This document is a Request for Information (RFI) related to Solicitation SP0604-24-R-0421 issued by the Defense Logistics Agency Energy (DLA Energy) for the purchase of carbon pollution-free electricity (CFE) and supplemental grid energy to meet the electricity requirements of federal civilian and defense agencies located in the PJM Interconnection/Regional Transmission Operator (PJM/RTO) region.
The RFI seeks feedback on several topics, including: whether the government would accept a parental guarantee as an alternative to a letter of credit, clarification on expected load and usage requirements, the proposal due date, and a potential extension to the proposal due date. The solicitation will be structured as a requirements contract, with firm fixed price CFE CLINs and requirements-type CLINs for supplemental grid energy. The contract will have a 20-year delivery period. DLA Energy is committed to a fair and expeditious procurement to support the federal government's goal of 100% CFE by 2030. Interested offerors must be on the approved list of licensed retail electricity suppliers in the applicable states.
View the file
Other files
Show 40 more
Latest 50 of 59 listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
PJM CFE 2024 Amendment 0008 RFP SP0604-24-R-0421 Page 1 of 1
Request for Information – Group 7
1. Respective of the costs associated with the letter of credit requirements, can you review the below. Would the government accept an alternative method of surety than a letter of credit? Would it accept a parental guarantee?
Can you clarify the timeline required to provide it should it be needed? With the various line items and length of term for the solicitation, the amount would vary based on potential award.
a. Yes, the Government will accept a parental guarantee if the parent company is investment grade. If at any point during contract performance, their rating drops beneath investment grade, then a letter of credit would be necessary. The timeline required would be for the entire term of the contract performance period.
2. There are some discrepancies regarding expected load and returned usage Regarding NIH, SPE60424R0408 – PJM 2024 Amendment 2 includes the below language from the screenshot regarding load reduction on account.
055014022291. Will an amendment be released to revise the respective pages for the CFE bid to update the expected load requirements?
a. Please refer to Amd. 0008
3. Regarding MPO, SPE60424R0408 – PJM 2024 Amendment 3 includes the below language from the screenshot regarding load increase on for the line item. Solicitation SPE60424R0408 indicates growth year over year but does not provide the anticipated end date for the load growth. Can the DLA please provide clarity for the year over year growth profile and the expected date and volume with which it reaches an expected normal average usage?
a. Please refer to Amd. 0008. The Government requests that CFE projects be sized in accordance with Table I of the solicitation.
4. With the revised offer due date of DEC 20, 2024 in Amendment 3, can you confirm this applies to the submission of the technical response and if it does include pricing.
a. Please refer to Amd. 0007. Technical and price proposals are due 20 Dec 2024.
5. With the revised offer date set for DEC 20 and respective of the 30 day pricing review hold , would the government consider the submission date revision till a date after Jan 1, 2025 to avoid holiday and holiday related schedule challenges?
a. Please provide a more detailed reason for this request.