Industry Questions and Government Responses
View the file
Other files
Show 40 more
Latest 50 of 62 listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Question
| RFP Page |
| RFP Para, |
| Government Response |
| 1. |
| In Section L Evaluation Factor 4, the Government instructs Offerors to “describe their approach to providing at contract award, the minimum requirements for existing indoor storage and existing outdoor storage as described in Table 3.” Further, Evaluation Factor 5, Transition Approach and PWS C-1.8, Transition Plan, the Government has established a timeline that requires Offerors “to have IT infrastructure prepared to install Government Data Systems no later than 28 days after Contract award, and have the capability to start receiving material for processing beginning 61 days after Contract award IAW the requirements in Section C-5.” |
The Offeror has completed an exhaustive search for a solution that meets both the Government’s facility requirements, as identified in Table 3, Bahrain Space Requirements, and the aforementioned transition timeline. We have determined that no such facility is currently available in Bahrain within the 20-mile radius of the Mina Salman Pier.
This requires Offerors to undertake some level of construction to meet facility requirements of the solicitation; to include the incumbent contractor. Due to the complex nature of OCONUS construction management, all offers will present the Government some level of schedule risk.
The Government’s requirement that the minimum indoor storage and outdoor storage be provided at Contract award and the imposed schedule requirements in PWS C-1.8 strongly favor the incumbent facility, to the exclusion of other solutions, which could provide significant long-term value to the Government.
Due to non-availability of suitable facilities, including the incumbent facility, in the specified geographic area, the Government's stated transition timeline unnecessarily restricts competition and excludes viable solutions that provide significant capability enhancements or cost savings to DLA. The Offeror understands that a stated Contract award of March 2018 and a 120-day transition period will require the Government to execute the incumbent contractor's pre-negotiated 6-month contract extension.
While we acknowledge the Government's desire for the transition timeline stated in PWS C-1.8, we request the Government consider, for the purpose of evaluation, the best value trade-off of longer transition schedules in exchange for facility enhancements and significant cost savings that are possible through innovation in this market—so long as the proposed solution would be complete prior to the final period of performance of the current contract extension period.
| A0006 |
| Section L Factor 4 |
Section M Via Amendment 0007, the IT Infrastructure timeline has been extended to 45 days. The warehouse preparation timeline has been modified to 80 days. The date that the contractor will need to be ready to receive stock is now specified as 20 May 2018. Contract Award and Full Performance dates as well as transition duration have not changed.
| 2. |
| Offeror request clarification of the following. |
Amendment 6, Q&A 23 requested clarification as to the Additional HATS Cost being Cost Reimbursable under CLIN X0005, The Contracting Officer response was - "Additional HATS costs shall be captured under CLIN X003.".
Offeror request the Contracting Officer confirm the Additional HAST Cost will be captured under CLIN X003, additionally if the Cost is a CLIN X0003 requirement the Offeror request detail as to the acquisition Cost, and expected Maintenance Responsibility for the Offeror.
| A0006 |
| Q&A 23 |
| The HATS costs shall be captured under CLIN X003. |
The average price of the HATS including installation and shipping in the AOR is ~$195K.
| 3. |
| Offeror request clarification of the following. |
Offeror assumes that if the Indoor Facilities Solution for CLIN X002 is acceptable for all subfactor requirements, and the promised completion date is past the Section B Contract Start date, that the Offer Section B, and J.34 Proposed Productive Hours required realignment with our acceptable solution, that the Government will not rate the Offerors proposal unacceptable.
Request the Government consideration that our assumption is correct?
| A0006 |
| Section B, J.34 Period of Performance |
| The offeror’s proposal must meet all requirements of the solicitation to be considered acceptable. |