Question_and_Answers.docx
DOCX document 15 KB Posted
- Attached to
- DLA Distribution Bahrain, Southwest Asia Contractor Owned Contractor Operated (COCO) Distribution Center
- Solicitation number
- SP330017R5010
- Issued by
-
Defense Logistics Agency Distribution
About this file
Question and Answers
View the file
Other files
Show 40 more
Latest 50 of 62 listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
DDNB Pre Proposal Conference – Question and Answer 6/29/2017
| Question |
| Answer |
| 1. |
| Can the Government define the difference between storage shed-open sides (outdoor uncovered) vice storage shed-open sides (outdoor covered)? |
| The definition will be provided via amendment, along with clarification of the requirement. |
| 2. |
| Are the (4) HATS currently delivered and installed? |
| Yes |
| 3. |
| If so, how are the costs covered for movement of the HATS in the case of new construction? Who is responsible? |
| This will be answered via amendment. |
| 4. |
| Is it mandatory to have both indoor and outdoor facilities in a single location or multiple locations acceptable? |
| It is not mandatory. |
| 5. |
| Is the K12 gate currently installed at the current facility? |
| No. But they will be installed before transition begins. |
| 6. |
| The guard SOP requires British regiment Gurkhas of Indian or Nepalese nationality. Can DLA advise what other nationalities have been previously approved? |
| None. |
| 7. |
| If our space solution includes an annex location, is a separate communications room required if the two locations can be connected via fiber optic line? |
| The Government will consult with the information operations group and provide an answer via an amendment. |
| 8. |
| What are the expectations for surge & sustainment? What percent increase for how long as a guide? |
| This information is not available. This will be addressed via a request for quote when a task order is issued, if the government opts to utilize CLIN X008 for support. |
| 9. |
| How does DLA define the weight bands for workload? Can DLA provide volume (Qty of lines or other metric) for each weight band? |
| The definition of weight bands can be found in TE 2.1. The volume can be found in TEs 5.1 and 5.2. |