This solicitation seeks proposals for the USS ROSS (DDG 71) Extended Dry-Docking Selected Restricted Availability (EDSRA) to be performed from July 2022 through November 2023. The Naval Sea Systems Command will award a single-award, cost-plus-fixed-fee contract for maintenance, modernization, and repair work. Interested parties must register in the System for Award Management and the Procurement Integrated Enterprise Environment to receive solicitation attachments and submit proposals, with proposals due in July 2022. The work includes over 200 maintenance items and will be performed at East or Gulf Coast facilities. The contractor must have extensive shipyard capabilities and qualified personnel to complete all required work during the 16-month period of performance.
View the file
Other files
Show all 23
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Prioritized List
| USS ROSS (DDG 71) FY22 EDSRA - J-10 Milestone Reports Due | |||||
| No. | Work Item | Title | Para. | Milestone | |
| 110-11-001 | Underwater Hull; inspect and repair | 3.2.1 | 20% O&I Docking | ||
| 3.4.1 | 20% O&I Docking | ||||
| 113-11-001 | Drain Well; repair | 3.4.2.8 | 20% O&I Docking | ||
| 123-10-002 | Auxiliary Machinery Room Number One Bilge; repair | 3.4.1 | 20% O&I Docking | ||
| 3.5.1 | 20% O&I Docking | ||||
| 123-11-002 | Compensated Fuel Tank; repair | 3.2.1 | 20% O&I Docking | ||
| 123-11-004 | Fuel Oil Service and Gravity Head Tank; repair | 3.1.1 | 20% O&I Docking | ||
| 3.2.1 | 20% O&I Docking | ||||
| 123-15-002 | Controllable Pitch Propeller Hydraulic Oil Sump Tank; repair | 3.1.1 | 20% O&I Docking | ||
| 123-19-001 | Waste Water Tank; repair | 3.2.1 | 20% O&I Docking | ||
| 123-21-001 | Accessible Void; repair | 3.2.1 | 20% O&I Docking | ||
| 123-22-002 | Chain Locker and Chain Locker Sump; repair | 3.2.1 | 20% O&I Docking | ||
| 161-11-001 | Strut; repair | 3.1.1 | 20% O&I Docking | ||
| 163-11-001 | Sea Chest; inspect and repair | 3.3.2.1 | 20% O&I Docking | ||
| 3.4.1.1 | 20% O&I Docking | ||||
| 165-11-001 | Sonar Dome Pressurization System Valve; repair and replace | 3.2.7 | 20% O&I Docking | ||
| 165-11-002 | Sonar Dome Rubber Window (SDRW); inspect and repair | 3.5.3.9 | 20% O&I Docking | ||
| 3.7 | 20% O&I Docking | ||||
| 167-11-001 | Scuttle Lower Sonar Dome; repair | 3.1.1 | 20% O&I Docking | ||
| 3.2.2.2 | 20% O&I Docking | ||||
| 243-11-002 | Starboard Stern Tube Shaft Seal; overhaul | 3.2.2.1 | 20% O&I Docking | ||
| 243-11-003 | Starboard Waterborne Propulsion Shafting; install | 3.1.1 | 20% O&I Docking | ||
| 243-12-002 | Port Stern Tube Shaft Seal; overhaul | 3.2.2.1 | 20% O&I Docking | ||
| 243-12-003 | Port Waterborne Propulsion Shafting; install | 3.1.1 | 20% O&I Docking | ||
| 244-10-002 | Stern Tube and Strut Bearing Strap; install (OPTION ITEM) | 3.1.3 | 20% O&I Docking | ||
| 3.2.3 | 20% O&I Docking | ||||
| 244-11-001 | Starboard Outboard Propulsion Shafting Bearing Clearance Measurement; accomplish | 3.1.4 | 20% O&I Docking | ||
| 3.2.3.2 | 20% O&I Docking | ||||
| 3.3.2 | 20% O&I Docking | ||||
| 3.3.3.1 | 20% O&I Docking | ||||
| 3.6.6.1 | 20% O&I Docking | ||||
| 244-12-001 | Port Outboard Propulsion Shafting Bearing Clearance Measurement; accomplish | 3.1.4 | 20% O&I Docking | ||
| 3.2.3.2 | 20% O&I Docking | ||||
| 3.3.2 | 20% O&I Docking | ||||
| 3.3.3.1 | 20% O&I Docking | ||||
| 3.6.6.1 | 20% O&I Docking | ||||
| 245-11-001 | Number One Controllable Pitch Propeller (CPP) Blade Set Repair and Propeller Hub Replacement; accomplish | 3.2.2 | 20% O&I Docking | ||
| 3.4.1 | 20% O&I Docking | ||||
| 3.5.1 | 20% O&I Docking | ||||
| 3.7.3 | 20% O&I Docking | ||||
| 3.9.7 | 20% O&I Docking | ||||
| 245-11-003 | Controllable Pitch Propeller (CPP) Prairie Air and Valve Rod Assembly Starboard; repair | 3.2.1.1 | 20% O&I Docking | ||
| 3.2.2.3 | 20% O&I Docking | ||||
| 3.2.4.1 | 20% O&I Docking | ||||
| 3.3.1.1 | 20% O&I Docking | ||||
| 3.3.2.4 | 20% O&I Docking | ||||
| 3.3.4.1 | 20% O&I Docking | ||||
| 245-11-004 | Controllable Pitch Propeller (CPP) Standby Hydraulic Pump Number One Mechanical Seal and Shaft Coupling; install | 3.2.1 | 20% O&I Docking | ||
| 245-12-002 | Number 2 Controllable Pitch Propeller (CPP) Blade Set Repair and Propeller Hub Replacement; accomplish | 3.2.2 | 20% O&I Docking | ||
| 3.4.1 | 20% O&I Docking | ||||
| 3.5.1 | 20% O&I Docking | ||||
| 3.7.3 | 20% O&I Docking | ||||
| 3.9.7 | 20% O&I Docking | ||||
| 245-12-003 | Controllable Pitch Propeller (CPP) Prairie Air and Valve Rod Assembly Port; repair | 3.2.1.1 | 20% O&I Docking | ||
| 3.2.2.3 | 20% O&I Docking | ||||
| 3.2.4.1 | 20% O&I Docking | ||||
| 3.3.1.1 | 20% O&I Docking | ||||
| 3.3.2.4 | 20% O&I Docking | ||||
| 3.3.4.1 | 20% O&I Docking | ||||
| 245-12-004 | Controllable Pitch Propeller (CPP) Standby Hydraulic Pump Number 2 Mechanical Seal and Shaft Coupling; install | 3.2.1 | 20% O&I Docking | ||
| 442-10-001 | TR-232B/WQC-2A and TR-233B/WQC-2A Transducer Cabling; install | 3.1.2.1 | 20% O&I Docking | ||
| 3.3.1 | 20% O&I Docking | ||||
| 462-08-001 | DT-513/BQA-8 Hydrophone and Cable Assembly; install | 3.1.2.1 | 20% O&I Docking | ||
| 463-89-001 | AN/SQQ-89 Sonar Transducer and Stave Cable Connectorized; install | 3.5.1 | 20% O&I Docking | ||
| 3.5.2.1 | 20% O&I Docking | ||||
| 3.5.4.1 | 20% O&I Docking | ||||
| 3.5.5.3 | 20% O&I Docking | ||||
| 520-11-001 | Sea Valve and Waster Sleeve; repair and install | 3.2.1.1 | 20% O&I Docking | ||
| 562-11-001 | Starboard Rudder, inspect and repair | 3.1.3.1 | 20% O&I Docking | ||
| 3.3.2 | 20% O&I Docking | ||||
| 3.4.1 | 20% O&I Docking | ||||
| 562-11-002 | Port Rudder; inspect and repair | 3.1.3.1 | 20% O&I Docking | ||
| 3.3.2 | 20% O&I Docking | ||||
| 3.4.1 | 20% O&I Docking | ||||
| 562-11-003 | Rudder Bearing Seal and Rudderstock Seal; repair | 3.2.3.1 | 20% O&I Docking | ||
| 631-31-001 | Underwater Hull Preservation with Paint Company Original Equipment Manufacturers' (OEM) Technical Representative; accomplish | 3.1.1 | 20% O&I Docking | ||
| 3.3.1 | 20% O&I Docking | ||||
| 631-41-001 | Freeboard; preserve | 3.1.1 | 20% O&I Docking | ||
| 633-21-001 | Impressed Current Cathodic Protection (ICCP) System; inspect and repair | 3.1.1 | 20% O&I Docking | ||
| 3.2.2 | 20% O&I Docking | ||||
| 3.4.3 | 20% O&I Docking | ||||
| 3.5.3 | 20% O&I Docking | ||||
| 997-11-001 | Drydocking and Undocking; accomplish | 3.3.1 | 20% O&I Docking | ||
| 3.7.1.5 | 20% O&I Docking | ||||
| 122-20-001 | Number 3 Generator Room; repair | 3.3.1 | 20% O&I/High Pri | ||
| 3.4.4 | 20% O&I/High Pri | ||||
| 122-20-002 | Auxiliary Machinery Room Number One Transverse Bulkhead; inspect and repair | 3.3.4 | 20% O&I/High Pri | ||
| 123-12-002 | JP-5 Tank; repair | 3.1.1 | 20% O&I/High Pri | ||
| 123-15-001 | Lube Oil Tank; repair | 3.2.1 | 20% O&I/High Pri | ||
| 123-17-002 | Contaminated Oil Tank; repair | 3.2.1 | 20% O&I/High Pri | ||
| 123-19-004 | Vacuum, Collection, Holding and Transfer (VCHT) Tank; repair | 3.2.1 | 20% O&I/High Pri | ||
| 150-80-001 | AER DDG51-83007D, Increase Deck Plate Thickness; accomplish (partial) | 3.1.1 | 20% O&I/High Pri | ||
| 167-11-004 | Hatch Hold Back Device; repair | 3.1.1 | 20% O&I/High Pri | ||
| 167-11-006 | Bolted Equipment Removal Plate (BERP); repair | 3.3.1 | 20% O&I/High Pri | ||
| 251-30-001 | Number 2 Gas Turbine Module (GTM) Clean Air Intake; repair | 3.4.1 | 20% O&I/High Pri | ||
| 3.5.1 | 20% O&I/High Pri | ||||
| 251-31-001 | Air Intake and Exhaust Louver; preserve | 3.5.1.1 | 20% O&I/High Pri | ||
| 251-32-001 | Number One Gas Turbine Intake; repair | 3.2.1.1 | 20% O&I/High Pri | ||
| 251-32-002 | Number One Gas Turbine Module (GTM) Clean Air Intake; repair | 3.4.1 | 20% O&I/High Pri | ||
| 3.5.1 | 20% O&I/High Pri | ||||
| 251-32-003 | Number 2 Gas Turbine Intake; repair | 3.2.1.1 | 20% O&I/High Pri | ||
| 259-10-001 | Number One Gas Turbine Mixing Room, Uptake and Boundary Layer Infra-Red Suppression System (BLISS) Cap; | ||||
| repair | 3.3.1 | 20% O&I/High Pri | |||
| 3.4.1 | 20% O&I/High Pri | ||||
| 259-10-002 | Number 2 Gas Turbine Mixing Room, Uptake and Boundary Layer Infra-Red Suppression System (BLISS) Cap; | ||||
| repair | 3.3.1 | 20% O&I/High Pri | |||
| 3.4.1 | 20% O&I/High Pri | ||||
| 259-10-003 | Gas Turbine (GTRB) Exhaust Duct Collector; repair | 3.3.1 | 20% O&I/High Pri | ||
| 3.4.1` | 20% O&I/High Pri | ||||
| 262-40-002 | Main Reduction Gear (MRG) Lube Oil Cooler Tube Bundle; install | 3.4.2.1 | 20% O&I/High Pri | ||
| 264-31-001 | Number One Lube Oil Purifier Heater; clean | 3.2.1.1 | 20% O&I/High Pri | ||
| 3.3.1.1 | 20% O&I/High Pri | ||||
| 264-32-001 | Number 2 Lube Oil Purifier Heater; clean | 33.3.1.1 | 20% O&I/High Pri | ||
| 264-32-001 | Number 2 Lube Oil Purifier Heater; clean | 3.2.1.1 | 20% O&I/High Pri | ||
| 3.3.1.1 | 20% O&I/High Pri | ||||
| 311-31-001 | Number One Ship Service Gas Turbine Generator (SSGTG); repair | 3.1.1 | 20% O&I/High Pri | ||
| 311-32-001 | Number 2 Ship Service Gas Turbine Generator (SSGTG); repair | 3.1.1 | 20% O&I/High Pri | ||
| 311-33-001 | Number 3 Ship's Service Gas Turbine Generator (SSGTG); repair | 3.1.1 | 20% O&I/High Pri | ||
| 321-80-001 | DDG51 Class AER 64201D, Stuffing Tube Replacement; accomplish(PARTIAL) | 3.1.1.1 | 20% O&I/High Pri | ||
| 514-20-001 | Air Conditioning (AC) Plant Condenser; mechanically clean | 3.1.4.1 | 20% O&I/High Pri | ||
| 3.3.1 | 20% O&I/High Pri | ||||
| 514-20-002 | Air Conditioning Plant Condenser Water Control Valve (CWCV); replace | 3.1.1 | 20% O&I/High Pri | ||
| 514-23-001 | Air Conditioning Plant; repair | 3.3.1.1 | 20% O&I/High Pri | ||
| 516-11-001 | Refrigeration Plant Piping; replace | 3.3.2 | 20% O&I/High Pri | ||
| 521-11-001 | Firemain Piping System; repair | 3.1.1 | 20% O&I/High Pri | ||
| 521-11-003 | Firemain System; clean and inspect | 3.1.6.1 | 20% O&I/High Pri | ||
| 561-11-001 | Steering Ram Seal Packing; install | 3.1.1.1 | 20% O&I/High Pri | ||
| 571-11-003 | Sliding Padeye, Tilting; install new | 3.1.4 | 20% O&I/High Pri | ||
| 593-20-001 | Oily Waste Transfer piping; replace | 3.2.1 | 20% O&I/High Pri | ||
| 624-11-001 | Balanced Joiner Door; repair | 3.1.2 | 20% O&I/High Pri | ||
| 631-11-001 | Machinery Space Bilge and Access Trunk; preserve | 3.3.1 | 20% O&I/High Pri | ||
| 631-11-002 | Engine Room Number 2 Bilge and Access Trunk; preserve | 3.3.1 | 20% O&I/High Pri | ||
| 631-13-001 | Collective Protection System (CPS) Zone 2 Fan Room; repair and preserve | 3.3.1 | 20% O&I/High Pri | ||
| 631-13-002 | Collective Protection System (CPS) Zone One Fan Room; repair and preserve | 3.3.1 | 20% O&I/High Pri | ||
| 631-13-003 | Collective Protection System (CPS) Zone 3 Fan Room; repair and preserve | 3.3.1 | 20% O&I/High Pri | ||
| 631-13-004 | Collective Protection System (CPS) Zone 4 Fan Room; repair and preserve | 3.3.1 | 20% O&I/High Pri | ||
| 631-13-005 | Fan Room; preserve and repair | 3.1.2.1 | 20% O&I/High Pri | ||
| 631-13-008 | Bilge; preserve | 3.2.1.1 | 20% O&I/High Pri | ||
| 631-21-001 | Mast Preservation; accomplish | 3.1.2 | 20% O&I/High Pri | ||
| 991-11-001 | Antenna Array Temporary Staging for Use by Ship's Force; provide | 3.2.1 | 20% O&I/High Pri | ||
| 993-31-002 | Temporary Main Reduction Gear (MRG) Dehumidifier System; provide | 3.2.1 | 20% O&I/High Pri | ||
| 993-31-004 | Waveguide and Transmission Dry Air Lay-Up; accomplish | 3.3.1.1 | 20% O&I/High Pri | ||
| 121-11-002 | Longitudinal Bulkhead; repair | 3.1.1 | 20% O&I/Low Pri | ||
| 130-11-001 | Aircraft Securing Fitting; install | 3.1.3.1 | 20% O&I/Low Pri | ||
| 150-11-003 | 01 Level Bulkhead; repair | 3.1.1 | 20% O&I/Low Pri | ||
| 421-11-001 | Pelorus Foundation; replace | 3.1.1 | 20% O&I/Low Pri | ||
| 512-11-001 | Dry Ice Ventilation Cleaning; accomplish | 3.1.1 | 20% O&I/Low Pri | ||
| 3.4.1 | 20% O&I/Low Pri | ||||
| 581-11-001 | Anchor and Anchor Chain; inspect and preserve | 3.3.11 | 20% O&I/Low Pri | ||
| 581-11-002 | Anchor Windlass Stroke Control; repair | 3.1.1 | 20% O&I/Low Pri | ||
| 582-11-001 | Retractable Bitt and Chock; repair and preserve | 3.1.3.1 | 20% O&I/Low Pri | ||
| 583-11-001 | Boat Handling and Stowage System; repair | 3.4.3.1 | 20% O&I/Low Pri | ||
| 593-11-001 | Vacuum, Collection, Holding and Transfer (VCHT) Ejector Pump and Motor; install | 3.3.3.1 | 20% O&I/Low Pri | ||
| 634-21-001 | Forecastle Nonskid; replace | 3.2.1 | 20% O&I/Low Pri | ||
| 3.3.1 | 20% O&I/Low Pri | ||||
| 634-21-002 | Flight Deck Nonskid; install | 3.3.1 | 20% O&I/Low Pri | ||
| 3.4.1 | 20% O&I/Low Pri |