Solicitation Attachment XX - TOPR - Seed Project - B63.xlsx

XLSX spreadsheet 24 KB Posted

Attached to
Joint Base Charleston (JB CHS) Multiple Award Construction Contract (MACC) Federal contract opportunity
Solicitation number
FA441822R0019
Issued by
Department of the Air Force Air Mobility Command

View the file

Other files for this federal contract opportunity

Other files attached to Joint Base Charleston (JB CHS) Multiple Award Construction Contract (MACC), newest first.
File Type Posted
Solicitation Amendment 01 - Attachment 1 - Addendum 01 - Repair Aircraft MX Facility B63 Revised Drawing Sheets.pdf PDF
Solicitation Amendment 01 - Attachment 4 - Addendum 01 SOW - 08 Nov 22.pdf PDF
Solicitation Amendment 01 - Attachment 9 - Orangeburg County WD SC20220016.pdf PDF
Solicitation Amendment 01 - Attachment 2 - As Built Drawings B61.pdf PDF
Solicitation Amendment 01 - Attachment 8 - Dorchester WD SC20220024.pdf PDF
Solicitation Amendment 01 - Attachment 3 - As Built Drawings B63.pdf PDF
Solicitation Amendment 01 - Attachment 5 - Solicitation Section B - Seed Project - 08 Nov 22.pdf PDF
Solicitation Amendment 01 - Attachment 7 - Charleston County WD SC20220023.pdf PDF
Solicitation Amendment 01 - Attachment 6 - Berkeley County WD SC20210022.pdf PDF
Solicitation Amendment 01 - Attachment 10 - Wayne County WD NC20220041.pdf PDF
JB CHS MACC - Questions and Answers - 09 Nov 22.pdf PDF
Update 1 - JB CHS MACC - Pre-Proposal Conference Slides.pdf PDF
Update 2 - JB CHS MACC - Sign-In Sheet for Attendees.pdf PDF
Amendment 1 - JB CHS MACC - Pre-Proposal Conference Slides.pptx PPTX presentation
Solicitation Attachment YT Seed Project Drawings -Updated.pdf PDF
Solicitation Attachment XT - JB Charleston - Question and Answer Form.xlsx XLSX spreadsheet
Solicitation Attachment XU - Past Performance Customer Questionnaire.pdf PDF
Solicitation Attachment XV - Past Performance Survey.pdf PDF
Solicitation Attachment YS Seed Project Specifications.pdf PDF
Solicitation Attachment YT Seed Project Drawings.pdf PDF
Statement of Work - JB CHS MACC.pdf PDF
Statement of Work - Attachment 4 - 01 14 00 - Work Restrictions.docx DOCX document
Statement of Work - Attachment 9 - 01 33 00 - Attachment A - JB CHS Transmittal Form 4025.pdf PDF
Solicitation Attachment XZ - Past Performance Project List.xlsx XLSX spreadsheet
Solicitation Attachment YU Seed Project Hydraulics.pdf PDF
Solicitation Section B - JB CHS MACC - Seed.pdf PDF
Statement of Work - Attachment 5 - 01 30 00 - Administrative Requirements.docx DOCX document
Statement of Work - Attachment 7 - 01 32 00 - Attachment A - Schedule and Pay Request Calendar Example 2.xlsx XLSX spreadsheet
Statement of Work - Attachment 12 - 01 33 00 - Attachment D - Form 4289-R (RFI Register).pdf PDF
Solicitation Attachment XX - TOPR - Seed Project - B63.pdf PDF
Solicitation Attachment XW - JB Charleston MACC Work Load Estimate.pdf PDF
Statement of Work - Attachment 1 - JB Charleston Statement of Work for Architect_Engineering (A_E) Services.pdf PDF
Statement of Work - Attachment 2 - Architectural Compatibility Plan.pdf PDF
Statement of Work - Attachment 3 - 01 11 00 - Summary of Work.docx DOCX document
Statement of Work - Attachment 8 - 01 32 00 - Project Schedule.docx DOCX document
Statement of Work - Attachment 11 - 01 33 00 - Attachment C - Form 4288-R (Submittal Register).pdf PDF
Statement of Work - Attachment 12 - 01 33 00 - Attachment D - Form 4289-R (RFI Register).xlsx XLSX spreadsheet
Statement of Work - Attachment 13 - 01 33 00 - Submittal Procedures.docx DOCX document
Statement of Work - Attachment 14 - 01 35 26 - Attachment A - Accident Investigation Form (CIRS).pdf PDF
Statement of Work - Attachment 15 - 01 35 26 - Governmental Safety Requirements.docx DOCX document
Statement of Work - Attachment 16 - 01 45 00 - Quality Control.docx DOCX document
Solicitation - FA441822R0019.pdf PDF
Solicitation Attachment XY - On and Off-Ramp Procedures.pdf PDF
Solicitation Attachment YV Seed Project Fire Pump Curves.pdf PDF
Statement of Work - Attachment 6 - 01 32 00 - Attachment A - Schedule and Pay Request Calendar Example 1.pdf PDF
Statement of Work - Attachment 10 - 01 33 00 - Attachment B - JB CHS RFI Form.pdf PDF
Statement of Work - Attachment 11 - 01 33 00 - Attachment C - Form 4288-R (Submittal Register).xlsx XLSX spreadsheet
Statement of Work - Attachment 17 - 01 78 00 - Closeout Requirements.docx DOCX document
Show all 48

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

TOPR

Task Order Proposal Request (TOPR)
Contracting Office:628th Contracting Squadron - Joint Base Charleston, SC 29404
Contractor Name:Contractor 1
Project Title:TWCF - Repair Aircraft Maintenance Facility, B63
Project Number:DKFX1069835Project Location:Joint Base Charleston - Air Base
Project Magnitude:$5M - $10MSite Visit Date:SEE SOLICITATION
Solicitation Date:SEE SOLICITATIONProposal Due Date:SEE SOLICITATION
Period of Performance (PoP):440 Calendar Days from Notice to Proceed (NTP)
Solicitation Attachments:
SEE SOLICITATION
Summary of Work:
The work includes repair and renovation of TWCF - Aircraft Maintenance Facility B.63 which includes but not limited to repair/replacement of fire suppressions system, fire alarm/mass notification system, roof, HVAC, Electrical, renovate locker room/shower/restrooms/offices, repair/repaint exterior siding, repair/replace translucent panels, clean/repaint interior of hangar bay, replace select hangar floor slabs, demolition, and incidental related work.
Key Government Personnel
NamePositionOrganizationPhone
Robert MeltonContracting Officer628 CONS843-963-5173
Jonathan HirschContracting Specialist628 CONS843-963-3704
James BrennanProject Manager628 CES843-963-1461
Rick MartinezInspector628 CES843-963-1403
Notice to Offeror: Funds are not presently available for this effort. No award will be made under this solicitation until funds are available. The Government reserves the right to cancel this solicitation, either before or after the closing date. In the event the Government cancels this solicitation, the Government has no obligation to reimburse an offeror for any costs.
Proposal Requirements:
The proposal shall be prepared in accordance with the Schedule B.
Bond Requirements:
XPROPOSAL BOND: The offeror shall submit a Proposal Bond (Standard Form 24) with good and sufficient surety or sureties acceptable to the Government. Proposal Bond, in the amount of 20 percent (20%) of the proposal price. The Proposal Bond penalty may be expressed in terms of a percentage of the proposal price or may be expressed in dollars and cents. The contractor shall submit a Performance Bond (Standard Form 25) and a Payment Bond (Standard Form 25-A) with good and sufficient surety and sureties to the Government within 10 days of award. The penal sum of such bonds will be as follows:

X PERFORMANCE BOND: The penal sum of the performance bonds shall equal one hundred percent (100%) of the contract price. PAYMENT BOND: The penal sum of the payment bonds shall equal one hundred percent (100%) of the contract price.

Pre-Proposal Site Visit:
a. In accordance with FAR Clause 52.237-2, Site Visit (Construction), a site visit will be conducted at [6877 Dorchester Road, North Charleston, SC 29404] (Lat: 32°53’9.31322” N, Long: 80°4’3.0629” W). The Point of Contact (POC) for the site visit is [Jonathan Hirsch], Contracting Specialist, 628 CONS. He can be contacted at Phone Number: [843-963-3704] or e-mail at [jonathan.hirsch@us.af.mil.]. Additional site visit instructions are provided in Solicitation Section [H].

b. Attendance of the site visit for the Seed Project is highly encouraged. Attendance of the site visit on MACC TOPRs after initial MACC award is required for an offerer to be to be considered responsive, unless otherwise specified. Failure to visit the project site will not relieve the Offeror from responsibility for performance of the work and compliance with the terms and conditions of any resultant contract. In no event will a failure to inspect the site constitute grounds for a claim after award of the task order.

Requirement Special Conditions:

Signatures
Contractor Representative:Contracting Officer:
Not applicable for Seed ProjectNot applicable for Seed Project

Lists

Contracting Office List:
628th Contracting Squadron - Joint Base Charleston, SC 29404
20th Contracting Squadron - Shaw AFB, SC 29152
4th Contracting Squadron - Seymour Johnson AFB, NC 27531
Contractor Name:
Contractor 1
Contractor 2
Contractor 3
Contractor 4
Contractor 5
Contractor 6
Contractor 7
Project Number
DKFX
DKGV
DKSK
JBCS
SBML
JBCY
JBCI
JBCE
VKAG
VLSB
Project Location
Joint Base Charleston - Air Base
Joint Base Charleston - Naval Weapons Station
Joint Base Charleston - Defense Fuel Supply Point
Joint Base Charleston - Short Stay
Joint Base Charleston - North Auxillary Air Field
Joint Base Charleston - NIWC
Seymour Johnson Air Force Base
Shaw Air Force Base
Project Magnitude
<$250K
$250K - $1M
$1M - $5M
$5M - $10M
> $10M

File details come from the government source that posted it. Updated .