This is a Technical Specifications document prepared by the Florida Department of Transportation (FDOT) for Contract Number ITB 24-040B on behalf of Flagler County Board of County Commissioners. The project involves the widening and resurfacing of County Road 205, Phase 2, extending approximately 1.9 miles from State Road 100 to a private dirt road (Station 98+00/Mile Post 1.856) in Flagler County, Florida. The scope of work includes roadway widening and resurfacing, full-depth roadway repair and reconstruction of designated sections, maintenance of traffic, clearing and grubbing, grading and excavation, embankment work, guardrail installation, stormwater improvements, signage, pavement markings, and all related incidental work as outlined in the Base Bid. The project must comply with Americans with Disabilities Act (ADA) requirements, and all pay items are detailed in the Bid Submission Form (BS-1). The specifications package was digitally signed and sealed by John A. Dillard, Jr., Professional Engineer (Florida License No. 37256) of Zev Cohen & Associates on February 17, 2026, and is based on the FY 2025-26 Edition of Florida Department of Transportation Standard Specifications.

The specifications modify Division II, Section 105 (Control of Materials) by eliminating the requirement for test data to be entered into FDOT and/or Flagler County databases. All costs for work shown on plans or called for in the contract documents must be included in the prices for bid items, with no additional direct payment to be made for work or materials required to complete any bid item. The contractor is responsible for ensuring that any modifications to the contract documents are submitted in writing to the Engineer for written approval prior to implementation.

View the file

Other files

File Type Posted
County_Road_205_Phase_2_Roadway_Widening_&_Resurfacing_From_SR_100_to_Private_Dirt_Road_FPN_433614-2-54-01_(Addendum_#6_Revision).pdf PDF
Question_&_Answer_Questions_24_and_25.pdf PDF
Question_&_Answer_Report_.pdf PDF
CAD_Files_Zip.zip ZIP file
Pre-Bid_Meeting_Sign_In.pdf PDF
County_Road_205_Phase_2_Roadway_Widening_&_Resurfacing_From_SR_100_to_Private_Dirt_Road_FPN_433614-2-54-01.pdf PDF
Melodie_Park_Pond_Dock_Decking_Construction_Project.pdf PDF
Melodie_Park_2026-012126-Proposed.pdf PDF
Community_Development_Block_Grant_Funds.pdf PDF
Payroll_Form_WH-347.pdf PDF
Intructions_For_Completing_Payroll_Form_WH-347.pdf PDF
FEDERAL_LABOR_STANDARDS_PROVISIONS.pdf PDF
BID_FORM_8H_Listing_of_Subcontractors.pdf PDF
BID_FORM_8G_Professional_References_for_Previous_Experience.pdf PDF
BID_FORM_8J_Bid_Bond.pdf PDF
STANDARD_AGREEMENT_FOR_SERVICES.pdf PDF
BID_FORM_8B__Bid_Form_.pdf PDF
BID_FORM_8E_Anti-Collusion_Statement.pdf PDF
BID_FORM_8D_Public_Entity_Crimes_Statement.pdf PDF
BID_FORM_8F_Statement_of_Vendor_Qualifications.pdf PDF
BID_FORM_8C_Drug-Free_Preference_Statement.pdf PDF
1_14144_CR_205_-_PH2_(ss)_Project_Plans.pdf PDF
20251015_Permit_ACOE.pdf PDF
SJRWMD_CR205_8603838.pdf PDF
Project_Forms.pdf PDF
Payment_and_Performance_Bond_Form_337_18_Example.pdf PDF
Example_of_Contract_Form.pdf PDF
Example_of_Warranty_Bond_Form.pdf PDF
Show all 28

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

FPID(S): 433614-2-54-01

-1-

REISSUED February 17, 2026

PREPARED BY: John Dillard

SPECIFICATION PACKAGE

Contract Number: ITB 24-040B

FINANCIAL PROJECT ID(S).433614-2-54-01

DISTRICT FIVE

FLAGLER COUNTY

The FY 2025-26 Edition of the Florida Department of Transportation Standard Specifications is revised as follows:

I hereby certify that this specifications package has been properly prepared by me, or under my responsible charge, in accordance with procedures adopted by the Florida Department of

Transportation.

This item has been digitally signed and sealed by John A Dillard, Jr. on the date adjacent to the seal. Printed copies of this document are not considered signed and sealed and the signature must be verified on any electronic copies.

Date: 2/17/2026

State of Florida, Professional Engineer, License No.: Fl.# 37256

Firm/Agency Name: Zev Cohen & Associates

Firm/Agency Address: 300 Interchange Blvd., Suite C

City, State, Zip Code: Ormond Beach, Florida 32174

Page(s): 5 Pages

-2-

TABLE OF CONTENTS

SCOPE OF WORK - INTENT OF CONTRACT…………………………………..….………3

DIVISION II

SECTION 105 - CONTROL OF MATERIALS……………………………………………….4

THIS COMPLETES THIS SPECIFICATIONS PACKAGE……..……………………….5

-3-

SCOPE OF WORK – INTENT OF CONTRACT.

(REV 10-25-21) (FA 1-26-22) (FY 2025-26)

ARTICLE 4-1 is expanded by the following:

The Improvements under this Contract consist of It is the intent of the Plans and Contract

Documents to complete the WIDENING AND RESURFACING OF COUNTY ROAD 205, PHASE 2 (from SR 100 to Private Dirt Road at STA 98+00/MP 1.856) and associated improvements in Flagler County, Florida, in conformance with the project plans and contract documents. The construction project length along County Road 205 is approximately ±1.9 miles.

The project shall be fully compliant with the Americans with Disabilities Act (ADA). The scope of work includes but is not limited to the following: Construction of roadway improvements along an approximate ±1.9-mile section of County Road 205 from State Road 100 to a private dirt road, identified at STA 99+43 on the project construction plans. This project will include widening and resurfacing of the roadway, full depth roadway repair/reconstruction of certain sections, maintenance of traffic, clearing and grubbing, grading excavation and embankment, guardrail, stormwater improvements, signage, pavement markings and other related items incidental to the work as the Base Bid. The summary of pay items for this project is listed in the Bid Submission Form (BS-1). Any commission or omission shown or implied shall not be cause for deviating from the intent of the Contract Documents. If any modifications of the

Contract Documents are deemed necessary by the Contractor, details of such modifications and the reasons therefore shall be submitted in writing to the Engineer for written approval prior to beginning such modified work. All costs required to perform the work shown on the plans or called for in the Contract Documents shall be included in the prices for the various items in the

Bid Form. No additional direct payment will be made for any work or materials required to complete any of the bid items, but the cost therefore shall be included in the price bid for that item, whether specifically so noted or not. Items for which no direct payment shall be made include but are not necessarily

-4-

105 CONTRACTOR QUALITY CONTROL GENERAL REQUIREMENTS

SUBARTICLE 105-1.1.2. is deleted and the following substituted:

Test data shall not be required to be entered into any FDOT and/or Flagler County databases.

-5-

THIS COMPLETES

THIS

SPECIFICATIONS

PACKAGE

2026-02-17T15:02:55-0500
This Item has been digitally signed and sealed by John A. Dillard, Jr. on the date adjacent to the seal. Printed copies of this document are not considered signed and sealed and the signature must be verified on any electronic copies.
John A Dillard