U-2023-023_2nd_Street_Bike_and_Ped_Improvements_PS&E_Special_Provisions.pdf
PDF 2 MB Posted
- Solicitation number
- 260178
- Issued by
- Pima County, Tucson City, Arizona
About this file
This is a Special Provisions document for the City of Tucson and University of Arizona's UA 2nd Street Bike and Pedestrian Improvements project, funded by the Federal Highway Administration (FHWA) under the Transportation Alternatives Program (Federal Aid Number TAP-TUC-0(252)D). The project scope includes converting the existing paved UA Maintenance Road into a 14-16 foot wide mixed-use path, reconstructing ADA-compliant curb access ramps and sidewalks, eliminating two-way traffic on Olive Road to create one-way northbound traffic with two bicycle lanes and a widened sidewalk, installing high-visibility crosswalks, and adding lighting to existing streetcar and overhead conductor poles. The work encompasses approximately 2,207 linear feet of pavement removal and 1,747 square yards of improvements across two primary work areas. The contract must be completed within 90 calendar days during the UA Summer Session from May 18, 2026, through August 16, 2026, with work restricted to daytime hours and prohibited during peak traffic periods (7:00-9:00 a.m. and 4:00-6:00 p.m., Monday through Friday). A pre-bid meeting is scheduled for March 26, 2026, at 9:00 a.m. Arizona time via Zoom, with bids due April 7, 2026, at 2:00 p.m. Arizona time. The contract will be awarded to the lowest responsive and responsible bidder, with Notice of Intent to Award issued within 60 days of bid opening.
The estimated project cost ranges between $500,000 and $1,000,000, with payment structured according to predetermined unit prices and reimbursement rates for traffic control elements and no retainage permitted on progress payments due to federal funding. Bidders must comply with multiple federal and local requirements including Section 3 of the Housing and Urban Development Act (requiring 25 percent of labor hours performed by Section 3 workers and 5 percent by Targeted Section 3 workers), Disadvantaged Business Enterprise (DBE) participation documentation, Small Business Enterprise (SBE) subcontractor identification, Davis-Bacon prevailing wage requirements, Build America Buy America Act (BABAA) domestic preference requirements, and federal non-discrimination assurances. Contractors must provide bid security equal to 10 percent of the total bid amount and 100 percent performance and payment bonds prior to contract execution, perform at least 30 percent of total contract work with their own organization, maintain workers' compensation and liability insurance with minimum limits ($1,000,000 per occurrence, $2,000,000 general aggregate for commercial general liability), and coordinate extensively with the University of Arizona Project Manager regarding permits, staging areas, traffic control, utility protection, historic preservation (including a 5-foot buffer around the historic lava rock wall requiring hand excavation), environmental compliance, and construction scheduling.
View the file
Other files
Show all 21
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SPECIAL PROVISIONS
for
UA 2nd St Bike and Pedestrian Improvements
Federal Aid Number TAP-TUC-0(252)D ADOT Project Number SF025 01C
City of Tucson Plan Number U-2023-023
January 2026
PROFESSIONAL ENGINEER SEALS
These Special Provisions represent the combined efforts of the following organizations:
(1) AECOM Technical Services, Inc.
(2) City of Tucson Department of Transportation & Mobility
A representative of each organization has affixed their seal below, which attests that portions of these Special Provisions were prepared under their direction.
(1) AECOM Technical Services, Inc. (Civil, Traffic)
(2) City of Tucson Department of Transportation & Mobility
/29 /26
1/2 9/2
EXPIRES: December 31, 2027
UA 2ND ST BIKE AND PEDESTRIAN IMPROVEMENTS
Table of Contents
SPECIFICATIONS AND DETAILS
PROPOSED WORK
GENERAL REQUIREMENTS
DIVISION 100 GENERAL PROVISIONS
SECTION 104 SCOPE OF WORK
SECTION 105 CONTROL OF WORK
SECTION 106 CONTROL OF MATERIAL
SECTION 107 LEGAL RELATIONS AND RESPONSIBILITY TO PUBLIC22
SECTION 108 PROSECUTION AND PROGRESS
SECTION 109 MEASUREMENT AND PAYMENT
SECTION 206 FURNISH WATER SUPPLY
SECTION 303 AGGREGATE BASE COURSE
ITEM 5103101 – POTABLE WATER, ADJUST EXISTING VALVE BOX AND
COVER
SECTION 607 SIGN SUPPORTS
ITEM 6070010 – SIGN POST (PERFORATED) (SINGLE)
ITEM 6070110 – FOUNDATION FOR SIGN POST (PERFORATED)
ITEM 6070210 – REMOVE AND SALVAGE SIGNS
SECTION 608 SIGN PANELS
SECTION 701 MAINTENANCE AND PROTECTION OF TRAFFIC
SECTION 704 THERMOPLASTIC STRIPES AND MARKINGS
SECTION 705 PREFORMED PLASTIC PAVEMENT MARKING
SECTION 708 PAINTED PAVEMENT MARKINGS
SECTION 802 LANDSCAPE GRADING
SECTION 908 CONCRETE CURBS, GUTTERS, SIDEWALKS AND
DRIVEWAYS
ITEM 9300110 – MISCELLANEOUS WORK 1 (SOLAR POWERED FLASHING
LED SIGN PANELS)
ITEM 9300120 – MISCELLANEOUS WORK 10 (SHARED USE PATH CURB,
DETAIL C1)
ITEM 9300121 – MISCELLANEOUS WORK 11 (AC BERM, DETAIL C2) .. 61
ITEM 9300127 – MISCELLANEOUS WORK 17 (VERTICAL CURB CUT, DETAIL
C3)
ATTACHMENT A – UTILITY CLEARANCE SUMMARY
SPECIFICATIONS AND DETAILS
The work embraced herein shall be performed in accordance with the requirements of the following separate documents:
Specifications
Pima Association of Governments (PAG), Standard Specifications for Public Improvement, 2015 Edition, Volume 1 (typically referenced as “Standard Specifications” unless otherwise specified) http://apps.pagnet.org/standardspecifications
Details
Pima Association of Governments (PAG), Standard Details for Public Improvements, 2015 Edition, Volume 2 http://apps.pagnet.org/standardspecifications/
Manuals
U.S. Department of Transportation, Federal Highway Administration, Manual on Uniform Traffic Control Devices for Streets and Highways, December 2009, and amendments http://mutcd.fhwa.dot.gov/pdfs/2009/pdf_index.htm
Arizona Supplement to the Manual on Uniform Traffic Control Devices (MUTCD), 2009 edition (January 2012) https://azdot.gov/sites/default/files/2019/07/arizona-supplement-to-the-manual-on-uniform-traffic-control-devices-2009-mutcd-edition.pdf
2015 Edition of the Additions by the City of Tucson to the Manual on Uniform Traffic Control Devices, for Temporary Traffic Control https://www.tucsonaz.gov/files/transportation/files/2015_COT_Additions_Final.pdf
City of Tucson Department of Transportation, Traffic Signal Design Manual, May 2003 and current revisions https://www.tucsonaz.gov/files/transportation/Design_Manual.pdf
Pima County/City of Tucson, Signing and Pavement Marking Manual, December 2020 https://content.civicplus.com/api/assets/c8d13f95-b46c-446e-97fe-8e5127201983
Other Specifications and Details
The Arizona Department of Transportation (ADOT) Standard Specifications for Road and Bridge Construction, 2021 Edition https://azdot.gov/business/contracts-and-specifications/specifications-pay-items-list
Pima County Regional Wastewater Reclamation Department, Standard Specifications and Details for Construction, 2022 Edition https://webcms.pima.gov/UserFiles/Servers/Server_6/File/Government/Wastewater%20Reclamatio n/Engineering/SSDC_2022_Updated.pdf
Tucson Water, Standard Specifications and Details Manual, 2017 Edition https://www.tucsonaz.gov/files/water/docs/StandardSpecsDetails/Tucson_Water_Standard_Specifi cations_and_Details_Manual_Complete_Dec_2017_V1.pdf
These Special Provisions and Bid Schedule.
PROPOSED WORK
The proposed work is located in Sections 7, T14S, R14E of the Gila and Salt River Meridian, within the City of Tucson, Pima County, Arizona. This project provides improvements to the 2nd Street University of Arizona (UA) Maintenance Road from James E. Rogers Way to the Harshbarger Pathway and Olive Road from 2nd Street to the Alleyway approximately 250’ north of 2nd Street.
The scope of the project consists of:
Conversion of the existing paved UA Maintenance Road between James E. Rogers Way and 2nd Street into a mixed-use path replacing the pavement section and striping the new path, Reconstruct ADA curb access ramps at the entrance to the UA Maintenance Road and James E. Rogers Way
Eliminate the two-way traffic on Olive Road north of 2nd Street by closing the east lane and creating a one-way northbound only traffic lane, Convert the closed east lane on Olive Road to two bicycle lanes and widen the existing sidewalk, Install a high-visibility, mixed-use crosswalk on 2nd Street at the Harshbarger mixed-use path
Add lighting to existing streetcar pole at the mixed-use crosswalk on 2nd Street at the Harshbarger mixed-use path.
Install a light at the Harshbarger and 2nd Street intersection on a existing overhead conductor pole used for the Sun Link Streetcar system.
Designate temporary detour routes for bicycles and pedestrians during construction.
GENERAL REQUIREMENTS
(1) Contract Time
The work specified shall be completed within 90 calendar days. Work must be completed during the UA Summer Session which commences May 18, 2026 and ends August 16, 2026.
(2) Maintenance & Protection of Traffic
Traffic control shall protect vehicles and pedestrian traffic in the work area from construction equipment. Traffic control shall comply with the referenced traffic control manuals and guidelines.
The Contractor shall prepare a Traffic Control Plan for construction. The traffic control plan shall comply with all dimensions, signing, restrictions, signalization and detours for all phases of construction. At the pre-construction meeting the Contractor shall provide a copy of the proposed traffic control plan to the Project Engineer for review and approval. No construction shall be done unless the approved traffic control signs are in place.
Convenient access for the University of Arizona Facilities Management shall be maintained and shall be available at all times during construction. It shall be the Contractor’s responsibility to coordinate their work with the University of Arizona to minimize local traffic disruptions through the work area.
The pedestrian access closures will need to be coordinated with the UA during construction.
Areas where sidewalk is being constructed shall be barricaded and pedestrian access around construction shall be provided during and after regular work hours.
Access should also be provided for UA service vehicles, and garbage pick-up.
Pedestrian access shall be maintained throughout construction and temporary signage shall be erected to redirect pedestrians away from the construction zone.
The Contractor shall, at a minimum, be required to maintain access on the UA Maintenance Road which shall be maintained during construction for UA service vehicles.
Appropriate signage and/or flagmen shall be utilized at all times during operations with lane restrictions. The Contractor is advised of peak period traffic during the following intervals, whereby lane restrictions are prohibited:
Morning 7:00 a.m. to 9:00 a.m.
Evening 4:00 p.m. to 6:00 p.m.
The contractor is advised of the Civil Sanctions for Temporary Traffic Control Violations included in Section 20 of the Additions by the City of Tucson to the Manual on Uniform Traffic Control Devices, for Temporary Traffic Control.
Payment for Maintenance and Protection of Traffic shall be included under Item 7010001 – Maintenance & protection of Traffic.
(3) Permits
Before undertaking work at any location covered by this project, the contractor shall obtain all applicable permits, including but not limited to: water quality, air quality, traffic control, street closure and right of way. The approved plan is considered the right-of-way use permit for work within City of Tucson when administered or funded by the City of Tucson. The contractor is responsible for paying all applicable fees, taxes, and other costs for all work performed on this project, and for obtaining all permits including those in other jurisdictions.
Before undertaking work outside the limits of the plans, specifications and project clearances, a separate right-of-way use permit is required.
The contractor shall file a Notice of Intent to use the statewide Construction General Permit for Discharge to Waters of the United States and a Notice of Termination when the site is stabilized with the Arizona Department of Environmental Quality (ADEQ). The contractor shall maintain and implement Pima County’s Stormwater Pollution Prevention Plan under the Construction General Permit. The contractor is directed to Section 810 of these Special Provisions and the Stormwater Pollution Prevention Plan for the project.
Prior to any ground disturbing activity, the contractor shall obtain an Activity Permit from the Pima County Department of Environmental Quality. The contractor shall implement the standard specifications for dust suppression.
The UA will require permitting to work on their property and for inspections from various departments at the university. The contractor shall contact the UA project manager, Chris Stebe at 520-440-7131 or cstebe@arizona.edu prior to construction operations to obtain the necessary permitting.
Track Access Permit and Coordination with Sun Link
A Track Access Permit will be required for any work on or near the Sun Link right of way.
This will include the contractor's barricade company, work at the curb, light installation and refreshing the existing crosswalk at 2nd Street & Olive Road.
The Track Access training class must be completed before a permit can be issued. For information on Track Access training classes contact Xavier Soto at 520-307-1925 or Xavier.Soto@tucsonaz.gov.
To obtain a Track Access Permit contact Jeannette Haro at 520-429-1151 or jeannette.haro@tucsonaz.gov. There is no fee for either the Track Access training class or Track Access Permit.
(4) Construction Survey and GPS Documentation
The contractor shall provide surveying or GPS location documentation. The survey GPS data shall be in the most recent State Plane Coordinates (NAD 1983 State Plane Arizona Central) and will be gathered using survey quality equipment, and accurate to within 0.5 feet. The Basis of Coordinates will be included. The format shall include coordinates in northings and eastings, as well as by Station and Offset. Stationing shall be based on a pre-determined basis indicated in on the striping plans. Each point shall contain a description of the utility appurtenance, etc. All water & gas valves, manholes and cleanouts shall be documented by GPS methods before they are lowered. The surveying/GPS documentation of utility appurtenances shall be considered incidental and included in the respective pre-lowering utility item.
City of Tucson forces will perform survey for monument and project layout (refer to Special Provisions Section 105-8).
(5) Construction Surveillance
City of Tucson forces, including consultant inspectors, shall perform the inspection of the contractor’s work. Assistance may be provided by the Engineering Division inspection staff.
(6) Existing Vegetation
Protection of vegetation shall be in accordance with the University of Arizona’s requirements.
Those items in these areas which are damaged shall be repaired, remedied, or replaced at the contractor’s expense.
Existing plant material in the Right-of-Way not shown on the project plans to be removed will be Preserved-in-Place. If any trees are to potentially be impacted by construction, the UA Project Manager must be contacted prior to commencing work., Chris Stebe (Phone: 520-440- 7131, Email: cstebe@arizona.edu.
(7) Project Limits
The contractor shall perform all work on Arizona Board of Regents property.
(8) Work Hours/Noise Abatement Ordinance
Work hours and noise abatement will be coordinated with the UA Project Manager prior to construction commencing.
(9) Contractor’s Staging or Storage Yard
Contractor staging areas will be determined in collaboration with the UA Project Manager where equipment may be stored near the project area.
(10) Construction Water/Dust Control
The contractor shall provide potable water for use in construction, compaction and dust control. Reclaimed water may only be used if there is no discharge of this water to surface waters of the U.S. and the reclaimed water remains on-site. The contractor shall notify the Arizona Department of Environmental Quality (ADEQ) for all discharges of reclaimed water to surface waters of the U.S. or off-site.
(11) Contractor’s Environmental Responsibilities
City of Tucson Responsibilities
If any active bird nests cannot be avoided by vegetation clearing or construction activities, the Engineer will contact the UA Project Manager (520-484-5569) to evaluate the situation. The following restricted work areas have been identified and require protection in place:
Contractor Responsibilities
If vegetation clearing will occur during the migratory bird breeding season (March 1 – August 31), the contractor shall avoid any active bird nests. If the active nests cannot be avoided, the contractor shall notify the Engineer to evaluate the situation. During the non-breeding season (September 1-February 28) vegetation removal is not subject to this restriction.
The following restricted areas have been identified and require protection in place:
Area 1: James E Rodgers Way to 2nd Street (East side) and N Park Ave to Harshbarger Mixed Use Path (south side)
The contractor shall employ hand excavation for replacing curbs and pavement within five feet of the wall and will protect the wall and existing vegetation inside the wall.
The project improvements will be near historic features that run parallel to the pavement within the project area. These features include the historic lava rock wall and historic buildings, which are also along the University of Arizona maintenance road. The contractor shall be experienced working with historic features when working near these features and avoid disturbance to the maximum extent possible.
The contractor shall take caution when working near the historic lava rock wall within the project area. No mechanical equipment shall be allowed to be used within 5 feet of the lava rock wall. The contractor shall employ hand tools within these limits to avoid damage to this historic feature. The contractor shall not place construction tools, equipment, or other materials on the top of the historic lava wall during construction activities.
The contractor shall establish a 5-foot buffer around the historic lava wall and that area shall be delineated with methods approved by the University of Arizona Project Manager. If work needs to be completed within the 5-foot buffer area, the contractor shall contact the University of Arizona Project Manager prior to commencing work to ensure that University of Arizona staff is on site during these activities.
Any damage to the historic lava rock wall shall be the responsibility of the Contractor to repair this feature according to University of Arizona and State Historic Preservation Office specifications at no additional cost to the University of Arizona or the City of Tucson. If damage occurs to the wall during construction, the Contractor shall cease work within 20 feet of the area of damage and contact the University of Arizona Project Manager immediately.
For milling activities, the roadway surface preceding the milling machine shall be kept sufficiently wet so as to prevent the generation of any visible fugitive dust particles, but not so wet as to cause excess runoff from the roadway surface onto the roadway shoulder.
DIVISION 100 GENERAL PROVISIONS
101-3 DEFINITIONS of the Standard Specifications is modified to add:
Major Items – A major item is an item whose total cost, determined by multiplying the bidding schedule quantity and the contract unit price, is equal to or greater than the amount indicated below.
A major item will remain a major item unless it is eliminated.
When the original total and including:
contract amount is from A m a j o r i t em shall be equal to or greater than the following amount:
$ 0.00 $ 100,000 $ 5,000
100,001 200,000 10,000
200,001 450,000 15,000
450,001 750,000 25,000
750,001 1,100,000 35,000
1,110,001 1,500,000 45,000
1,500,001 2,000,000 55,000
2,000,001 2,500,000 65,000
2,500,001 3,000,000 75,000
3,000,001 5,000,000 85,000
5,000,001 7,000,000 120,000
7,000,001 10,000,000 150,000
10,000,001 25,000,000 250,000
25,000,001 50,000,000 350,000 over 50,000,000 500,000
Minor Item – A minor item is any item which is not a major item.
SECTION 104 SCOPE OF WORK
104-2 ALTERATIONS TO THE CONTRACT
104-2.01 By the Agency. The Standard Specifications is revised to read:
The Agency reserves the right to revise the contract at any time. Such revisions shall neither invalidate the contract nor release the surety. The contractor agrees to complete the contract as revised. The contractor shall not proceed with work for which a revision to the contract is required without prior approval from the Engineer. Once approval is received, the contractor shall proceed with such direction immediately, whether the Engineer considers that the contract has been revised or not.
It is the contractor's obligation to notify the Engineer in writing that a revision to the contract is necessary and provide such notification in accordance with Subsection 104-4. Whenever the words notice, notification, request or notify are used in this subsection, such notice or request shall be provided in accordance with the requirements of Subsection 104-4.
Supplemental Agreements will be issued for the reasons specified in 104-2.03 and 104-2.04 of the Standard Specifications, in addition to the following reasons:
(A) To accomplish extra work as defined in Subsection 101-3 and specified in subsection 104-3.
(B) If the work is suspended by order of the Engineer as provided below:
(1) If the performance of all or any portion of the work is suspended or delayed by the Engineer in writing for an unreasonable period of time (not originally anticipated, customary, or inherent to the construct ion industry) and the contractor believes that additional compensation and/or contract time is due as a result of such suspension or delay, the contractor shall submit to the Engineer, in writing, a request for adjustment within seven calendar days of receipt of the notice to resume work. The request shall set forth the reasons and support for such adjustment.
(2) Upon receipt, the Engineer will evaluate the contractor's request. If the Engineer agrees that the cost and/or time required for the performance of the contract has increased as a result of such suspension and the suspension was caused by conditions beyond the control of and not the fault of the contractor, its suppliers, or subcontractors at any approved tier, and not caused by weather, the Engineer will make an adjustment (excluding profit) and modify the contract in writing accordingly. The contractor will be notified of the Engineer's determination whether an adjustment of the contract is warranted.
(3) No contract adjustment will be allowed unless the contractor has submitted the request for adjustment within the time prescribed.
(4) No contract adjustment will be allowed under this clause to the extent that performance would have been suspended or delayed by any other cause, or for which an adjustment is provided or excluded under any other term or condition of this contract.
(C) If there are significant changes in the character of work as provided below:
(1) The Engineer reserves the right to make, in writing, at any time during the work, such changes in quantities and such alterations in the work as are necessary to satisfactorily complete the project. Changes in quantities and alterations shall not invalidate the contract nor release the surety. The contractor agrees to perform the work as altered.
(2) If the alterations or changes in quantities significantly change the character of the work under the contract, whether such alterations or changes are in themselves significant changes to the character of the work or, by affecting other work, cause such other work to become significantly different in character, an adjustment, excluding anticipated profit, will be made to the contract. The basis for the adjustment shall be agreed upon prior to the performance of the work. If a basis cannot be agreed upon, then an adjustment will be made either for or against the contractor in such amount as the Engineer may determine to be fair and equitable.
(3) If the alterations or changes in quantities do not significantly change the character of the work to be performed under the contract, the altered work will be paid for as provided in the contract.
(4) The term "significant change" shall be construed to apply only to the following circumstances:
(a) When the character of the work as altered differs materially in kind or nature from that involved or included in the original proposed construct ion; or
(b) When a major item of work, as defined elsewhere in the contract, is increased more than 125 percent or decreased below 75 percent of the original contract quantity. Any adjusted unit price for an increase in quantity shall apply only to that portion more than 125 percent of original contract item quantity. Any adjustment in contract unit price for a decrease in quantity below 75 percent shall apply only to the actual amount of work performed, except that the product of the adjusted unit price and the reduced quantity of work performed shall in no case exceed the product of the original contract unit price and 75 percent of the Bid Schedule quantity.
(D) To revise the contract time in accordance with Subsection 108-08. If the Supplemental Agreement is to provide for an increase or decrease in the contract price or time, such increases or decreases will be determined in accordance with the requirements herein and Subsections 108-8 and 109-4.
When the Agency makes alterations in the details of construction or Specifications, that are limited in scope, to the extent that the cost of the alterations will not exceed $10,000.00, the Agency and the contractor may reach agreement upon the scope of work and an amount to cover the cost of the work to be performed. This agreement shall be reflected in a letter from the Agency to the contractor, which, when executed by both parties, shall have the same force and effect as a supplemental agreement. Work shall not proceed until both parties have signed the agreement. This work will be paid for under ITEM 9240101 – Miscellaneous Work (Minor Alterations in Details of Construction), which shall serve as an account for the payment of letter agreements in accordance with this specification. Any balance left in this account at the end of the construction phase will not be paid and will be expunged from the contract.
104-2.02 Due to Physical Conditions. The Standard Specifications is revised to read:
104-2.02 Differing Site Conditions.
(A) During the progress of the work, if subsurface or latent physical conditions are encountered at the site differing materially from those indicated in the contract or if unknown physical conditions of an unusual nature, differing materially from those ordinarily encountered and generally recognized as inherent in the work provided for in the contract, are encountered at the site, the party discovering such conditions shall promptly notify the other party in writing of the specific differing conditions before the site is disturbed and before the affected work is performed.
(B) Upon written notification, the Engineer will investigate the conditions and if it is determined that the conditions materially differ and cause an increase or decrease in the cost or time required for the performance of any work under the contract, an adjustment, excluding anticipated profits, will be made and the contract modified in writing accordingly. The Engineer will notify the contractor of the determination whether an adjustment of the contract is warranted.
(C) No contract adjustment, which results in a benefit to the contractor, will be allowed unless the contractor has provided the required written notice.
(D) No contract adjustment will be allowed under this clause for any effects caused on unchanged work.
(E) The contract contains no indication of the soil conditions to be encountered. Caliche-like material is prevalent throughout the Tucson area and the contractor is expected to utilize the proper equipment to excavate the material. Hard digging is not considered a differing site condition.
(F) Archaeological or cultural features shall be treated as noted in Subsection 107-6.
104-10 Miscellaneous Work. The Standard Specifications is modified to add:
General.
Miscellaneous work shall be considered as a part of the total project, and there shall be no separate measurement or payment item for this work.
Miscellaneous Work shall include but not be limited to remobilization to and from the original bid work, equipment facilities and staging areas, minor pavement repair (existing pavement match), and removal of debris and excess material from the site. Miscellaneous Work shall include load testing for hauling legal loads and potholing for utility locations. Dump fees required for disposal of demolished or excess material shall be incidental and included in the respective removal item or total cost of the project.
Damages to public facilities within the right-of-way or on private property caused by the Contractor shall be restored in-kind and at no cost to the Department. Temporary relocation of street, traffic, business, and bus stop signs and mailboxes, unless specifically itemized for the contract, shall be incidental to the overall cost of the project.
Miscellaneous work shall also include all coordination and notification necessary to complete the project. Such coordination shall include, but not be limited to: utility coordination, coordination with businesses and residences for pedestrian and vehicular access, coordination required by the plans and/or the specifications, resident and business owner work hour notification, and all other coordination necessary whether mentioned on the plans or not.
(A) Notification.
Not later than seven (7) calendar days prior to the commencement of work, the Contractor shall distribute notices of the intent of the City of Tucson to begin construction on this project.
The notices shall be distributed to the businesses and residences abutting the project rights-of-way.
Such notices shall be furnished by the Contractor to the Office of the City Engineer for review and approval prior to distribution. The contractor will be required to make enough copies of this notice for distribution. Notices are not to be placed in mailboxes. Where there is no response or there is no answer at the door, the notice is to be left in the door/screen door.
There shall be no separate pay item for the cost of the resident notification and shall be included as a part of the overall project.
SECTION 105 CONTROL OF WORK
105-8 Construction Stakes, Lines and Grades. The second paragraph of the Standard
Specifications is modified to read:
During the course of construction, the contractor shall submit requests for staking. The request shall indicate the type of staking information requested, stations and offsets of anticipated construction, when the area to be staked shall be ready, and when the work will commence.
Depending on the complexity of the work, adequate notice for staking shall be given to the Inspector; however, in no event shall the time be less than 48 hours from the time the area is made ready. The contractor shall include in his schedule time for the staking request to be completed.
105-8 Construction Stakes, Lines and Grades. The fourth paragraph of the Standard
Specifications is revised to read:
The contractor shall be responsible for the preservation of all stakes and marks. If any of the construction stakes or marks have been carelessly or willfully destroyed or disturbed by the contractor, the cost of replacing them shall be charged against the contractor and shall be deducted from payment for work. The charge to re-stake shall be one hundred fifty dollars per hour ($150 per hour). Payments for re-staking shall be paid under bid item 1055001, Re-staking Fees, through a change order.
105-8 Construction Stakes, Lines and Grades. The fifth paragraph of the Standard
Specifications is revised to read:
The Agency shall be responsible for the accuracy of the lines, slopes, grades and other Engineering work which it provides under this Subsection. The contractor shall use said lines, slopes, and grades provided by the Agency in the layout and construction of the applicable improvements. Improvements constructed without use of the marks or grades established by the Agency may be directed to be removed and rebuilt at no cost to the Agency.
105-13 Load Restrictions. The Standard Specifications is modified to add:
The contractor shall coordinate haul routes with the Project Inspector and Traffic Engineering Division. The contractor is responsible for all damage caused by hauling the contractor’s equipment. Residential streets or private parking lots are not designed for use by heavy traffic loads. Hauling equipment operators are required to use major arterial streets.
105-18 Claims. The Standard Specifications is modified to add:
If the contractor rejects the decision of the Department, the dispute or claim will be forwarded to the Procurement Department for resolution in accordance with the Tucson Procurement Code.
105-18.01 Notice of Claims. The Standard Specifications is modified to add:
Reference to the authorized representative shall mean the Procurement Contract Officer.
References to submissions to the Engineer or authorized representative shall be modified to include submissions to both the Engineer and authorized representative.
105-18.02 Submission of Claims. The Standard Specifications is modified to add:
Reference to the authorized representative shall mean the Procurement Contract Officer.
References to submissions to the Engineer or authorized representative shall be modified to include submissions to both the Engineer and authorized representative.
Content of the Claim: The claim shall be in writing and shall include the following information:
(a) The name, address, telephone number and email address of the claimant
(b) The signature of the claimant or its representative
(c) Identification of the solicitation or contract number
(d) A detailed statement of the legal and factual grounds of the claim including copies of relative documents as described in Section A and Section B of the Standard Specifications; and
(e) The form of relief requested.
105-18.03 Decision of Claims. The Standard Specifications is revised to read:
The decision of claims shall be made by the Procurement Department’s Contract Officer in accordance with Tucson Procurement Code Section 28-92.
105-19 ARBITRATION OF CLAIMS AND DISPUTES
The last paragraph of the Standard Specifications is revised to read:
Final decisions, appeals to the director, hearings and mediation shall be made in accordance with the Tucson Procurement Code, Sections 28-92 through 29-98.
105-22 SUBSTANTIAL COMPLETION is hereby added to the Standard Specifications:
The project is substantially complete and liquidated damages will no longer be assessed when all of the following have occurred:
(A) All original bid items of work have been completed and accepted and pedestrian and vehicular traffic can move unimpeded through the project.
(B) The only work left for completion is incidental, causes no disruption to pedestrian and vehicular traffic, and does not affect the safety and convenience of the public.
The decision whether the project is substantially complete is within the sole discretion of the Engineer. Once substantial completion is granted, the Contractor shall actively work to achieve Final Acceptance of the construction phase of the Contract within 15 calendar days from the Substantial Completion date of that phase. Failure to prosecute the remaining work within this time period will result in the resumption of time charges and the application of liquidated damages from the date scheduled for final acceptance.
The Contractor is responsible for maintenance and repairs of any project work until final acceptance, at which time the City will accept the improvements for operation and maintenance.
SECTION 106 CONTROL OF MATERIAL
106-4 TESTS AND ACCEPTANCE OF MATERIALS
The Standard Specifications is revised to read:
106-4 (A) Contractor Quality Control.
The contractor is responsible for quality control measures necessary to provide acceptable quality in production, handling, and placement of all materials. The contractor shall provide all the personnel, equipment, materials, supplies, and facilities necessary to obtain samples and perform tests listed in the applicable section. The contractor shall designate a qualified employee as Quality Control Manager to be responsible for implementing, monitoring, and as necessary, adjusting the processes to assure acceptable quality. All testing shall be performed by a laboratory listed for the tests to be performed in the ADOT Directory of Approved Materials Testing Laboratories, meeting the requirements of “System for the Evaluation of Testing Laboratories.” Sampling and testing shall be performed by and under the direction of ATI and ACI certified technicians and supervisor. The directory and certification requirements may be obtained from the City’s Materials Laboratory at 520-791-3127.
The City will perform the quality assurance testing for the purpose of accepting the contractor’s test results.
Minimum Testing Frequency information is shown in the following tables (Table 106-1) for any appropriate testing required as needed for the items in the project. Additional testing requirements are as specified in the most recent update of Section 900 of the Arizona Department of Transportation, Materials Testing Manual. The contractor may provide certificates of analysis or certificates of compliance for items identified in the City of Tucson/Pima County Standard Specifications for Public Improvement in lieu of the testing requirements of those materials identified in the ADOT Materials Testing Manual.
106-4 (B) Specific Contractor Quality Control Measures.
Quality Control Plan: At the preconstruction conference, the contractor shall designate a qualified employee as Quality Control Manager to be responsible for implementing, monitoring and, as necessary, adjusting the processes to assure acceptable quality. Also at the preconstruction conference, the contractor shall be prepared to discuss his understanding of the quality control responsibilities for the specified materials.
Records: The contractor shall maintain complete testing records and make them available to the Engineer for review and copies as requested.
Weekly Quality Control Reports: The contractor shall submit Weekly Quality Control Reports to the Engineer. The weekly reports shall state the types of work, such as earthwork, Portland cement concrete, or asphaltic concrete, which have been performed during the report period, and shall also include the process control measures taken to assure quality. The weekly report shall provide sample identification information for materials tested during the report period, including sample number, date sampled, sample location, person obtaining sample, and original source of material. The report shall also provide the results for all required tests and any retests, corrective actions, and any other information relevant to quality control. Although hand-written documentation can be included, the quality control report narrative, sample identification information, results for tests and any retests, and corrective actions shall be typed to ensure the Department can make clear reproductions of the documents.
The report period shall end at midnight each Friday, and the report shall be submitted to the Engineer no later than 5:00 p.m. of the following Wednesday or at a time agreed upon by the Engineer.
Table 106-1
CONTRACTOR QUALITY CONTROL TESTING REQUIREMENTS
TYPE OF
TEST
TEST
METHOD
SAMPLING
POINT
MINIMUM TESTING
FREQUENCY
Structural Backfill (203-5, 501, 502, 503, 505, 508, 509, 510, 610, 731, 732, 906 & 920) Gradation ARIZ 201
Stockpile 1 per 500 CY per Source 1 per source PI AASHTO T 89, T 90
Proctor Density ARIZ 225, ARIZ 226, ARIZ 245
1 per Source
Compaction ARIZ 227, ARIZ 230, ARIZ 231, ARIZ 232, ARIZ
235, ARIZ 246
In-place 1 per 200 CY, minimum 1 per lift
Roadway Subgrade Gradation ARIZ 201
Roadway
1 per Soil Type
PI AASHTO T 89, T 90
Proctor Density ARIZ 225, ARIZ 226, ARIZ 245
Compaction ARIZ 227, ARIZ 230, ARIZ 231, ARIZ 232, ARIZ
235, ARIZ 246
Roadway 1 per 1,000 feet
Sidewalk Subgrade Proctor Density ARIZ 225, ARIZ 226, ARIZ 245
Roadway Prism 1 per Soil Type
Compaction ARIZ 227, ARIZ 230, ARIZ 231, ARIZ 232, ARIZ
235, ARIZ 246
Roadway Prism 1 per 2000 square feet of sidewalk and/or 1 per 500 square feet of curb access ramp
Proctor Density ARIZ 225, ARIZ 226, ARIZ 245
In-place 1 per Soil Type
Compaction ARIZ 227, ARIZ 230, ARIZ 231, ARIZ 232, ARIZ
235, ARIZ 246
In-place 1 per 1,000 feet per lift
Borrow Within Three Feet of Finished Subgrade Elevation Gradation ARIZ 201 Stockpile 1 per Source
1 per Source PI AASHTO T 89, T 90 Aggregate Base
Fractured Coarse Aggregate Particles
ARIZ 212
1 per Source
Gradation ARIZ 201
Crusher belt or Stockpile
1 per 600 CY
PI AASHTO T89, T90
Proctor Density ARIZ 225, ARIZ 226, ARIZ 245
1 per Source
Compaction ARIZ 227, ARIZ 230
ARIZ 331, ARIZ 232
ARIZ 235, ARIZ 246
Roadway 1 per 600 CY
Asphaltic Concrete Aggregate (all types) MA for AC Sand Equivalent AASHTO T 176 Cold Feed 1 per 2000 tons of total aggregate.
TYPE OF
TEST
TEST
METHOD
SAMPLING
POINT
MINIMUM TESTING
FREQUENCY
Fractured Course Aggregate Particles
ARIZ 212 Cold Feed 1 per 2000 tons of total aggregate.
Uncompacted Void Content ARIZ 247 Cold Feed 1 per 2000 tons of total aggregate.
Gradation ARIZ 201 Cold Feed 1 per 500 tons Asphaltic Concrete Voids ARIZ 415, ARIZ 417, ARIZ 424
Roadway or Plant 1 per 500 tons of asphaltic concrete production Asphalt Content ARIZ 421, ARIZ 427 or other approved methods Roadway or Plant 1 per 500 tons of each mix
Gradation ARIZ 201 or ARIZ 427 Cold Feed or Plant 1 per 500 tons
Compaction ARIZ 412 OR ARIZ 104, Sec. 3, ARIZ 415, ARIZ 410a
Roadway 1 per 300 tons of asphaltic concrete production, minimum of one per shift
Asphaltic Concrete (Asphalt Rubber) (in addition to the requirements above)
Asphalt Rubber Content ARIZ 421 Roadway 4 times per full shift Nuclear Gauge
Backfill and Bedding Material (501, 502, 508, 510, 511, 732 & 932) Gradation ARIZ 201
Stockpile 1 per 500 CY 1 per Source PI AASHTO T 89, T 90
Proctor Density ARIZ 225, 226, 245 1 per Source Compaction ARIZ 227, 230, 231, 232, 235, 246 In-place 1 per 200 CY, minimum 1 per lift Thermoplastic Striping (704)
Thickness Standard Specification 704- 3.03
In-place 1 per color per production day of long line and of short line
Fine Aggregate for Portland Cement Concrete Gradation ARIZ 201 Crusher Belt or Stockpile 1 every other day
1 every other day Sand Equivalent AASHTO T176 Coarse Aggregate for Portland Cement Concrete
Gradation ARIZ 201 Crusher Belt or Stockpile 1 every other day Class B and Class S Portland Cement Concrete
Entrained Air (above 3,000
ft. elev. only)
AASHTO T 152 At Point of Discharge 1 per 100 Cubic Yards of Ea.
Class of Concrete
Slump AASHTO T 119 At Point of Discharge 1 per 100 CY or fraction thereof of continuously placed concrete, on a daily basis, for each class or source
Temperature ASTM C 1064 At Point of Discharge (SS –1006-5.02 and 5.03)
1 per 100 CY or fraction thereof of continuously placed concrete, on a daily basis, for each class or source
Fabrication of Test Cylinders
AASHTO T 141 At Point of Discharge
(SS-1006-7.02)
1 set per 100 CY or fraction thereof of continuously placed concrete, on a daily basis, for each class or source
TYPE OF
TEST
TEST
METHOD
SAMPLING
POINT
MINIMUM TESTING
FREQUENCY
Compressive Strength Test Cylinders 28 day *
AASHTO T 23 At Point of Discharge
(SS-1006-7.06)
1 set per 100 CY or fraction thereof of continuously placed concrete, on a daily basis, for each class or source
(a) * Additional cylinders may be taken by the contractor for their convenience for early breaks at the contractor’s cost.
(b) For asphalt concrete testing the contractor shall perform the quality control measures described in the table above and the measures detailed below. At the weekly meeting, the contractor shall be prepared to explain and discuss how the following processes will be employed.
(c) Aggregate production, including crusher methods, pit extraction, and washing.
(d) Stockpile management, including stacking methods, separation technique, plant feed technique, stockpile pad thickness, and segregation prevention.
(e) Proportioning and plant control, including plant scale calibration, mix temperature control, storing method, and addition of admixture.
(f) Transporting and placing, including hauling distance and temperature control, segregation and non-uniform placement control, and joint placement and technique.
(e) Compaction, including types and weight of rollers, establishing and monitoring of roller patterns, and temperature controls.
SECTION 107 LEGAL RELATIONS AND RESPONSIBILITY TO PUBLIC
107-6.01 Archaeological Features. The Standard Specifications is modified to add:
In the event that archaeological or historical features are encountered, cease work that could damage the features and contact Desiree Aranda, the City of Tucson Historic Preservation Officer, at 520.837.6968 (office) or 520.780.0251 (mobile) and the Engineer.
107-8 PUBLIC CONVENIENCE AND SAFETY
The Standard Specifications is modified to add:
The contractor shall provide pedestrian and bicycle access at all times, adjacent to the work area. Any disturbance of landscaping by grading needed to provide access shall be replaced when the work is complete. Materials necessary to meet the intent of this requirement shall be removed upon completion. The costs of said work or materials shall be considered incidental to the contract and included in the overall bid price.
In general, business access will be maintained at all times. Where additional driveway access is necessary to provide access and to ensure the safe traffic circulation of large delivery vehicles, secondary driveways or affecting improvements, driveways shall be built one half at a time to provide at least one lane ingress/egress during the respective construction.
107-15 PREVENTION OF LANDSCAPE DEFACEMENT; PROTECTION OF
STREAMS, LAKES AND RESERVOIRS is hereby added to the Standard Specifications:
107-15.01 National Pollution Discharge Elimination System
107-15.01(A) General.
This project is less than 1 acre. The Contractor shall implement the Arizona Department of Environmental Quality (ADEQ) requirements for protecting the quality of stormwater runoff during construction, as specified under the Arizona Pollutant Discharge Elimination System (AZPDES) General Permit for Construction Activities.
The construction activities are considered “Exempt Discharges” under AZPDES General Permit for Construction Activities, Part 1.D.6.b. However, efforts to prevent pollutants from discharging from the project must be utilized by providing, installing, maintaining, removing and disposing of erosion control measures including, but not limited to, such items as gravel filter berms, dikes, catch basin inlet protection, end-of-pipe filtering devices, silt fences, dams, sediment basins, netting, straw bale barriers, slope drains, and other erosion control devices or methods.
107-15.01(B) Materials.
The Contractor shall not be required to prepare a Stormwater Pollution Prevention Plan (SWPPP) but shall follow Best Management Practices in accordance with the AZPDES General Permit for Construction Activities, in conjunction with the City of Tucson Construction Project Manager and the City of Tucson Stormwater Management Section.
A Notice of Intent (NOI) and Notice of Termination (NOT) shall not be required.
107-15.01(C) Construction.
As part of the contractor’s Best Management Practices, the following items shall be considered to protect stormwater quality during the course of construction:
Spill Containment Plan
Stabilized construction entrances
Equipment maintenance procedures Designated washout areas
Protected chemical and materials storage area
Solid Waste Management
Dust control
Construction road stabilizing Protection of catch basins
Sediment traps and barriers Any non-stormwater discharges
107-15.01(D) Method of Measurement.
There shall be no separate measurement for providing ‘good housekeeping’ practices, the cost being considered as included in the price of the other items.
107-15.01(E) Basis of Payment.
No measurement or direct payment will be made for the contractor’s Best Management Practices to protect stormwater quality.
107-21 CONTRACTOR’S RESPONSIBILITY FOR UTILITY PROPERTY AND
SERVICES
The Standard Specifications is modified to add:
The contractor shall contact “Arizona 811” (dial 811 or 1-800-782-5348) a minimum of two
(2) business days prior to commencing construction activities. The contractor shall keep all underground facility location requests up-to-date and comply with Arizona revised statutes (A.R.S.), title 40, chapter 1, Article 6.3, section 40-360.22. Concerns regarding the accuracy between the underground facility markings and the project plans shall be immediately reported to the Engineer.
The following agencies and utility companies have facilities in the area but are not anticipated to be in conflict:
PCRWRD
Thomas Porter
Technical Services and Engineering 201 N. Stone Ave, 3rd Floor
Tucson, AZ 85701 520-724-6719
Pima County Regional Wastewater Reclamation Department (PCRWRD) has sewer an 8” sewer line that runs down the centerline of 2nd Street through the project limits. There are sewer connections that connect to this trunkline that service the dormitories south of 2nd Street.
The sewer main and connections will not be disturbed and shall be protected in place.
Southwest Gas Fernando Soto
Distribution Engineer 3401 E. Gas Road Tucson, AZ 85714
520-262-6551
Southwest Gas (SWG) has a 4” distribution main that runs from Park Ave and heads east and runs under the UA maintenance road/shared use path up to the Harshbarger Pathway and then heads north and runs east under 2nd Street. There are multiple service connections of multiple sizes that run from this gas main that service the UA buildings north and south of 2nd Street.
All these facilities are to be protected in place.
Please be aware that SWG requires a minimum one foot separation from distribution facilities.
Therefore, SWG requests the contractor caution when working in the vicinity of gas facilities.
Please be aware that if structures are to be installed above/underneath these existing SWG facilities, the contractor’s responsibility is to support and protect them in place during construction. If exposed, SWG personnel will have to inspect the gas main to ensure there is no damage prior to re-shading. SWG requests the contractor use extreme caution when crossing or working near existing gas facilities located within the project limits.
Tucson Electric Power Miranda Jackson
Public Improvement Project Manager 4350 East Irvington Road
Tucson, AZ 85714 520-449-4309
Tucson Electric Power (TEP) has facilities near the project limits that are not anticipated to conflict with the project improvements. TEP has reviewed the design with no conflicts identified.
Tucson Water Stephen Espinoza
Distribution Design 310 W. Alameda Street
Tucson, AZ 85701 520-837-9284
Tucson water has a 6” water main that runs from Park Avenue and heads east down the center of James E. Rogers Way. The system tees at the intersection of James E. Rogers Way and heads north and south with a stub out near the beginning of the path improvement with fire hydrant connection behind the northeast radius return.
There are multiple fire hydrant connections that cross the shared use path just south of 2nd Street that service the UA dormitories. Those service connections and the fire hydrants shall not be disturbed as a part of this project and shall be protected in place.
There is a 6” water main along 2nd Street. A 6” main runs under Olive Rd. and heads north under the roadway. All of these facilities that have been identified shall be protected in place.
University of Arizona Information Technology Chris Stebe
Landscape Architect 1200 E University Blvd
Tucson, AZ 85721 520-440-7131
The University of Arizona (UA) has communication facilities that run along the south side of the UA maintenance road/shared use path from just east of Gila Hall and heads east just south of the pathway. The UA owns this infrastructure with third-party communication companies occupying some of these conduits. UA information technology has reviewed the design and identified no conflicts with its facilities.
SECTION 108 PROSECUTION AND PROGRESS
108-4 PROSECUTION AND PROGRESS of the Standard Specifications is modified to add:
The Contractor shall provide the Engineer with a written, detailed work schedule at each weekly construction meeting. This schedule shall document the anticipated construction activities for the upcoming, two-week period. The Contractor must work diligently on this project.