This is a solicitation for a paving indefinite-delivery, indefinite-quantity (IDIQ) contract covering multiple construction disciplines to be managed by the 75th Civil Engineering Group at Hill Air Force Base and Utah Air National Guard Base. The contract will include projects at remote sites such as Little Mountain, Utah; Utah Test and Training Range; and Carter Creek, Utah. Responses are due no later than July 14, 2022. The purpose is to establish the Hill Air Force Base Paving IDIQ from which task orders will be issued to define specific project requirements. Products and services will include exterior and interior pavement projects such as installation, removal, excavation, maintenance, repair, and replacement of flexible and rigid pavement, roads, parking lots, sidewalks, and airfield surfaces. A new question and answer matrix is attached for offerors to submit any new or unanswered questions by June 20, 2022. Point of contacts are provided for further information.

View the file

Other files

File Type Posted
Solicitation Amendment FA820122R00120006.pdf PDF
Atch 3-Section L-Instructions Conditions and Notices to Bidders 220712.pdf PDF
Atch 4 - Section M - Evaluation Factors for Award 220711.pdf PDF
Atch 3-Section L-Instructions Conditions and Notices to Bidders 220711.pdf PDF
Solicitation Amendment FA820122R00120005.pdf PDF
Paving Solicitation Q and A Matrix 220706.xlsx XLSX spreadsheet
Atch 3-Section L-Instructions Conditions and Notices to Bidders 220706.pdf PDF
Solicitation Amendment FA820122R00120004.pdf PDF
Atch 4 - Section M - Evaluation Factors for Award 220706.pdf PDF
Atch 3-Section L-Instructions Conditions and Notices to Bidders 220705.pdf PDF
Solicitation Amendment FA820122R00120003.pdf PDF
Atch 4 - Section M - Evaluation Factors for Award 220705.pdf PDF
Paving Solicitation Q and A Matrix 220705.xlsx XLSX spreadsheet
Solicitation Amendment FA820122R00120002.pdf PDF
Atch 1 - BASIC IDIQ SOW-220628.pdf PDF
Solicitation Amendment FA820122R00120001.pdf PDF
Paving Solicitation Q and A Matrix-220627.xlsx XLSX spreadsheet
Atch 1 - BASIC IDIQ SOW-220627.pdf PDF
Appendix 15 - UFGS 32 17 23.pdf PDF
Atch 2 - Paving Contractor Ordering Procedures 220525.pdf PDF
Atch 3 - Section L - Instructions Conditions and Notices to Bidders.pdf PDF
Appendix 13 - UFGS 32 13 13.06.pdf PDF
Appendix 12 - UFGS 32 12 36.13.pdf PDF
Paving Solicitation Q and A Matrix.xlsx XLSX spreadsheet
Atch 9 - Sublette County Wage Determination 220107.pdf PDF
Atch 7 - Davis County Wage Determination 220107.pdf PDF
Appendix 10 - UFGS 32 01 11.51.pdf PDF
Appendix 16 - Safety Appendix.pdf PDF
Atch 4 - Section M - Evaluation Factors for Award.pdf PDF
Atch 8 - Salt Lake County Wage Determination 220107.pdf PDF
Appendix 2 - UFGS 01 42 00.pdf PDF
Appendix 5 - UFGS 03 01 00.pdf PDF
Atch 11 - Weber County Wage Determination 220107.pdf PDF
Appendix 3 - UFGS 01 57 19.pdf PDF
Appendix 14 - UFGS 32 16 19.pdf PDF
Atch 6 - Paving Past Performance Relevancy Baseline.pdf PDF
Appendix 6 - UFGS 03 30 00.pdf PDF
Appendix 4 - UFGS 01 78 00.pdf PDF
Atch 5 - Past Performance Information (PPI) Sheet.pdf PDF
Appendix 9 - UFGS 31 00 00.pdf.pdf PDF
Appendix 8 - UFGS 07 61 14.00 20.pdf PDF
Atch 10 - Tooele County Wage Determination 220107.pdf PDF
Appendix 11 - UFGS 32 11 26.pdf PDF
Atch 1 - BASIC IDIQ SOW.pdf PDF
Appendix 1 - UFC 1-200-01.pdf PDF
Appendix 7 - UFGS 03 37 00.pdf PDF
Show all 46

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

IMPORTANT - The "offer" section on the reverse must be fully completed by offeror.

4. CONTRACT NUMBER 5. REQUISITION/PURCHASE REQUEST NUMBER 6. PROJECT NUMBER

7. ISSUED BY CODE 8. ADDRESS OFFER TO

9. FOR INFORMATION

CALL:

a. NAME b. TELEPHONE NUMBER (Include area code) (NO COLLECT CALLS)

SOLICITATION

NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid and "bidder".

10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS (Title, identifying number, date)

11. The contractor shall begin performance within calendar days and complete it within calendar days after receiving award, notice to proceed. This performance period is mandatory negotiable. (See ).

13. ADDITIONAL SOLICITATION REQUIREMENTS:

a. Sealed offers in original and copies to perform the work required are due at the place specified in Item 8 by (hour) local time (date). If this is a sealed bid solicitation, offers will be publicly opened at that time. Sealed envelopes containing offers shall be marked to show the offeror's name and address, the solicitation number, and the date and time offers are due.

b. An offer guarantee is, is not required.

c. All offers are subject to the (1) work requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.

d. Offers providing less than calendar days for Government acceptance after the date offers are due will not be considered and will be rejected.

STANDARD FORM 1442 (REV. 8/2014)

Prescribed by GSA - FAR (48 CFR) 53.236-1(d)

12a. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?

(If "YES", indicate within how many calendar days after award in Item 12b.)

12b. CALENDAR DAYS

YES NO

SOLICITATION, OFFER,

AND AWARD

(Construction, Alteration, or Repair)

1. SOLICITATION NUMBER 2. TYPE OF SOLICITATION

SEALED BID (IFB)

NEGOTIATED (RFP)

3. DATE ISSUED PAGE OF PAGES

AMOUNTS

OFFER (Must be fully completed by offeror)

14. NAME AND ADDRESS OF OFFEROR (Include ZIP Code) 15. TELEPHONE NUMBER (Include area code)

16. REMITTANCE ADDRESS (Include only if different than Item 14.)

CODE FACILITY CODE

17. The offeror agrees to perform the work required at the prices specified below in strict accordance with the terms of this solicitation, if this offer is accepted by the Government in writing within calendar days after the date offers are due. (Insert any number equal to or greater than the minimum requirement stated in Item 13d. Failure to insert any number means the offeror accepts the minimum in Item 13d.)

18. The offeror agrees to furnish any required performance and payment bonds.

19. ACKNOWLEDGMENT OF AMENDMENTS

(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each)

AMENDMENT

NUMBER

DATE.

20a. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN OFFER (Type or print) 20b. SIGNATURE 20c. OFFER DATE

21. ITEMS ACCEPTED:

AWARD (To be completed by Government)

CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE

28. NEGOTIATED AGREEMENT (Contractor is required to sign this document and return copies to issuing office.) Contractor agrees to furnish and deliver all items or perform all work requirements identified on this form and any continuation sheets for the consideration stated in this contract. The rights and obligations of the parties to this contract shall be governed by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, certifications, and specifications incorporated by reference in or attached to this contract.

29. AWARD (Contractor is not required to sign this document.) Your offer on this solicitation is hereby accepted as to the items listed. This award consummates the contract, which consists of (a) the Government solicitation and your offer, and (b) this contract award. No further contractual document is necessary.

30a. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED TO SIGN (Type or print)

31a. NAME OF CONTRACTING OFFICER (Type or print)

30b. SIGNATURE 30c. DATE 31b. UNITED STATES OF AMERICA

BY

31c. DATE

STANDARD FORM 1442 (REV. 8/2014) BACK

22. AMOUNT 23. ACCOUNTING AND APPROPRIATION DATA

24. SUBMIT INVOICES TO ADDRESS SHOWN IN

(4 copies unless otherwise specified)

ITEM 25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO

10 U.S.C. 2304(c) ( ) 41 U.S.C. 3304(a) ( )

26. ADMINISTERED BY 27. PAYMENT WILL BE MADE BY

Section A - Solicitation/Contract Form

Hill AFB, Utah Air National Guard, and Geographically Separated Locations Paving Requirement

Purchase Requisition Number: A020670 Date: 15 Feb 2022 Proposal Identifier: FA820122R0012 Date: 31 May 2022

Section B - Supplies or Services & Prices or Costs

Additional Information/Notes

NAICS: 237310

PSC: Z2LB

Minimum guarantee is $250.00.

Estimated maximum is $92,500,581.60.

Period of Performance: Starts from the first date of the delivery period to the last day of the task order issued on or before the last day of the ordering period (est. 02 November 2022 to 01 May 2028 (includes 6-month option))

FAR 52.232-18 Availability of Funds Funds are not presently available for this contract. The Government's obligation under this contract is contingent upon the availability of appropriated funds from which payment for contract purposes can be made. No legal liability on the part of the Government for any payment may arise until funds are made available to the Contracting Officer for this contract and until the Contractor receives notice of such availability, to be confirmed in writing by the Contracting Officer.

Item Supplies/Service Qty Unit Unit Price

Amount

Paving Construction Project

The contractor shall provide all labor, material and equipment to perform exterior/interior pavement projects in accordance with (IAW) this SOW and the TO SOW. Service projects include, but are not limited to, installation, removal, excavation, maintenance, repair, and/or replacement of: e.g., flexible and rigid pavement; road and parking lot construction; slab-on-grade, curb and gutter, waterway, and sidewalk construction; aggregate based road construction; airfield pavement surface construction; water/storm drain and sewer utility; exterior parking lot/roadway/airfield lighting; airfield rubber; pavement striping, joint sealant, crack sealant, slurry/chip seal, pothole repair, asphalt mill and overlay.

Product Service Code: Z2LB Pricing Arrangement: Firm Fixed Price

500 Lot

Post Award Conference with delivery of Safety Plan

The contractor shall attend a Post Award Orientation Conference. Required Attendees: Contract Manager for the Prime Contract. An Agenda of the meeting will be sent within three (3) days of the meeting date. PLEASE

NOTE- A UNIT PRICE FOR CLIN 0002 IS NOT REQUIRED AS THE

MINIMUM GUARANTEE WILL BE FULFILLED WITH CONTRACTOR

ATTENDANCE AT THE POST AWARD ORIENTATION

CONFERENCE. MINIMUM GUARANTEE AMOUNT IS DETERMINED

BY THE GOVERNMENT.

Product Service Code: Z2LB Pricing Arrangement: Firm Fixed Price

1 Lot

Paving Construction Project

The contractor shall provide all labor, material and equipment to perform exterior/interior pavement projects in accordance with (IAW) this SOW and the TO SOW. Service projects include, but are not limited to, installation, removal, excavation, maintenance, repair, and/or replacement of: e.g., flexible and rigid pavement; road and parking lot construction; slab-on-

Option Line Item grade, curb and gutter, waterway, and sidewalk construction; aggregate based road construction; airfield pavement surface construction; water/storm drain and sewer utility; exterior parking lot/roadway/airfield lighting; airfield rubber; pavement striping, joint sealant, crack sealant, slurry/chip seal, pothole repair, asphalt mill and overlay.

Product Service Code: Z2LB Pricing Arrangement: Firm Fixed Price

100 Lot

Section C - Description/Specifications/Statement of Work

Requirements The scope of this effort includes a broad range of exterior/interior pavement projects and appurtenances at Hill Air Force Base (HAFB), Utah Air National Guard Base (UTANG), areas under HAFB jurisdiction, which include, but are not limited to the following Geographically Separated Locations (GSL): Little Mountain Test Annex (LMTA), Utah Test and Training Range (UTTR - North/South Range), Wendover (UT/NV), Dugway Proving Grounds (DPG), Wendover Peak, Bovine, Trout Creek, Carter Creek, Grassy, Boulder, WY.

Section D - Packaging and Marking

Section E - Inspection and Acceptance

FAR Clauses Incorporated by Reference

Number Title Effective Date 52.246-12 Inspection of Construction. Aug 1996

Overall Contract Inspection/Acceptance Locations

Inspection and Acceptance Location

Both Destination Instructions: Inspection and Acceptance location and POC will be identified for each task order.

DoDAAC: F2D0AC CountryCode: USA

75 CE

AF BPN NO MILSBILLS PROCESSES

7302 WARDLEIGH RD

HILL AFB, UT 84056-5129

UNITED STATES

Casey Anderson Email: casey.anderson.17@us.af.mil Telephone: 801-777-4904

Inspection and Acceptance Location

Both Destination Instructions: Inspection and Acceptance location and POC will be identified for each task order.

DoDAAC: F2D0AC CountryCode: USA

75 CE

AF BPN NO MILSBILLS PROCESSES

7302 WARDLEIGH RD

HILL AFB, UT 84056-5129

UNITED STATES

Casey Anderson Email: casey.anderson.17@us.af.mil Telephone: 801-777-4904

Option Line Item

Inspection and Acceptance Location

Both Destination Instructions: Inspection and Acceptance location and POC will be identified for each task order.

DoDAAC: F2D0AC CountryCode: USA

75 CE

AF BPN NO MILSBILLS PROCESSES

7302 WARDLEIGH RD

HILL AFB, UT 84056-5129

UNITED STATES

Casey Anderson

Email: casey.anderson.17@us.af.mil Telephone: 801-777-4904

Section F - Deliveries or Performance

Overall Contract Delivery Period

From date of lead time event to beginning of performance 10 Calendar Days Date of Notice to Proceed Receipt

From date of lead time event to completion of performance 90 Calendar Days Date of Notice to Proceed Receipt

Line Item Delivery Schedule QTY Address and POC

Period of Performance From 02 Nov 2022 To 01 Nov 2027

500 Lot

Period of Performance From 02 Nov 2022 To 01 Nov 2027

1 Lot

Option Line Item

Period of Performance From 02 Nov 2027 To 01 May 2028

100 Lot

FAR Clauses Incorporated by Reference

Number Title Effective Date 52.247-34 F.o.b. Destination. Nov 1991

Section G - Contract Administration Data

DFARS Clauses Incorporated by Reference

Number Title Effective Date 252.201-7000 Contracting Officer's Representative. Dec 1991 252.204-7006 Billing Instructions. Oct 2005 252.232-7003 Electronic Submission of Payment Requests and Receiving Reports. Dec 2018 252.236-7000 Modification Proposals--Price Breakdown. Dec 1991

DFARS Clauses Incorporated by Full Text

252.232-7006 Wide Area WorkFlow Payment Instructions. Dec 2018

As prescribed in 232.7004(b), use the following clause:

WIDE AREA WORKFLOW PAYMENT INSTRUCTIONS (DEC 2018)

(a) As used in this clause- Definitions.

"Department of Defense Activity Address Code (DoDAAC)" is a six position code that uniquely identifies a unit, activity, or organization.

"Document type" means the type of payment request or receiving report available for creation in Wide Area WorkFlow (WAWF).

"Local processing office (LPO)" is the office responsible for payment certification when payment certification is done external to the entitlement system.

"Payment request" and "receiving report" are defined in the clause at 252.232-7003, Electronic Submission of Payment Requests and Receiving Reports.

(b) The WAWF system provides the method to electronically process vendor payment requests and receiving reports, as Electronic invoicing.

authorized by Defense Federal Acquisition Regulation Supplement (DFARS) 252.232-7003, Electronic Submission of Payment Requests and Receiving Reports.

(c) To access WAWF, the Contractor shall- WAWF access.

(1) Have a designated electronic business point of contact in the System for Award Management at https://www.sam.gov; and

(2) Be registered to use WAWF at https://wawf.eb.mil/ following the step-by-step procedures for self-registration available at this web site.

(d) The Contractor should follow the training instructions of the WAWF Web-Based Training Course and use the Practice WAWF training.

Training Site before submitting payment requests through WAWF. Both can be accessed by selecting the "Web Based Training" link on the WAWF home page at https://wawf.eb.mil/

(e) Document submissions may be via web entry, Electronic Data Interchange, or File Transfer WAWF methods of document submission.

Protocol.

(f) The Contractor shall use the following information when submitting payment requests and receiving reports WAWF payment instructions.

in WAWF for this contract or task or delivery order:

(1) The Contractor shall submit payment requests using the following document type(s): Document type.

(i) For cost-type line items, including labor-hour or time-and-materials, submit a cost voucher.

(ii) For fixed price line items-

(A) That require shipment of a deliverable, submit the invoice and receiving report specified by the Contracting Officer.

(Contracting Officer: Insert applicable invoice and receiving report document type(s) for fixed price line items that require shipment of a deliverable.)

(B) For services that do not require shipment of a deliverable, submit either the Invoice 2in1, which meets the requirements for the invoice and receiving report, or the applicable invoice and receiving report, as specified by the Contracting Officer.

(Contracting Officer: Insert either "Invoice 2in1" or the applicable invoice and receiving report document type(s) for fixed price line items for services.)

(iii) For customary progress payments based on costs incurred, submit a progress payment request.

(iv) For performance based payments, submit a performance based payment request.

(v) For commercial item financing, submit a commercial item financing request.

(2) ) Fast Pay requests are only permitted when Federal Acquisition Regulation (FAR) 52.213-1 is included in the contract.

(f) [Note: The Contractor may use a WAWF "combo" document type to create some combinations of invoice and receiving report in one step.]

(3) The Contractor shall use the information in the Routing Data Table below only to fill in applicable fields in Document routing.

WAWF when creating payment requests and receiving reports in the system.

Routing Data Table*

Field Name in WAWF Data to be entered in WAWF

Pay Official DoDAAC ____

Issue By DoDAAC ____

Admin DoDAAC ____

Inspect By DoDAAC ____

Ship To Code ____

Ship From Code ____

Mark For Code ____

Service Approver (DoDAAC) ____

Service Acceptor (DoDAAC) ____

Accept at Other DoDAAC ____

LPO DoDAAC ____

DCAA Auditor DoDAAC ____

Other DoDAAC(s) ____

(*Contracting Officer: Insert applicable DoDAAC information. If multiple ship to/acceptance locations apply, insert "See Schedule" or "Not applicable.")

(**Contracting Officer: If the contract provides for progress payments or performance-based payments, insert the DoDAAC for the contract administration office assigned the functions under FAR 42.302(a)(13).)

(4) The Contractor shall ensure a payment request includes documentation appropriate to the type of payment request in Payment request.

accordance with the payment clause, contract financing clause, or Federal Acquisition Regulation 52.216-7, Allowable Cost and Payment, as applicable.

(5) The Contractor shall ensure a receiving report meets the requirements of DFARS Appendix F. Receiving report.

(g) WAWF point of contact.

(1) The Contractor may obtain clarification regarding invoicing in WAWF from the following contracting activity's WAWF point of contact.

(Contracting Officer: Insert applicable information or "Not applicable.")

(2) Contact the WAWF helpdesk at 866-618-5988, if assistance is needed.

(End of clause)

Section H - Special Contract Requirements

Paving On-Ramp Procedures, 12 May 22, AFSC OL:H/PZIEB: The Government reserves the right to "on-ramp" additional contractors during the life of this IDIQ contract. The Government will do so by reopening the competition using a separate solicitation and evaluation at any time during the term of the IDIQ ordering period.

The Government may choose to on-ramp any number of On-Ramp IDIQ awardees when the Contracting Officer determines it is in the Government's best interest to do so in order to enhance the competitive environment of Task Order (TO) solicitations under the originally awarded IDIQ contracts.

The evaluation and selection of new IDIQ contract awardees for any on-ramp shall meet the requirements established in the initial solicitation and be subject to the same evaluation and award criteria used for the initial IDIQ contract awards. Current effective IDIQ contract holders will not re-compete. Once the new IDIQ contract awardees are selected, the awardees will be included in the IDIQ contract pool and will compete among all other IDIQ contract holders for future orders.

Contracts made effective under these on-ramp procedures will not exceed the ordering period or period of performance for the length of time remaining in the originally awarded IDIQ contract.

The Government's actions to add new IDIQ contracts under the on-ramp process shall not constitute a basis of contractual adjustment for any existing IDIQ contract awardees.

Section I - Contract Clauses

Any clause not incorporated in the Basic solicitation/contract may be incorporated at the Task Order level as determined by the CO.

FAR Clauses Incorporated by Reference

Number Title Effective Date 52.203-19 Prohibition on Requiring Certain Internal Confidentiality Agreements or Statements. Jan 2017 52.204-9 Personal Identity Verification of Contractor Personnel. Jan 2011 52.204-13 System for Award Management Maintenance. Oct 2018 52.204-18 Commercial and Government Entity Code Maintenance. Aug 2020 52.204-19 Incorporation by Reference of Representations and Certifications. Dec 2014

52.204-23 Prohibition on Contracting for Hardware, Software, and Services Developed or Provided by Kaspersky Lab and Other Covered Entities.

Nov 2021

52.204-25 Prohibition on Contracting for Certain Telecommunications and Video Surveillance Services or Equipment.

Nov 2021

52.209-10 Prohibition on Contracting with Inverted Domestic Corporations. Nov 2015 52.219-6 Notice of Total Small Business Set-Aside. Nov 2020 52.219-8 Utilization of Small Business Concerns. Oct 2018 52.219-13 Notice of Set-Aside of Orders. Mar 2020 52.222-6 Construction Wage Rate Requirements. Aug 2018 52.222-7 Withholding of Funds. May 2014 52.222-8 Payrolls and Basic Records. Jul 2021 52.222-9 Apprentices and Trainees. Jul 2005 52.222-10 Compliance with Copeland Act Requirements. Feb 1988 52.222-11 Subcontracts (Labor Standards). May 2014 52.222-12 Contract Termination-Debarment. May 2014 52.222-13 Compliance with Construction Wage Rate Requirements and Related Regulations. May 2014 52.222-14 Disputes Concerning Labor Standards. Feb 1988 52.222-15 Certification of Eligibility. May 2014 52.222-21 Prohibition of Segregated Facilities. Apr 2015 52.222-26 Equal Opportunity. Sep 2016 52.222-32 Construction Wage Rate Requirements-Price Adjustment (Actual Method). Aug 2018 52.222-50 Combating Trafficking in Persons. Nov 2021 52.223-5 Pollution Prevention and Right-to-Know Information. May 2011 52.223-5 Alternate I Pollution Prevention and Right-to-Know Information. - (Alternate I) May 2011 52.223-18 Encouraging Contractor Policies to Ban Text Messaging While Driving. Jun 2020 52.225-13 Restrictions on Certain Foreign Purchases. Feb 2021 52.228-2 Additional Bond Security. Oct 1997 52.228-5 Insurance-Work on a Government Installation. Jan 1997 52.228-11 Individual Surety-Pledge of Assets. Feb 2021 52.228-14 Irrevocable Letter of Credit. Nov 2014 52.229-12 Tax on Certain Foreign Procurements. Feb 2021 52.232-18 Availability of Funds. Apr 1984 52.232-33 Payment by Electronic Funds Transfer-System for Award Management. Oct 2018 52.232-39 Unenforceability of Unauthorized Obligations. Jun 2013 52.232-40 Providing Accelerated Payments to Small Business Subcontractors. Nov 2021 52.233-1 Disputes. May 2014 52.233-3 Protest after Award. Aug 1996 52.233-4 Applicable Law for Breach of Contract Claim. Oct 2004 52.236-2 Differing Site Conditions. Apr 1984 52.236-5 Material and Workmanship. Apr 1984 52.236-7 Permits and Responsibilities. Nov 1991 52.236-8 Other Contracts. Apr 1984

52.236-9 Protection of Existing Vegetation, Structures, Equipment, Utilities, and Improvements.

Apr 1984

52.236-10 Operations and Storage Areas. Apr 1984 52.236-11 Use and Possession Prior to Completion. Apr 1984 52.236-12 Cleaning Up. Apr 1984 52.236-13 Accident Prevention. Nov 1991 52.236-15 Schedules for Construction Contracts. Apr 1984 52.236-17 Layout of Work. Apr 1984 52.242-14 Suspension of Work. Apr 1984 52.243-1 Alternate I Changes-Fixed-Price. - (Alternate I) Aug 1987 52.243-4 Changes. Jun 2007 52.243-5 Changes and Changed Conditions. Apr 1984

52.244-6 Subcontracts for Commercial Products and Commercial Services. Nov 2021 52.249-4 Termination for Convenience of the Government (Services) (Short Form). Apr 1984 52.249-10 Default (Fixed-Price Construction). Apr 1984

DFARS Clauses Incorporated by Reference

Number Title Effective Date 252.203-7000 Requirements Relating to Compensation of Former DoD Officials. Sep 2011 252.203-7002 Requirement to Inform Employees of Whistleblower Rights. Sep 2013 252.204-7003 Control of Government Personnel Work Product. Apr 1992 252.204-7004 Antiterrorism Awareness Training for Contractors. Feb 2019 252.204-7012 Safeguarding Covered Defense Information and Cyber Incident Reporting. Dec 2019 252.204-7015 Notice of Authorized Disclosure of Information for Litigation Support. May 2016

252.204-7018 Prohibition on the Acquisition of Covered Defense Telecommunications Equipment or Services.

Jan 2021

252.222-7002 Compliance with Local Labor Laws (Overseas). Jun 1997 252.223-7006 Prohibition on Storage, Treatment, and Disposal of Toxic or Hazardous Materials. Sep 2014 252.223-7008 Prohibition of Hexavalent Chromium. Jun 2013 252.225-7001 Buy American and Balance of Payments Program. Dec 2017 252.225-7002 Qualifying Country Sources as Subcontractors. Dec 2017 252.225-7043 Antiterrorism/Force Protection for Defense Contractors Outside the United States. Jun 2015 252.225-7048 Export-Controlled Items. Jun 2013 252.232-7010 Levies on Contract Payments. Dec 2006 252.232-7011 Payments in Support of Emergencies and Contingency Operations. May 2013

252.232-7017 Accelerating Payments to Small Business Subcontractors-Prohibition on Fees and Consideration.

Apr 2020

252.233-7001 Choice of Law (Overseas). Jun 1997 252.237-7010 Prohibition on Interrogation of Detainees by Contractor Personnel. Jun 2013 252.241-7001 Government Access. Dec 1991 252.243-7001 Pricing of Contract Modifications. Dec 1991 252.244-7000 Subcontracts for Commercial Items. Oct 2020 252.246-7004 Safety of Facilities, Infrastructure, and Equipment for Military Operations. Oct 2010

FAR Clauses Incorporated by Full Text

52.204-1 Approval of Contract. Dec 1989

As prescribed in 4.103 , insert the following clause: Approval of Contract (Dec 1989) This contract is subject to the written approval of __PROCURING CONTRACTING OFFICER (PCO)__ and shall not be binding until so approved. (End of clause)

52.211-12 Liquidated Damages-Construction. Sep 2000

As prescribed in 11.503(b), insert the following clause in solicitations and contracts:

Liquidated Damages-Construction (Sept 2000)

(a) If the Contractor fails to complete the work within the time specified in the contract, the Contractor shall pay liquidated damages to the Government in the amount of ($373.84) for Task Orders <$1M or ($747.68) for Task Orders >$1M for each calendar day of delay until the work is completed or accepted.

(b) If the Government terminates the Contractor's right to proceed, liquidated damages will continue to accrue until the work is completed. These liquidated damages are in addition to excess costs of repurchase under the Termination clause.

(End of clause)

52.216-18 Ordering. Aug 2020

As prescribed in 16.506(a), insert the following clause: Ordering (Aug 2020) (a) Any supplies and services to be furnished under this contract shall be ordered by issuance of delivery orders or task orders by the individuals or activities designated in the Schedule. Such orders may be issued from __2 November 2022__ through __1 May 2028__. (b) All delivery orders or task orders are subject to the terms and conditions of this contract. In the event of conflict between a delivery order or task order and this contract, the contract shall control. (c) A delivery order or task order is considered "issued" when- (1) If sent by mail (includes transmittal by U.S. mail or private delivery service), the Government deposits the order in the mail; (2) If sent by fax, the Government transmits the order to the Contractor's fax number; or (3) If sent electronically, the Government either- (i) Posts a copy of the delivery order or task order to a Government document access system, and notice is sent to the Contractor; or (ii) Distributes the delivery order or task order via email to the Contractor's email address. (d) Orders may be issued by methods other than those enumerated in this clause only if authorized in the contract. (End of clause)

52.216-19 Order Limitations. Oct 1995

As prescribed in 16.506(b), insert a clause substantially the same as follows:

Order Limitations (Oct 1995)

(a) Minimum order. When the Government requires supplies or services covered by this contract in an amount of less than _$250.00_, the Government is not obligated to purchase, nor is the Contractor obligated to furnish, those supplies or services under the contract.

(b) Maximum order. The Contractor is not obligated to honor-

(1) Any order for a single item in excess of __$20,000,000.00_;

(2) Any order for a combination of items in excess of __$20,000,000.00_; or

(3) A series of orders from the same ordering office within __180__ days that together call for quantities exceeding the limitation in paragraph (b)(1) or (2) of this section.

(c) If this is a requirements contract (i.e., includes the Requirements clause at subsection 52.216-21 of the Federal Acquisition Regulation (FAR)), the Government is not required to order a part of any one requirement from the Contractor if that requirement exceeds the maximum-order limitations in paragraph (b) of this section.

(d) Notwithstanding paragraphs (b) and (c) of this section, the Contractor shall honor any order exceeding the maximum order limitations in paragraph (b), unless that order (or orders) is returned to the ordering office within __5__ days after issuance, with written notice stating the Contractor's intent not to ship the item (or items) called for and the reasons. Upon receiving this notice, the Government may acquire the supplies or services from another source.

(End of clause)

52.216-22 Indefinite Quantity. Oct 1995

As prescribed in 16.506(e), insert the following clause: Indefinite Quantity (Oct 1995) (a) This is an indefinite-quantity contract for the supplies or services specified, and effective for the period stated, in the Schedule. The quantities of supplies and services specified in the Schedule are estimates only and are not purchased by this contract. (b) Delivery or performance shall be made only as authorized by orders issued in accordance with the Ordering clause. The Contractor shall furnish to the Government, when and if ordered, the supplies or services specified in the Schedule up to and including the quantity designated in the Schedule as the "maximum." The Government shall order at least the quantity of supplies or services designated in the Schedule as the "minimum." (c) Except for any limitations on quantities in the Order Limitations clause or in the Schedule, there is no limit on the number of orders that may be issued. The Government may issue orders requiring delivery to multiple destinations or performance at multiple locations. (d) Any order issued during the effective period of this contract and not completed within that period shall be completed by the Contractor within the time specified in the order. The contract shall govern the Contractor's and Government's rights and obligations with respect to that order to the same extent as if the order were completed during the contract's effective period; provided, that the Contractor shall not be required to make any deliveries under this contract after 1 May 2029. (End of clause)

52.216-32 Alternate I Task-Order and Delivery-Order Ombudsman. (Alternate I) Sep 2019

As prescribed in 16.506(j), insert the following clause:

Task-Order and Delivery-Order Ombudsman (Sept 2019)

(a) In accordance with 41 U.S.C. 4106(g), the Agency has designated the following task-order and delivery-order Ombudsman for this contract. The Ombudsman must review complaints from the Contractor concerning all task-order and delivery-order actions for this contract and ensure the Contractor is afforded a fair opportunity for consideration in the award of orders, consistent with the procedures in the contract.

____Ms. Melinda Schmidt, 6038 Aspen Ave, Bldg 1289 Upstairs, Hill AFB, UT 84056, Phone: (801) 777-6549, melinda.schmidt@us.af.mil.

(b) Consulting an ombudsman does not alter or postpone the timeline for any other process (e.g., protests).

(c) Before consulting with the Ombudsman, the Contractor is encouraged to first address complaints with the Contracting Officer for resolution.

When requested by the Contractor, the Ombudsman may keep the identity of the concerned party or entity confidential, unless prohibited by law or agency procedure.

As prescribed in 16.506(j), add the following paragraph (d) to the basic clause.

(d) Contracts used by multiple agencies.

(1) This is a contract that is used by multiple agencies. Complaints from Contractors concerning orders placed under contracts used by multiple agencies are primarily reviewed by the task-order and delivery-order Ombudsman for the ordering activity.

(2) The ordering activity has designated the following task-order and delivery-order Ombudsman for this order:

Ms. Melinda Schmidt, 6038 Aspen Ave, Bldg 1289 Upstairs, Hill AFB, UT 84056, Phone: (801) 777-6549, melinda.schmidt@us.af.mil.

(3) Before consulting with the task-order and delivery-order Ombudsman for the ordering activity, the Contractor is encouraged to first address complaints with the ordering activity's Contracting Officer for resolution. When requested by the Contractor, the task-order and delivery-order Ombudsman for the ordering activity may keep the identity of the concerned party or entity confidential, unless prohibited by law or agency procedure.

52.217-9 Option to Extend the Term of the Contract. Mar 2000

As prescribed in 17.208(g), insert a clause substantially the same as the following:

Option to Extend the Term of the Contract (Mar 2000)

(a) The Government may extend the term of this contract by written notice to the Contractor within _45 days_; provided that the Government gives the Contractor a preliminary written notice of its intent to extend at least __60 days before the contract expires. The preliminary notice does not commit the Government to an extension.

(b) If the Government exercises this option, the extended contract shall be considered to include this option clause.

(c) The total duration of this contract, including the exercise of any options under this clause, shall not exceed 5 years and 6 months.

(End of clause)

52.228-15 Performance and Payment Bonds-Construction. Jun 2020

As prescribed in , insert a clause substantially as follows:28.102-3(a)

PERFORMANCE AND PAYMENT BONDS-CONSTRUCTION (JUN 2020)

. As used in this clause-(a) Definitions means the award price of the contract; or, for requirements contracts, the price payable for the estimated total quantity; Original contract price or, for indefinite-quantity contracts, the price payable for the specified minimum quantity. Original contract price does not include the price of any options, except those options exercised at the time of contract award.

. Unless the resulting contract price is valued at or below the threshold specified in Federal Acquisition (b) Amount of required bonds Regulation 28.102-1(a) on the date of award of this contract, the successful offeror shall furnish performance and payment bonds to the Contracting Officer as follows:

. The penal amount of performance bonds at the time of contract award shall be 100 percent of (1) Performance bonds (Standard Form 25) the original contract price.

. The penal amount of payment bonds at the time of contract award shall be 100 percent of the (2) Payment Bonds (Standard Form 25A) original contract price.

Additional bond protection. (3) The Government may require additional performance and payment bond protection if the contract price is (i) increased. The increase in protection generally will equal 100 percent of the increase in contract price.

The Government may secure the additional protection by directing the Contractor to increase the penal amount of the existing bond (ii) or to obtain an additional bond.

. The Contractor shall furnish all executed bonds, including any necessary reinsurance agreements, to the (c) Furnishing executed bonds Contracting Officer, within the time period specified in the Bid Guarantee provision of the solicitation, or otherwise specified by the Contracting Officer, but in any event, before starting work.

. The bonds shall be in the form of firm commitment, supported by corporate sureties whose names (d) Surety or other security for bonds appear on the list contained in Treasury Department Circular 570, individual sureties, or by other acceptable security such as postal money order, certified check, cashier's check, irrevocable letter of credit, or, in accordance with Treasury Department regulations, certain bonds or notes of the United States. Treasury Circular 570 is published in the or may be obtained from the:Federal Register

U.S. Department of the Treasury, Financial Management, Service Surety Bond Branch, 3700 East West Highway, Room 6 F01, Hyattsville, MD 20782.

Or via the internet at http://www.fms.treas.gov/c570/.

(40 U.S.C. 3133(c)). Any waiver of the right to sue on the payment bond is void unless it is in (e) Notice of subcontractor waiver of protection writing, signed by the person whose right is waived, and executed after such person has first furnished labor or material for use in the performance of the contract.

(End of clause)

52.232-5 Payments under Fixed-Price Construction Contracts. May 2014

As prescribed in 32.111(a)(5), insert the following clause:

Payments under Fixed-Price Construction Contracts (May 2014)

(a) Payment of price. The Government shall pay the Contractor the contract price as provided in this contract.

(b) Progress payments. The Government shall make progress payments monthly as the work proceeds, or at more frequent intervals as determined by the Contracting Officer, on estimates of work accomplished which meets the standards of quality established under the contract, as approved by the Contracting Officer.

(1) The Contractor's request for progress payments shall include the following substantiation:

(i) An itemization of the amounts requested, related to the various elements of work required by the contract covered by the payment requested.

(ii) A listing of the amount included for work performed by each subcontractor under the contract.

(iii) A listing of the total amount of each subcontract under the contract.

(iv) A listing of the amounts previously paid to each such subcontractor under the contract.

(v) Additional supporting data in a form and detail required by the Contracting Officer.

(2) In the preparation of estimates, the Contracting Officer may authorize material delivered on the site and preparatory work done to be taken into consideration. Material delivered to the Contractor at locations other than the site also may be taken into consideration if-

(i) Consideration is specifically authorized by this contract; and

(ii) The Contractor furnishes satisfactory evidence that it has acquired title to such material and that the material will be used to perform this contract.

(c) Contractor certification. Along with each request for progress payments, the Contractor shall furnish the following certification, or payment shall not be made: (However, if the Contractor elects to delete paragraph (c)(4) from the certification, the certification is still acceptable.)

I hereby certify, to the best of my knowledge and belief, that-

(1) The amounts requested are only for performance in accordance with the specifications, terms, and conditions of the contract;

(2) All payments due to subcontractors and suppliers from previous payments received under the contract have been made, and timely payments will be made from the proceeds of the payment covered by this certification, in accordance with subcontract agreements and the requirements of Chapter 39 of Title 31, United States Code;

(3) This request for progress payments does not include any amounts which the prime contractor intends to withhold or retain from a subcontractor or supplier in accordance with the terms and conditions of the subcontract; and

(4) This certification is not to be construed as final acceptance of a subcontractor's performance.

____ (Name)

____ (Title)

____ (Date)

(d) Refund of unearned amounts. If the Contractor, after making a certified request for progress payments, discovers that a portion or all of such request constitutes a payment for performance by the Contractor that fails to conform to the specifications, terms, and conditions of this contract (hereinafter referred to as the "unearned amount"), the Contractor shall-

(1) Notify the Contracting Officer of such performance deficiency; and

(2) Be obligated to pay the Government an amount (computed by the Contracting Officer in the manner provided in paragraph (j) of this clause) equal to interest on the unearned amount from the 8 thday after the date of receipt of the unearned amount until-

(i) The date the Contractor notifies the Contracting Officer that the performance deficiency has been corrected; or

(ii) The date the Contractor reduces the amount of any subsequent certified request for progress payments by an amount equal to the unearned amount.

(e) Retainage. If the Contracting Officer finds that satisfactory progress was achieved during any period for which a progress payment is to be made, the Contracting Officer shall authorize payment to be made in full. However, if satisfactory progress has not been made, the Contracting Officer may retain a maximum of 10 percent of the amount of the payment until satisfactory progress is achieved. When the work is substantially complete, the Contracting Officer may retain from previously withheld funds and future progress payments that amount the Contracting Officer considers adequate for protection of the Government and shall release to the Contractor all the remaining withheld funds. Also, on completion and acceptance of each separate building, public work, or other division of the contract, for which the price is stated separately in the contract, payment shall be made for the completed work without retention of a percentage.

(f) Title, liability, and reservation of rights. All material and work covered by progress payments made shall, at the time of payment, become the sole property of the Government, but this shall not be construed as-

(1) Relieving the Contractor from the sole responsibility for all material and work upon which payments have been made or the restoration of any damaged work; or

(2) Waiving the right of the Government to require the fulfillment of all of the terms of the contract.

(g) Reimbursement for bond premiums. In making these progress payments, the Government shall, upon request, reimburse the Contractor for the amount of premiums paid for performance and payment bonds (including coinsurance and reinsurance agreements, when applicable) after the Contractor has furnished evidence of full payment to the surety. The retainage provisions in paragraph (e) of this clause shall not apply to that portion of progress payments attributable to bond premiums.

(h) Final payment. The Government shall pay the amount due the Contractor under this contract after-

(1) Completion and acceptance of all work;

(2) Presentation of a properly executed voucher; and

(3) Presentation of release of all claims against the Government arising by virtue of this contract, other than claims, in stated amounts, that the Contractor has specifically excepted from the operation of the release. A release may also be required of the assignee if the Contractor's claim to amounts payable under this contract has been assigned under the Assignment of Claims Act of1940 (31 U.S.C.3727 and 41 U.S.C.6305).

(i) Limitation because of undefinitized work. Notwithstanding any provision of this contract, progress payments shall not exceed 80 percent on work accomplished on undefinitized contract actions. A "contract action" is any action resulting in a contract, as defined in FAR subpart 2.1, including contract modifications for additional supplies or services, but not including contract modifications that are within the scope and under the terms of the contract, such as contract modifications issued pursuant to the Changes clause, or funding and other administrative changes.

(j) Interest computation on unearned amounts. In accordance with 31 U.S.C.3903(c)(1), the amount payable under paragraph (d)(2) of this clause shall be-

(1) Computed at the rate of average bond equivalent rates of 91-day Treasury bills auctioned at the most recent auction of such bills prior to the date the Contractor receives the unearned amount; and

(2) Deducted from the next available payment to the Contractor.

52.232-8 Discounts for Prompt Payment. Feb 2002

As prescribed in , insert the following clause:32.111(b)(1)

DISCOUNTS FOR PROMPT PAYMENT (FEB 2002)

Discounts for prompt payment will not be considered in the evaluation of offers. However, any offered discount will form a part of the (a) award, and will be taken if payment is made within the discount period indicated in the offer by the offeror. As an alternative to offering a discount for prompt payment in conjunction with the offer, offerors awarded contracts may include discounts for prompt payment on individual invoices.

In connection with any discount offered for prompt payment, time shall be computed from the date of the invoice. If the Contractor has not (b) placed a date on the invoice, the due date shall be calculated from the date the designated billing office receives a proper invoice, provided the agency annotates such invoice with the date of receipt at the time of receipt. For the purpose of computing the discount earned, payment shall be considered to have been made on the date that appears on the payment check or, for an electronic funds transfer, the specified payment date. When the discount date falls on a Saturday, Sunday, or legal holiday when Federal Government offices are closed and Government business is not expected to be conducted, payment may be made on the following business day.

(End of clause)

52.232-11 Extras. Apr 1984

As prescribed in , insert the following clause, appropriately modified with respect to payment due dates in accordance with agency 32.111(c)(2) regulations, in solicitations and contracts when a fixed-price supply contract, fixed-price service contract, or transportation contract is contemplated:

EXTRAS (APR 1984)

Except as otherwise provided in this contract, no payment for extras shall be made unless such extras and the price therefor have been authorized in writing by the Contracting Officer.

(End of clause)

52.232-27 Prompt Payment for Construction Contracts. Jan 2017

As prescribed in , insert the following clause:32.908(b)

PROMPT PAYMENT FOR CONSTRUCTION CONTRACTS (JAN 2017)

Notwithstanding any other payment terms in this contract, the Government will make invoice payments under the terms and conditions specified in this clause. The Government considers payment as being made on the day a check is dated or the date of an electronic funds transfer. Definitions of pertinent terms are set forth in sections 2.101, 32.001, and 32.902 of the Federal Acquisition Regulation. All days referred to in this clause are calendar days, unless otherwise specified. (However, see paragraph (a)(3) concerning payments due on Saturdays, Sundays, and legal holidays.)

Invoice payments- (a) . For purposes of this clause, there are several types of invoice payments that may occur (1) Types of invoice payments under this contract, as follows:

Progress payments, if provided for elsewhere in this contract, based on Contracting Officer approval of the estimated amount and (i) value of work or services performed, including payments for reaching milestones in any project.

The due date for making such payments is 14 days after the designated billing office receives a proper payment request. If the (A) designated billing office fails to annotate the payment request with the actual date of receipt at the time of receipt, the payment due date is the 14 thday after the date of the Contractor’s payment request, provided the designated billing office receives a proper payment request and there is no disagreement over quantity, quality, or Contractor compliance with contract requirements.

The due date for payment of any amounts retained by the Contracting Officer in accordance with the clause at 52.232-5, (B) Payments Under Fixed-Price Construction Contracts, is as specified in the contract or, if not specified, 30 days after approval by the Contracting Officer for release to the Contractor.

Final payments based on completion and acceptance of all work and presentation of release of all claims against the Government (ii) arising by virtue of the contract, and payments for partial deliveries that have been accepted by the Government ( each separate building, public e.g., work, or other division of the contract for which the price is stated separately in the contract).

The due date for making such payments is the later of the following two events:(A)

The 30 thday after the designated billing office receives a proper invoice from the Contractor.(1)

The 30 thday after Government acceptance of the work or services completed by the Contractor. For a final invoice when the (2) payment amount is subject to contract settlement actions ( release of claims), acceptance is deemed to occur on the effective date of the contract e.g., settlement.

If the designated billing office fails to annotate the invoice with the date of actual receipt at the time of receipt, the invoice (B) payment due date is the 30 thday after the date of the Contractor’s invoice, provided the designated billing office receives a proper invoice and there is no disagreement over quantity, quality, or Contractor compliance with contract requirements.

. The Contractor shall prepare and submit invoices to the designated billing office specified in the contract. A proper (2) Contractor's invoice invoice must include the items listed in paragraphs (a)(2)(i) through (a)(2)(xi) of this clause. If the invoice does not comply with these requirements, the designated billing office must return it within 7 days after receipt, with the reasons why it is not a proper invoice. When computing any interest penalty owed the Contractor, the Government will take into account if the Government notifies the Contractor of an improper invoice in an untimely manner.

Name and address of the Contractor.(i)

Invoice date and invoice number. (The Contractor should date invoices as close as possible to the date of mailing or transmission.)(ii)

Contract number or other authorization for work or services performed (including order number and line item number).(iii)

Description of work or services performed.(iv)

Delivery and payment terms ( discount for prompt payment terms).(v) e.g., Name and address of Contractor official to whom payment is to be sent (must be the same as that in the contract or in a proper notice (vi) of assignment).

Name (where practicable), title, phone number, and mailing address of person to notify in the event of a defective invoice.(vii)

For payments described in paragraph (a)(1)(i) of this clause, substantiation of the amounts requested and certification in accordance (viii) with the requirements of the clause at 52.232-5, Payments Under Fixed-Price Construction Contracts.

Taxpayer Identification Number (TIN). The Contractor shall include its TIN on the invoice only if required elsewhere in this (ix) contract.

Electronic funds transfer (EFT) banking information.(x)

The Contractor shall include EFT banking information on the invoice only if required elsewhere in this contract.(A)

If EFT banking information is not required to be on the invoice, in order for the invoice to be a proper invoice, the Contractor (B) shall have submitted correct EFT banking information in accordance with the applicable solicitation provision ( 52.232-38, Submission of e.g., Electronic Funds Transfer Information with Offer), contract clause ( 52.232-33, Payment by Electronic Funds Transfer-System for Award e.g., Management, or 52.232-34, Payment by Electronic Funds Transfer-Other Than System for Award Management), or applicable agency procedures.

EFT banking information is not required if the Government waived the requirement to pay by EFT.(C)

Any other information or documentation required by the contract.(xi)

. The designated payment office will pay an interest penalty automatically, without request from the Contractor, if (3) Interest penalty payment is not made by the due date and the conditions listed in paragraphs (a)(3)(i) through (a)(3)(iii) of this clause are met, if applicable. However, when the due date falls on a Saturday, Sunday, or legal holiday, the designated payment office may make payment on the following working day without incurring a late payment interest penalty.

The designated billing office received a proper invoice.(i)

The Government processed a receiving report or other Government documentation authorizing payment and there was no…

This is the start of the file's text. The full file is on GovTribe.

File details come from the government source that posted it. Updated .