SOW-_Elati_Mariposa_SCC_Heating,_Ventilation_and_Air_Conditioning_Replacements.pdf
PDF 81 KB Posted
- Attached to
- HVAC Replacements at Elati, Mariposa, and Security Command Center Locations (15% SBE Goal)
- Solicitation number
- IFB 325DH003
- Issued by
- Denver County, Colorado
About this file
This Statement of Work (SOW) is for the Regional Transportation District (RTD) in Denver, Colorado, detailing a comprehensive HVAC replacement project across three facilities: Elati Light Rail Facility, Mariposa Light Rail Facility, and the Security Command Center. The project involves removing and replacing various HVAC equipment, including three makeup air units, one hot water boiler, one air-cooled chiller, two Computer Room Cooling (CRAC) units, three data center inrow cooling units, and two rooftop heating and cooling units. Additional work includes upgrading structural supports, installing a humidification system, hot aisle/cold aisle separation strip curtains, replacing registers, and installing balance dampers. All new equipment must be compatible with the existing Johnson Controls, Inc. Building Automation System (JCI BAS).
The project requires the contractor to obtain all necessary permits, provide new materials with manufacturer warranties, and supply their own tools and equipment. Safety requirements include licensed crane operators, specific Personal Protective Equipment (PPE), a Lockout/Tagout (LOTO) program, and coordination with RTD to deenergize overhead catenary system wires. The project will be fully commissioned, with the contractor supporting the commissioning agent in testing and providing required deliverables such as Operations and Maintenance Manuals, Test and Balance Reports, and As-built drawings. The document is dated February 7, 2025, suggesting this is a future planned infrastructure improvement project aimed at modernizing and maintaining RTD's HVAC systems across multiple facilities.
View the file
Other files
Show all 12
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Elati, Mariposa, SCC HVAC Replacement
Statement of Work
Replace Heating, Ventilation and Air Conditioning (HVAC) equipment at Elati, Mariposa, and Security Command Center
February 7, 2025
Provide construction services to replace HVAC equipment at three Regional Transportation District (RTD) Denver facilities according the Technical Specifications contained in the attached Project Manuals and Drawings for each RTD facility. Major work includes but not limited to the demolition of old HVAC equipment and installation of replacement equipment. The work to be provided at each location is listed below. For detailed specifications and descriptions of each task listed below, review the attached Project Manuals and Drawings.
1. Elati Light Rail Facility - 2701 South Elati Street-Englewood, CO 80110:
a. Remove and replace three makeup air units
i. Upgrade structure for heavier equipment
b. Remove and replace one hot water boiler
c. Remove and replace one air cooled chiller
d. Remove and replace valves and variable frequency drives (VFD)
e. Extend existing radiant heater flue vents to outdoors
2. Mariposa Light Rail Facility – 655 Mariposa Street-Denver, CO 80204
a. Remove two Computer Room Cooling (CRAC) Units
b. Install three data center inrow cooling units
i. Upgrade structure for heavier equipment
c. Install one humidification system
d. Install hot aisle/cold aisle separation strip curtains
3. Security Command Center – 1205 W. 7th Avenue-Denver, CO 80204
a. Remove and replace two rooftop heating and cooling units
b. Replace registers
c. Install balance dampers
All HVAC equipment shall be connected to integrated and compatible with existing Johnson Controls, Inc. Building Automation System (JCI BAS). All package equipment shall use JCI controllers to ensure maximum compatibility with the JCI BAS system.
Contractor shall obtain all permits and arrange for inspections.
All materials and preventive maintenance parts shall be new, of good quality and warranted according to the manufacturer.
Contractor shall provide their own tools and equipment. RTD will not loan manlifts or material handling equipment.
Contractor shall coordinate with RTD to deenergize overhead catenary system wires to safely perform work.
Elati, Mariposa, SCC HVAC Replacement
All crane lifts must be done by licensed operators. Lift plans and hoisting and rigging equipment will be checked by RTD Safety staff.
Construction site Personal Protective Equipment (PPE) includes hardhats, safety shoes, high visibility vests, and safety glasses.
Contractor shall have a Lockout/Tagout (LOTO) program and provide workers LOTO equipment.
Contractor shall provide equipment submittals for approval by Engineer of Record and RTD.
Punchlist inspections shall be conducted after all work scope is completed.
This project will be fully commissioned. Contractor shall support commissioning agent in gathering information and executing testing.
Operations and Maintenance Manuals, Test and Balance Reports, and As-built drawings are required deliverables.