.

4. Minutes: Entity conducting meeting will record and distribute meeting minutes.

E. Progress Meetings: Conduct progress meetings at biweekly intervals.

1. Coordinate dates of meetings with preparation of payment requests.

2. Attendees: In addition to representatives of Owner, Owner's Commissioning Authority and Architect, each contractor, subcontractor, supplier, and other entity

PROJECT MANAGEMENT

AND COORDINATION

013100 - 7/10 concerned with current progress or involved in planning, coordination, or performance of future activities shall be represented at these meetings. All participants at the meeting shall be familiar with Project and authorized to conclude matters relating to the Work.

3. Agenda: Review and correct or approve minutes of previous progress meeting.

Review other items of significance that could affect progress. Include topics for discussion as appropriate to status of Project.

a. Contractor's Construction Schedule: Review progress since the last meeting.

Determine whether each activity is on time, ahead of schedule, or behind schedule, in relation to Contractor's construction schedule. Determine how construction behind schedule will be expedited; secure commitments from parties involved to do so. Discuss whether schedule revisions are required to ensure that current and subsequent activities will be completed within the Contract Time.

1) Review schedule for next period.

b. Review present and future needs of each entity present, including the following:

1) Interface requirements.

2) Sequence of operations.

3) Status of submittals.

4) Deliveries.

5) Off-site fabrication.

6) Access.

7) Site utilization.

8) Temporary facilities and controls.

9) Progress cleaning.

10) Quality and work standards.

11) Status of correction of deficient items.

12) Field observations.

13) Status of RFIs.

14) Status of proposal requests.

15) Pending changes.

16) Status of Change Orders.

17) Pending claims and disputes.

18) Documentation of information for payment requests.

4. Minutes: Entity responsible for conducting the meeting will record and distribute the meeting minutes to each party present and to parties requiring information.

a. Schedule Updating: Revise Contractor's construction schedule after each progress meeting where revisions to the schedule have been made or recognized. Issue revised schedule concurrently with the report of each meeting.

1.7 COORDINATION DRAWINGS

1. COORDINATION DRAWING AND BIM MODEL REQUIREMENTS

PROJECT MANAGEMENT

AND COORDINATION

013100 - 8/10

A. All major sub-contractors will participate in the creation of coordination drawings.

Coordination participants include: HVAC Contractor, Plumbing Contractor, Electrical Contractor (including telecom), Fire Protection Contractor and General Trades Contractor.

B. Coordination Drawings are to be prepared utilizing a Auto-Desk �Revit� three dimensional Building Information Modeling (BIM) software. The Architectural, Mechanical, Plumbing, Fire Suppression, and Electrical Construction Documents were prepared utilizing Revit BIM software. The level of development varies amongst the A/E models and portions of the Construction Documents were not developed three dimensionally. The A/E will share the model information with the Contractors to facilitate the preparation of coordination drawings if requested by the Contractor. The Contractor assumes all responsibility for accuracy, completeness and model level development for development of the Coordination Drawings.

1. The BIM will be developed with true solid modeling, object oriented software. Clash d e t e c t i o n s o f t w a r e i s to be utilized for development of the BIM by all Coordination Participants.

C. Coordination Drawings are required for all of the building.

1. Field verify all existing conditions when preparing Coordination Drawings in renovated areas. Incorporate findings into the BIM.

D. The HVAC Contractor shall manage the model and coordinate activities of all Coordination Participants. Each Coordination Participant shall prepare their portion of the Work utilizing BIM and clash detection software utilized by the HVAC Contractor. Each Coordination Participant will obtain or provide at their cost, trained personnel, hardware and software necessary to complete the 3D BIM.

1. Each Coordination Participant is responsible for updating their portion of the Work on a weekly basis and uploading it to the final model.

2. The HVAC Contractor is responsible for producing a weekly updated combined BIM utilizing the clash detection software.

3. Each Coordination Participant shall attend a weekly meeting to identify and resolve spatial interferences. These meetings will be facilitated by the HVAC Contractor. The weekly meetings will be full day working sessions during which conflict resolution will be completed, to the extent possible, during the meeting.

The model will be presented onto a common screen for the Coordination Participants to review the progress and facilitate the coordination process.

4. The HVAC Contractor will be responsible for establishing an electronic workspace at the project site facilitating the coordination process, and providing an FTP site or other means, such as an onsite server for the purpose of efficient and timely transfer of coordination files.

5. The Coordination Participants will upload their coordination files as often as necessary to maintain the coordination schedule.

E. Refer to the General Conditions for additional Coordination Drawing workflow requirements between the various Contractors.

PROJECT MANAGEMENT

AND COORDINATION

013100 - 9/10

SCHEDULE 1 - COORDINATION DRAWINGS

A. Prepare coordination drawings to a scale of ¼ inch equals 1 foot 0 inch or larger, with BIM software, detailing major elements, components and systems of mechanical equipment and materials in relationship with other systems, installations, and building components. Indicate locations where sequencing and coordination of installations are of importance to the efficient flow of the Work, including (but not necessarily limited to) the following:

1. Indicate the proposed location of piping, ductwork, equipment and materials.

Include the following:

a. Clearances for installation and maintaining insulation.

b. Clearances for servicing and maintaining equipment, including filter removal, and space for equipment disassembly required for periodic maintenance.

c. Equipment connections and support details.

d. Exterior wall, roof and foundation penetrations.

e. Fire-rated wall and floor penetrations.

f. Sizes and locations of required concrete pads and bases.

g. Planned piping layout, including valve and specialty locations and valve stem movement.

h. Planned duct systems layout, including elbow radii and duct accessories.

i. Clearances for servicing and maintaining equipment, including space for equipment disassembly required for periodic maintenance.

j. Equipment service connections and support details.

k. Mechanical equipment yard with all equipment and underground utilities.

2. Indicate scheduling sequencing, movement and positioning of large equipment into or on the building during construction.

3. Prepare floor plans, elevations, and details to indicate penetrations in floors, walls, and ceilings and their relationship to other penetrations and installations.

4. Prepare reflected ceiling plans to coordinate and integrate installations, air outlets and inlets, light fixtures, communication systems components, sprinklers and other ceiling mounted items.

5. Coordinate electrical and mechanical requirements of equipment. Provide necessary changes to comply with manufacturer�s requirements.

6. Construction documents are diagrammatic. Contractor shall coordinate and provide changes to accommodate minor relocation of equipment.

7. HVAC Contractor shall prepare electronic files (PDF format) of Coordination Drawings and submit the files to the Construction Manager, A/E and CxA, if applicable.

a. Multiple submissions may be required to resolve different areas of the project and parallel Work Sequence events.

SCHEDULE 2 - APPROVAL

PROJECT MANAGEMENT

AND COORDINATION

013100 - 10/10

A. Each Coordination Participant must sign off on the final Coordination Drawings. This Signature indicates the participating contractor has reviewed and accepted the Coordination Drawings and shall complete installation as indicated on the Coordination Drawings.

B. After Contractor�s written Approval of Coordination Drawings, Contractors and all participants shall be responsible for resolving conflicts and determining the method used to resolve interferences not previously identified.

C. Modifications required as a result of failure to resolve interferences, shall be paid for by the responsible Contractor.

PART 2 - PRODUCTS (Not Used)

END OF SECTION 013100

CONSTRUCTION PROGRESS

DOCUMENTATION

013200 - 1/7

SECTION 013200 - CONSTRUCTION PROGRESS DOCUMENTATION

PART 1 - GENERAL

1.1 SUMMARY

A. Section includes administrative and procedural requirements for documenting the progress of construction during performance of the Work, including the following:

1…

This is the start of the file's text. The full file is on GovTribe.

File details come from the government source that posted it. Updated .