ReqDescriptionALQ1613624v2.pdf
PDF 377 KB Posted
- Attached to
- Power Supply Solutions Virtual Industry Day Federal contract opportunity
- Solicitation number
- SPRWA1-19-R-0007
About this file
This requirements description and federal contract opportunity outline requirements for the redesign and production of AN/ALQ-161A power supplies. The requirements description seeks proposals to redesign the power supply assembly to address obsolescence, break it into multiple new national stock numbers to facilitate maintenance, and develop a full technical data package. Prototypes and qualification units are required, along with associated testing and technical order updates. The notional schedule includes a requirements review in two months, preliminary design review in six months, and first article qualification testing completed in 20 months. The federal contract opportunity is a draft request for proposal for a multiple award indefinite delivery indefinite quantity contract worth an estimated $800 million over ten years to provide power supply solutions ranging from low voltage to 20kV for various military aircraft. Initial requirements include three national stock numbers for power supplies with estimated quantities provided. The response date for questions on the draft request for proposal is March 18, 2019.
View the file
Other files for this federal contract opportunity
Show all 27
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
For the best experience, open this PDF portfolio in
Acrobat X or Adobe Reader X, or later.
Get Adobe Reader Now!
http://www.adobe.com/go/reader
AN/ALQ-161A POWER SUPPLY REDESIGN AND PRODUCTION
Requiring Office and Address:
Directorate: 408th Supply Chain Management Office Symbol: 408th SCMS/GUEA Attention line: Daniel Eidson, 478-926-2076 Address: 235 Byron Street, Ste. 19-A, Robins AFB, GA 31098-1670
REQUIREMENTS DESCRIPTION
OBJECTIVE
This Requirements Description is for the redesign and qualification of the AN/ALQ-161A Power Supply Assembly, NSN 6130-01-269-3624EW, P/N: 442529-6. The effort will be to evaluate current specifications, build functional, flight-worthy prototypes, test, and certify a qualified manufacturer of the ALQ-161A Power Supply Assembly. The detailed Scope of Work is contained in Attachment 1 and is entitled “Statement of Work for PS2 Multi Award Contract”.
The power supply accounts for one half of an RF transmitter LRU. In addition to modernization and resolution of obsolescence, a goal of this redesign is to break the power supply into multiple new NSNs to facilitate maintenance; therefore, it is requested that design proposals maximize modularity and ease of maintenance.
APPLICABLE DOCUMENTS
442529 Power Supply Assembly Rev AE 439906-3 Specification for Dual-TWT Power Supply Rev J 235010 General Specification for Functional Assemblies Rev AB 435335 Specification for Traveling Wave Tube Rev N 438228 Cooling Plate Subassembly Rev R 438230 Cooling Plate Assembly – Band 5 XMTR Rev U 438463 Envelope Drawing, Band 5 Power Supply Rev B
SPECIFIC TASKS
-Review specifications -Develop first articles/qualification units (Quantity 4) -Validate first articles via acceptance/qualification testing -Assist with system level integration testing / flight test as required -Develop full level 3 technical data package -Develop Technical Order updates -Manufacture production units in accordance with production schedule levied by contract
NOTIONAL FIRST ARTICLE PROGRAM SCHEDULE
• Requirements Review 2 months after contract award (ACA)
• Preliminary Design Review / 50% TDP/TO 6 months ACA
• Critical Design Review / 100% TDP/TO 12 months ACA
• First Article Acceptance Testing Complete 18 months ACA
• FCA/PCA 20 months ACA
• First Article Qualification Testing Complete 20 months ACA
• Support Integration/Flight Test 20-24 months ACA
DELIVERABLES/REPORTING REQUIREMENTS
DD Form 1423 Block 16 Continued Block 8, 10-13 instructions are provided in the following table.
CDRL Description Due Date Gov’t Review Corrections/Updates
A001 Government Property Inventory Report Annually by January 15 N/A N/A
A002 IUID Marking Plan 90 days ACA 60 days 15 days
A003 IUID Marking Activity, Validation, and Verification Report
One report per delivery order, no later than 15 days after final delivery
N/A N/A
A004 Counterfeit Prevention Plan 30 days ACA 60 days 15 days
A007 Product Drawings/Models and Associated Lists
50% TDP due 180 days ACA;
final TDP due 360 days ACA
60 days after each submission 30 days
A008 Test and Evaluation Program Plan 180 days ACA 60 days 15 days
A009 Configuration Management Plan 90 days ACA 60 days 15 days
A010 Configuration Audit Summary Report
30 days after successful FCA/PCA 60 days 15 days
A011 Program Management Plan 30 days ACA 30 days 15 days
A015 Status Report
During FA development, monthly by the 15th day;
during production, quarterly by the 15th day
N/A N/A
A016 Design Review Information Package
30 days prior to design reviews
(PDR, CDR) N/A N/A
A017 Acceptance Test Procedure 270 days ACA 60 days 15 days A018 Acceptance Test Report 15 days after completion of test N/A N/A A019 Qualification Test Procedure 270 days ACA 60 days 15 days A020 Qualification Test Report 30 days after completion of test N/A N/A
CDRL REQUIREMENTS
DD1423(s) Block 16 Continued (Applicable to all CDRLs listed in the table above)
1. Block 9 Distribution Statement: Data items requiring a distribution statement shall use the following:
Distribution Statement D: Distribution authorized to Department of Defense and U.S. DoD contractors only (Administrative or Operational Use, 07JAN2019). Other requests for this document shall be referred to the 408th Supply Chain Management Squadron, 408SCMS/GUEA, 235 Byron St. STE 19A, Robins AFB, GA 31098.
2. Block 7 WAWF Accepter: Data items requiring DD250/WAWF acceptance shall have the following requirement:
WAWF accepter: The Government will accept the receiving report through WAWF. The contractor shall submit the receiving report upon final submission to DODAAC FA8522. The Government will indicate approval or disapproval through WAWF within 30 days of submittal.
3. Block 4 Electronic submission: Contractor format is acceptable. Data items requiring submission via email shall be submitted to the ALQ-161 Program Manager and Program Engineer, currently Kim Urzua (kimberly.urzua@us.af.mil) and Daniel Eidson (james.eidson.1@us.af.mil); however, the Contractor shall verify the current points of contact prior to submission.
Specific CDRL requirements: refer to Attachment A for the continuation pages for CDRL A007, Product Drawings/Models and Associated Lists.
Attachment A - ALQ-161A Band 5 XM