This is a technical inspection document identifying ultrasonic testing trouble spots for marine vessel maintenance and repair. The document specifies locations requiring ultrasonic testing inspection divided into two primary areas: the engine room and the outside hull. Engine room trouble spots include six specific locations between frames 34-37 on the port side and around the oil tank area, including sections under the plugger and both port and starboard of the center frame. Outside hull trouble spots include stern zincs located by rudders and fore of rudders on both port and starboard sides, any zincs exhibiting corrosion around tabs, gouging on the port keel cooler aft, and the port stabilizer weld line area. The document serves as a work specification guide for identifying areas of concern requiring detailed ultrasonic thickness testing.

The document does not contain information regarding pricing terms, contract awards, bidding timelines, funding sources, or other contractual elements. This appears to be a technical specification or scope of work attachment that would support a larger marine vessel inspection and repair contract opportunity, likely issued by a maritime authority or naval shipyard. The specific nature and quantity of testing work required, along with contract duration and pricing structures, would be detailed in associated procurement documents.

View the file

Other files

File Type Posted
Drawing 4 -1 Medeia Zinc Location & Types -port.jpg JPG image
Elander2014-4.jpg JPG image
Ultrasonic Testing Findings 2023.docx DOCX document
10-1 TW-200LP Steel 4 View Drawing.pdf PDF
Drawing 9-1 General Scanting.PDF PDF
MSD INSTRUCTION MANUAL.doc DOC document
Drawing 4 -2 Medeia Zinc Location & Types -starboard.jpg JPG image
Elander2014-6.jpg JPG image
Elander2014-7.jpg JPG image
Elander 2006 Shell Expansion.jpg JPG image
Drawing 17-2 Hold Plan.PDF PDF
Drawing 17 -1 Medeia Bilge & Ballast Piping.pdf PDF
Drawing 16-5 Medeia 42 Circuit Panel 5.pdf PDF
Drawing 13-1 General Arrangement for Clad Welding.PDF PDF
Drawing 12-3 Crane Specs.pdf PDF
Elander2014 Ultrasonic Test.jpg JPG image
Elander2006-7.jpg JPG image
Medeia Megger Report 2023.pdf PDF
RV_Medeia_Paint_Specification.docx DOCX document
Drawing 16-3 Medeia 42 Circuit Panels 1 & 2.pdf PDF
Drawing 3 -1 Medeia Bilge & Ballast Piping.pdf PDF
Drawing 5-2 Medeia Rudder Fabrication -Allied.PDF PDF
Elander2014-2.jpg JPG image
Drawing 2-1 Medeia Outboard Profile.pdf PDF
Drawing 5-1 Medeia Rudder Fabrication -Allied.PDF PDF
Drawing 8-1 Medeia Keel Cooler Arrangements Drawing.pdf PDF
Ultrasonic Report 2011.pdf PDF
Elander2006-8.jpg JPG image
Elander KeelCoolers 2006.jpg JPG image
Accuren Ultrasonic Testing Report 2020.pdf PDF
Drawing 12-2 Crane Diagram.pdf PDF
Elander 2006-2.jpg JPG image
Drawing 1-2 Medeia Electrical Service -Shore Tie.jpg JPG image
Drawing 12-1 Medeia Crane Load Chart.pdf PDF
Elander 2006-3.jpg JPG image
Elander 2006-4.jpg JPG image
Elander2006 UltraSonic Test.jpg JPG image
ADF&G RFI 1127018 - FY27 RV Medeia Shipyard Services.pdf PDF
Ultrasonic Thickness Measurements 2011.pdf PDF
Drawing 16-1 Medeia Electrical pilot house panel.PDF PDF
Elander2014-5.jpg JPG image
Drawing 16-4 Medeia 42 Circuit Panels 3 & 4.pdf PDF
Elander 2006-5.jpg JPG image
Drawing 9-2 Trans. Frs & Long'L Section.PDF PDF
Elander2006-6.jpg JPG image
Drawing 1-1 Medeia Docking Plan.pdf PDF
Elander2014-3.jpg JPG image
Drawing 16-2 Medeia Wiring Schematic.pdf PDF
Elander2014-8.jpg JPG image
Show all 49

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Ultrasonic Testing Trouble Spots

· Engine room:

1. Between 35 and 36 Port side

2. Between 36 and 37 Port side

3. Between 34 and 35 under plugger

4. Between 36 and 37 just port of oil tank (center frame)

5. “ “ “ starboard of center frame

6. Between 35 and 36 just port of oil tank (center frame)

· Outside hull: (circled in white chalk)

1.Stern zincs by rudders (P&S)

2. Stern zincs just fore of rudder zincs (P&S)

3. Any zincs with corrosion around the tabs

4. Gouging on port keel cooler aft 2 coolers in from outboard

5. Port stabilizer just fore on weld line