Addendum No. 7 for the McGhee Tyson Airport Terminal Apron Expansion project, issued by CHA Consulting, Inc. on behalf of the Metropolitan Knoxville Airport Authority, provides updates and additional documentation for the Runway 5R-23L Rehabilitation - Project 1. The addendum includes attachments such as boring logs, a Taxiway S Access Road Typical Section, and a Perimeter Road Staking Plan. The document modifies the previous contract documents, with the new items taking precedence over previously published materials. Bidders are advised that the attached information is for informational purposes only and may not be considered entirely accurate, and they are encouraged to conduct their own investigations, such as pavement core sampling, to determine the structural capacity of existing airport roads.
The addendum replaces the Bid Form Page B-4 dated February 9, 2025, with a revised version dated February 28, 2025. The document provides a template for bidders to acknowledge receipt of addenda, state their business address for formal notices, and provide information about their organization. The bid form includes various certifications and statements required for participation, such as non-segregated facilities, identification of principals, financial statements, experience records, and compliance with workplace and immigration regulations. The addendum emphasizes the bidder's responsibility to review and understand the provided materials and make independent assessments of the project requirements.
View the file
Other files
Show all 27
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Addendum No. 7
Project: McGhee Tyson Airport
Terminal Apron Expansion
Project No.: 088400.000
Date: February 28, 2025
The following addendum items modify, change, delete from or add to, the requirements of the contract documents for this project. The articles contained in the addendum take precedence over the requirements of the previously published contract documents. Where any article of the contract specifications or any detail of the contract drawings is modified or any paragraph, subparagraph or clause thereof is modified or deleted by the articles contained in this addendum, the unaltered provisions of that article, paragraph, subparagraph, or clause shall remain in effect.
ITEM NO. 2 – Project Manual
Attachments: The attached boring logs, Taxiway S Access Road Typical Section, and the Perimeter Road
Staking Plan and Typical Sections are added to the Project Manual. The attachments are being provided for informational purposes only and shall not be considers as accurate. The Bidder shall make their own assumptions and determinations as to the accuracy of the information.
If desired, the Bidder may request access to the road to perform additional exploratory investigations such as pavement cores to determine the structural capacity of the existing interior airport roads being used as haul routes.
Deleted: Bid Form Page B-4 dated February 9, 2025 is deleted.
Added: Bid Form Page B-4, Revised by Addendum 6 dated February 28, 2025 is added (attached).
ITEM NO. 4 – ATTACHMENTS
Project Manual
Access Road Boring Logs and Typical Sections
Bid Form Page B-4
Sincerely, Scott Crimmins, PMP
CHA Consulting, Inc.
BID FORM B-4
(i) Certification of Non-segregated Facilities (B-24)
(j) Identification of Principals (B-25)
(k) Financial Statement (B-26)
(l) Experience Record and List of Equipment (B-27)
(m) Performance of Work by Contractor (B-28)
(n) Performance of Work by Subcontractors (B-29)
(o) Bidder Qualification Questionnaire (B-30 to B-33)
(p) Drug Free Workplace Affidavit (B-34)
(q) Statement of Compliance Certificate Illegal Immigrants (B-35)
(r) Certification Against All Debarment (B-36)
9. Name and business address (mailing and street) of Bidder to which all formal Notices shall be sent:
10. The terms used in this Bid which are defined in the General Provisions of the Construction
Contract included as a part of the Contract Documents have the meanings assigned to them in the General Provisions.
11. Bidder hereby acknowledges receipt of the following addenda:
Addendum No. Date
12. The Bidder shall state on the line below, if a corporation or limited liability company, the name of state in which organized and the date of said organization.
Signed this __________ day of _________________, 2025.
MCGHEE TYSON AIRPORT
ALCOA, TENNESSEE
RUNWAY 5R-23L REHABILITATION - PROJECT 1
ADDENDUM 7 - FEBRUARY 28, 2025
Addendum No. Date
RECORD
DRAWINGS
DATE: 12-14-2018
BY: CRS
Text Box
TAXIWAY S ACCESS ROAD
Project: McGhee Tyson Airport
Project Location: Alcoa, TN
Client CHA
Log of Boring B-9
Date(s) Drilled 1/13/2022
Drilling Method Hollow Stem Auger
Drill Rig Type Bobcat Skid Steer
Borehole Backfill Quikrete
Drilling Contractor CML- Knox
Logged By NC
Checked By PA
Sampling Method Undisturbed Shelby Tube
Comments Boring Termination at 7.0 feet
FSE File Number 322016
Total Depth of Borehole 7.0'
Approximate Surface Elevation N/A
Groundwater Depth (ft) N/A
LL
P I, % REMARKS AND OTHER
TESTS
DCP = 8-10-12
P. P. = 3.75
P. P. = 2.75 tsf
P. P. = 4.0 tsf
G ra ph ic
L og
W at er C on te nt
MATERIAL DESCRIPTION
Asphalt (6.8 inches) Compacted Base Stone (3.0 inches) FILL, Very Stiff, Moist, Tan Red Silty CLAY with Gravel
Boring Terminated at 7.0 feet
D ep th fe et
S am pl e
N um be r
S am pl e
T yp e
S am pl in g R es is ta nc e, bl ow s/ ft
E le va tio n (f ee t)
C :\U se rs
\r ha ll\ A pp D at a\
Lo ca l\T em p\ bo rin gs
_t em p\ tm pf ile
.b gs
[F S
E S
P T
0.
tp l]
Sheet 1 of 1
● 2 Split Asphalt Samples 7.6” in Total Core
Length
● 1st Sample – 2 Layers – 3.1” in Total
Length
*1st Layer – 0.9” of Surface Mix with Vugs
*2nd Layer- 2.2” of Base Mix
**Samples Split Cleanly 3.1” in Depth, No
Tack Coat Layer Present
● 2nd Sample – 1 Layer of Base Mix – 4.5” in
Total Length with Large Vugs
● Base Stone – 3.0”
● DCP – 10-6-12
**Approximately 10.6” from Top of Asphalt to Soil Subgrade
● 1 Solid Asphalt Core 6.8” in Total Length
● 1st Layer – 2.3” of Surface Mix with Few
Vugs
● 2nd Layer – 4.5” of Base Mix with
Numerous Vugs (Large in upper 1.5”)
● Base Stone = 3.0” Compacted Base
● DCP – 8-10-12
**Approximately 9.8” from Top of Asphalt to Soil Subgrade