LJB_Concourse_Cost_Estimates_REVISED.pdf

PDF 90 KB Posted

Attached to
2026 Fall Protection Systems Installation
Solicitation number
26-014-ITB
Issued by
Kenton County, Erlanger City, Kentucky

About this file

This is a cost estimate document prepared by LJB, Inc. for the Kenton County Airport Board (KCAB), operator of CVG Airport in Erlanger, Kentucky, detailing installation costs for three fall protection systems packages designed in accordance with ANSI/ASSP Z359.6 standards. The project encompasses fall protection installations across three distinct locations: Concourse A Roof, T3 Parking Deck, and Storm Water Treatment Plant (SWTP). A pre-bid meeting and site visit are scheduled for Thursday, March 19, 2026 at 10:00 am at CVG Centre Admin. Offices, 77 Comair Blvd., Erlanger, KY 41018. Bidders must submit questions by 11:59 pm on Friday, April 3, 2026, with answers posted no later than Tuesday, April 7, 2026 at 11:59 pm. Bids are due by Thursday, April 16, 2026 at 2:00 pm. Bidders may respond to any or all three packages independently.

The installation cost estimates total $2,447,000 and include all materials and labor for installations shown in submitted design drawings. Specific costs are: Concourse A (all solutions) $1,910,000, rotating beacon (parking deck) $113,000, and SWTP $424,000. The estimate explicitly excludes permitting costs and any construction administration (CA) work, which will be completed by LJB under the existing contract. Pricing is based on current materials costs and subject to change based on market conditions. The estimate was initially prepared on July 15, 2025 and revised on October 10, 2025.

View the file

Other files

File Type Posted
26-014-ITB_Pre-Bid_Sign_In_Sheets.pdf PDF
26-014-ITB_Pre-Bid_Meeting_Agenda.pdf PDF
26-014-ITB_Pre-Bid_Sign_In_Sheets.pdf PDF
26-014-ITB_Pre-Bid_Meeting_Agenda.pdf PDF
2026_Fall_Protection_Systems_Installation.pdf PDF
2026_Fall_Protection_Systems_Installation.pdf PDF
2026_Fall_Protection_Systems_Installation.pdf PDF
KCAB_-_RSVP_Instructional_Guide_for_OpenGov.pdf PDF
KCAB_-_RSVP_Instructional_Guide_for_OpenGov.pdf PDF
KCAB_-_RSVP_Instructional_Guide_for_OpenGov.pdf PDF
26-014-ITB_2026_Fall_Protection_Systems_Installation_-_Ad.pdf PDF
26-014-ITB_2026_Fall_Protection_Systems_Installation_-_Ad.pdf PDF
26-014-ITB_2026_Fall_Protection_Installation_-_Exhibit_B_-_Contract_&_Bonds.pdf PDF
26-014-ITB_2026_Fall_Protection_Installation_-_Exhibit_A_-_Proposal_Forms.pdf PDF
26-014-ITB_2026_Fall_Protection_Installation_-_Exhibit_A_-_Proposal_Forms.pdf PDF
26-014-ITB_2026_Fall_Protection_Installation_-_Exhibit_B_-_Contract_&_Bonds.pdf PDF
26-014-ITB_2026_Fall_Protection_Installation_-_Exhibit_A_-_Proposal_Forms.pdf PDF
26-014-ITB_2026_Fall_Protection_Systems_Install_-_Drawings_&_Photos.pdf PDF
26-014-ITB_2026_Fall_Protection_Systems_Install_-_Technical_Specs.pdf PDF
26-014-ITB_2026_Fall_Protection_Systems_Install_-_Drawings_&_Photos.pdf PDF
Buy_American_Certification-Equipment-Building_Projects.docx DOCX document
NonSegregated_Facilities_Certification.docx DOCX document
Non_Debarment_or_Suspension_Certification.docx DOCX document
PLANS_IFB_R2_2026-02-27.pdf PDF
RE__LJB_Engineering_-_Proposal_for_Advisory_Role_-_CVG_Centre_Roof_Project.msg MSG file
Buy_American_Certification-Equipment-Building_Projects.docx DOCX document
Disclosure_of_Lobbying_Activities_Certification.docx DOCX document
EEO_Certification.docx DOCX document
NonSegregated_Facilities_Certification.docx DOCX document
RE__LJB_Engineering_-_Proposal_for_Advisory_Role_-_CVG_Centre_Roof_Project.msg MSG file
Affirmative_Action_Certification.docx DOCX document
Affirmative_Action_Certification.docx DOCX document
EEO_Certification.docx DOCX document
Affirmative_Action_Certification.docx DOCX document
Certification_of_Offeror-Bidder_Regarding_Tax_Delinquency_and_Felony_Convictions.docx DOCX document
Non_Debarment_or_Suspension_Certification.docx DOCX document
Certification_of_Offeror-Bidder_Regarding_Tax_Delinquency_and_Felony_Convictions.docx DOCX document
RE__LJB_Engineering_-_Proposal_for_Advisory_Role_-_CVG_Centre_Roof_Project.msg MSG file
Tech_Specs_Rev2.pdf PDF
Buy_American_Certification-Construction_Projects.docx DOCX document
Disclosure_of_Lobbying_Activities_Certification.docx DOCX document
Tech_Specs_Rev2.pdf PDF
LJB_Concourse_Cost_Estimates_REVISED.pdf PDF
Tech_Specs_Rev2.pdf PDF
Buy_American_Certification-Equipment-Building_Projects.docx DOCX document
Disclosure_of_Lobbying_Activities_Certification.docx DOCX document
EEO_Certification.docx DOCX document
LJB_Concourse_Cost_Estimates_REVISED.pdf PDF
Non_Debarment_or_Suspension_Certification.docx DOCX document
PLANS_IFB_R2_2026-02-27.pdf PDF
Show 40 more

50 files listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

2500 Newmark Drive Miamisburg, OH 45342 | (866) 552-3536 | LJBinc.com

Installation Cost Estimates CVG Airport Fall Protection

LJB Project numbers: 0129051A.00, 0129467A.00, 0128276A.00, 0127047A.00

Date: July 15, 2025

Revised October 10, 2025

Client name: CVG Airport

Project manager: Dan Buck

The installation costs below include all materials and labor for the installation of what is shown in the submitted design drawings. Permitting is not included in the costs. Any CA work associated with the installation is to be completed by LJB and is included in the current LJB contract for each project. Prices are based on current materials pricing and may change based on market conditions.

Item Installation Cost Estimate

Concourse A (all solutions) $1,910,000

Rotating beacon (parking deck) $113,000

SWTP $424,000

Total $2,447,000