This document is a WebAIM Short Form Task Group Instruction (TGI) for the USS Blue Ridge (LCC-19), dated 13-MAR-2025, focusing on a Modular Refrigeration Unit (6-52-2 Op) with project number 19P and system 51611. The task involves a tightness and operational test for the Modular Refrigeration Unit, with work to be performed by a contractor (22/KE), quality assurance team (33/G1), and support/follow-up team (EXSA). The primary reference document is TP 51611-3-313KTR, which provides detailed instructions for conducting the test. Key personnel include Mizushima Masaki (prepared by), Ohta Jason Y. (approved by), and Yaginuma Takehide (zone manager), with the document marked as For Official Use Only (FOUO).
View the file
Other files
Show 40 more
Latest 50 of 61 listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
FOUO
WebAIM Short Form TASK GROUP INSTRUCTION
13-MAR-2025 1049
20.14.15.2.9020 (September 2024) ICN: 3819P51602 KeyOp: T08
COMPONENT NAME: TYPE: PHASE: REPEAT: CHG/VER:TGI NO: 51611-3-313KTR TT T 5 0/0
SHIP/HULL NO: SHIP/HULL NAME: PROJECT: SYSTEM: PLANT ID: CASREP CAT:
LCC-19 USS BLUE RIDGE 19P 51611
CU PHASE TITLE: MODULAR REFRIGERATION UNIT 6-52-2 (OP), S/A 83424K - KTR
WORK CERTIFICATION SIGNATURES: DLs
COMPLETION OF WORK REVIEW: BADGE NO: SHOP/CODE: PHONE: DATE:
RECORDS REVIEW: BADGE NO: SHOP/CODE: PHONE: DATE:
FOUO Pg 1 of 2
EXSAZC54
PREPARING ACTIVITY: STATUS: APP WORKING STATUS:
PREPARED BY: CODE: PHONE: DATE:
MIZUSHIMA, MASAKI 246.2 3152434112 25-FEB-2025
APPROVED BY: CODE: PHONE: DATE:
OHTA, JASON Y. 246.2 3152435901 12-MAR-2025
CONCURRED BY: CODE: PHONE: DATE:
REASON FOR WORK/NEED FOR CHANGE:
JCN:
EXSA-ZC54
SPECIAL REQUIREMENTS:
CU PHASE DESCRIPTION:
ZONE MANAGER: ZONE: COMPARTMENT: LEVEL: FRAME: SIDE:
YAGINUMA, TAKEHIDE U
JOB SUMMARY ID: TOT MAN HR.: TOT DUR: TOT JML COST: PLANNING ACCEPTANCE:
516G1002
Tightness & Operational Test for MODULAR REFRIGERATION UNIT - KTR.
TGI Short Form
FOUO
WebAIM Short Form TASK GROUP INSTRUCTION
13-MAR-2025 1049
20.14.15.2.9020 (September 2024) (Continued) ICN: 3819P51602 KeyOp: T08
COMPONENT NAME: TYPE: PHASE: REPEAT: CHG/VER:TGI NO: 51611-3-313KTR TT T 5 0/0
SHIP/HULL NO: SHIP/HULL NAME: PROJECT: SYSTEM: PLANT ID: CASREP CAT:
LCC-19 USS BLUE RIDGE 19P 51611
CU PHASE TITLE: MODULAR REFRIGERATION UNIT 6-52-2 (OP), S/A 83424K - KTR
FOUO Pg 2 of 2
Ref.
No.
Document/Drawing Number DOCUMENT/DRAWING TITLE REV
CHG
NO.
CPY
REQ PARAGRAPH SECT PG CHPT
1 TP 51611-3-313KTR MODULAR REFRIGERATION
UNIT (T & OP) - KTR
LAT Y
TASK NAME / TASK DESCRIPTION
SHOP/
TSD TS
SF
WC
CREW
# MHRS RWRK
(V) Contractor work:
Accomplish/document the tightness & operational test in accordance with reference, TP 51611-3-313KTR.
22/KE PC N
(G) QA work:
Accomplish/document the tightness & operational test in accordance with reference, TP 51611-3-313KTR.
33/G1 QA N
(S) S/F work:
Accomplish/document the tightness & operational test in accordance with reference, TP 51611-3-313KTR.
/ EXSA N
MATERIAL LIST
ITEM
NO.
PC
NO.
REF
NO.
M
C DESCRIPTION
STOCK
NUMBER
GENERIC
MATL
TYPE LVL QA
HAZ
MAT
DOC
NO.
QTY
REQD/
UNIT
QTY
USED/
UNIT
MATERIAL REFERENCES
REF
NO.
DOCUMENT/DRAWING NUMBER DOCUMENT/DRAWING TITLE
REV
ICN: 3819P51602 KEY OP: T08