This is a technical specifications document prepared by the Kenton County Airport Board for the 2026 Fall Protection Systems Installation program. The project encompasses three distinct bid packages designed by LJB, Inc., to address fall protection hazards across the airport in accordance with ANSI/ASSP Z359.6 standards. Bid Package 1 involves the Storm Water Treatment Plant (SWTP) and includes engineered fall protection and confined space retrieval systems for the sludge tank, digesters, splitter, and clarifiers, utilizing davit arms with permanently mounted bases, access platforms, and travel restraint anchorages. Bid Package 2 addresses the T3 parking structure and includes a fixed ladder, roof edge protection, guardrails, a swing gate, and roof markings around the new rotating beacon installation. Bid Package 3 covers the entire Concourse A roof and includes guardrails, rigid rails, roof delineation lines, ladder replacements, hatch guardrails, skylight load ratings, and horizontal lifelines on cooling towers. A pre-bid meeting and site visit will be held on March 19, 2026, at 10:00 am at CVG Centre in Erlanger, Kentucky. Questions must be submitted by 11:59 pm on April 3, 2026, with answers posted by April 7, 2026. Bids are due by 2:00 pm on April 16, 2026. Bidders may submit bids for any or all three packages independently.

The specifications require comprehensive project management including a project manager, site superintendent, and dedicated safety manager. All preconstruction documents must be submitted at least five business days prior to a preconstruction meeting, with weekly progress meetings thereafter. The contractor must submit a CPM schedule identifying critical path activities, coordinate X-ray and NDT scanning prior to all penetrations, and provide three-week lookahead schedules at progress meetings. All metal fabrications must conform to AISC and AWS D1.1 standards, with hot-dip galvanized exterior steel and stainless steel fasteners for roof penetrations. The contractor must coordinate with roofing manufacturers for approved penetration and patch methods to maintain warranties and provide training and commissioning reports for airport personnel upon project closeout. No pricing information, set-asides, incumbent contractor details, or funding sources are specified in these technical specifications.

View the file

Other files

File Type Posted
26-014-ITB_Pre-Bid_Sign_In_Sheets.pdf PDF
26-014-ITB_Pre-Bid_Meeting_Agenda.pdf PDF
26-014-ITB_Pre-Bid_Sign_In_Sheets.pdf PDF
26-014-ITB_Pre-Bid_Meeting_Agenda.pdf PDF
2026_Fall_Protection_Systems_Installation.pdf PDF
2026_Fall_Protection_Systems_Installation.pdf PDF
2026_Fall_Protection_Systems_Installation.pdf PDF
KCAB_-_RSVP_Instructional_Guide_for_OpenGov.pdf PDF
KCAB_-_RSVP_Instructional_Guide_for_OpenGov.pdf PDF
KCAB_-_RSVP_Instructional_Guide_for_OpenGov.pdf PDF
26-014-ITB_2026_Fall_Protection_Systems_Installation_-_Ad.pdf PDF
26-014-ITB_2026_Fall_Protection_Systems_Installation_-_Ad.pdf PDF
26-014-ITB_2026_Fall_Protection_Installation_-_Exhibit_B_-_Contract_&_Bonds.pdf PDF
26-014-ITB_2026_Fall_Protection_Installation_-_Exhibit_A_-_Proposal_Forms.pdf PDF
26-014-ITB_2026_Fall_Protection_Installation_-_Exhibit_A_-_Proposal_Forms.pdf PDF
26-014-ITB_2026_Fall_Protection_Installation_-_Exhibit_B_-_Contract_&_Bonds.pdf PDF
26-014-ITB_2026_Fall_Protection_Installation_-_Exhibit_A_-_Proposal_Forms.pdf PDF
26-014-ITB_2026_Fall_Protection_Systems_Install_-_Drawings_&_Photos.pdf PDF
26-014-ITB_2026_Fall_Protection_Systems_Install_-_Technical_Specs.pdf PDF
26-014-ITB_2026_Fall_Protection_Systems_Install_-_Drawings_&_Photos.pdf PDF
26-014-ITB_2026_Fall_Protection_Systems_Install_-_Drawings_&_Photos.pdf PDF
Buy_American_Certification-Equipment-Building_Projects.docx DOCX document
NonSegregated_Facilities_Certification.docx DOCX document
Non_Debarment_or_Suspension_Certification.docx DOCX document
PLANS_IFB_R2_2026-02-27.pdf PDF
RE__LJB_Engineering_-_Proposal_for_Advisory_Role_-_CVG_Centre_Roof_Project.msg MSG file
Buy_American_Certification-Equipment-Building_Projects.docx DOCX document
Disclosure_of_Lobbying_Activities_Certification.docx DOCX document
EEO_Certification.docx DOCX document
NonSegregated_Facilities_Certification.docx DOCX document
RE__LJB_Engineering_-_Proposal_for_Advisory_Role_-_CVG_Centre_Roof_Project.msg MSG file
Affirmative_Action_Certification.docx DOCX document
Affirmative_Action_Certification.docx DOCX document
EEO_Certification.docx DOCX document
Affirmative_Action_Certification.docx DOCX document
Certification_of_Offeror-Bidder_Regarding_Tax_Delinquency_and_Felony_Convictions.docx DOCX document
Non_Debarment_or_Suspension_Certification.docx DOCX document
Certification_of_Offeror-Bidder_Regarding_Tax_Delinquency_and_Felony_Convictions.docx DOCX document
RE__LJB_Engineering_-_Proposal_for_Advisory_Role_-_CVG_Centre_Roof_Project.msg MSG file
Tech_Specs_Rev2.pdf PDF
Buy_American_Certification-Construction_Projects.docx DOCX document
Disclosure_of_Lobbying_Activities_Certification.docx DOCX document
LJB_Concourse_Cost_Estimates_REVISED.pdf PDF
Tech_Specs_Rev2.pdf PDF
Buy_American_Certification-Equipment-Building_Projects.docx DOCX document
Disclosure_of_Lobbying_Activities_Certification.docx DOCX document
EEO_Certification.docx DOCX document
LJB_Concourse_Cost_Estimates_REVISED.pdf PDF
Non_Debarment_or_Suspension_Certification.docx DOCX document
PLANS_IFB_R2_2026-02-27.pdf PDF
Show 40 more

50 files listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

2026 Airport Fall Protection Program

TECHNICAL SPECIFICATIONS

Prepared for: Airport Authority Prepared by: Construction Project Management

Date: February 27, 2026

Table of Contents

Bid Package Detailed Discription

01 14 00 – Work Restrictions

01 31 00 – Project Management & Coordination 01 32 00 – Construction Progress Documentation 01 33 00 – Submittal Procedures

05 50 00 – Metal Fabrications

07 72 00 – Roof Accessories

11 24 23 – Fall Protection Systems

Bid Pack 1: Storm Water Treatment Plant (SWTP) - Detailed Description

Revised February 24, 2026 (LJB Document Modified by CVG)

Re: Fall protection and confined space design for sludge tank, digesters, splitter, clarifiers

Engineered fall protection and confined design for accessing areas in and around the sludge tank, digesters, splitter, and clarifiers at the stormwater treatment plant (SWTP).

The final design primarily will utilize a combination of davit arms with permanently mounted davit bases, confined space retrieval systems, and access platforms. LJB completed a conceptual design report for the SWTP in 2020. The design is based on that report. CVG has purchased several davit bases already. The designs will incorporate these already-purchased products as much as is feasible.

Splitter

Digesters Sludge Tank

Clarifiers

The proposed abatement design will include the fall protection and confined space systems and other modifications outlined below:

• Splitter

− Mount a maximum of 8 davit bases to the concrete structure for access into splitter to provide complete coverage of the grating area.

» Davits to be utilized for confined space retrieval in addition to fall protection.

− Modify and reinforce grating as necessary to accommodate davit bases.

− Mount several travel restraint anchorages for use when grating sections are temporarily removed.

• Sludge Tank (1 tank)

− Mount approximately 4 davit bases to wall for portable ladder access into tank and confined space retrieval (1 davit base per platform location).

− Modify existing guardrail at 3 locations on existing access platform to correct deficient guardrail and allow for easy access into tank.

− Design approximately 3 new ground supported access platforms with stairs to be placed around the sludge tank. New platforms will be designed to be similar in size to existing access platforms around the digester tanks. Each platform will also have a corresponding davit base to be attached to the tank wall.

Platforms will be designed to be used in conjunction with confined space retrieval winches or self-retracting devices (SRD) with retrieval capabilities These platforms will be beneficial for personnel working in the tanks to allow for a greater range while connected to davit arms.

• Digester Tanks (2 tanks)

− Mount 1 davit base on concrete at 1 control platform per tank for portable ladder access into tank

− Install 1 travel restraint point at 1 valve platform per tank for use when accessing valves for greasing or cleaning.

− Design removeable gate or guardrail piece at 1 valve platform per tank to provide compliant guardrail for personnel working on platform.

− Design approximately 3 new ground supported access platforms per tank with stairs to be placed around each digester tank (total of 6 platforms). New platforms will be designed to be similar in size to existing access platforms around the tanks. Each platform will also have a corresponding davit base to be attached to the tank wall. Platforms will be designed to be used in conjunction with confined space retrieval winches or SRDs with retrieval capabilities. These platforms will be beneficial for personnel working in the tanks to allow for a greater range while connected to davit arms.

• Clarifiers (3 clarifiers)

− Mount davit base to concrete at each clarifier location for portable ladder access into clarifier tank.

− Modify existing guardrail as necessary to allow for proper davit base locations.

− Design the locations for confined space davit or retrieval winch locations around clarifiers

» Approximately 8 total retrieval locations around clarifiers.

• Diversion Valve Pits (2 pits)

− Install 1 new stainless steel ladder and hatch guardrail system at each pit.

Bid Pack 2: Beacon Fall Protection – Detailed Description

November 8, 2024 (LJB Document Modified by CVG)

Re: Rotating Beacon Guardrail and Ladder

Engineered fall protection abatement design for the roof and access to the new rotating beacon on top of the T3 parking structure.

Below are the elements included in the design:

• (1) fixed ladder to access the rotating beacon roof level.

− Ladder length approximately 12 ft

− Ladder will include a locking security gate/cover.

• Roof edge protection around equipment

− Guardrail designed at ladder access point and around beacon, electrical panels, sirens/speakers less than 15 ft from a roof edge.

» Free-standing guardrail is preferred due to post-tensioned concrete on the parking garage structure.

− Swing gate at ladder opening

− Administrative control/roof marking

» Roof marking to be added at 15 ft from unprotected edge to serve as administrative control where guardrail not required. Roof marking to be designed only around the immediate area of the beacon.

Bid Pack 3: Concourse A – Detailed Description

Revised February 25, 2026 (LJB Document Modified by CVG)

Re: Phase 3 Abatement Design for Concourse A Part 2 LJB Project Number:0129467A.00

The work is detailed in two separate focuses: The eastern portion of Concourse A – Guardrail; and All remaining hazards identified on the Concourse A roof. The design is based on the 2022 assessment for details on abatement solutions.

The following, detail the Concourse A fall hazards and proposed solutions. Each fall hazard listed includes the fall hazard identification number (FHID) associated with that hazard in the risk assessment platform.

CONCOURSE A ROOF LAYOUT EAST CONCOURSE A GUARDRAILS

CONCOURSE A ROOF LAYOUT WITH PHASE 3 SCOPE

Concourse A Remaining Hazards

• Roof Level A2: Unprotected roof edge and non-compliant access ladder.

− Proposed Solutions: Roof delineation line, and modify existing access ladder (FHID 1078 and 1079)

• Roof Levels A1, B1, B2: Unprotected roof edge, unguarded skylight, non-compliant access ladder, and hatch guardrail.

− Proposed solutions: Roof guardrail, rigid rail, roof delineation line, replace hatch guardrail, modify ladder, load rate skylight (FHID 1072, 1073, 1074, 1075, 1076, 1077)

• Roof Levels C3 and C4: Unprotected roof edge, non-compliant ladder, unguarded ladder opening.

− Proposed solutions: Roof guardrail, fall protection anchor with vertical lifeline, replace ladder, add hatch guardrail (FHID 1070, 1071)

• Roof Level C2: Unprotected roof edge, non-compliant ladder, stair, and platform.

− Proposed solutions: Roof guardrail, rigid rail, replace ladder, replace landing, replace stair (FHID: 1063, 1065, 1066, 1067)

• Roof Levels D, E, F: Unprotected roof edge, non-compliant ladders, non-compliant hatch guardrail, unprotected top of cooling tower

− Proposed solutions: Rigid rails, replace ladder, modify ladder, replace hatch guardrail, horizontal lifeline on cooling tower. (FHID: 1047, 1050, 1051, 1053, 1055, 1058, 1061 and 1062)

The proposed solutions are based on what was included as part of the roof fall hazard risk assessment conceptual layout submitted to CVG in 2022.

By abating this list of fall hazards identified in the fall hazard risk assessment, CVG will be reducing the roof fall hazard risk at CVG by more than 22%.

SECTION 01 14 00 – WORK RESTRICTIONS

Comply with airport security protocols including badging, escorts, and access restrictions. Maintain sterile and secure areas at all times.

Limit noisy or disruptive work to approved windows. Coordinate shutdowns and rooftop access with Airport Operations in advance.

Maintain egress paths, fire lanes, and emergency access. Protect passengers, staff, and the public from hazards with barriers and signage.

SECTION 01 31 00 – PROJECT MANAGEMENT &

COORDINATION

Provide a Project Manager and Site Superintendent responsible for communication, safety, scheduling, quality control, and field coordination.

Provide a safety manager to be responsible for this project's safety mitigation.

Provide all Preconstruction documents a minimum of (5) business days prior to a Preconstruction Meeting.

Hold a Preconstruction Meeting; conduct weekly Progress Meetings; issue minutes within 48 hours.

Coordinate all X■ray/NDT scanning prior to penetrations; notify Airport immediately of conflicts or discrepancies.

Provide all MOT plans, wayfinding signage, and parking space capture for passengers in the T3 parking garage for the Beacon Fall Projection.

SECTION 01 32 00 – CONSTRUCTION PROGRESS

DOCUMENTATION

Submit a CPM schedule showing sequencing across Treatment Plant, Parking Deck, and Concourse A.

Identify critical path activities including scanning, fabrication lead times, roofing penetrations, required inspections, and material deliveries.

Provide monthly schedule updates with narrative. Submit 3■week look■ahead schedules at progress meetings.

Provide progress photos, daily reports, and manpower logs as requested.

SECTION 01 33 00 – SUBMITTAL PROCEDURES

Maintain a submittal register with required/received/approved dates. Do not fabricate or install until submittals are approved.

Provide a comprehensive list of all submittals required for the project, including MOT Plans for approval, passenger signage and parking space capture for the T3 garage Beacon project.

Provide product data, shop drawings, samples, welding procedures, anchor data, roofing patch details, and manufacturer certifications.

Use RFI process for clarifications. Do not use RFIs in lieu of coordination or complete submittals.

SECTION 05 50 00 – METAL FABRICATIONS

Provide all materials in accordance with the project plans.

Provide fabricated steel platforms, stairs, ladders, guards, and support frames. Conform to AISC and

AWS D1.1.

Hot■dip galvanize exterior steel where indicated; shop prime interior steel. Provide stainless steel fasteners for roof penetrations unless noted otherwise.

Submit shop drawings with member sizes, connections, and embed/anchor layouts coordinated with post■tension locations.

SECTION 07 72 00 – ROOF ACCESSORIES

Provide all materials in accordance with the project plans.

Provide hatch rails, roof guardrail interfaces, pitch pockets, and flashing kits compatible with existing roofing systems.

Coordinate with roofing manufacturer for approved penetration and patch methods to maintain warranties.

Seal all penetrations watertight; provide protection for roof surfaces during installation and transport.

SECTION 11 24 23 – FALL PROTECTION SYSTEMS

Provide all materials in accordance with the project plans.

Provide engineered fall arrest and travel■restraint systems designed in accordance with ANSI/ASSP Z359.6. Include anchor points, davit bases, lifelines (where indicated), and compatible connectors.

Perform X■ray/NDT scanning prior to drilling. Maintain minimum clearances to post■tension tendons per drawings and specifications.

Provide training for airport personnel on system use; submit certifications, torque logs, and commissioning reports at closeout.