Statement of Work - Attachment 5 - 01 30 00 - Administrative Requirements.docx

DOCX document 29 KB Posted

Attached to
Joint Base Charleston (JB CHS) Multiple Award Construction Contract (MACC) Federal contract opportunity
Solicitation number
FA441822R0019
Issued by
Department of the Air Force Air Mobility Command

View the file

Other files for this federal contract opportunity

Other files attached to Joint Base Charleston (JB CHS) Multiple Award Construction Contract (MACC), newest first.
File Type Posted
Solicitation Amendment 01 - Attachment 3 - As Built Drawings B63.pdf PDF
Solicitation Amendment 01 - Attachment 5 - Solicitation Section B - Seed Project - 08 Nov 22.pdf PDF
Solicitation Amendment 01 - Attachment 7 - Charleston County WD SC20220023.pdf PDF
Solicitation Amendment 01 - Attachment 6 - Berkeley County WD SC20210022.pdf PDF
Solicitation Amendment 01 - Attachment 10 - Wayne County WD NC20220041.pdf PDF
Solicitation Amendment 01 - Attachment 1 - Addendum 01 - Repair Aircraft MX Facility B63 Revised Drawing Sheets.pdf PDF
Solicitation Amendment 01 - Attachment 4 - Addendum 01 SOW - 08 Nov 22.pdf PDF
Solicitation Amendment 01 - Attachment 9 - Orangeburg County WD SC20220016.pdf PDF
Solicitation Amendment 01 - Attachment 2 - As Built Drawings B61.pdf PDF
Solicitation Amendment 01 - Attachment 8 - Dorchester WD SC20220024.pdf PDF
JB CHS MACC - Questions and Answers - 09 Nov 22.pdf PDF
Update 1 - JB CHS MACC - Pre-Proposal Conference Slides.pdf PDF
Update 2 - JB CHS MACC - Sign-In Sheet for Attendees.pdf PDF
Amendment 1 - JB CHS MACC - Pre-Proposal Conference Slides.pptx PPTX presentation
Solicitation Attachment YT Seed Project Drawings -Updated.pdf PDF
Solicitation Attachment XW - JB Charleston MACC Work Load Estimate.pdf PDF
Statement of Work - Attachment 1 - JB Charleston Statement of Work for Architect_Engineering (A_E) Services.pdf PDF
Statement of Work - Attachment 2 - Architectural Compatibility Plan.pdf PDF
Statement of Work - Attachment 3 - 01 11 00 - Summary of Work.docx DOCX document
Statement of Work - Attachment 8 - 01 32 00 - Project Schedule.docx DOCX document
Statement of Work - Attachment 11 - 01 33 00 - Attachment C - Form 4288-R (Submittal Register).pdf PDF
Statement of Work - Attachment 12 - 01 33 00 - Attachment D - Form 4289-R (RFI Register).xlsx XLSX spreadsheet
Statement of Work - Attachment 13 - 01 33 00 - Submittal Procedures.docx DOCX document
Statement of Work - Attachment 14 - 01 35 26 - Attachment A - Accident Investigation Form (CIRS).pdf PDF
Statement of Work - Attachment 15 - 01 35 26 - Governmental Safety Requirements.docx DOCX document
Statement of Work - Attachment 16 - 01 45 00 - Quality Control.docx DOCX document
Solicitation - FA441822R0019.pdf PDF
Solicitation Attachment XY - On and Off-Ramp Procedures.pdf PDF
Solicitation Attachment YV Seed Project Fire Pump Curves.pdf PDF
Statement of Work - Attachment 6 - 01 32 00 - Attachment A - Schedule and Pay Request Calendar Example 1.pdf PDF
Statement of Work - Attachment 10 - 01 33 00 - Attachment B - JB CHS RFI Form.pdf PDF
Statement of Work - Attachment 11 - 01 33 00 - Attachment C - Form 4288-R (Submittal Register).xlsx XLSX spreadsheet
Statement of Work - Attachment 17 - 01 78 00 - Closeout Requirements.docx DOCX document
Solicitation Attachment XT - JB Charleston - Question and Answer Form.xlsx XLSX spreadsheet
Solicitation Attachment XU - Past Performance Customer Questionnaire.pdf PDF
Solicitation Attachment XV - Past Performance Survey.pdf PDF
Solicitation Attachment XX - TOPR - Seed Project - B63.xlsx XLSX spreadsheet
Solicitation Attachment YS Seed Project Specifications.pdf PDF
Solicitation Attachment YT Seed Project Drawings.pdf PDF
Statement of Work - JB CHS MACC.pdf PDF
Statement of Work - Attachment 4 - 01 14 00 - Work Restrictions.docx DOCX document
Statement of Work - Attachment 9 - 01 33 00 - Attachment A - JB CHS Transmittal Form 4025.pdf PDF
Solicitation Attachment XZ - Past Performance Project List.xlsx XLSX spreadsheet
Solicitation Attachment YU Seed Project Hydraulics.pdf PDF
Solicitation Section B - JB CHS MACC - Seed.pdf PDF
Statement of Work - Attachment 7 - 01 32 00 - Attachment A - Schedule and Pay Request Calendar Example 2.xlsx XLSX spreadsheet
Statement of Work - Attachment 12 - 01 33 00 - Attachment D - Form 4289-R (RFI Register).pdf PDF
Solicitation Attachment XX - TOPR - Seed Project - B63.pdf PDF
Show all 48

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SECTION 01 30 00

ADMINISTRATIVE REQUIREMENTS

JB Charleston (Dec 2021)

PART 1 GENERAL

1.1 SUBMITTALS

Government approval is required for submittals with a "G" designation; submittals not having a "G" designation are for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. Submit the following in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:

SD-01 Preconstruction Submittals

Resume for the proposed Superintendent; G

Preconstruction Survey; FIO

SD-04 Samples

Color Boards; G

SD-07 Certificates

Progress and Completion Pictures; FIO

1.2 COLOR BOARDS FOR AIR FORCE PROJECTS

[IF REQUIRED] Submit three sets of color boards within 90 calendar days after Contract Award for Design/Bid/Build construction contracts and no later than the 95% Design Submittal for Design/Build contracts. Each set of boards shall include samples of colors and finishes of interior surfaces, such as walls, floors, and ceilings. Samples shall be presented on 8 by 10-1/2 inches boards (modules) with a maximum spread of 24 by 31-1/2 inches for foldouts. Modules shall be designed to fit in a standard loose-leaf, three-ring binder. Where special finishes such as architectural concrete, carpet, or prefinished textured metal panels are required, samples not less than 12 inches square shall be submitted with the board. If more space is needed, more than one board per set may be submitted. The Contractor shall certify that he has reviewed the color samples in detail and that the color samples are in strict accordance with contract drawings and specifications, except as may be otherwise explicitly stated. Submittal of color samples shall not relieve the Contractor of the responsibility to submit samples required elsewhere herein.

1.3 PRECONSTRUCTION SURVEY AND PROGRESS AND COMPLETION PICTURES

Photographically document site conditions prior to start of construction operations. Submit these photographs with a narrative report indicating the existing conditions of the project site prior to mobilization.

Provide monthly, and within one month of the completion of work, digital photographs, 1600 x 1200 x 24 bit true color 5-megapixel minimum resolution in jpeg file format showing the sequence and progress of work.

Take a minimum of 20 digital photographs each week throughout the entire project from a minimum of ten views from points located by the Contracting Officer’s Representative. Submit a view location sketch indicating points of view upon request.

Photographs for each month shall be in a separate monthly directory and each file name shall include a date designator. Cross-reference submittals in the appropriate daily report. Photographs shall be provided for unrestricted use by the Government.

1.4 MINIMUM INSURANCE REQUIREMENTS

Procure and maintain during the entire period of performance under this contract the following minimum insurance coverage:

a. Comprehensive general liability: $500,000 per occurrence

b. Automobile liability: $200,000 per person, $500,000 per occurrence for bodily injury, $20,000 per occurrence for property damage

c. Workmen's compensation as required by Federal and State workers' compensation and occupational disease laws.

d. Employer's liability coverage of $100,000, except in States where workers compensation may not be written by private carriers.

e. Others as required by State law.

1.5 CONTRACTOR SPECIAL REQUIREMENTS

1.5.1 Space Temperature Control, HVAC TAB, and Apparatus Inspection

[CONFIRM SPECIFICATIONS ARE IN DESIGN] All contract requirements of Section 23 05 XX TESTING, ADJUSTING AND BALANCING FOR HVAC, Section 23 09 XX SPACE TEMPERATURE CONTROL SYSTEMS, and Section 26 08 XX APPARATUS INSPECTION AND TESTING shall be accomplished directly by a first tier subcontractor, including the Commissioning Agent. No work required by Section 23 05 XX, 23 09 XX, or 26 08 XX shall be accomplished by a second tier subcontractor.

1.6 SUPERVISION

1.6.1 Minimum Communication Requirements

Have at least one qualified superintendent capable of reading, writing, and conversing fluently in the English language, on the job-site during working hours. In addition, if a Quality Control (QC) representative is required on the contract, then that individual must also have fluent English communication skills.

1.6.2 Superintendent Qualifications

Superintendent must have a minimum of 5 years experience as a project manager, project engineer, superintendent, or quality control manager on projects similar in size, scope and complexity to this project as identified in Section 01 11 00. The project superintendent is subject to removal by the Contracting Officer for non-compliance with requirements specified in the contract and for failure to manage the project to ensure timely completion. Furthermore, the Contracting Officer may issue an order stopping work on all or part of the work until satisfactory corrective action has been taken. No part of the time lost due to such stop work orders shall be made the subject of a claim for extension of time for excess costs or damages by the contractor.

Approval of the project superintendent is required prior to the start of construction. Provide a resume for the proposed superintendent describing their experience with references and qualifications to the contracting officer for approval. The contracting officer reserves the right to interview the proposed project superintendent at any time in order to verify the submitted qualifications.

1.7 PRECONSTRUCTION CONFERENCE

After award of the contract but prior to commencement of any work at the site, meet with the Contracting Officer to discuss and develop a mutual understanding relative to the administration of the contract and safety program, preparation of the schedule of prices, shop drawings, and other submittals, scheduling programming, prosecution of the work, and clear expectations of the "Interim DD Form 1354" Submittal. Major subcontractors who will engage in the work must also attend.

1.8 AVAILABILITY OF CADD DRAWING FILES

After award and upon request, the electronic "Computer-Aided Drafting and Design (CADD)" drawing files will only be made available to the Contractor for use in preparation of construction drawings and data related to the referenced contract subject to the following terms and conditions.

Data contained on these electronic files shall not be used for any purpose other than as a convenience in the preparation of construction drawings and data for the referenced project. Any other use or reuse shall be at the sole risk of the Contractor and without liability or legal exposure to the Government. The Contractor shall make no claim and waives to the fullest extent permitted by law, any claim or cause of action of any nature against the Government, its agents or sub consultants that may arise out of or in connection with the use of these electronic files. The Contractor shall, to the fullest extent permitted by law, indemnify and hold the Government harmless against all damages, liabilities or costs, including reasonable attorney's fees and defense costs, arising out of or resulting from the use of these electronic files.

These electronic CADD drawing files are not construction documents. Differences may exist between the CADD files and the corresponding construction documents. The Government makes no representation regarding the accuracy or completeness of the electronic CADD files, nor does it make representation to the compatibility of these files with the Contractors hardware or software. In the event that a conflict arises between signed and sealed construction documents prepared by the Government and the furnished CADD files, the signed and sealed construction documents shall govern. The Contractor is responsible for determining if any conflict exists. Use of these CADD files does not relieve the Contractor of duty to fully comply with the contract documents, including and without limitation, the need to check, confirm and coordinate the work of all contractors for the project.

If the Contractor uses, duplicates and/or modifies these electronic CADD files for use in producing construction drawings and data related to this contract, all previous indicia of ownership (seals, logos, signatures, initials and dates) shall be removed.

1.9 ELECTRONIC MAIL (E-MAIL) ADDRESS

The Contractor shall establish and maintain electronic mail (e-mail) capability along with the capability to open various electronic attachments in Microsoft, Adobe Acrobat, and other similar formats. Within 10 days after contract award, the Contractor shall provide the Contracting Officer a single (only one) e-mail address for electronic communications from the Contracting Officer related to this contract including, but not limited to contract documents, invoice information, request for proposals, and other correspondence. The Contracting Officer may also use email to notify the Contractor of base access conditions when emergency conditions warrant, such as hurricanes or terrorist threats, etc.. Multiple email addresses will not allowed.

It is the Contractor's responsibility to make timely distribution of all Contracting Officer initiated e-mail with its own organization including field office(s). The Contractor shall promptly notify the Contracting Officer, in writing, of any changes to this email address.

PART 2 PRODUCTS

Not Used

PART 3 EXECUTION

Not Used

-- End of Section -- Section 01 30 00 Page 1