TGI_3819P55107T03_c0v0_redact.pdf
PDF 95 KB Posted
- Attached to
- USS BLUE RIDGE 5C1 DSRA MODERNIZATION BUNDLE 4
- Solicitation number
- N6264925RA052
About this file
This document is a Task Group Instruction (TGI) for the USS Blue Ridge, specifically focused on the Oily Waste Water System Tightness and Operational Test. The TGI is dated 06-MAR-2025 and is associated with Project 19P and System 59321, with a job summary ID of 551G2107. The document outlines work tasks for three groups: Contractor (22/KE), Quality Assurance (33/G1), and Support/Facilities (S/F), all of whom are required to accomplish and document the tightness and operational test in accordance with the referenced technical procedure TP 59321-3-300KTR. The instruction is marked FOUO (For Official Use Only) and involves personnel from different departments, including Kouichiro Noda (Prepared By), Jason Y. Ohta (Approved By), and Yasuhiko Takahashi (Zone Manager).
View the file
Other files
Show 40 more
50 files listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
FOUO
WebAIM Short Form TASK GROUP INSTRUCTION
06-MAR-2025 1517
20.14.15.2.9020 (September 2024) ICN: 3819P55107 KeyOp: T03
COMPONENT NAME: TYPE: PHASE: REPEAT: CHG/VER:TGI NO: 59321-3-300KTR TT T 1 0/0
SHIP/HULL NO: SHIP/HULL NAME: PROJECT: SYSTEM: PLANT ID: CASREP CAT:
LCC-19 USS BLUE RIDGE 19P 59321
CU PHASE TITLE: OILY WASTE WATER SYS (T & OP), S/A 72976K - KTR
WORK CERTIFICATION SIGNATURES: DLs
COMPLETION OF WORK REVIEW: BADGE NO: SHOP/CODE: PHONE: DATE:
RECORDS REVIEW: BADGE NO: SHOP/CODE: PHONE: DATE:
FOUO Pg 1 of 2
EXSAZBV2
PREPARING ACTIVITY: STATUS: APP WORKING STATUS:
PREPARED BY: CODE: PHONE: DATE:
NODA, KOUICHIRO 246.2 3152434116 11-FEB-2025
APPROVED BY: CODE: PHONE: DATE:
OHTA, JASON Y. 246.2 3152435901 06-MAR-2025
CONCURRED BY: CODE: PHONE: DATE:
REASON FOR WORK/NEED FOR CHANGE:
JCN:
EXSA-ZBV2
SPECIAL REQUIREMENTS:
CU PHASE DESCRIPTION:
ZONE MANAGER: ZONE: COMPARTMENT: LEVEL: FRAME: SIDE:
TAKAHASHI, YASUHIKO U
JOB SUMMARY ID: TOT MAN HR.: TOT DUR: TOT JML COST: PLANNING ACCEPTANCE:
551G2107
Tightness & Operational Test for Oily Waste Water System - KTR.
TGI Short Form
FOUO
WebAIM Short Form TASK GROUP INSTRUCTION
06-MAR-2025 1517
20.14.15.2.9020 (September 2024) (Continued) ICN: 3819P55107 KeyOp: T03
COMPONENT NAME: TYPE: PHASE: REPEAT: CHG/VER:TGI NO: 59321-3-300KTR TT T 1 0/0
SHIP/HULL NO: SHIP/HULL NAME: PROJECT: SYSTEM: PLANT ID: CASREP CAT:
LCC-19 USS BLUE RIDGE 19P 59321
CU PHASE TITLE: OILY WASTE WATER SYS (T & OP), S/A 72976K - KTR
FOUO Pg 2 of 2
Ref.
No.
Document/Drawing Number DOCUMENT/DRAWING TITLE REV
CHG
NO.
CPY
REQ PARAGRAPH SECT PG CHPT
1 TP 59321-3-300KTR OILY WASTE WATER SYS (T)
- KTR
LAT Y
TASK NAME / TASK DESCRIPTION
SHOP/
TSD TS
SF
WC
CREW
# MHRS RWRK
(V) Contractor work:
Accomplish/document the tightness & operational test in accordance with reference, TP 59321-3-300KTR.
22/KE PC N
(G) QA work:
Accomplish/document the tightness & operational test in accordance with reference, TP 59321-3-300KTR.
33/G1 QA N
(S) S/F work:
Accomplish/document the tightness & operational test in accordance with reference, TP 59321-3-300KTR.
/ EXSA N
MATERIAL LIST
ITEM
NO.
PC
NO.
REF
NO.
M
C DESCRIPTION
STOCK
NUMBER
GENERIC
MATL
TYPE LVL QA
HAZ
MAT
DOC
NO.
QTY
REQD/
UNIT
QTY
USED/
UNIT
MATERIAL REFERENCES
REF
NO.
DOCUMENT/DRAWING NUMBER DOCUMENT/DRAWING TITLE
REV
ICN: 3819P55107 KEY OP: T03