TGI_3819P51602T01_c0v0_redact.pdf

PDF 97 KB Posted

Attached to
USS BLUE RIDGE 5C1 DSRA MODERNIZATION BUNDLE 4
Solicitation number
N6264925RA052
Issued by

About this file

This document is a WebAIM Short Form Task Group Instruction (TGI) for the USS Blue Ridge, dated 13-MAR-2025, specifically focused on the Chill Water System Tightness & Operational Test. The TGI is part of the FY25 5C1 Dry-Docking Selected Restricted Availability (DSRA) Modernization Bundle 4 for the ship, with reference number TP 51411-3-300KTR. The task involves contractor, quality assurance, and ship/facility work to accomplish and document the tightness and operational test of the chill water system, with work to be performed at the US Naval Base Yokosuka, Ship Repair Facility - Japan Regional Maintenance Center (SRF-JRMC).

The document includes detailed sections for task description, with work to be performed by contractor (22/KE), quality assurance (33/G1), and ship/facility teams, though no specific man-hours or material requirements are populated in the material list sections. The TGI is part of a larger naval ship repair and modernization effort with a period of performance from 12-Jan-2026 through 15-May-2027, involving multiple task group instructions and 21 test phases of ship repair, overhaul, preservation, and replacement work.

View the file

Other files

File Type Posted
N6264925RA0520004.pdf PDF
N6264925RA0520003.pdf PDF
TGI_3819P58316A01_c0v0_redact.pdf PDF
TGI_3819P55107T05_c0v0_redact.pdf PDF
TGI_3819P55107T09_c0v0_redact.pdf PDF
TGI_3819P51602T09_c0v0_redact.pdf PDF
TGI_3819P55107T08_c0v0_redact.pdf PDF
TGI_3819P55107T01_c0v0_redact.pdf PDF
TGI_3819P51602T07_c0v0_redact.pdf PDF
TGI_3819P51602T12_c0v0_redact.pdf PDF
TGI_3819P51602T04_c0v0_redact.pdf PDF
TGI_3819P51602T01_c0v0_redact.pdf PDF
N6264925RA0520002.pdf PDF
TGI_3819P55107T07_c0v0_redact.pdf PDF
TGI_3819P55107T06_c0v0_redact.pdf PDF
TGI_3819P55107T04_c0v0_redact.pdf PDF
TGI_3819P51602T10_c0v0_redact.pdf PDF
TGI_3819P51602T06_c0v0_redact.pdf PDF
TGI_3819P51602T02_c1v1_redact.pdf PDF
TGI_3819P51602T03_c0v0_redact.pdf PDF
N6264925RA0520001.pdf PDF
TGI_3819P55107T03_c0v0_redact.pdf PDF
TGI_3819P55107T04_c0v0_redact.pdf PDF
TGI_3819P51602T08_c0v0_redact.pdf PDF
TGI_3819P51602T04_c0v0_redact.pdf PDF
Attachment VII Warranty Tracking Information.pdf PDF
Attachment III GFP_List_rev1.xlsx XLSX spreadsheet
TGI_3819P55107A01_c0v0_redact.pdf PDF
TGI_3819P58316T01_c0v0_redact.pdf PDF
TGI_3819P55107T06_c0v0_redact.pdf PDF
TGI_3819P55107T08_c0v0_redac.pdf PDF
TGI_3819P55107T09_c0v0_redac.pdf PDF
TGI_3819P51602T07_c0v0_redact.pdf PDF
TGI_3819P51602T11_c0v0_redact.pdf PDF
TGI_3819P51602T06_c0v0_redact.pdf PDF
Exhibit (A) CDRL BUNDLE 4 signed.pdf PDF
Attachment V Contract data.pdf PDF
2.01 N6264925RA052 Solicitation.pdf PDF
TGI_3819P55107T01_c0v0_redact.pdf PDF
TGI_3819P55107T07_c0v0_redact.pdf PDF
TGI_3819P55107T05_c0v0_redact.pdf PDF
TGI_3819P51602T05_c0v0_redact.pdf PDF
TGI_3819P51602T03_c0v0_redact.pdf PDF
TGI_3819P51602T02_c1v1_redact.pdf PDF
TGI_3819P51602T12_c0v0_redact.pdf PDF
Attachment VIII Source of Repair Instruction.pdf PDF
Attachment IV RFI.docx DOCX document
Attachment II Proposal Sheet Generator v1.2 .xlsx XLSX spreadsheet
TGI_3819P58316A01_c0v0_redact.pdf PDF
TGI_3819P51602A02_c2v1_redac.pdf PDF
Show 40 more

50 files listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

FOUO

WebAIM Short Form TASK GROUP INSTRUCTION

13-MAR-2025 0955

20.14.15.2.9020 (September 2024) ICN: 3819P51602 KeyOp: T01

COMPONENT NAME: TYPE: PHASE: REPEAT: CHG/VER:TGI NO: 51411-3-300KTR TT T 3 0/0

SHIP/HULL NO: SHIP/HULL NAME: PROJECT: SYSTEM: PLANT ID: CASREP CAT:

LCC-19 USS BLUE RIDGE 19P 51411

CU PHASE TITLE: CHILL WATER SYS (T & OP), S/A 83424K - KTR

WORK CERTIFICATION SIGNATURES: DLs

COMPLETION OF WORK REVIEW: BADGE NO: SHOP/CODE: PHONE: DATE:

RECORDS REVIEW: BADGE NO: SHOP/CODE: PHONE: DATE:

FOUO Pg 1 of 2

EXSAZC54

PREPARING ACTIVITY: STATUS: APP WORKING STATUS:

PREPARED BY: CODE: PHONE: DATE:

FUKUDA, YUUJI 246.2 3152435265 25-FEB-2025

APPROVED BY: CODE: PHONE: DATE:

OHTA, JASON Y. 246.2 3152435901 12-MAR-2025

CONCURRED BY: CODE: PHONE: DATE:

REASON FOR WORK/NEED FOR CHANGE:

JCN:

EXSA-ZC54

SPECIAL REQUIREMENTS:

CU PHASE DESCRIPTION:

ZONE MANAGER: ZONE: COMPARTMENT: LEVEL: FRAME: SIDE:

YAGINUMA, TAKEHIDE U

JOB SUMMARY ID: TOT MAN HR.: TOT DUR: TOT JML COST: PLANNING ACCEPTANCE:

516G1002

Tightness & Operational Test for Chill Water System - KTR.

TGI Short Form

FOUO

WebAIM Short Form TASK GROUP INSTRUCTION

13-MAR-2025 0955

20.14.15.2.9020 (September 2024) (Continued) ICN: 3819P51602 KeyOp: T01

COMPONENT NAME: TYPE: PHASE: REPEAT: CHG/VER:TGI NO: 51411-3-300KTR TT T 3 0/0

SHIP/HULL NO: SHIP/HULL NAME: PROJECT: SYSTEM: PLANT ID: CASREP CAT:

LCC-19 USS BLUE RIDGE 19P 51411

CU PHASE TITLE: CHILL WATER SYS (T & OP), S/A 83424K - KTR

FOUO Pg 2 of 2

Ref.

No.

Document/Drawing Number DOCUMENT/DRAWING TITLE REV

CHG

NO.

CPY

REQ PARAGRAPH SECT PG CHPT

1 TP 51411-3-300KTR CHILL WATER SYS (T & OP) -

KTR

LAT Y

TASK NAME / TASK DESCRIPTION

SHOP/

TSD TS

SF

WC

CREW

# MHRS RWRK

(V) Contractor work:

Accomplish/document the tightness & operational test in accordance with reference, TP 51411-3-300KTR.

22/KE PC N

(G) QA work:

Accomplish/document the tightness & operational test in accordance with reference, TP 51411-3-300KTR.

33/G1 QA N

(S) S/F work:

Accomplish/document the tightness & operational test in accordance with reference, TP 51411-3-300KTR.

/ EXSA N

MATERIAL LIST

ITEM

NO.

PC

NO.

REF

NO.

M

C DESCRIPTION

STOCK

NUMBER

GENERIC

MATL

TYPE LVL QA

HAZ

MAT

DOC

NO.

QTY

REQD/

UNIT

QTY

USED/

UNIT

MATERIAL REFERENCES

REF

NO.

DOCUMENT/DRAWING NUMBER DOCUMENT/DRAWING TITLE

REV

ICN: 3819P51602 KEY OP: T01