A-Bid Schedule - Addendum 3.xlsm
XLSM spreadsheet 36 KB Posted
- Attached to
- TYS RW 5R-23L Rehab Project 1
- Solicitation number
- IFB-MKAA-0000000002
- Issued by
- Bradley County, Tennessee
About this file
The document is a detailed Bid Schedule (Addendum 3) for the Metropolitan Knoxville Airport Authority's McGhee Tyson Airport Runway 5R-23L Rehabilitation - Project 1 located in Alcoa, Tennessee. The comprehensive bid schedule includes 97 line items covering a wide range of construction and infrastructure services, including temporary erosion control measures, storm pipe installation, pavement removal, electrical work, landscaping, and traffic maintenance. The project involves extensive site preparation, including unclassified excavation (approximately 95,160 cubic yards), clearing and grubbing, tree removal, and infrastructure modifications such as installing various sizes of storm pipes (24-inch to 42-inch), electrical duct banks, and runway/taxiway guidance signs.
The bid schedule indicates a complex airport infrastructure project with multiple technical specifications and no unit pricing currently listed (all line items show $0.00). The project encompasses significant electrical infrastructure work, including cable installations, duct bank construction, junction structures, and fiber optic communication elements. Additional project components include maintenance of traffic, safety plan compliance, temporary runway closure markers, and site-specific requirements like project security, badging, and training. The scope suggests a comprehensive airport runway rehabilitation effort with extensive underground utility, electrical, and surface infrastructure upgrades, potentially funded through airport authority or federal aviation infrastructure investment programs.
View the file
Other files
Show all 27
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
2 - ITEMIZED PROPOSAL
ITEMIZED PROPOSAL
| ITEM NO. | SPECIFICATION | DESCRIPTION OF ITEM | UNIT | QUANTITY | UNIT PRICE | TOTAL |
| 1 | C-102-5.1A | TEMPORARY SEEDING (UNDISTRIBUTED) | KSF | 2,200 | $0.00 | |
| 2 | C-102-5.1B | TEMPORARY MULCHING (UNDISTRIBUTED) | KSF | 2,200 | $0.00 | |
| 3 | C-102-5.1C | TEMPORARY FERTILIZER (UNDISTRIBUTED) | KSF | 2,200 | $0.00 | |
| 4 | C-102-5.1E | SILT FENCE | LFT | 7,000 | $0.00 | |
| 5 | C-102-5.1F | INLET PROTECTION | EA | 25 | $0.00 | |
| 6 | C-102-5.1G | CONSTRUCTION ENTRANCE/EXIT | EA | 1 | $0.00 | |
| 7 | C-102-5.1H | CONCRETE WASHOUT | EA | 1 | $0.00 | |
| 8 | C-102-5.1I | TIRE WASHING FACILITY | EA | 2 | $0.00 | |
| 9 | C-102-5.1J | TYPE 1 SEDIMENT TRAP | EA | 3 | $0.00 | |
| 10 | C-102-5.1K | TYPE 2 SEDIMENT TRAP | EA | 3 | $0.00 | |
| 11 | C-102-5.1L | TYPE 3 SEDIMENT TRAP | EA | 3 | $0.00 | |
| 12 | C-102-5.1M | ROCK CHECK DAM | LFT | 3 | $0.00 | |
| 13 | C-102-5.1N | SEDIMENT TUBES (DITCH APPLICATION) | EA | 18 | $0.00 | |
| 14 | C-102-5.1O | ROCK PIPE INLET PROTECTION | EA | 1 | $0.00 | |
| 15 | C-102-5.1P | FOD CONTROL MAT | EA | 5 | $0.00 | |
| 16 | C-102-5.1Q | EROSION CONTROL BLANKET | SYD | 10,500 | $0.00 | |
| 17 | C-105 | MOBILIZATION | LSUM | 1 | $0.00 | |
| 18 | 701-5.1a | 24-INCH STORM PIPE | LFT | 346 | $0.00 | |
| 19 | 701-5.1b | 30-INCH STORM PIPE | LFT | 742 | $0.00 | |
| 20 | D-701-5.1c | 36-INCH STORM PIPE | LFT | 1,187 | $0.00 | |
| 21 | D-701-5.1d | 42-INCH STORM PIPE | LFT | 477 | $0.00 | |
| 22 | D-701-5.3 | PIPE CRADLE | EA | 1 | $0.00 | |
| 23 | D-705-5.1a | 4-INCH NON-PERFORATED UNDERDRAIN PIPE | LFT | 200 | $0.00 | |
| 24 | D-705-5.1b | 6 INCH NON-PERFORATED UNDERDRAIN PIPE | LFT | 300 | $0.00 | |
| 25 | D-705-5.1c | 6 INCH NON-PERFORATED UNDERDRAIN PIPE (UNDISTRIBUTED) | LFT | 500 | $0.00 | |
| 26 | D-705-5.1d | 8-INCH NON-PERFORATED UNDERDRAIN PIPE | LFT | 500 | $0.00 | |
| 27 | D-751-5.1a | TYPE A INLET | EA | 6 | $0.00 | |
| 28 | D-751-5.1b | TYPE B INLET | EA | 3 | $0.00 | |
| 29 | D-751-5.1c | TYPE 1 CLEANOUT | EA | 1 | $0.00 | |
| 30 | D-751-5.1d | TYPE 2 CLEANOUT | EA | 8 | $0.00 | |
| 31 | P-101-5.1 | PAVEMENT REMOVAL HMA (20 INCH TO 30 INCH) | SYD | 1,700 | $0.00 | |
| 32 | P-101-5.2 | PAVEMENT REMOVAL CONCRETE (20 INCH TO 25 INCH) | SYD | 900 | $0.00 | |
| 33 | P-101-5.3 | REMOVAL OF FOREIGN SUBSTANCES/CONTAMINATES | SFT | 25,000 | $0.00 | |
| 34 | P-101-5.4 | REMOVE STORM SEWER STRUCTURE | EA | 18 | $0.00 | |
| 35 | P-101-5.5 | REMOVE STORM SEWER (24 INCH DIAMETER AND UNDER) | LFT | 1,800 | $0.00 | |
| 36 | P-101-5.6 | REMOVE STORM SEWER (OVER 24 INCH DIAMETER) | LFT | 2,500 | $0.00 | |
| 37 | P-101-5.7 | REMOVE ELECTRICAL OR FIBER OPTIC MANHOLE | EA | 15 | $0.00 | |
| 38 | P-101-5.8 | REMOVE ELECTRICAL BASECAN | EA | 29 | $0.00 | |
| 39 | P-101-5.9 | REMOVE ELECTRICAL CABLE FROM CONDUIT TO REMAIN | LFT | 33,000 | $0.00 | |
| 40 | P-101-5.10 | REMOVE ELECTRICAL OR FIBER OPTIC CABLE AND CONDUIT | LFT | 11,500 | $0.00 | |
| 41 | P-101-5.11 | REMOVE CONCRETE ENCASED ELECTRICAL DUCT BANK AND CABLE | LFT | 1,000 | $0.00 | |
| 42 | P-101-5.12 | REMOVE DISTANCE REMAINING SIGN AND CONCRETE FOUNDATION | EA | 3 | $0.00 | |
| 43 | P-101-5.13 | REMOVE OF DISTANCE REMAINING SIGN | EA | 13 | $0.00 | |
| 44 | P-101-5.14 | REMOVE OF AIRFIELD GUIDANCE SIGN AND SALVAGE | EA | 1 | $0.00 | |
| 45 | P-101-5.15 | ABANDON STRUCTURE | EA | 1 | $0.00 | |
| 46 | P-101-5.16 | ABANDON PIPE (24 INCH) | LFT | 110 | $0.00 | |
| 47 | P-151-4.2 | CLEARING AND GRUBBING | AC | 3 | $0.00 | |
| 48 | P-151-4.3 | TREE REMOVAL | AC | 1 | $0.00 | |
| 49 | P-152-4.1 | UNCLASSIFIED EXCAVATION | CYD | 90,160 | $0.00 | |
| 50 | P-152-4.2 | UNCLASSIFIED EXCAVATION (UNDISTRIBUTED) | CYD | 5,000 | $0.00 | |
| 51 | P-620-5.1a | SURFACE PREPARATION | SFT | 25,000 | $0.00 | |
| 52 | P-620-5.2b | MARKING | SFT | 25,000 | $0.00 | |
| 53 | P-620-5.3c | REFLECTIVE MEDIA | LB | 1,800 | $0.00 | |
| 54 | T-901-5.1 | SEEDING | AC | 50 | $0.00 | |
| 55 | T-904-5.1 | SODDING | SYD | 7,050 | $0.00 | |
| 56 | T-905-5.1 | TOPSOIL | CYD | 11,436 | $0.00 | |
| 57 | T-908-5.1 | MULCHING | AC | 50 | $0.00 | |
| 58 | L-108-5.1 | NO. 6 AWG , 5 KV L824, TYPE C CABLE, INSTALLED IN TRENCH, DUCT BANK, OR CONDUIT | LFT | 5,500 | $0.00 | |
| 59 | L-108-5.2 | NO. 8 AWG, 5 KV L824, TYPE C CABLE, INSTALLED IN TRENCH, DUCT BANK, OR CONDUIT | LFT | 20,000 | $0.00 | |
| 60 | L-109-7.4 | INSTALLATION OF EQUIPMENT WITHIN EXISTING VAULT | EA | 0 | $0.00 | |
| 61 | L-110-5.1 | NON-CONCRETE ENCASED ELECTRICAL DUCT BANK, 1-WAY, 2-INCH | LFT | 1,600 | $0.00 | |
| 62 | L-110-5.2 | NON-CONCRETE ENCASED ELECTRICAL DUCT BANK, 2-WAY, 2-INCH | LFT | 200 | $0.00 | |
| 63 | L-110-5.8 | CONCRETE ENCASED ELECTRICAL DUCT BANK, 12-WAY, 2-INCH (4X3) | LFT | 953 | $0.00 | |
| 64 | L-110-5.9 | CONCRETE ENCASED FAA FOTS DUCT BANK, 1-WAY, 4-INCH | LFT | 5,500 | $0.00 | |
| 65 | L-115-5.2 | ELECTRICAL JUNCTION STRUCTURE - 12 UNIT PULLCAN PLAZA | EA | 2 | $0.00 | |
| 66 | L-115-5.3 | ELECTRICAL JUNCTION STRUCTURE - 8 UNIT PULLCAN PLAZA | EA | 1 | $0.00 | |
| 67 | L-115-5.4 | BASECAN HANDHOLE | EA | 4 | $0.00 | |
| 68 | L-115-5.5 | FAA FIBER OPTIC COMMUNICATION HANDHOLE | EA | 15 | $0.00 | |
| 69 | L-125-5.1 | L-858 RUNWAY/TAXIWAY GUIDANCE SIGN ADB, L-858 TWO MODULE DOUBLE FACE SALVAGED LED GUIDANCE SIGN WITH NEW POURED FOUNDATION | EA | 1 | $0.00 | |
| 70 | EST-03-1 | CONDUIT, 1-WAY, 4-INCH DIRECTIONAL DRILLED | LFT | 700 | $0.00 | |
| 71 | EST-03-2 | CONDUIT, 8-WAY, 2-INCH, DIRECTIONAL DRILLED | LFT | 300 | $0.00 | |
| 72 | MST-02.1 | MAINTENANCE OF TRAFFIC | LSUM | 1 | $0.00 | |
| 73 | MST-02.2 | SAFETY PLAN COMPLIANCE DOCUMENT | LSUM | 1 | $0.00 | |
| 74 | MST-02.3 | CONTROL AND WARNING DEVICES | LSUM | 1 | $0.00 | |
| 75 | MST-02.4 | TEMPORARY RUNWAY CLOSURE MARKERS | MONTH | 6 | $0.00 | |
| 76 | MST-02.5 | ACTIVE TAXIWAY CROSSING GUARD | DAY | 220 | $0.00 | |
| 77 | MST-02.6 | VISUAL BARRIERS | LFT | 20,000 | $0.00 | |
| 78 | MST-02.7 | MOWING | LSUM | 1 | $0.00 | |
| 79 | MST-03.1 | CONSTRUCTION ENGINEERING | LSUM | 1 | $0.00 | |
| 80 | MST-03.2 | RECORD DRAWINGS | LSUM | 1 | $0.00 | |
| 81 | MST-04.1 | PROJECT SECURITY | LSUM | 1 | $0.00 | |
| 82 | MST-04.2 | SECURITY BADGING AND TRAINING | LSUM | 1 | $0.00 | |
| 83 | MST-06 | 16 INCH AGGREGATE BASE COURSE HAUL ROAD (TDOT 303, TYPE A, GRADING D) | SYD | 17,900 | $0.00 | |
| 84 | PST-10.1 | INVERTED FILTER CONSTRUCTION - SHOT ROCK (UNDISTRIBUTED) | TON | 50 | $0.00 | |
| 85 | PST-10.2 | INVERTED FILTER CONSTRUCTION - NO. 2 STONE (UNDISTRIBUTED) | TON | 50 | $0.00 | |
| 86 | PST-10.3 | INVERTED FILTER CONSTRUCTION - NO. 57 STONE (UNDISTRIBUTED) | TON | 50 | $0.00 | |
| 87 | PST-10.4 | INVERTED FILTER CONSTRUCTION - DENSE GRADED AGGREGATE (UNDISTRIBUTED) | TON | 50 | $0.00 | |
| 88 | PST-10.5 | INVERTED FILTER CONSTRUCTION - FLOWABLE FILL (UNDISTRIBUTED) | CYD | 50 | $0.00 | |
| 89 | PST-10.6 | INVERTED FILTER CONSTRUCTION - GEOTEXTILE FABRIC (UNDISTRIBUTED) | SYD | 25 | $0.00 | |
| 90 | PST-10.7 | INVERTED FILTER CONSTRUCTION - STRUCTURAL SOIL FILL (UNDISTRIBUTED) | CYD | 100 | $0.00 | |
| 91 | PST-10.8 | CAP AND COMPACTION GROUTING - MOBILIZATION AND DEMOBILIZATION (UNDISTRIBUTED) | EA | 1 | $0.00 | |
| 92 | PST-10.9 | CAP AND COMPACTION GROUTING - EROSION CONTROL (UNDISTRIBUTED) | EA | 1 | $0.00 | |
| 93 | PST-10.10 | CAP AND COMPACTION GROUTING - CASING INSTALLATION (UNDISTRIBUTED) | LFT | 20 | $0.00 | |
| 94 | PST-10.11 | CAP AND COMPACTION GROUTING - GROUT PLACEMENT (UNDISTRIBUTED) | CYD | 50 | $0.00 | |
| 95 | PST-10.12 | CAP AND COMPACTION GROUTING - SITE RESTORATION (UNDISTRIBUTED) | EA | 1 | $0.00 | |
| 96 | SST-01.1 | SUSTAINABILITY MANAGEMENT PLAN | LSUM | 1 | $0.00 | |
| 97 | N-100 | FIBER OPTIC CABLE, 24 STRAND, SINGLE MODE, IN DUCT | LFT | 10,400 | $0.00 | |
| Total = | $0.00 | |||||
| SUBMITTED BY: | ||||||
| TITLE: | ||||||
| ADDRESS: |
END OF ITEMIZED PROPOSAL
MCGHEE TYSON AIRPORT
ALCOA, TENNESSEE RUNWAY 5R-23L REHABILITATION - PROJECT 1
ADDENDUM 3 - FEBRUARY 25, 2025
BID SCHEDULE BS-&P
File details come from the government source that posted it. Updated .