TO 2 PWS Attch 2 Kelly Base Spec Req Central South vf3.docx

DOCX document 51 KB Posted

Attached to
BASE REALIGNMENT AND CLOSURE (BRAC) ENVIRONMENTAL CONSTRUCTION AND OPTIMIZATION SERVICES (BECOS) Central South Region Federal contract opportunity
Solicitation number
FA890320R0010
Issued by
Department of the Air Force Materiel Command Installation and Mission Support Center Installation Contracting Agency

About this file

This document is a performance work statement (PWS) outlining environmental remediation and monitoring services required at the former Kelly Air Force Base in San Antonio, Texas. Services include properly plugging and abandoning shallow groundwater wells, conducting land use control inspections and five-year review reports, and maintaining web-based mapping systems for wells. The contractor will be responsible for all community involvement and public meeting requirements. Relevant documents include the hazardous waste permit and compliance plan for the base. Transition of work is currently being conducted under contract FA8903-09-D-8580 Task Order 11, with field support completion by June 30, 2020 and final reporting by September 25, 2020.

View the file

Other files for this federal contract opportunity

Other files attached to BASE REALIGNMENT AND CLOSURE (BRAC) ENVIRONMENTAL CONSTRUCTION AND OPTIMIZATION SERVICES (BECOS) Central South Region, newest first.
File Type Posted
05202020_FA8903-20-R-0010_Two Questions.xlsx XLSX spreadsheet
FA8903-20-R-0010_BECOS RFP Questions_05-15-20.xlsx XLSX spreadsheet
20200511_FA8903-20-R-0010_BECOS RFP Questions and Answers.xlsx XLSX spreadsheet
Solicitation Amendment FA890320R00100002 SF 30 (002).pdf PDF
FA890320R0010 Central South Amendment Changes.docx DOCX document
20200427_Central South TO2 Price Model Amendment 01.xlsx XLSX spreadsheet
FOUO_Attach2_Reference_Docs_Homestead_Central_Southv4.docx DOCX document
20200427_FA8903-20-R-0010_BECOS RFP Questions and Answers.xlsx XLSX spreadsheet
Solicitation Amendment FA890320R00100001 SF 30 (1).pdf PDF
20200427_FA890320R0010_BECOS_Central South_Section_L Amendment 01.docx DOCX document
TX20190231 10042019 Bexar Building.pdf PDF
CO20190002 09272019 Denver Heavy.pdf PDF
TO 2 PWS Attch 2 England Base Spec Req Central South vf2.docx DOCX document
IDIQ PWS Central South BECOS vf4.docx DOCX document
IDIQ DD1423 CDRLS EXHIBIT B002-B003 (MGMT) Central South BECOS vf1.pdf PDF
20200131_FA890320R0010_BECOS_Relevancy_Matrix v2.docx DOCX document
IDIQ DD1423 CDRLS EXHIBIT A001-A002-A004 (MISC) Central South BECOS vf1.pdf PDF
20200203_FA890320R0010_BECOS_Central South_Section_L v5.docx DOCX document
20200131_FA890320R0010_BECOS_Relevancy_PPQ v2.docx DOCX document
TX20190280 10042019 Lubbock Building.pdf PDF
IDIQ DD1423 CDRLS EXHIBIT A007-A008-A009 (ENVR) Central South BECOS vf1.pdf PDF
20200122_Central South FFP FBLR Tables.xlsx XLSX spreadsheet
20191217_Compensation Plan Model.xlsx XLSX spreadsheet
20200109_Central South TO2 Price Model.xlsx XLSX spreadsheet
IDIQ DD1423 CDRLS EXHIBIT C001 (MGMT) Central South BECOS vf1.pdf PDF
TO 2 PWS Attch 2 Carswell Base Spec Req Central South vf2.docx DOCX document
IDIQ DD1423 CDRLS EXHIBIT B004 (CMAN) Central South BECOS vf1.pdf PDF
TX20190026 10042019 Tarrant Heavy.pdf PDF
TX20190271 10042019 Travis Building.pdf PDF
IDIQ PWS Attch 4 Central South Perf Obj Def and Req BECOS vf2.docx DOCX document
TO 1 CDRLs Exhibit A B Central South BECOS vf1.docx DOCX document
IDIQ DD1423 CDRLS EXHIBIT A010 (QCIC) Central South BECOS vf1.pdf PDF
TO 2 PWS Attch 2 Bergstrom Base Spec Req Central South vf2.docx DOCX document
TO 2 PWS Attch 2 Reese Base Spec Req Central South vf5.docx DOCX document
Solicitation FA890320R0010 Central South.pdf PDF
TX20190002 01042019 Lubbock Heavy.pdf PDF
20200131_FA8903-20-R-0010_BECOS RFP Questions and Answers Template v2.xlsx XLSX spreadsheet
IDIQ DD1423 CDRLS EXHIBIT B005-B006-B007 (ADMN) Central South BECOS vf1.pdf PDF
FL20190215 10252019 Miami-Dade Building.pdf PDF
TO 2 PWS Attch 2 Myrtle Beach Base Spec Req Central South vf2.docx DOCX document
TO 2 PWS Attch 1 Central South Site List BECOS vf8.xlsx XLSX spreadsheet
FL20190125 11012019 Miami-Dade Heavy.pdf PDF
AR20190022 10252019 Mississippi County Building.pdf PDF
IDIQ DD1423 CDRLS EXHIBIT A014 (DRPR) Central South BECOS vf1.pdf PDF
Central South IDIQ_Sched B_CLIN Structure and Price Model_v1_02032020.xlsx XLSX spreadsheet
TO 2 PWS Attch 2 Homestead Base Spec Req Central South vf2.docx DOCX document
TO 2 CDRLs Exhibit A B Central South BECOS vf1.docx DOCX document
IDIQ PWS Attch 3 Central South Del Rev Process BECOS vf2.docx DOCX document
TO 2 PWS Attch 2 Eaker Base Spec Req Central South vf2.docx DOCX document
TO 2 PWS Central South BECOS vf3.docx DOCX document
Show all 50

BASE REALIGNMENT AND CLOSURE (BRAC) ENVIRONMENTAL CONSTRUCTION AND OPTIMIZATION SERVICES (BECOS) Central South Region has more files on GovTribe.

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

FA4890-06-R-9999

Attachment 1

APRIL XX, 2009

- final – fa8903-20-r-0010 to 2 Attachment 2 Central South Region - Kelly 5 December 2019

1.1 Scope

The former Kelly AFB is not listed on the National Priorities List (NPL). Environmental restoration is executed through the Texas Commission on Environmental Quality (TCEQ) issued Resource Conservation and Recovery Act (RCRA) post-closure care permit and compliance plan, consequently there is no Federal Facility Agreement or Records of Decision. Property transfer at the former Kelly AFB was completed in 2010.

In addition to the requirements presented in this PWS, this scope includes the following:

· Properly plug and abandon all former Kelly AFB shallow groundwater wells no longer regulatory required in Zones 2, 3, 4 and 5 and outside the former Kelly AFB’s base boundary and not needed for future PFC investigations.

Contractors are not responsible for the following:

· Investigation and remediation of PFAS, except as noted in Attachment 1.

1.3 Applicable Documents

Key Documents

Entry No.
Document Title
Location
Date Issued
1
Class 2 Permit/Compliance Plan Modification to Hazardous Waste Permit and Compliance Plan No. 50310

Industrial Solid Waste Registration No. 31750, former Kelly Air Force Base, San Antonio, Texas

AR#558124.3

Pages 1333 to 1398 October 15, 2015

2
Hazardous Waste Permit and Compliance Plan No. 50310, Industrial Solid Waste Registration No. 31750, Former Kelly Air Force Base, San Antonio, Texas. Permit and Compliance Plan renewal will likely occur prior to award of this PBR. (Permit revision to be issued 4th quarter of 2019)
AR#3926
April 13, 2009

1.4 Work Ramp-Up and Transition

Transition of Work

Contract No.
Project Name
Field Support

Complete Reporting Complete

Worldwide Environmental Restoration and Construction 2009 (WERC-09) Contract FA8903-09-D-8580, Task Order No. 11
Performance Based Remediation Services at the Former Kelly Air Force Base and Joint Base San Antonio – Lackland (JBSA-LAK)
6/30/2020
9/25/2020

2.6.1 Meeting/Teleconference Support

· Former Kelly BCT meetings are currently held on a semi-annually basis. BCT meetings are typically held in San Antonio at an off-site location, typically at a hotel located in proximity to the former Kelly AFB.

2.6.2 Public Meetings and Hearings

· The Contractor is responsible for all community involvement requirements to meet RCRA and other regulatory requirements including public meetings and public notices in English and Spanish.

· The former Kelly AFB restoration advisory board (RAB) has been adjourned, however, the Air Force may elect to conduct Ad-Hoc meetings to inform the San Antonio community of the environmental cleanup progress.

2.6.5 Site Access: Permits, Easements, and Work Site Access

· The Contractor may be required to prepare and to obtain regulatory approval for modifications to existing Kelly AFB RCRA Permit based upon the Contractor’s proposed technical approach for achieving the objectives of this TO.

3.4 Computer Aided Design Drawing (CADD) and Geographic Information Systems (GIS) Updates

· The Contractor shall maintain a web-based mapping system of active monitoring/recovery wells and abandoned wells (e.g. Web AppBuilder for ArcGIS).

· The Contractor shall be responsible for creating and updating semiannually a web-based GIS system of all current shallow groundwater wells and adding any new wells as they are installed during this TO.

6.14 Land Use Controls (LUC)

· The Contractor shall conduct LUC/IC inspections for sites identified in Attachment 1. Currently LUC/IC monitoring is held on an annual basis.

6.15 Five-Year Reviews

· The Contractor shall prepare a Five-Year Review Report for sites identified in Attachment 1. The next Five-Year Review is due June 2025.

· The Contractor shall implement all Five-Year Review recommendations included in the 2020 Kelly AFB Five-Year Review being prepared by another Contractor (the PBR contractor will have an opportunity to review the 2020 document prior to submittal to the regulators).

File details come from the government source that posted it. Updated .