TGI_3819P55107T01_c0v0_redact.pdf
PDF 95 KB Posted
- Attached to
- USS BLUE RIDGE 5C1 DSRA MODERNIZATION BUNDLE 4
- Solicitation number
- N6264925RA052
About this file
This document is a WebAIM Short Form Task Group Instruction (TGI) for a Low Pressure Air (Tightness & Operational) Test for the USS Blue Ridge (LCC-19). The TGI is dated 06-MAR-2025 with document number 55121-3-300KTR, associated with Project 19P and System 5512. The instruction details specific contractor, quality assurance (QA), and support function (S/F) work tasks to accomplish and document a tightness and operational test for the Low Pressure Air System, referencing technical procedure TP 55121-3-300KTR. Key personnel include Yuuji Fukuda (preparer), Jason Y. Ohta (approver), and Yasuhiko Takahashi (zone manager), with the document marked as For Official Use Only (FOUO).
View the file
Other files
Show 40 more
50 files listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
FOUO
WebAIM Short Form TASK GROUP INSTRUCTION
06-MAR-2025 1517
20.14.15.2.9020 (September 2024) ICN: 3819P55107 KeyOp: T01
COMPONENT NAME: TYPE: PHASE: REPEAT: CHG/VER:TGI NO: 55121-3-300KTR TT T 2 0/0
SHIP/HULL NO: SHIP/HULL NAME: PROJECT: SYSTEM: PLANT ID: CASREP CAT:
LCC-19 USS BLUE RIDGE 19P 55121
CU PHASE TITLE: LOW PRESSURE AIR (T & OP), S/A 72976K - KTR
WORK CERTIFICATION SIGNATURES: DLs
COMPLETION OF WORK REVIEW: BADGE NO: SHOP/CODE: PHONE: DATE:
RECORDS REVIEW: BADGE NO: SHOP/CODE: PHONE: DATE:
FOUO Pg 1 of 2
EXSAZBV2
PREPARING ACTIVITY: STATUS: APP WORKING STATUS:
PREPARED BY: CODE: PHONE: DATE:
FUKUDA, YUUJI 246.2 3152435265 11-FEB-2025
APPROVED BY: CODE: PHONE: DATE:
OHTA, JASON Y. 246.2 3152435901 06-MAR-2025
CONCURRED BY: CODE: PHONE: DATE:
REASON FOR WORK/NEED FOR CHANGE:
JCN:
EXSA-ZBV2
SPECIAL REQUIREMENTS:
CU PHASE DESCRIPTION:
ZONE MANAGER: ZONE: COMPARTMENT: LEVEL: FRAME: SIDE:
TAKAHASHI, YASUHIKO U
JOB SUMMARY ID: TOT MAN HR.: TOT DUR: TOT JML COST: PLANNING ACCEPTANCE:
551G2107
Tightness & Operational Test for Low Pressure Air System - KTR.
TGI Short Form
FOUO
WebAIM Short Form TASK GROUP INSTRUCTION
06-MAR-2025 1517
20.14.15.2.9020 (September 2024) (Continued) ICN: 3819P55107 KeyOp: T01
COMPONENT NAME: TYPE: PHASE: REPEAT: CHG/VER:TGI NO: 55121-3-300KTR TT T 2 0/0
SHIP/HULL NO: SHIP/HULL NAME: PROJECT: SYSTEM: PLANT ID: CASREP CAT:
LCC-19 USS BLUE RIDGE 19P 55121
CU PHASE TITLE: LOW PRESSURE AIR (T & OP), S/A 72976K - KTR
FOUO Pg 2 of 2
Ref.
No.
Document/Drawing Number DOCUMENT/DRAWING TITLE REV
CHG
NO.
CPY
REQ PARAGRAPH SECT PG CHPT
1 TP 55121-3-300KTR LOW AND MEDIUM
PRESSURE AIR (T & OP) -
KTR
LAT Y
TASK NAME / TASK DESCRIPTION
SHOP/
TSD TS
SF
WC
CREW
# MHRS RWRK
(V) Contractor work:
Accomplish/document the tightness & operational test in accordance with reference, TP 55121-3-300KTR.
22/KE PC N
(G) QA work:
Accomplish/document the tightness & operational test in accordance with reference, TP 55121-3-300KTR.
33/G1 QA N
(S) S/F work:
Accomplish/document the tightness & operational test in accordance with reference, TP 55121-3-300KTR.
/ EXSA N
MATERIAL LIST
ITEM
NO.
PC
NO.
REF
NO.
M
C DESCRIPTION
STOCK
NUMBER
GENERIC
MATL
TYPE LVL QA
HAZ
MAT
DOC
NO.
QTY
REQD/
UNIT
QTY
USED/
UNIT
MATERIAL REFERENCES
REF
NO.
DOCUMENT/DRAWING NUMBER DOCUMENT/DRAWING TITLE
REV
ICN: 3819P55107 KEY OP: T01
File details come from the government source that posted it. Updated .