Design and Construction Procedures - Piping Ducts and Electrical Conduits.pdf

PDF 244 KB Posted

Attached to
Z2DA--Design Build Replace Air Handling Units 9, 15, 17, 24, 28, 29, 34, and 39
Solicitation number
36C24821R0082
Issued by

About this file

This document provides details for a federal design-build contract opportunity to replace air handling units at a Veterans Affairs medical center. The Department of Veterans Affairs, through its Veterans Integrated Service Network 8, is seeking to award a firm-fixed-price contract for design and construction services to replace eight air handling units at the West Palm Beach Veterans Affairs Medical Center in Florida. The contract value is estimated between $2-5 million. Interested parties must register in the System for Award Management, as the solicitation will be issued on or around May 12, 2021 via beta.SAM.gov. This requirement is set aside for Service-Disabled Veteran-Owned Small Businesses. The selected contractor will be responsible for designing, demolishing, and constructing new air handling systems and associated components. The response deadline is June 14, 2021.

View the file

Other files

File Type Posted
Attachment J Specialized Experience Information Sheet.docx DOCX document
36C24821R0082 0005.docx DOCX document
Questions and Answers.pdf PDF
36C24821R0082 0004.docx DOCX document
H3 Drawing.pdf PDF
36C24821R0082 0003.docx DOCX document
36C24821R0082 0002.docx DOCX document
36C24821R0082 Sign In Sheet_Redacted.pdf PDF
36C24821R0082 0001.docx DOCX document
1-H9R.pdf PDF
Attachment E VHA Directive 7712 FIRE PROTECTION CODE REVIEWS.pdf PDF
1-H106R.pdf PDF
1-H107.pdf PDF
1-H4R.pdf PDF
Attachment J Experience Information Sheet.pdf PDF
1-H32.pdf PDF
Design and Construction Procedures - Drawings.pdf PDF
Attachment L Architect Engineering Submission Instructions.pdf PDF
1-H48R.pdf PDF
Attachment 1 AHU Unit(s) and Return Fan Expansion Detail Specifications.pdf PDF
1-H104.pdf PDF
Technical Information Library Specifications.pdf PDF
Attachment C CITP Statement of Work.pdf PDF
Attachment D Pre-Award Contractor Safety and Environmental Record Form.pdf PDF
Design Review Check List Electrical.pdf PDF
36C24821R0082_1.pdf PDF
1-108R.pdf PDF
1-H110R.pdf PDF
1-57.pdf PDF
1-H106.pdf PDF
3-H3.pdf PDF
Attachment G Limitations on Subcontracting Offerors Certification.pdf PDF
Attachment H Project Price Breakdown.xlsx XLSX spreadsheet
1-106.pdf PDF
Attachment K PAST PERFORMANCE QUESTIONNAIRE.pdf PDF
1-H34.pdf PDF
1-H107R.pdf PDF
AHU Test and Balance Reports.pdf PDF
36C24821R0082_1.docx DOCX document
1-H105.pdf PDF
Attachment P Mask Specification.pdf PDF
Attachment A Wage Grade Determination FL20210220 04092021.pdf PDF
1-105.pdf PDF
AE Check List HVAC.pdf PDF
Design and Construction Procedures - Codes Standards and Executive Orders.pdf PDF
Design Review Checklist HVAC.pdf PDF
Attachment F Above Ceiling Permit 11-10-17.pdf PDF
HVAC Design Manual.pdf PDF
Attachment B West Palm Beach VAMC Campus Map.pdf PDF
1-H108.pdf PDF
Show 40 more

Latest 50 of 54 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

PG 18-3 – DESIGN AND CONSTRUCTION PROCEDURES September 2010

PIPING AND DUCTS 7-1

TOPIC 7 – PIPING AND DUCTS

1. GENERAL: Exposed piping and ducts are acceptable where finished ceilings are not provided. Maintain standard ceiling height in the space.

NOTE: Do not allow pressure pipes, ducts, clean-outs, and drains, not serving the area, to enter or pass through gas storage rooms and elevator and dumbwaiter machinery rooms and hoistways.

2. CONSTRUCTION:

a. Locate vertical runs in pipe spaces, pipe chases, or furred-in spaces, in walls adjacent to permanent structures such as stairwells or elevator shafts.

b. In main kitchens, place steam, condensate, gas, and water headers below the floor or in trenches. In laundries, place horizontal drain runs, and low-pressure condensate lines below the floor or in trenches; however, water and steam may be exposed overhead. In warehouse buildings or rooms, place horizontal runs at height that will not reduce or restrict the net usable space.

NOTE: Do not locate piping and ducts where they will be subject to damage or rupture or other conditions of risk according to VA Physical Security Design Manual. Where unavoidable conditions occur, provide suitable protection.

c. In geographical areas where pipes conveying liquids that are subject to freezing, minimize locating those pipes in exterior walls or in unheated areas, such as attics, spaces between ceilings and roofs, or near exterior doors. If pipes are located in those areas, provide appropriate insulation.

NOTE: Do not design pipes conveying liquids or gases within masonry walls, concrete walls, or cast in place floors.

d. Provide access panels or doors for concealed items requiring operation, maintenance, or periodic inspection; for example, clean-outs, coils, dampers, filter, fire alarm apparatus, strainers, switches, traps, and valves. Appropriately mark access panels and doors to preserve the required fire resistance and acoustical characteristics.

File details come from the government source that posted it. Updated .