Technical Information Library Specifications.pdf
PDF 670 KB Posted
- Solicitation number
- 36C24821R0082
About this file
This pre-solicitation notice announces a design-build contract opportunity to replace eight air handling units at the West Palm Beach VA Medical Center in Florida. The contract value is estimated between $2 million to $5 million. The Department of Veterans Affairs Network Contracting Office 8 will issue a solicitation on or around May 12, 2021 seeking proposals from service-disabled veteran-owned small businesses to provide design-build services for replacing air handling units 9, 15, 17, 24, 28, 29, 34, and 39. The selected contractor will be responsible for designing, demolishing, and constructing new air handling systems, mixing boxes, filter sections, heating and cooling valves, actuators, all dampers, and pneumatic controls. The work must be completed at the West Palm Beach VA Medical Center located at 7305 N. Military Trail, West Palm Beach, Florida. The closing date for responses to the forthcoming solicitation is June 14, 2021. Additional details will be posted on beta.SAM.gov when the solicitation is issued.
View the file
Other files
Show 40 more
Latest 50 of 54 listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
11-01-15
00 11 21-1
SECTION 00 11 21
REQUEST FOR PROPOSAL TO DESIGN BUILD
REPLACE AIR HANDLING UNITS 9,15,17,28,24,29,34,39
548-18-605
WEST PALM BEACH VA MEDICAL CENTER
A. PART I - GENERAL
A1. Scope of Contract
Provide all labor, materials, tools and equipment, and design-build services necessary for design and construction of a project described here in other specific tasks as further defined by this request for proposal (RFP).
Replace Air Handling Units 9,15,17,28,24,29,34,39
Provide all labor, materials, tools and equipment, and design-build services necessary for design and construction of a project described here called “Replace Air Handling Units 9,15,17,28,24,29,34,39”. Work involves designing, demolition, and installation of eight (8) new air handler systems to replace existing air handler units, heating and cooling valves, actuators, ultraviolet lights, and all dampers.
Structural engineer shall review existing steel support frames and modify as required for new Air Handling Units. Work involves modifying plumbing systems, electrical systems, building automation systems, structural steel frame as required and air distribution supply, return and exhaust systems. All units shall be designed and sized to allow return air and adjustable minimum 15% outside air with new electric/digital modulating dampers according to current VA and ASHRAE standards and VA HVAC Design Manual November 2017 edition.
All cooling coils shall be selected for maximum dehumidification and factory coated as per VA specifications.
Outside air flow sensors shall have 2% accuracy or better. Return, relief/exhaust air flow sensors shall have 3% accuracy or better. All existing air flow stations shall be removed and replaced. Existing shut off valves will be replaced with same size new shut off valves.
Interior of air handler unit casings shall be stainless steel, outside return and exhaust air dampers shall be opposed blade, aluminum with stainless steel hardware and shall be coated at factory with epoxy, with switch package to remotely indicate damper blade position. All
00 11 21-2 motors shall be premium efficiency motors. Provide VFD’s for AHUs and associated exhaust and return systems as required. VFDs shall be Eaton or approved equal with soft start, manual bypass switch and NEMA 12 box. All return and exhaust fans shall be inspected for proper operation.
All AHU’s shall meet the latest ASHRAE and VA design standards. These standards can be found at https://www.cfm.va.gov/til/
Temporary air conditioning units “will” be utilized to install new units without major disruption to the affected areas. Temporary air will be designed to mee the CFM and discharge temperature of the existing units.
Certified Independent Third-Party (CITP) Consultant
The Design Build Contractor is responsible to obtain a CITP to review drawings in refence to NFPA Life Safety and Fire Protection Compliance per VHA Directive 7712.
1. In each submission, the DB Contractor shall incorporate all material specified and all revisions according to comments made by the Department of Veterans Affairs, as well as the CITP.
2. For the final construction documents, the DB Contractor will be required to submit written documentation, signed by the CITP that the design has been reviewed to be compliant with Statement of
Work.
Contractor to provide all labor, materials, tools and equipment to provide a comprehensive survey to the Government of all of the rooms impacted by the replacement of air handlers 9, 15, 17, 24, 28, 29, 34, 39. The survey shall include a map of the rooms, identifying the room number and purpose of the room. The purpose of this survey is to assist the
COR in communicating to the end users the areas impacted by the shutdown of the air handlers during the scheduling phase.
A2. Definitions
A. Design-Build (DB) as defined by the Department of Veterans Affairs (VA) is the procurement by the Government, under one contract, with one firm
00 11 21-3 or joint venture (JV) for both design and construction services for a specific project.
1. Contracting Officer: The services to be performed under this contract are subject to the general supervision, direction, control and approval of the Contracting Officer.
2. Project Manager: The Contracting Officer's representative responsible for administering contracts under the immediate direction of the Contracting Officer.
3. COR: The Contracting Officer's authorized representative at the construction site. The COR is responsible for protecting the
Government's interest in the execution of the construction contract work. His duties include surveillance of all construction work to assure compliance with the contract documents, interpretation of the contract documents, approval of all submittals, samples, shop drawings, etc. The COR may “NOT” issue change orders to the
Contractor. Only the Contracting Officer has the authority to make changes to the contract.
4. Design Build Contract: This term, as used herein, refers to the
Contract(s) to perform the design and construction of the project.
5. Contractor: This term, as used herein, refers to the contractor under this contract or the DB team.
6. AE: This term, as used herein, refers to the Architect-Engineer firm(s)that are a part of the DB team, also referred to as DB/AE.
B. Selection Procedure - During the review of offers the VA may ask for additional information. The VA may initiate action to award a contract at any point after review of the offers. Therefore, offers should reflect the offeror’s best terms both from a technical and cost standpoint. See FAR 52. 215-1, Instructions to Offerors - Competitive Acquisition (Jan
2004.
C. Tentative Schedule:
Reserved.
D. Schedule Objectives - The anticipated completion of this project is 365 days after “Notice to Proceed” (NTP). The proposed schedule may be shorter than this, see Part III, C3, 3c.
A3. Cost Range
The anticipated cost range for this project is between $2 million and
$5 million.
00 11 21-4
A4. Pre-Proposal Conference
See solicitation documentation.
A5. Selection Criteria and Weightings
See solicitation documentation.
B. PART II - RESPONSIBILITIES
B1. VA Team
A. The Contracting Officer will administer the contract and is the only individual that has the authority to modify the contract.
B. The VA team is also comprised of a COR who will be located at the construction site and VA medical center staff. The coordinator/manager of the VA team will be the COR, who’s duties will include surveillance of all construction work to assure compliance with the contract documents, interpretation of the contract documents, approval of all submittals, samples, shop drawings, and serve as the Contracting
Officers Technical Representative.
B2. Design-Build Team:
A. The DB team includes all J/V partners, consultants and sub-contractors to the one firm. The DB team shall provide Architectural and
Engineering disciplines for the preparation of construction documents, and construction contractor capabilities for construction of the project.
B. If the DB Team A/E and contractor are a J/V (not one and the same firm) engineering and other technical consultants shall be subcontractors of the J/V Architect - not the Design-Build construction contractor or sub-contractors. If the DB Team A/E and contractor are one and the same firm (not a J/V) those consultants shall be subcontractors of DB firm not the construction subcontractors.
C. The RFP documents are intended to define existing conditions, certain required items, and design parameters to be included in the project. It is the DB Team’s responsibility to complete the documents and construction in a manner consistent with the intent of the RFP documents within the required time period (contract length).
C. PART III - PROPOSAL REQUIREMENTS
C1. General
A. See Solicitation Documentation.
00 11 21-5
D. PART IV - POST AWARD REQUIREMENTS
D1. Construction Document Preparation:
A. Design Review Submissions:
1. The Design-Build Team A/E (DB A/E) shall prepare and submit complete construction documents for review and approval by the VA in accordance with standard professional practice, the Department of
Veterans Affairs RFP (VA RFP), and prevailing codes.
2. The documents may be divided into multiple review submission packages.
3. All submission packages will be reviewed at (30%) and (95%) completion stages. The (95%) review submission packages will incorporate the final review comments from the (30%) review. If any package is not complete for the required stage a post review may be required the cost of which will be borne by the DB Team.
4. Each review submission package shall include 5 hard copy sets and 2 set on CD-ROM. The package will include an index of drawings (by sheet number and title) and specifications (by section number and tittle) submitted. The packages will be distributed to the VA
Project Manager, the VA Medical Center, and others as determined to be appropriate by the VA Project Manager.
B. Design Review Meetings:
1. A review meeting to resolve design issues will be held for each design review package submitted. The meeting will include discussion of VA comments on functional relationships and technical peer review comments (by others).
2. Participants will include, VA Staff and DB team members as appropriate for the specific package to be reviewed and others. The
DB team members will each allow for (1) full day for each discipline/package design review meeting. DB team management will be present at each review meeting.
3. The DB team shall allow a minimum of ten (10) working days for each review cycle. A cycle includes:
a. The VA’s receipt of the design review submission package.
b. The review meeting.
c. DB teams receipt of comments from the VA, either electronically, by fax, or by hard copy delivery.
4. Coordination of the review meeting schedules will be the responsibility of the VA Project Manager (for the VA) and the DB
00 11 21-6
Team Project Manager (for the DB Team). See section H. Quality
Assurance/Quality Control.
C. Electronic Media:
1. Design review submission drawings and final Construction Document submission drawings will be executed in electronic format AutoCAD version 2018 or later
2. The drawings included in the VA RFP will be available to the DB team in electronic format in AutoCAD version 2018 or later for use in preparing the construction drawings. Since data stored on electronic media can deteriorate undetected or be modified without the VA’s knowledge, the CADD drawing files are provided without warranty or obligation on the part of the VA as to accuracy or information contained in the files. The user shall independently verify all information in the files. Any user shall agree to indemnify and hold the VA harmless from any and all claims, damages, losses, and expenses including, but not limited to, attorney’s fee arising out of the use of the CADD drawing files.
3. Design review submission specifications and other 8 1/2 by 11 formatted material and final Construction Document submission specifications and other 8 1/2 by 11 formatted material will be executed in electronic format Microsoft Office.
4. The specifications included in the VA RFP shall be available to the
DB team in electronic format in Microsoft Office, for use in preparing the construction specifications. Since data stored on electronic media can deteriorate undetected or be modified without the VA’s knowledge, the PDF version drawing files are provided without warranty or obligation on the part of the VA as to accuracy or information contained in the files. The design builder shall independently verify all information in the files and shall agree to indemnify and hold the VA harmless from any and all claims, damages, losses, and expenses including, but not limited to, attorney’s fee arising out of the use of the electronic files.
5. The construction record drawings shall be completed in AutoCAD version 2018 or later.
6. Construction shop drawings are not required to be completed in
AutoCAD.
D. Professional Licensing:
00 11 21-7
1. The DB A/E who prepares the construction documents shall be a professional architect or engineer licensed in the State of Florida which the design work is completed.
2. The professional seal indicating such license by the state shall appear on the final construction documents. The architect whose seal is shown will be known as the Architect of Record. The DB A/E shall certify compliance with the VA RFP and all applicable codes.
E. Approved Construction Documents:
1. The final construction document submission package will be submitted by the DB team for approval by the VA after completion of the 95% review cycle for the final package to be submitted by the DB team.
The VA will have 5 days to take approval action.
2. The final construction documents submission package will include a full set of construction documents including all disciplines/packages.
3. The final construction documents submission package will incorporate all VA supplied comments from the earlier 30% and 95% submission package reviews and will comply with the VA RFP.
4. If the final construction documents submission package is not complete a post submittal may be required the cost of which will be borne by the DB Team.
5. The approved final construction documents include such details that the project can be constructed and will be used for construction of the project.
6. See PART IV, D2 CONSTRUCTION PERIOD SUBMITTALS for Approved
Construction Document distribution.
F. Construction Drawing Preparation - Mandatory material and equipment schedules and details may be indicated either on the drawings or in the specifications, at the option of the DB team. The construction drawings shall include a coordinated set of the following:
1. Structural drawings including foundation plans, framing plans, schedules, and details, including general notes and all calculations.
2. Architectural drawings including floor plans, and other details.
3. Fire protection drawings including floor and roof plans, riser diagrams, equipment schedules, and details, including general notes calculations and all related calculations.
00 11 21-8
4. HVAC drawings including floor and roof plans, one-line flow diagrams, equipment schedules, and details, including general notes and all related calculations. Also provide sections for mechanical equipment rooms and sequence of operation for all HVAC equipment.
5. Electrical drawings including site demolition plans, site, floor and roof plans (power, lighting, and other systems), one-line diagrams, panel schedules, equipment schedules, light fixture schedules calculations and details
G. Construction Specifications - Project specifications shall include specifications for all products, materials, equipment, methods, and systems shown on the construction drawings in accordance with standard professional practice and the VA RFP. The specification submitted for review shall include:
1. The name of the manufacturer, the product name, model number, or other identification as appropriate to clearly identify the product that will be used in the construction of the project;
2. Other data as appropriate to clearly identify the product that will be used in the construction of the project i.e. shop drawings, product data, and samples as required by the VA RFP documents; and
3. The required stamp of the licensed architect or engineer of record will be considered as certification of compliance with the RFP requirements.
H. Design Requirements - Compliance with codes and standards.
1. Project design shall be in compliance with applicable standards and codes described in VA Program Guides and design materials included or referenced in the solicitation materials.
2. See Section E. Approved Construction documents, above, for required inclusion of design review comments.
3. In the design of new building and alteration work under this contract, the DB team shall consider all requirements (other than procedural requirements) of:
l. Zoning laws:
2. Environmental and erosion control regulations; and
3. Laws relating to landscaping, open space, minimum distance of a building from the property line, maximum height of a building, historic preservation, and esthetic qualities of a building. Also similar laws, of the State and local political division, which
00 11 21-9 would apply to the building if it were not to be constructed or altered by the U.S. Government.
4. The DB and VA shall give due consideration to the recommendations of the referenced building officials. VA will also permit inspection by the officials described above during the construction period in accordance with the customary schedule of inspections in the locality of the building construction. Such officials shall provide
VA with a copy of the schedule before construction begins or give reasonable notice of their intention to inspect before conducting an inspection.
5. The DB team shall provide prompt, written notification to the
Contracting Officer concerning conflicts with, or recommended deviations from codes, laws, regulations, standards, and opinions of review officials as described above. No work altering the scope of this contract shall be undertaken prior to receipt of written approval from the Contracting Officer.
6. No action may be brought against the DB Team or VA and no fine or penalty may be imposed for failure to carry out any of the previously described recommendations of Federal, state, or local officials. VA and its contractors, shall not be required to pay any amount for any action taken by a state or political division of a state in carrying out functions described in this article, including reviewing plans, carrying out on-site inspections, issuing permits, and making recommendations.
7. The DB team shall advise the Contracting Officer of any variances with the applicable Department of Labor, Occupational Safety and
Health Standards, for occupancy requirements.
I. Quality Assurance/Quality Control:
1. To reduce design errors and omissions, the DB team shall develop and execute a QA/QC plan that demonstrates the project plans and specifications have gone through a rigorous, thorough review and coordination effort.
2. Within 2 weeks of receipt of Notice to Proceed, the DB Team will submit a detailed QA/QC plan describing each QA/QC task that will be taken during the development of the various design submission packages and the name of the DB Team member responsible for QA/QC.
a. Upon its completion each task shall be initialed and dated by the responsible DB Team member.
00 11 21-10
b. A 100% completed QA/QC plan shall be submitted with the final construction document submission package.
D2. Construction Period Submittals
A. The DB contractor shall distribute a total of 3 sets of the approved construction documents prepared by the DB Team to the VA, as directed by the VA Project Manager.
B. Other submittals - The DB team shall submit test results, certificates, manufacturer’s instructions, manufacturers field reports, etc. as required by the VA RFP specifications, to the VA COR.
C. Project record drawings - The DB team will maintain a set of construction documents (field as-built drawings) to record actual construction changes during the construction process as required by the
RFP specifications. The project record drawings will be available for review by the VA COR at all times.
D. Shop drawings and submittals - The DB A/E shall check government furnished and/or the DB construction contractor's shop drawings, detail drawings, schedules, descriptive literature and samples, testing labor-laboratory reports, field test data and review the color, texture and suitability of materials for conformity with the RFP Documents and construction documents. The DB A/E shall recommend approval, disapproval, or other suitable disposition to the VA COR. The VA CO will have final approval authority. The DB AE shall evaluate the submittals with reference to any companion submittals that constitute a system. When necessary, the DB A/E will request the DB Construction
Contractor to submit related components of a system before acting on a single component. Should this procedure be inappropriate, the DB A/E shall review all prior submittals for related components of the system before acting on a single component. The DB A/E may be required to hold joint reviews with the VA technical staff on complicated system submittals. The DB A/E shall notify the VA CO in writing of any and all deviations from the requirements of the construction documents that he has found in the submittals.
D3. Project Close-Out
The DB team shall comply with the requirements in FAR 4.804 Closeout of
Contract Files, for submission of final RFP as built drawings, manuals, and other documents as noted. Required as built drawings and specifications will be submitted in the same format required for the construction documents.
00 11 21-11
D4. Site Visits and Inspections
During the construction period the DB A/E shall make weekly visits to the project site when requested by the Contracting Officer. The
Contracting Officer may also request visits for special purposes. Only registered architects and engineers thoroughly familiar with the project may make these site visits. The COR has the prerogative to determine the professional discipline(s) required for any visit. The DB
A/E shall observe the construction, advise the CO and COR of any deviations or deficiencies or solutions to issues discussed. A site inspection report which includes the purpose of the inspection, items reviewed, deficiencies observed, recommendations and additional actions required, shall be furnished to the COR within three work days following the site visit date.
- - - E N D - - -
548-18-605 10-01-17
01 00 00 -1
SECTION 01 00 00
GENERAL REQUIREMENTS
1.1 SAFETY REQUIREMENTS
Refer to section 01 35 26, SAFETY REQUIREMENTS for safety and infection control requirements.
1.2 GENERAL INTENTION
A. Contractor shall completely prepare site for building operations, including demolition and removal of existing structures, and furnish labor and materials and perform work for the removal and replacement of eight (8) air handler units throughout the Medical Center as required by drawings and specifications.
B. Reserved.
C. Before placement and installation of work subject to tests by testing laboratory retained by Department of Veterans Affairs, the Contractor shall notify the COR in sufficient time to enable testing laboratory personnel to be present at the site in time for proper taking and testing of specimens and field inspection. Such prior notice shall be not less than three work days unless otherwise designated by the COR.
E. All employees of general contractor and subcontractors shall comply with VA security management program and obtain permission of the VA police, be identified by project and employer, and restricted from unauthorized access.
1.3 STATEMENT OF BID ITEM(S)
A. Mechanical Work: Work includes all labor, material, equipment and supervision to perform the required Mechanical construction work on this project including.
Replace Air Handling Units 9,15,17,28,24,29,34,39
Provide all labor, materials, tools and equipment, and design-build services necessary for design and construction of a project described here called “Replace Air Handling Units 9,15,17,28,24,29,34,39”. Work involves designing, demolition, and installation of eight (8) new air handler systems to replace existing air handler units, heating and cooling valves, actuators, ultraviolet lights and all dampers.
Structural engineer shall review existing steel support frames and
01 00 00 -2 modify as required for new Air Handling Units. Work involves modifying plumbing systems, electrical systems, building automation systems, structural steel frame as required and air distribution supply, return and exhaust systems. All units shall be designed and sized to allow return air and adjustable minimum 15% outside air with new electric/digital modulating dampers according to current VA and ASHRAE standards and VA HVAC Design Manual November 2017 edition rev 3/1/2020.
All cooling coils shall be selected for maximum dehumidification and factory coated as per VA specifications.
Outside air flow sensors shall have 2% accuracy or better. Return, relief/exhaust air flow sensors shall have 3% accuracy or better. All existing air flow stations shall be removed and replaced. Existing shut off valves will be replaced with same size new shut off valves.
Interior of air handler unit casings shall be stainless steel, outside return and exhaust air dampers shall be opposed blade, aluminum with stainless steel hardware and shall be coated at factory with epoxy, with switch package to remotely indicate damper blade position. All motors shall be premium efficiency motors. Provide VFD’s for AHUs and associated exhaust and return systems as required. VFDs shall be Eaton or approved equal with soft start, manual bypass switch and NEMA 12 box. All return and exhaust fans shall be inspected for proper operation.
All AHU’s shall meet the latest ASHRAE and VA design standards. These standards can be found at https://www.cfm.va.gov/til/
Contractor to provide all labor, materials, tools and equipment to provide a comprehensive survey to the Government of all of the rooms impacted by the replacement of air handlers 9, 15, 17, 24, 28, 29, 34,
39. The survey shall include a map of the rooms, identifying the room number and purpose of the room. The purpose of this survey is to assist the COR in communicating to the end users the areas impacted by the shutdown of the air handlers during the scheduling phase.
01 00 00 -3
Temporary air conditioning units “will” be utilized to install new units without major disruption to the affected areas. Temp air units will have to be designed based on existing conditions of the space, to include CFM and discharge temperatures.
Certified Independent Third-Party (CITP) Consultant
The Design Build Contractor is responsible to obtain a CITP to review drawings in refence to NFPA Life Safety and Fire Protection Compliance per VHA Directive 7712.
1. In each submission, the DB Contractor shall incorporate all material specified and all revisions according to comments made by the Department of Veterans Affairs, as well as the CITP.
2. For the final construction documents, the DB Contractor will be required to submit written documentation, signed by the CITP that the design has been reviewed to be compliant with Statement of
Work.
1.4 CONSTRUCTION SECURITY REQUIREMENTS
A. Security Plan:
1. The security plan defines both physical and administrative security procedures that will remain effective for the entire duration of the project.
2. The General Contractor is responsible for assuring that all sub-contractors working on the project and their employees also comply with these regulations.
B. Security Procedures:
1. General Contractor’s employees shall not enter the project site without appropriate badge. They may also be subject to inspection of their personal effects when entering or leaving the project site.
2. Before starting work the General Contractor shall give one week’s notice to the Contracting Officer so that security arrangements can be provided for the employees. This notice is separate from any notices required for utility shutdown described later in this section.
01 00 00 -4
3. No photography of VA premises is allowed without written permission of the Contracting Officer.
4. VA reserves the right to close down or shut down the project site and order General Contractor’s employees off the premises in the event of a national emergency. The General Contractor may return to the site only with the written approval of the Contracting Officer.
D. Key Control:
1. The General Contractor shall provide duplicate keys and lock combinations to the Contracting officers representative (COR) for the purpose of security inspections of every area of project including tool boxes and parked machines and take any emergency action.
E. Document Control:
1. Before starting any work, the General Contractor/Sub Contractors shall submit an electronic security memorandum describing the approach to following goals and maintaining confidentiality of
“sensitive information”.
2. The General Contractor is responsible for safekeeping of all drawings, project manual and other project information. This information shall be shared only with those with a specific need to accomplish the project.
3. Certain documents, sketches, videos or photographs and drawings may be marked “Law Enforcement Sensitive” or “Sensitive Unclassified”.
Secure such information in separate containers and limit the access to only those who will need it for the project. Return the information to the Contracting Officer upon request.
4. These security documents shall not be removed or transmitted from the project site without the written approval of Contracting
Officer.
5. All paper waste or electronic media such as CD’s and diskettes shall be shredded and destroyed in a manner acceptable to the VA.
6. Notify Contracting Officer and Site Security Officer immediately when there is a loss or compromise of “sensitive information”.
01 00 00 -5
7. All electronic information shall be stored in specified location following VA standards and procedures using an Engineering Document
Management Software (EDMS).
a. Security, access and maintenance of all project drawings, both scanned and electronic shall be performed and tracked through the
EDMS system.
b. “Sensitive information” including drawings and other documents may be attached to e-mail provided all VA encryption procedures are followed.
F. Motor Vehicle Restrictions
A limited number of permits shall be issued for General Contractor and its employees for parking in designated areas only.
1.5 OPERATIONS AND STORAGE AREAS
A. The Contractor shall confine all operations (including storage of materials) on Government premises to areas authorized or approved by the Contracting Officer. The Contractor shall hold and save the
Government, its officers and agents, free and harmless from liability of any nature occasioned by the Contractor's performance.
B. Temporary buildings (e.g., storage sheds, shops, offices) and utilities may be erected by the Contractor only with the approval of the
Contracting Officer and shall be built with labor and materials furnished by the Contractor without expense to the Government. The temporary buildings and utilities shall remain the property of the
Contractor and shall be removed by the Contractor at its expense upon completion of the work. With the written consent of the Contracting
Officer, the buildings and utilities may be abandoned and need not be removed.
C. The Contractor shall, under regulations prescribed by the Contracting
Officer, use only established roadways. When materials are transported in prosecuting the work, vehicles shall not be loaded beyond the loading capacity recommended by the manufacturer of the vehicle or prescribed by any Federal, State, or local law or regulation. When it is necessary to cross curbs or sidewalks, the Contractor shall protect them from damage. The Contractor shall repair or pay for the repair of any damaged curbs, sidewalks, or roads.
01 00 00 -6
(FAR 52.236-10)
D. Working space and space available for storing materials shall be as determined by the COR.
E. Workmen are subject to rules of Medical Center applicable to their conduct. Execute work in such a manner as to interfere as little as possible with work being done by others. Keep roads clear of construction materials, debris, standing construction equipment and vehicles at all times.
F. Execute work so as to interfere as little as possible with normal functioning of Medical Center as a whole, including operations of utility services, fire protection systems and any existing equipment, and with work being done by others. Use of equipment and tools that transmit vibrations and noises through the building structure, are not permitted in buildings that are occupied, during construction, jointly by patients or medical personnel, and Contractor's personnel, except as permitted by COR where required by limited working space.
1. Do not store materials and equipment in other than assigned areas.
2. Schedule delivery of materials and equipment to immediate construction working areas within buildings in use by Department of
Veterans Affairs in quantities sufficient for not more than two work days. Provide unobstructed access to Medical Center areas required to remain in operation.
3. Where access by Medical Center personnel to vacated portions of buildings is not required, storage of Contractor's materials and equipment will be permitted subject to fire and safety requirements.
G. Utilities Services: Where necessary to cut existing pipes, electrical wires, conduits, cables, etc., of utility services, or of fire protection systems or communications systems (except telephone), they shall be cut and capped at suitable places where shown; or, in absence of such indication, where directed by COR. All such actions shall be coordinated with the COR:
H. Phasing:
The Medical Center must maintain its operation 24 hours a day 7 days a week. Therefore, any interruption in service must be scheduled and
01 00 00 -7 coordinated with the COR to ensure that no lapses in operation occur.
It is the CONTRACTOR'S responsibility to develop a work plan and schedule detailing, at a minimum, the procedures to be employed, the equipment and materials to be used, the interim life safety measure to be used during the work, and a schedule defining the duration of the work with milestone subtasks. The work to be outlined shall include, but not be limited to:
To insure such executions, Contractor shall furnish the COR with a schedule of approximate phasing dates for removal and replacement of each air handler unit, one at a time. In addition, Contractor shall notify the COR two weeks in advance of the proposed date of starting work in each specific area of site, building or portion thereof.
Arrange such phasing dates to insure accomplishment of this work in successive phases mutually agreeable to COR and Contractor, as follows:
Only one air handler is to be replaced at a time.
I. Building No. 1 will be occupied during performance of work.
1. Contractor shall take all measures and provide all material necessary for protecting existing equipment and property in affected areas of construction against dust and debris, so that equipment and affected areas to be used in the Medical Centers operations will not be hindered. Contractor shall permit access to Department of
Veterans Affairs personnel and patients through other construction areas which serve as routes of access to such affected areas and equipment. These routes whether access or egress shall be isolated from the construction area by temporary partitions and have walking surfaces, lighting etc to facilitate patient and staff access.
Coordinate alteration work in areas occupied by Department of
Veterans Affairs so that Medical Center operations will continue during the construction period.
J. When a building and/or construction site is turned over to Contractor, Contractor shall accept entire responsibility including upkeep and maintenance therefore:
01 00 00 -8
1. Contractor shall maintain in operating condition existing fire protection and alarm equipment.
K. Utilities Services: Maintain existing utility services for Medical
Center at all times. Where necessary to cut existing water, gases, or air pipes, or conduits, wires, cables, etc. of utility services or of fire protection systems and communications systems (including telephone), they shall be cut and capped at suitable places where shown; or, in absence of such indication, where directed by COR.
1. No utility service such as water, gas, steam, or electricity, or fire protection systems and communications systems may be interrupted without prior approval of COR[RJW1] and Chief of Facilities
Management. Electrical work shall be accomplished with all affected circuits or equipment de-energized. When an electrical outage cannot be accomplished, work on any energized circuits or equipment shall not commence without a detailed work plan, the Medical Center
Director’s prior knowledge and written approval. Refer to specification Sections 26 05 11, REQUIREMENTS FOR ELECTRICAL
INSTALLATIONS, 27 05 11 REQUIREMENTS FOR COMMUNICATIONS
INSTALLATIONS and 28 05 00, COMMON WORK RESULTS FOR ELECTRONIC
SAFETY AND SECURITY for additional requirements.
2. Contractor shall submit a request to interrupt any such services to
COR, in writing, 7 days in advance of proposed interruption. Request shall state reason, date, exact time of, and approximate duration of such interruption.
3. Contractor will be advised (in writing) of approval of request, or of which other date and/or time such interruption will cause least inconvenience to operations of Medical Center. Interruption time approved by Medical Center may occur at other than Contractor's normal working hours.
4. Major interruptions of any system must be requested, in writing, at least 15 calendar days prior to the desired time and shall be performed as directed by the COR.
5. In case of a contract construction emergency, service will be interrupted on approval of COR. Such approval will be confirmed in writing as soon as practical.
01 00 00 -9
L. Abandoned Lines: All service lines such as wires, cables, conduits, ducts, pipes and the like, and their hangers or supports, which are to be abandoned but are not required to be entirely removed, shall be sealed, capped or plugged at the main, branch or panel they originate from. The lines shall not be capped in finished areas, but shall be removed and sealed, capped or plugged in ceilings, within furred spaces, in unfinished areas, or within walls or partitions; so that they are completely behind the finished surfaces.
M. To minimize interference of construction activities with flow of
Medical Center traffic, comply with the following:
Keep roads, walks and entrances to grounds, to parking and to occupied areas of buildings clear of construction materials, debris and standing construction equipment and vehicles.
N. Coordinate the work for this contract with other construction operations as directed by COR. This includes the scheduling of traffic and the use of roadways, as specified in Article, USE OF ROADWAYS.
1.6 ALTERATIONS
A. Survey: Before any work is started, the Contractor shall make a thorough survey with the COR of areas of buildings in which alterations occur and areas which are anticipated routes of access, and furnish a report, signed by both, to the Contracting Officer. This report shall list by rooms and spaces:
1. Existence and conditions of items such as plumbing fixtures and accessories, electrical fixtures, equipment,
2. Shall note any discrepancies between drawings and existing conditions at site.
3. Shall designate areas for working space, materials storage and routes of access to areas within buildings where alterations occur and which have been agreed upon by Contractor and COR.
B. Any items required by drawings to be either reused or relocated or both, found during this survey to be nonexistent, or in opinion of COR, to be in such condition that their use is impossible or impractical, shall be furnished and/or replaced by Contractor with new items in accordance with specifications which will be furnished by Government.
01 00 00 -10
Provided the contract work is changed by reason of this subparagraph B, the contract will be modified accordingly, under provisions of clause entitled "DIFFERING SITE CONDITIONS" (FAR 52.236-2) and "CHANGES" (FAR
52.243-4 and VAAR 852.236-88).
C. Re-Survey: Fourteen days before expected partial or final inspection date, the Contractor and COR together shall make a thorough re-survey of the areas of buildings involved. They shall furnish a report on conditions then existing, of flooring, doors, windows, walls and other surfaces as compared with conditions of same as noted in first condition survey report:
1. Re-survey report shall also list any damage caused by Contractor to such flooring and other surfaces, despite protection measures; and, will form basis for determining extent of repair work required of
Contractor to restore damage caused by Contractor's workmen in executing work of this contract.
D. Protection: Provide the following protective measures:
1. Wherever existing roof surfaces are disturbed they shall be protected against water infiltration. In case of leaks, they shall be repaired immediately upon discovery.
2. Temporary protection against damage for portions of existing structures and grounds where work is to be done, materials handled and equipment moved and/or relocated.
3. Protection of interior of existing structures at all times, from damage, dust and weather inclemency. Wherever work is performed, floor surfaces that are to remain in place shall be adequately protected prior to starting work, and this protection shall be maintained intact until all work in the area is completed.
1.7 DISPOSAL AND RETENTION
A. Materials and equipment accruing from work removed and from demolition of buildings or structures, or parts thereof, shall be disposed of as follows:
1. Reserved items which are to remain property of the Government are identified by attached tags or noted on drawings or in specifications as items to be stored. Items that remain property of
01 00 00 -11 the Government shall be removed or dislodged from present locations in such a manner as to prevent damage which would be detrimental to re-installation and reuse. Store such items where directed by COR.
2. Items not reserved shall become property of the Contractor and be removed by Contractor from Medical Center.
3. Items of portable equipment and furnishings located in rooms and spaces in which work is to be done under this contract shall remain the property of the Government. When rooms and spaces are vacated by the Department of Veterans Affairs during the alteration period, such items which are NOT required by drawings and specifications to be either relocated or reused will be removed by the Government in advance of work to avoid interfering with Contractor's operation.
1.8 RESTORATION
A. Remove, cut, alter, replace, patch and repair existing work as necessary to install new work. Except as otherwise shown or specified, do not cut, alter or remove any structural work, and do not disturb any ducts, plumbing, steam, gas, or electric work without approval of the
COR. Existing work to be altered or extended and that is found to be defective in any way, shall be reported to the COR before it is disturbed. Materials and workmanship used in restoring work, shall conform in type and quality to that of original existing construction, except as otherwise shown or specified.
B. Upon completion of contract, deliver work complete and undamaged.
Existing work (walls, ceilings, partitions, floors, mechanical and electrical work, lawns, paving, roads, walks, etc.) disturbed or removed as a result of performing required new work, shall be patched, repaired, reinstalled, or replaced with new work, and refinished and left in as good condition as existed before commencing work.
C. At Contractor's own expense, Contractor shall immediately restore to service and repair any damage caused by Contractor's workmen to existing piping and conduits, wires, cables, etc., of utility services or of fire protection systems and communications systems (including telephone) which are not scheduled for discontinuance or abandonment.
D. Expense of repairs to such utilities and systems not shown on drawings or locations of which are unknown will be covered by adjustment to
01 00 00 -12 contract time and price in accordance with clause entitled "CHANGES"
(FAR 52.243-4 and VAAR 852.236-88) and "DIFFERING SITE CONDITIONS" (FAR
52.236-2).
1.9 AS-BUILT DRAWINGS
A. The contractor shall maintain two full size sets of as-built drawings and specifications which will be kept current during construction of the project, to include all contract changes, modifications and clarifications.
B. All variations shall be shown in the same general detail as used in the contract drawings. To insure compliance, as-built drawings and specifications shall be made available for the COR’s review, as often as requested.
C. Contractor shall deliver two approved completed sets of as-built drawings in the electronic version (scanned PDF) to the COR after the acceptance of the project by the COR.
D. Paragraphs A, B, & C shall also apply to all shop drawings.
1.10 USE OF ROADWAYS
For hauling, use only established public roads and roads on Medical
Center property. When necessary to cross curbing, sidewalks, or similar construction, they must be protected by well-constructed bridges.
1.11 TEMPORARY USE OF EXISTING ELEVATORS
A. Use of existing elevators for handling building materials and
Contractor's personnel will be permitted subject to following provisions:
1. Contractor makes all arrangements with the COR for use of elevators.
The COR will ascertain that elevators are in proper condition.
Contractor may use service elevators only for daily use and for special nonrecurring time intervals when permission is granted.
Personnel for operating elevators will not be provided by the
Department of Veterans Affairs.
2. Contractor covers and provides maximum protection of following elevator components:
a. Entrance jambs, heads soffits and threshold plates.
01 00 00 -13
b. Entrance columns, canopy, return panels and inside surfaces of car enclosure walls.
c. Finish flooring.
1.12 AVAILABILITY AND USE OF UTILITY SERVICES
A. The Government shall make all reasonably required amounts of utilities available to the Contractor from existing outlets and supplies, as specified in the contract. The Contractor shall carefully conserve any utilities furnished without charge.
1.13 TESTS
A. As per specification section 23 05 93 the contractor shall provide a written testing and commissioning plan complete with component level, equipment level, sub-system level and system level breakdowns. The plan will provide a schedule and a written sequence of what will be tested, how and what the expected outcome will be. This document will be submitted for approval prior to commencing work. The contractor shall document the results of the approved plan and submit for approval with the as built documentation.
B. Pre-test mechanical and electrical equipment and systems and make corrections required for proper operation of such systems before requesting final tests. Final test will not be conducted unless pre-tested.
C. Conduct final tests required in various sections of specifications in presence of an authorized representative of the Contracting Officer.
Contractor shall furnish all labor, materials, equipment, instruments, and forms, to conduct and record such tests.
D. Mechanical and electrical systems shall be balanced, controlled and coordinated. A system is defined as the entire system which must be coordinated to work together during normal operation to produce results for which the system is designed. For example, air conditioning supply air is only one part of entire system which provides comfort conditions for a building. Other related components are return air, exhaust air, steam, chilled water, refrigerant, hot water, controls and electricity, etc.
E. All related components as defined above shall be functioning when any system component is tested. Tests shall be completed within a
01 00 00 -14 reasonably period of time during which operating and environmental conditions remain reasonably constant and are typical of the design conditions.
F. Individual test result of any component, where required, will only be accepted when submitted with the test results of related components and of the entire system.
1.14 INSTRUCTIONS
A. Contractor shall furnish Maintenance and Operating manuals (hard copies and electronic) and verbal instructions when required by the various sections of the specifications and as hereinafter specified.
B. Manuals: Maintenance and operating manuals and one compact disc (four hard copies and one electronic copy each) for each separate piece of equipment shall be delivered to the COR coincidental with the delivery of the equipment to the job site. Manuals shall be complete, detailed guides for the maintenance and operation of equipment. They shall include complete information necessary for starting, adjusting, maintaining in continuous operation for long periods of time and dismantling and reassembling of the complete units and sub-assembly components. Manuals shall include an index covering all component parts clearly cross-referenced to diagrams and illustrations. Illustrations shall include "exploded" views showing and identifying each separate item. Emphasis shall be placed on the use of special tools and instruments. The function of each piece of equipment, component, accessory and control shall be clearly and thoroughly explained. All necessary precautions for the operation of the equipment and the reason for each precaution shall be clearly set forth. Manuals must reference the exact model, style and size of the piece of equipment and system being furnished. Manuals referencing equipment similar to but of a different model, style, and size than that furnished will not be accepted.
C. Instructions: Contractor shall provide qualified, factory-trained manufacturers' representatives to give detailed training to assigned
Department of Veterans Affairs personnel in the operation and complete maintenance for each piece of equipment. All such training will be at the job site. These requirements are more specifically detailed in the various technical sections. Instructions for different items of
01 00 00 -15 equipment that are component parts of a complete system, shall be given in an integrated, progressive manner. All instructors for every piece of component equipment in a system shall be available until instructions for all items included in the system have been completed.
This is to assure proper instruction in…
This is the start of the file's text. The full file is on GovTribe.