SOUTH_FIRE_STATION_PHASE_4_ESTIMATE_OF_PROBABLE_COST_2025.04.24.pdf

PDF 36 KB Posted

Attached to
ARFF Station #1 (South) Refurbishment - Phase 4
Solicitation number
25-032-ITB
Issued by
Kenton County, Kentucky

About this file

This document is a detailed cost breakdown for the South Fire Station Phase 4 Interior/Exterior Upgrades project, prepared by CMTA Engineering with a date of April 24, 2025. The project involves comprehensive renovations across multiple divisions, including demolition, masonry, wood and plastics, doors and hardware, HVAC, plumbing, fire protection, and electrical work. Key scope items include HVAC demolition, tuckpointing, concrete paving, wall protection in bathrooms, replacement of hollow metal doors and frames, aluminum storefront windows and doors, VAV boxes and controls, and electrical system modifications.

The total project cost is $328,647.00, which includes a base bid of $259,800.00 for divisions 02-17, a 10% contingency of $25,980.00, and overhead and profit (OH&P) at 15% totaling $42,867.00. The project is broken down by division, with the most significant expenses in the doors, frame, and hardware category at $141,300.00, followed by HVAC, plumbing, and fire protection at $99,000.00. The document includes both a base bid and an alternate bid for the control tower storefront, providing flexibility in the project scope. The pricing structure allows for detailed cost tracking and potential adjustments during the renovation process.

View the file

Other files

Show all 18

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SOUTH FIRE STATION PHASE 4 INTERIOR/EXTERIOR UPGRADES EMBOSS DESIGN

CMTA ENGINEERING

DATE: 2025.04.24

PHASE 4

DIVISION ITEM QUANTITY UNIT COST/UNIT TOTAL DIVISION

TOTALS

02 DEMOLITION

02070 SELECTIVE DEMOLITION

02070.01 HVAC demolition 1 Lump sum 5,000.00 5,000.00

DIVISION SUB-TOTAL 5,000.00

04 MASONRY

04200.00 Tuckpointing 1 Lump sum 3,000.00 3,000.00

Grind concrete paving 1 Lump sum 1,000.00 1,000.00

DIVISION SUB-TOTAL 4,000.00

06 WOOD, PLASTICS, COMPOSITS

06411 WALL PROTECTION

06411.01 Wall protection in bathrooms 1 Lump sum 6,000.00 6,000.00

DIVISION SUB-TOTAL 6,000.00

08 DOORS, FRAME, AND HARDWARE

08110 08110.01 Replace hollow metal door,frame,hardware 6 EA 3,000.00 18,000.00

08411 08411.01 Replace aluminum storefront windows and doors - BASE BID

1 Lump Sum 105,300.00 105,300.00

08411.02 Replace control tower storefront - ALTERNATE

BID

1 Lump Sum 18,000.00 18,000.00

DIVISION SUB-TOTAL 141,300.00

15 HVAC, PLUMBING, AND FIRE PROTECTION

15000 15000.01

Replace remaining VAV boxes and controls

8 EA 10,000.00 80,000.00

15000.02 Testing and balancing 1 Lump sum 5,000.00 5,000.00

15000.03 Sheet metal - new VAV connections 8 EA 250.00 2,000.00

VAV piping, valves, and accessories 8 EA 1,000.00 8,000.00

Baseboard heater-3 way valve & controls 1 EA 4,000.00 4,000.00

DIVISION SUB-TOTAL 99,000.00

16 ELECTRICAL

26000 26000.01 Disconnect/reconnect door hardware access control

3 EA 1,500.00 4,500.00

DIVISION SUB-TOTAL 4,500.00

SUB-TOTAL DIVISIONS 02-17 259,800.00

CONTINGENCY AT 10% 25,980.00

SUB-TOTAL 285,780.00

OH&P AT 15% 42,867.00

TOTAL 328,647.00