This document contains questions and answers regarding Solicitation Number FA890320R0010 for Base Realignment and Closure (BRAC) Environmental Construction and Optimization Services (BECOS) for the Central South Region. Key details include that the solicitation is from the Department of the Air Force for environmental remediation and monitoring services at multiple installations, including Kelly Air Force Base, Homestead Air Force Base, Reese Air Force Base, Myrtle Beach Air Force Base, and England Air Force Base. The questions and answers provide clarification on the scope of work such as requirements for five-year review reports, permit renewals, well abandonment, and long-term monitoring programs. Pricing and labor rate information is also addressed.
View the file
Other files for this federal contract opportunity
Show all 50
BASE REALIGNMENT AND CLOSURE (BRAC) ENVIRONMENTAL CONSTRUCTION AND OPTIMIZATION SERVICES (BECOS) Central South Region has more files on GovTribe.
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Sheet1
| Q # | Document Reference | RFP QUESTIONS | DATE RCVD | Document Reference | GOV'T RESPONSE | RESPONSE DATE |
| 1 | TO 2 PWS Attachment 2 | Kelly Base Specific Req states that |
“The Contractor shall prepare a Five-Year Review Report for sites identified in Attachment 1. The next Five-Year Review is due June 2025.”
Question: Will the 2030 Five Year Review be also included in this contract?
| 2 | TO 2 PWS Attachment 2 | 1. Kelly Base Specific Req states that “The Contractor may be required to prepare and to obtain regulatory approval for modifications to existing Kelly AFB RCRA Permit based upon the Contractor’s proposed technical approach for achieving the objectives of this TO.” Question: Is 2029 renewal of RCRA Permit/Compliance Plan included in this contract? |
| 3 | TO 2 PWS Attachment 2 | Is renewal of Texas Pollution Discharge Elimination System (TPDES) permit for Kelly AFB in 2025 and 2030 included in the contract? |
| 4 | TO 2 PWS Attachment 2 | Kelly Base Specific Req states that: |
“In addition to the requirements presented in this PWS, this scope includes the following:
Properly plug and abandon all former Kelly AFB shallow groundwater wells no longer regulatory required in Zones 2, 3, 4 and 5 and outside the former Kelly AFB’s base boundary and not needed for future PFC investigations. Question: (a) How will determination be made for abandonment of wells in offsite areas in Zone 4 and 5? Is the deciding factor in determining whether wells at one of these sites can be abandoned based on whether or not the site has reached SC? (b) Will sampling of wells be required before abandonment? (c) Please provide number of wells anticipated to be abandoned in each of Zones 2, 3, 4, and 5. (d) Please provide how many wells will need to be retained for PFAS investigation
| 5 | Pricing Model: | Performance Objective for Kelly AFB sites SS036 and SS050 is RA-O. Is AF anticipating in situ bioremediation injections to be performed as part of RA-O to expedite achievement of RC or SC, even though RC or SC are not Performance Objectives for these two sites under this contract? | |||
| 95 | TO 2 PWS | For installations with active remediation systems with underground piping, is the BECOS contractor required to register utilities and LUC boundaries with utility locate services, and respond to locate requests. | 13-May-20 | TO 2 PWS | Yes, Contractor responsibility for utility notification and locate requirements are identified in PWS Para 2.6.5. This also applies to all remedies active or not and includes all components of the remedies including wells. Specifically for former Kelly AFB, former Kelly AFB - there is a requirement to respond to the Local Reuse Authority's locate requests to protect installed active AF remediation systems. Registering with utility locate services is not required. |
| 96 | TO 2 PWS | Attachment 2 Homestead AFB, Section 1.1, 1st bullet: Please confirm the referenced OWS is different than the former OWS removed in 1993-1994. If so, please provide location and background information on this OWS. It is not identified in the available historical documents. | 13-May-20 | TO 2 PWS | The OWS referenced in Attachment 2 Homestead AFB, Section 1.1 is different than the OWS removed in 1993-1994. |
The OWS was discovered at 25 29'53''N, 80 23'10''W during the excavation of Area 12 at OU-28 in 2019/2020. The OWS is approximately 42 inches wide, 92 inches long, and 60 inches deep. All liquids from the OWS were removed and were disposed of as hazardous waste in January 2019 (11, 55-Gallon Drums). The excavation performed at Area 12 included the removal of most soil adjacent the OWS without impacting the integrity of the structure; therefore, there is still some soil immediately surrounding the OWS that may be impacted with contaminants. Note that a figure has been uploaded to the Google Drive for reference since the draft report of excavation of soil at OU-28 is not yet available.
97 TO 2 PWS Please identify BECOS Central South sites that are known to be contaminated with PFOA/PFOS and require special waste handling, and identify maximum concentrations for comparison to AF's guidance document (e.g., At SD019 site at Myrtle Beach, what are the current PFOS/PFOA concentrations in groundwater sampling purge water needed to identify the required disposal facility). 13-May-20 TO 2 PWS Kelly - PFOS/PFOA sampling in not currently being conducted at IRP sites included in this TO. Purge water generated from groundwater sampling activities is treated at the Zone 2 GWTP. Groundwater from several treatment systems is directed to the Zone 2 GWTP. The post UV/OX, pre-GAC treatment concentrations are 0.551 ug/L PFOS and 0.127 ug/L PFOA. There are currently no TCEQ TPDES dicharge criteria for PFOS/PFOA. The disposal or regeneration of spent GAC must comply with AF guidance.
Reese - NA, there is no groundwater monitoring required for IRP sites included in the TO. Myrtle Beach - Wells in the vicinity of Site SD019 have PFOS+PFOA (summed) levels ranging from 0.239 to 1.705 ug/L for individual monitoring well samples. For England AFB, see Final Site Inspection Report for AFFF Areas at Former England AFB, AR 592556 (7 parts).
| 98 | TO 2 PWS, Section 3.2 | The PWS calls for a QPP. A) please confirm the QPP is programmatic covering all installations and should be included in the CLIN1 PMP pricing or specify alternate location. B) please confirm that base/ site specific addenda are to to be included in site specific CLINs. | 13-May-20 | TO 2 PWS | The QPP is base-specific and should be included in the base year site-specific CLINs. The QPP (i.e., UFP-QAPP) is a program/technical document that undergoes Air Force and regulatory review. The PMP is programmatic for the BECOS region and undergoes Air Force review only. B) Base/site specific addenda are to be included in the site-specific CLINs in the appropriate year that the addenda is required. |
| 99 | TO 2 PWS | Please confirm that 4 wells at the BH01 Area of Spill Site SS045 at England AFB are not to be included in the SS045 LTM events per the 2019 Arcadis work plans for SS045 (AR #593520). The 2019 RECAP Report recommended that 4 wells at the BH-01 Area be included in the SS045 LTM Program for sampling on an annual frequency (AR 592079). | 13-May-20 | TO 2 PWS | The four wells at BH01 Area of Spill Site SS045 will be included in the SS045 LTM events as found in the Final RECAP report BH-01 Area of Spill Site SS-045. |
| 100 | TO 2 PWS | Indicate whether sampling of the 4 wells at BH01 Area of Spill Site SS045 at England AFB is part of the scope of TO02. | 13-May-20 | TO 2 PWS | Sampling of the 4 wells at BH01 Area of Spill Site SS045 at England AFB is part of the scope of TO02. |
| 101 | Section L 5.5.c | Please confirm that if an Offeror is proposing as an unpopulated JV and each member is proposing separate FBLRs, the managing member rates should be included as the prime offeror as the JV Offeror will not have separate labor rates. | 13-May-20 | Section L 5.5.c | If each member of an unpopulated JV is proposing separate FBLRs, each member proposing FBLRs shall complete a separate FBLR tab in the FFP FBLR Table. |
If the JV is proposing one (1) team FBLR per LCAT for the entire team the FBLRs shall be entered in the prime tab of the FFP FBLR Table.
| 102 | Professional Compensation Plan Model | If an Offeror's standard accounting practice is that Fringe is a sub-pool of overhead and not separately applied, please clarify whether only the fringe rate or all indirect markups should be applied to the base rate should be included in the compensation model. If only the fringe rate is applied, it will not match the FBLR. | 13-May-20 | Professional Compensation Plan Model | Base Hourly Salary and Fringe rates are NOT the entire labor burden that would be included in the FBLRs but only two (2) elements of fully burdened labor. The Compensation Plan Excel Model shall include only the fringe rate NOT other indirect markups. |
| 103 | Wage Determinations | Please confirm whether or not SCA wage determinations (WD) will apply to categories such as engineering technician and clerical. If yes, please provide the applicable WDs. | 13-May-20 | Wage Determinations | The categories that do fall under SCA are incidental as they comprise less than 10% of the overall labor and therefore the SCA wage determinations are not included for the IDIQ. The company will still need to follow applicable department of labor standards for employees. |
| 15 | |||||
| 16 | |||||
| 17 | |||||
| 18 | |||||
| 19 | |||||
| 20 |