Atch 1 - BASIC IDIQ SOW.pdf

PDF 2 MB Posted

Attached to
Hill AFB, Utah Air National Guard, and Geographically Separated Locations Paving Requirement
Solicitation number
FA8201-22-R-0012
Issued by

About this file

This is a request for proposal for an indefinite-delivery, indefinite-quantity paving contract at Hill Air Force Base in Utah. The contract will cover paving and general construction projects at Hill AFB, the Utah Air National Guard Base, and remote sites including Boulder Seismic Station in Wyoming, Little Mountain in Utah, and the Utah Test and Training Range. Task orders will define specific project requirements. Proposals are due by July 14, 2022 and questions regarding the solicitation are due by June 20, 2022. The 75th Civil Engineering Group at Hill AFB will manage the contract.

View the file

Other files

File Type Posted
Solicitation Amendment FA820122R00120006.pdf PDF
Atch 3-Section L-Instructions Conditions and Notices to Bidders 220712.pdf PDF
Atch 4 - Section M - Evaluation Factors for Award 220711.pdf PDF
Atch 3-Section L-Instructions Conditions and Notices to Bidders 220711.pdf PDF
Solicitation Amendment FA820122R00120005.pdf PDF
Paving Solicitation Q and A Matrix 220706.xlsx XLSX spreadsheet
Atch 3-Section L-Instructions Conditions and Notices to Bidders 220706.pdf PDF
Solicitation Amendment FA820122R00120004.pdf PDF
Atch 4 - Section M - Evaluation Factors for Award 220706.pdf PDF
Atch 3-Section L-Instructions Conditions and Notices to Bidders 220705.pdf PDF
Solicitation Amendment FA820122R00120003.pdf PDF
Atch 4 - Section M - Evaluation Factors for Award 220705.pdf PDF
Paving Solicitation Q and A Matrix 220705.xlsx XLSX spreadsheet
Solicitation Amendment FA820122R00120002.pdf PDF
Atch 1 - BASIC IDIQ SOW-220628.pdf PDF
Solicitation Amendment FA820122R00120001.pdf PDF
Paving Solicitation Q and A Matrix-220627.xlsx XLSX spreadsheet
Atch 1 - BASIC IDIQ SOW-220627.pdf PDF
Appendix 15 - UFGS 32 17 23.pdf PDF
Atch 2 - Paving Contractor Ordering Procedures 220525.pdf PDF
Atch 3 - Section L - Instructions Conditions and Notices to Bidders.pdf PDF
Appendix 13 - UFGS 32 13 13.06.pdf PDF
Appendix 12 - UFGS 32 12 36.13.pdf PDF
Paving Solicitation Q and A Matrix.xlsx XLSX spreadsheet
Atch 9 - Sublette County Wage Determination 220107.pdf PDF
Atch 7 - Davis County Wage Determination 220107.pdf PDF
Appendix 10 - UFGS 32 01 11.51.pdf PDF
Appendix 16 - Safety Appendix.pdf PDF
Atch 4 - Section M - Evaluation Factors for Award.pdf PDF
Atch 8 - Salt Lake County Wage Determination 220107.pdf PDF
Appendix 2 - UFGS 01 42 00.pdf PDF
Appendix 5 - UFGS 03 01 00.pdf PDF
Atch 11 - Weber County Wage Determination 220107.pdf PDF
Appendix 3 - UFGS 01 57 19.pdf PDF
Appendix 14 - UFGS 32 16 19.pdf PDF
Atch 6 - Paving Past Performance Relevancy Baseline.pdf PDF
Solicitation - FA820122R0012.pdf PDF
Appendix 6 - UFGS 03 30 00.pdf PDF
Appendix 4 - UFGS 01 78 00.pdf PDF
Atch 5 - Past Performance Information (PPI) Sheet.pdf PDF
Appendix 9 - UFGS 31 00 00.pdf.pdf PDF
Appendix 8 - UFGS 07 61 14.00 20.pdf PDF
Atch 10 - Tooele County Wage Determination 220107.pdf PDF
Appendix 11 - UFGS 32 11 26.pdf PDF
Appendix 1 - UFC 1-200-01.pdf PDF
Appendix 7 - UFGS 03 37 00.pdf PDF
Show all 46

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Basic Indefinite Delivery Indefinite Quantity (IDIQ)

Statement of Work (SOW) for

Paving

1 June 2022

Preparing Organization:

AFMC 75 CES

5713 Lahm Lane, Bldg 593 Hill AFB, UT 84056

DISTRIBUTION STATEMENT A: Approved for public release; distribution is unlimited.

Paving SOW Hill AFB, Utah

2 | P a g e

Table of Contents

1.0 SCOPE

2.0 DESCRIPTION

3.0 REQUIREMENTS AND RESPONSIBILITIES

4.0 REQUIREMENTS

4.1. This section describes general requirements to be supported. Specific requirements will be identified at the TO level

4.2. Software and Unit Price Requirements:

4.3. IDIQ Management:

4.4. Site Conditions:

4.5. Contract Drawings and Specifications:

4.6. Submittals:

4.7. As-Built Record Drawings:

4.8. Storage of Materials:

4.9. Construction Evacuation Permit:

4.10. Testing:

4.11. Warranties:

4.12. Utility Outages and Traffic Closures:

4.13. Safety Requirements:

4.14. Cold Weather Precautions:

4.15. Protection of Government Property and Personnel:

4.16. Daily Cleanup:

4.17. Covering of Debris:

4.18. Removals and Salvage:

4.19. Final Cleaning:

4.20. Utility Marking:

4.21. Environmental Protection:

4.22. Storm Water Permitting:

4.23. Sanitary and Industrial Waste Water:

4.24. Green Procurement:

5.0 IDIQ AND TASK ORDER (TO) ADMINISTRATION

5.1. Ordering Procedures:

5.2. Bid, Performance and Payment Bond:

5.3. TO Performance:

5.4. Mitigation Plan:

5.5. Liquidated Damages:

5.6. Work Schedule:

5.7. Closeout Procedures:

5.8. Contractor Base Identification and Credentials:

5.9. Voluntary Protection Program (VPP):

5.10. Place of Performance:

5.11. Task Order (TO) Period of Performance (PoP):

APPENDIX A (PUBLICATIONS AND FORMS)

APPENDIX B (SUBMITTAL CHECKLIST)

APPENDIX C (BASE CIVIL ENGINEERING EXCAVATION PERMIT)

APPENDIX D (CONTRACTOR’S SAFETY AND HAZARDOUS MATERIAL REQUIREMENT)

APPENDIX E (MINIMUM EXPLOSIVE AWARENESS)

APPENDIX F (HILL AFB LANDFILL MAP)

3 | P a g e

1.0 SCOPE

1.1. This Statement of Work (SOW) describes overall construction services and support required to provide paving projects.

The scope of this effort includes a broad range of exterior/interior pavement projects and appurtenances at Hill Air Force Base (HAFB), Utah Air National Guard Base (UTANG), areas under HAFB jurisdiction, which include, but are not limited to the following Geographically Separated Locations (GSL): Little Mountain Test Annex (LMTA), Utah Test and Training Range (UTTR – North/South Range), Wendover (UT/NV), Dugway Proving Grounds (DPG), Wendover Peak, Bovine, Trout Creek, Carter Creek, Grassy, Boulder, WY. The contractor shall plan, manage, organize, direct, schedule, and control all resources, processes, activities and tasks to accomplish each Task Order (TO).

2.0 DESCRIPTION

2.1. The contractor shall provide all labor, material and equipment to perform exterior/interior pavement projects in accordance with (IAW) this SOW and the TO SOW. Service projects include, but are not limited to, installation, removal, excavation, maintenance, repair, and/or replacement of: e.g., flexible and rigid pavement; road and parking lot construction;

slab-on-grade, curb and gutter, waterway, and sidewalk construction; aggregate based road construction; airfield pavement surface construction; water/storm drain and sewer utility; exterior parking lot/roadway/airfield lighting; airfield rubber;

pavement striping, joint sealant, crack sealant, slurry/chip seal, pothole repair; asphalt mill and overlay; and appurtenances.

Appurtenances could include, but are not limited to: electrical and lighting; structural building; lightning protection and grounding; fire suppression and detection; landscaping.

3.0 REQUIREMENTS AND RESPONSIBILITIES

3.1. The contractor shall meet all requirements and responsibilities in support of AFMC and shall ensure quality work performance in accordance with the SOW. The contractor shall provide all personnel, training, certifications and supervision necessary to perform the services. In addition, each TO issued under the basic contract will include a TO level SOW. The contractor shall comply with all requirements listed in this SOW and the applicable TO SOW.

4.0 REQUIREMENTS

4.1. This section describes general requirements to be supported. Specific requirements will be identified at the TO level.

4.2. Software and Unit Price Requirements:

4.2.1. The contractor shall utilize and maintain a current year RSMeans based pricing tool, or Government-approved equivalent, to estimate and prepare cost/price proposals in order for the Government to determine a fair and reasonable proposal evaluation. Information on software and pricing may be obtained at https://www.rsmeansonline.com, https://www.4clicks.com, etc.

4.2.1.1. Pricing shall be determined by location.

4.2.1.2. If the contractor is not using RSMeans or 4clicks, the contractor shall provide information to demonstrate the proposed pricing tool’s equivalence to RSMeans or 4clicks prior to being approved.

4.2.1.3. If the contractor doesn’t use RSMeans or 4clicks, or have an equivalent pricing tool, the contractor shall be required to submit all of their estimates using the Construction Cost Estimate Breakdown worksheet, located in Air Force Federal Acquisition Regulation (AFFARS) 5336.9001.

4.2.2. The cost/price proposal shall consist of a unique line item number, description, unit cost (labor, materials, and equipment), quantity, overhead, profit, etc., for the work as described in the TO SOW, as identified in the RSMeans Cost Data Guide. If the cost/price proposal contains an item which does not have a unique line item number, then the item shall be submitted with three independent cost quotes including the line item number, description, labor, material, equipment, and supplier name breakdowns.

http://www.rsmeansonline.com/ http://www.4clicks.com/

4 | P a g e

4.3. IDIQ Management:

4.3.1. Key Contractor Personnel:

4.3.1.1. Key contractor personnel include: Project Manager/Contract Manager, Project Superintendent, Quality Control Officer, and Site Safety and Health Officer. Any personal identifiable information (PII) that identifies the key personnel shall be redacted or removed prior to submitting personnel related information to the Government (e.g. personal address, social security number, personal email, etc.)

4.3.1.1.1. The contractor shall provide a copy of the letter signed by an authorized official of the contractor’s firm describing the responsibilities and delegate sufficient authority to adequately perform the functions listed below.

4.3.1.1.2. The contractor shall provide different personnel for each of the below listed Key Personnel positions.

Unless approved via submittal, personnel shall not hold multiple key personnel positions.

4.3.1.1.3. Key contractor personnel shall be able to read, write, speak, and understand English.

4.3.1.2. If any of the proposed personnel become unavailable for performance prior to or during performance of this requirement, the contractor shall promptly notify the Contracting Officer within 24 hours and provide updated information indicating replacement personnel meet required qualifications for government verification and inclusion into the contract.

4.3.1.3. Project Manager/Contract Manager (PM/CM):

4.3.1.3.1. The contractor shall provide a PM/CM who shall be responsible for the overall management of this contract. The PM/CM, shall act on behalf of the contractor, shall be designated in writing to the CO upon award of each TO and shall be the primary point of contact (POC) for contractual issues. The PM/CM shall be responsible for ensuring effective systems are developed to meet the objectives of the required tasks. The PM/CM shall also ensure that quality work is completed safely, on schedule, and within the allocated budget.

4.3.1.3.2. The PM/CM shall have at least five (5) years of experience in the management of Government, commercial and/or industrial construction contracts with functional and technical expertise in the following areas:

architectural, civil engineering and interior/exterior electrical.

4.3.1.3.3. The PM/CM shall have full authority to act for, and on behalf of, the contractor on all contractor-related matters for daily operation of this contract.

4.3.1.3.4. The PM/CM shall be available by cellular phone and/or email during normal duty hours and non-normal duty hours when project work is being performed

4.3.1.3.5. During normal duty hours, the PM/CM shall be available to meet on the installation with Government personnel within one (1) hour of notification or a specified timeframe when necessary.

4.3.1.3.6. Project or warranty related issues, the PM/CM shall respond as stated below:

4.3.1.3.6.1. Non-emergency issues: The contractor shall respond to project or warranty related issues within twenty-four (24) hours of notification.

4.3.1.3.6.2. Emergency issues: The contractor shall respond to any emergency issues within two (2) hours of notification and begin repair actions. Examples of emergency work include, but are not limited to: work required to sustain/ensure continued mission operation, unscheduled water/electrical outages, absence of A/C or heat within a facility, pavement collapse, or any imminent danger to life/health/safety of personnel.

4.3.1.4. Project Superintendent (PS):

4.3.1.4.1. The PS shall be the primary POC for construction related issues during construction and shall be identified and designated, in writing, to the CO before the issuance of the notice to proceed (NTP). If the PS is changed

5 | P a g e during the TO Period of Performance (PoP), the contractor shall notify the CO in writing of the intended replacement. The PS shall be on site anytime construction work is being performed.

4.3.1.4.2. The PS shall have at least three (3) years of experience in construction management for similar size and scope to the seed project and be familiar with all aspects of general construction management, practices, methods, and materials.

4.3.1.4.3. The PS shall have full authority to act for the contractor on all construction matters relating to daily operation of the contract.

4.3.1.4.4. The PS shall be available by cellular phone and/or email.

4.3.1.4.5. Project or warranty related issues, the PS shall respond as stated below:

4.3.1.4.5.1. Non-emergency issues: The contractor shall respond to the required location within twenty-four

(24) hours of notification and begin repair actions.

4.3.1.4.5.2. Emergency issues: The contractor shall respond to the required location within two (2) hours of notification and begin repair actions. Examples of emergency work include, but are not limited to: work required to sustain/ensure continued mission operation, unscheduled or undetermined water/electrical outages, absence of A/C or heat within a facility, pavement collapse or any imminent danger to life/health/safety of personnel.

4.3.1.5. Quality Control Officer (QC):

4.3.1.5.1. The QC shall have at least three (3) years of experience in the area of construction quality control.

The QC shall manage the contractor’s quality control program. This person shall have the authority to direct contractor personnel to correct construction deficiencies and be available by cellular phone and/or email. The contractor shall correct quality related construction deficiencies and perform quality related rework at no additional cost to the Government.

4.3.1.6. Site Safety and Health Officer (SSHO):

4.3.1.6.1. The SSHO shall visit all active work sites to perform safety and occupational health management, surveillance, inspections, and safety enforcement for the contractor to verify compliance with all requirements. The contractor QC person may be the SSHO on projects if they possess the applicable safety and health qualifications required for QC and SSHO as specified herein. The SSHO shall meet the following requirements:

4.3.1.6.1.1. The SSHO shall be available by cellular phone and/or email.

4.3.1.6.1.2. SSHO must be certified, with the following requirements:

4.3.1.6.1.2.1. IAW Unified Facilities Guide Specifications (UFGS) 01 35 26 (November 2015) Change 4 - 02/17 and EM 385-1-1.

4.3.1.6.1.2.2. Competent person training: Occupational Safety and Health Administration (OSHA) defines a "competent person" as "one who is capable of identifying existing and predictable hazards in the surroundings or working conditions which are unsanitary, hazardous, or dangerous to employees, and who has authorization to take prompt corrective measures to eliminate them" [29 CFR 1926.32(f)]. By way of training and/or experience, a competent person is knowledgeable of applicable standards, is capable of identifying workplace hazards relating to the specific operation, and has the authority to correct them. Some standards add additional specific requirements which must be met by the competent person.

4.3.2. Key Government personnel:

4.3.2.1. Contracting Officer, Contracting Officer Representative, and Civil Engineering Project Manager. Additional personnel may be designated for a project at the TO level.

6 | P a g e

4.3.2.2. Contracting Officer (CO):

4.3.2.2.1. The CO is the sole Government official authorized to enter into, make changes/modifications to, or terminate contracts on behalf of the Government; no other Government representative has the authority to enter into an agreement on behalf of the Government. COs are responsible for ensuring performance and compliance with all necessary terms and requirements of the contract, and safeguard the interest of the Government in its contractual relationships.

4.3.2.3. Contracting Officer Representative (COR):

4.3.2.3.1. An individual designated and authorized, in writing, by the CO to perform specific technical or administrative functions. The COR will assist in the technical monitoring, performance, and administration of the contract.

4.3.2.4. Civil Engineering Project Manager (CE PM):

4.3.2.4.1. An individual designated at the TO level who is responsible for the overall management of the project.

4.3.3. Quality Control Plan (QCP):

4.3.3.1. The contractor shall develop, maintain, and periodically update (as needed) the construction Quality Control Plan (QCP) IAW UFGS 01 45 00.00 10 for the basic contract and may be required to provide a tailored QCP for individual TOs as defined in the FOPR. The primary function of a QCP is to design and successfully execute a realistic plan to ensure that the required standards of quality construction will be met. The contractor shall develop and implement procedures to identify and prevent deficiencies from occurring. Records of all inspections conducted by the contractor, and corrective action taken, shall be made available to the Government upon request.

4.3.4. Required Contractor Certifications:

4.3.4.1. The contractor or contractor teaming arrangement shall be licensed/insured as a GC-B100 or possess at least one of the following individual licenses at the submittal of proposal:

4.3.4.1.1. S260 General Concrete Contractor

4.3.4.1.2. S400 Asphalt Paving Contractor

4.3.4.1.3. S310 Excavation and Grading Contractor

4.3.4.1.4. S410 Pipeline and Conduit Contractor

4.3.4.2. All licensing requirements can be found underneath the Utah Construction Trades Licensing Act Rule R156- 55a-101.

4.4. Site Conditions:

4.4.1. The Contractor shall perform site investigation IAW the general provisions entitled Site Investigation and Conditions Affecting the Work (FAR 52.236-3). Contractors are strongly encouraged to attend site visits for each TO award.

4.4.2. The contractor is cautioned that projects that take place at existing facilities may present complex issues and situations which would not be encountered in new construction. Complex issues and situations may include, but are not limited to e.g., asbestos, lead, historic building preservation, limited utilities data.

4.4.3. The contractor shall obtain approved controlled access identification for work on HAFB and its remote sites that require an approved controlled access identification. The contractor shall obtain and retain Air Force Security Clearance for access to these sites. The Contracting Officer will coordinate with Security Forces and the contractor for required documents in order to submit for an approval.

7 | P a g e

4.5. Contract Drawings and Specifications:

4.5.1. The contractor shall comply with the general provisions entitled Specifications and Drawings for Construction (FAR 52.236-21), Contract Drawings and Specifications (DFAR 252.236- 7001), Base Facility Design Standard (BFDS), all UFGS, all Unified Facilities Criteria (UFC) and applicable location requirements. Where level of effort differs between the standards set forth herein and any such jurisdictional requirements and/or standards of practice occur, the more stringent requirement(s) shall apply. However, if there are conflicting requirements, the contractor shall notify the CO of the discrepancy. The CO will provide direction for which standard shall govern.

4.5.2. The contractor shall perform all work IAW all Air Force, federal, state, county and local statutes, laws, regulations, safety requirements, instructions, manuals, handbooks, guidance and policy letters, as well as the drawings, specifications, and standards set forth in the terms and conditions of the basic contract, this SOW, and subsequent TOs.

4.6. Submittals:

4.6.1. Submittals include, but are not limited to: e.g., as built drawings, shop drawings, diagrams, test reports, material data, material samples, data products, schedules, or any document that may demonstrate and/or illustrate conformance for the work to be completed. Submittals shall be submitted with form AF IMT 3000.

4.6.2. The contractor shall supply one (1) electronic copy of each submittal (shop drawings, product data, mix design, etc.)

to the CO.

4.6.3. Material Samples: One (1) sample may be submitted to the CO, unless otherwise noted in the TO.

4.6.4. Then contractor shall provide all items of related equipment or materials at one time. Submittals shall contain sufficient literature, catalog data, brochures, etc., to show compliance with the TO specifications and plans.

4.6.5. Submittals shall be specific to information required and will not include non-pertinent information. Example:

Catalog product data for storm drain box should only include specific information to the storm drain box and no other products.

4.6.6. Then contractor shall submit all items referenced in the drawings and specifications. The Submittal Checklist (See Appendix A) is included for convenience. The checklist may not include all required items, therefore it may need to be tailored towards the individual TO.

4.6.7. Then contractor shall provide submittals to the CO within one (1) week prior to the issuance of the NTP, unless otherwise noted in the TO.

4.6.8. Payments for work or materials are only authorized if the Government has approved all submittals.

4.6.9. Submittals approved by the CO shall not relieve the contractor from responsibility for complying with the requirements of this contract (See FAR 52.236-5 “Material and Workmanship). Substitutions are NOT authorized, unless approved in writing from the CO. If submittals show variations from the contract requirements, the contractor shall describe such variations in writing at the time of submission. It is the responsibility of the contractor to convey submittal requirement to the subcontractors, suppliers, and vendors.

4.7. As-Built Record Drawings:

4.7.1. The contractor shall maintain a complete set of full-size TO and shop drawings for record mark-up purposes for all projects at the TO level.

4.7.1.1. Contractors that receive the solicitation via the web shall produce one set of full-size prints to meet this requirement.

4.7.1.2. When changes occur, the contractor shall immediately mark-up drawings in red, to show changes and actual installation in sufficient detail to form a complete record of work accomplished. Sign and date each mark-up redline as it

8 | P a g e occurs. Marked-up drawings shall be complete, legible, precise and understandable to a computer aided design (CAD) operator who is not familiar with the project. When a revision is made the contractor shall ensure related section and elevation views, details, legend, plans, profiles, schedules and notes are marked accordingly to avoid conflicting data on all other sheets. Comments shall be complete without reference to change orders, letters, memos, etc. Marked- up drawings shall be bound in manageable sets covered with durable paper and labeled to show project title and number.

4.7.2. The contractor shall provide complete and accurate marked-up prints for concealed work, which will be difficult to measure and record after construction, and work which may require servicing or replacement during the life of the project. The following are areas of concern that need special checking to ensure that the marked-up prints are complete and accurate:

4.7.2.1. Location, size and type of existing and new utility lines. The contractor shall show measurements for all change of direction points and all surface or underground components such as valves, manholes, drain inlets, clean outs, meters, etc. The description of exterior utilities shall include the actual quantity, size, and material of the utility lines.

4.7.2.2. Changes to location, size and type of exterior plumbing and electrical lines below the surface grade.

4.7.2.3. Changes to layout and schematic drawings of electrical circuits and piping.

4.7.2.4. Correct dimensions and details transferred from shop drawings.

4.7.2.5. Actual location of anchors, construction and control joints, etc., in concrete.

4.7.2.6. Change in location of equipment and architectural features.

4.7.2.7. Cross out words such as “or equal” and list specifically the items of material provided.

4.7.2.8. Unusual or uncharted obstructions that are encountered in the construction site.

4.7.3. Upon TO completion, the contractor shall furnish a complete set of as-built drawings in Mylar reproducible and electronic format. These drawings shall show all changes and revisions made on the job.

4.7.4. The Government inspectors will review the contractor’s marked-up drawings to verify the performance shown by progress reports. If drawings are not current, the progress report will be adjusted downward by the CE PM to reflect the contractor’s non-compliance. Marked-up drawings shall be submitted within five (5) working days of substantial TO completion. Final payment shall not be authorized until complete and accurate red-lined drawings are accepted by the CE

PM.

4.8. Storage of Materials:

4.8.1. The storage of materials shall be in accordance with general provisions entitled Operations and Storage Areas (FAR 52.236-10) and Appendix C, Section II – SPECIFIC REQUIREMENTS, Contractor’s Notification of Hazardous Material Requirements. Materials shall be stored in a safe manner to avoid creating a hazard, hindering the work of other contractors, and to avoid damaging or soiling of materials or property. All materials and equipment shall be stored and handled to prevent the inclusion of foreign matter and damage by water or breakage. Store packaged materials in original containers until ready for use. Materials showing evidence of water or other damage shall be rejected and removed from the base at the expense of the contractor. All materials shall be stored as recommended by the manufacturer, unless specifically noted otherwise in the task order.

4.8.2. The contractor shall provide to the CE PM a truck weight ticket for all materials delivered to a project site.

4.8.3. On-site pipe and/or conduit shall be stored in racks or blocked to prevent rolling.

4.8.4. On-site combustible materials shall be stored in an OSHA approved combustible materials locker at least 50 feet from all buildings, unless otherwise specifically indicated by the CO.

4.8.5. When storing 1000 rounds or more of fastener gun charges, the contractor shall obtain an explosive license from the Civil Engineering Weapons Safety Manager. Coordination shall be through the CE PM.

9 | P a g e

4.8.6. It is the responsibility of the contractor to secure all property located on the construction site. The Government is not responsible for lost or stolen materials or equipment. If additional storage space is required the contractor shall notify the CE PM. Any required relocation of material or equipment, for any reason, shall be at the contractor’s expense.

4.9. Construction Evacuation Permit:

4.9.1. The contractor shall request a permit 14 calendar days prior to scheduled start of excavation. Hand digging shall be required to locate utilities shown on the contract drawings, Excavation Permit, or 3 feet on either side of locations identified by Base Maintenance Shops.

4.9.2. For work being accomplished at HAFB, LMTA, Carter Creek and Boulder- WY, no excavation shall be done prior to receiving a Base Civil Engineering Excavation Permit. Permits may be obtained from the Red Stake Office in Civil Engineering (see sample permit form in Appendix B of this SOW). If excavation is started without obtaining a permit, the contractor shall be held liable for repairs of any broken utility lines or other damage resulting from the broken lines. Permits shall be available on site with the contractor/subcontractor at all times during excavation work.

4.9.3. For work being accomplished at UTTR, no excavation shall be done prior to receiving a Range Civil Engineering Excavation Permit. The contractor shall call 801-777-1577 to obtain the form for submission. A copy of the AF form 332, Civil Engineering Work Request, and documentation indicating completion of the AF IMT 813, Environmental Impact Analysis, shall be included with the permit request. These are available from the CE PM. If excavation is started without obtaining a permit, the contractor shall be held liable for repairs of any broken utility lines and any other damage resulting from excavating without a permit.

4.9.4. The contractor shall be responsible for identifying all lawn sprinkler system components within the excavation area. Any component damaged during the course of construction shall be immediately brought to the Government’s attention and repaired by the contractor at their expense. Any damage to landscaping as a result of contractor damage to sprinkler system components shall also be repaired by the contractor at their expense. Protection of existing utilities and vegetation shall be IAW FAR 52.236-9.

4.9.5. Any damage done by the Contractor to existing real property shall be repaired to prior conditions. Contractor shall patch and repair any holes or damage done to walls during the removal of any items or materials. Contractor shall match the existing conditions and meet the requirements of these specifications. The COR will determine if the repair work done is sufficient. All repair work will be at the contractor’s expense.

4.9.6. The contractor must submit reports monthly showing the tons of material disposed of at a landfill and the tons of material diverted from a landfill. See UFGS Environmental Protection Section 01 57 20.04, paragraph 1.5.2 for further guidance.

4.10. Testing:

4.10.1. All material testing shall be done IAW UFGS specifications by an independent, third party, Government approved testing agency or company.

4.10.2. Where specific tests are required, the contractor shall notify the CE PM at least 24 hours prior to testing or as stated in the TO schedule.

4.10.3. The contractor shall provide a test report to the CE PM immediately after test results are released by the testing company.

4.10.4. Work being tested shall not be covered up or made inaccessible until it has been approved by the CE PM.

4.10.5. In the event of conflicting testing requirements, the Government reserves the right, at Government expense, to hire a different, independent, third party, for testing and/or inspection. This test shall take precedence over any other test.

4.11. Warranties:

10 | P a g e

4.11.1. All task orders shall be under warranty IAW FAR 52.246-21 as set forth in the general provision entitled Warranty of Construction. The contractor shall pass any commercial warranties obtained from manufacturers on to the Government.

4.12. Utility Outages and Traffic Closures:

4.12.1. All utility outages and traffic closures shall be scheduled during off duty hours and weekends unless otherwise approved by the CO. All outages and closures shall be scheduled as far in advance as possible with the CE PM and in no case less than 21 calendar days before the outage or closure. A road closure plan shall accompany any outage and closure schedule from the contractor. The contractor shall obtain in writing from the CE PM a statement or schedule giving the permissible times for the outage or closure for particular installations and the maximum time allowed for such outage or closure. The contractor shall strictly observe such schedules and will be held responsible for any violations.

4.13. Safety Requirements:

4.13.1. The contractor shall comply with all Occupational Safety and Health Regulations, Dept. of Labor, DoD, AF safety standards, including any requirements stated within the SOW, TO SOW, Appendix C, and applicable attachments. The contractor will implement a safety program plan and shall provide a safety plan IAW Appendix C including, but not limited to: e.g., accident prevention plan, activity hazard analysis, OSHA form 300A, Safety and Occupational Health deficiency tracking log. The contractor bears both the burden of proof and the burden of producing evidence for adequate compliance to all regulations and requirements.

4.13.2. Any cutting, welding, brazing, or other hot work shall comply with AFI 32- 2001/OO-ALC-HAFB Supplement 1, Attachment 16. A USAF Welding, Cutting and Brazing permit, AF Form 592, is required daily for all hot work. Contractor shall coordinate with the CE PM and contact the Fire Prevention Office at 801- 777-0236 for hot works permit. The Fire Prevention Office provides briefing on hot works permit every first Thursday of the month at 8:00 am in Bldg. 133.

4.13.3. The Explosive Clear Zone (ECZ) is defined as the area where personnel or assets are subject to the hazardous effects of explosives. The ECZ includes the following areas:

HAFB MAMS I Area.

HAFB MAMS II Areas.

LMTA.

UTTR.

Flight line area: Runway, taxiways, aprons, alert areas, hot pads, etc.

4.13.3.1. All contractor personnel required to work in the ECZ shall attend a one- hour Weapons Safety Briefing pertaining to explosive safety and shall sign an Explosive Safety Awareness statement verifying attendance. The contractor shall coordinate with the CE PM and attend the Weapons Safety Briefing conducted by the Base Safety Office, Bldg. 180, Room 232, on Mondays at 1:30 pm (if Monday is a holiday, then on Tuesday). For larger groups, may contact the HAFB Safety Office, 801-775-2224, to ensure room availability. Any person who is briefly visiting the construction site, including for contractor deliveries, shall be accompanied at all times by an individual who has attended the briefing and signed an awareness statement.

4.13.4. Before use of powder actuated tools and storage of loads within HAFB, LMTA, UTTR or other jurisdictional areas, contractor personnel shall attend the Weapons Safety Briefing, sign awareness statement, and obtain a temporary license for powder actuated tools.

4.13.5. In the event of lightning within 5 nautical miles (5.75 land miles) of construction work area, ALL contractor personnel SHALL evacuate outside the gated area of the ECZ.

4.14. Cold Weather Precautions:

4.14.1. Contractor shall be responsible for proper application of weather sensitive materials and shall not apply any such materials when weather conditions fall below the minimums recommended by the material manufacturer or the specifications

11 | P a g e stated in the TO.

4.14.2. Cover all concrete installed in weather below 320 F (00 C) with approved insulating blankets.

4.14.3. Contractor is responsible in weather below 400 F (40 C) that water lines, including fire protection systems, do not freeze.

4.14.4. The only temporary heating devices permitted are Underwriters Laboratories (UL) approved electric heaters.

The contractor shall physically monitor all temporary heating devices at least every four hours. Exception to this requires written approval from the Base Fire Department.

4.14.5. Asphalt Storage:

4.15.5.1. The contractor shall not dump the asphalt on the ground prior to placement. The asphalt shall have one transfer from the hot plant to the truck and one transfer from the truck to the paver, except for few instances. All Asphalt placed at the GSU’s shall require the use of an Asphalt Shuttle Buggy, unless otherwise coordinated by the PM.

4.15. Protection of Government Property and Personnel:

4.15.1. Work area definitions:

4.15.1.1. Construction Site: Area(s) in which the work of the TO is accomplished or performed.

4.15.1.2. Storage Area: Area(s) used for the storage of materials, devices, appliances, and/or equipment to be used in the work.

4.15.1.3. Transportation Area: Area(s) paved, treated or unpaved that is used for transportation or parking purposes.

4.15.2. The Government may require a project to be fenced and secured with temporary construction fencing. The contractor shall furnish and maintain all required barricades. All flight line areas shall have airfield management approved low profile barricades with flashing lights placed around the entire construction area at all times. Access drives and doors shall remain clear at all times. At a minimum, all projects shall be barricaded and/or demarcated with caution tape.

4.15.3. Furnish and spread drop cloths in the work areas as required for protection of surfaces, etc.

4.15.4. Any damage caused by the contractor, due to improper protection or safety measures, shall be repaired or replaced at no expense to the Government. If the contractor does not satisfactorily repair or replace the damaged area, the Government reserves the right to withhold payment until damages are satisfactorily remedied.

4.15.5. The contractor shall prevent any damage to existing pavements beyond the limits of indicated pavement removal.

4.15.5.1. Existing pavements that are damaged by the contractor shall be replaced in kind or repaired as directed by the CO, at no expense to the Government. Road/lane closures-traffic interruption require the contractor to submit a traffic control/controlled area plan, clearly showing work area, location, and type of sign to be placed for rerouting traffic, 15 calendar days, or as stated in the TO, prior to commencing work. The Manual on Uniform Traffic Control Devices (MUTCD) will be used for traffic signing and barricades.

4.15.6. Conduct work so that Government property, all personnel, and work areas shall be protected at all times from inconvenience, damage of any nature, and injury. Operations shall offer the least possible obstruction and inconvenience to public traffic, and all traffic shall be permitted to pass through work site with as little delay as possible. When construction machinery and/or operations present danger to passing traffic, applicable lights, signs, fences, barriers, or flaggers shall be used in order to give adequate warning. All warning and safety devices shall conform to applicable local, state, and federal requirements (MUTCD, UFC 3- 120-01, Base Facility Design Standard, etc.).

12 | P a g e

4.16. Daily Cleanup:

4.16.1. The contractor shall keep the entire construction site, structures, and access ways free of debris and obstructions at all times. The contractor will be notified of unsatisfactorily cleaned up areas by the CE PM and will have 24 hours to resolve the issue. No work will be allowed until the issues have been resolved. At a minimum of once each day all areas shall be cleaned by the contractor.

4.16.2. The contractor shall provide and maintain their own dumpster/refuse/recycling container. Base dumpster are not authorized for contractor use.

4.17. Covering of Debris:

4.17.1. All loads shall be properly covered by the contractor before and during transportation to ensure debris does not escape the truck. However, in the event debris does fall out of the truck while transporting, contractor shall be responsible to immediately clean it up and shall be responsible for any damages that have occurred as a direct result of the debris.

4.17.2. All chutes used for refuse, and the like, shall be covered or of such design to fully confine the material to prevent the dissemination of dust.

4.18. Removals and Salvage:

4.18.1. The contractor shall inform the CE PM of any surplus material. The CO will determine if these materials are salvageable or unsalvageable.

4.18.1.1. Salvageable materials, as determined by the CO, remain the property of the Government. Salvageable materials shall be managed as directed by the CO in coordination with the Installation Environmental Office. See UFGS Environmental Protection Section 01 57 20.04 for further guidance.

4.18.1.2. Unsalvageable materials, as determined by the CO, shall become the property of the contractor and disposed of at the contractor's expense. Materials to be removed shall be removed without damage to adjacent areas. All damage resulting from the removal activity shall be repaired by the Contractor at no cost to the Government. Repair shall be made with materials of like nature, type and construction as those which were damaged or as those which exist adjacent to the areas to be repaired. See UFGS Environmental Protection Section 01 57 20.04 for further guidance.

4.19. Final Cleaning:

4.19.1. The contractor shall execute a final cleaning prior to the final inspection. The contractor shall:

4.19.1.1. Replace/repair surrounding landscape affected by construction.

4.19.1.2. Clean site of all construction and project related debris.

4.19.1.3. Remove waste and surplus materials, garbage, and any construction devices, appliances, and/or equipment from all work areas.

4.20. Utility Marking:

4.20.1. The contractor shall provide and install #10 gage insulated copper trace wires within one foot of all new utilities placed underground (except metallic lines). If length of new utility 500 feet or less, the contractor shall install one terminal box of 2 ½” diameter pipe at each end of the wire marking the utility location. If length of new utility is greater than 500 feet, the contractor shall place terminal boxes at 500 foot intervals. Terminal boxes shall conform to UFGS and shall have a metal screw-on type lid. Terminal boxes shall be encased in an 18” diameter by 12” deep concrete cylinder, box lid shall be flush with the top of the concrete cylinder, and the top of the concrete cylinder shall be flush with adjacent surface grade. Trace wire shall have a metal identification tag attached at each terminal box. The tag shall be engraved with the type of utility, pipelines, and pipe size.

13 | P a g e

4.20.2. The contractor shall install detectable warning tape directly above all underground utilities, 12 inches below finished grade and 6 inches below sub-grade under pavements and slabs. Warning tape shall have an acid and alkali-resistant polyethylene finish and shall be at least 6 inches wide and 4 millimeters thick. Warning tape shall be corrosion resistant with a metallic core, and detectable when buried up to 30 inches. Project specific UFGS shall be provided to the contractor on TO.

4.20.3. Tape Colors: Provide tape colors to utilities as follows:

Red: Electric Yellow: Gas, oil, steam, and dangerous materials.

Orange: Telephone and other communications.

Blue: Water systems.

Green: Sanitary Sewer, Storm Sewer and Industrial Waste systems.

4.20.3. The contractor shall provide 14 calendar day notice, or as stated in the TO, to the CE PM to allow the Government to map all new utility lines. Contractor shall not backfill utility trenches until the lines have been mapped and approved.

4.21. Environmental Protection:

4.21.1. The contractor is required to comply with all applicable local, state, federal, and Air Force laws and regulations dealing with environmental and work place management and protection (Department of Environmental Quality, Division of Water Quality, Air Force Instructions, OSHA Standard 29 CFR 1910 and 1926, and as referenced in Appendix C). In the event of a conflict between any laws or regulations, the most stringent shall apply. These items include, but are not limited to, the following:

4.21.1.1. Vehicles and other powered equipment shall meet local air quality regulations for emissions, be mechanically sound and have all seals, grease rings, and other containment systems in place to ensure against leakage. Drip pans shall be maintained to prevent overflow and spills. No equipment maintenance including oil changes, filter replacements, or hydraulic equipment repair shall be performed on Government property.

4.21.1.2. All solid waste shall be collected and disposed of on a daily basis. There will be no accumulation of solid waste unless properly containerized or put within a fenced area to prevent material being blown about by the wind. No liquids of any kind shall be put into base dumpsters.

4.21.1.3. Paint Cans: Empty containers have to comply with the “RCRA (Resource Conservation and Recovery Act) empty rule” before they become a non-hazardous solid waste. Information for Construction, Demolition, and Renovation can be found at the following link:

https://www.epa.gov/hwgenerators/resource-conservation-and-recovery-act-rcra-focus- hazardous-waste-generator-guidance

4.21.1.4. Asphalt debris shall be managed in one of the following ways, which will be defined at the Task Order level:

4.21.1.4.1. Disposed of in an off-base Class I, II, III, or IV permitted landfill.

4.21.1.4.2. Reused as road base on Government property.

4.21.1.4.3. Disposed of in the asphalt storage cell at the Hill AFB Class IV landfill (See attached map in Appendix E). Primarily asphalt with minimal amounts of soil is allowed in the asphalt cell. The contractor must submit a request to the CE PM at least 24 hours in advance for approval. The request must include the disposal date and time, the material to be disposed, the estimated weight and volume, and the hauler’s company name. For landfill access contact the Pavement Shop at 801-777-5731.

4.21.1.5. Concrete debris shall be managed in one of the following ways, which will be defined at the Task Order level:

4.21.1.5.1 Concrete and excavated soils that have been determined by pre-contract laboratory analysis to be http://www.epa.gov/regulations/laws/rcra.html http://www.epa.gov/regulations/laws/rcra.html

14 | P a g e

“clean” shall be managed by disposing in the Concrete/Soil Cell at the Hill AFB Class IV landfill (See attached map in Appendix E). Only concrete and soil are allowed in this cell. No plant material generally present in the top 6-12 inches of soil will be allowed. The contractor must submit a request to the CE PM at least 24 hours in advance for approval. The request must include the disposal date and time, the material to be disposed, the estimated weight and volume, and the hauler’s company name.

4.21.1.5.2 Concrete to be disposed of in an off-base facility.

4.21.4.5.3 Concrete to be crushed and used as road base on Government property.

4.21.1.6. Wood that is recyclable shall be disposed of in an off-base Class I, II, III, IV or V permitted landfill.

4.21.1.7. All spills shall be reported by dialing 911 and providing information as to spill location, type of material and estimated quantity, and if the spill is contained. The contractor shall ensure appropriate Personnel Protective Equipment (PPE) is available to take care of spill cleanup and handling of residue.

4.21.2. Contractor sites shall be maintained at all times. The contractor shall be responsible for any damage due to erosion and control of fugitive dust. An on-site review will be conducted by the CO, the Construction Engineer, and the Environmental Management Division (75 CEG/CEIE) prior to use of any location for contractor setup. A follow-up program for site overview will be maintained by all parties. Release of the site by the contractor will be accompanied by a final site review, at which time site deficiencies will be noted. The contractor will have seven (7) calendar days, or as stated in the TO, to correct deficiencies. Final contract payment will be withheld pending completion of the deficiency list.

4.21.3. The contractor is cautioned that materials in and around this project may contain asbestos or be coated with Lead- Based Paint (LBP). The Government will make every effort to locate and identify all Asbestos Containing Materials (ACM) and LBP prior to bidding; however, this is not always possible. These materials are often hidden and cannot be discovered until after demolition has begun. The failure of the Government to identify all ACM and LBP in no way relieves the contractor from his legal obligation to comply with state and federal regulations regarding the handling of asbestos, lead, or LBP. If suspected asbestos containing materials or LBP surfaces are encountered, immediately cease work and notify the CO and the CE PM immediately. Do not conduct or continue with any work that will violate any AF, local, state or federal regulations regarding asbestos, lead, or LBP. If suspected materials or surfaces have not been disturbed, secure and post signs in the area where the materials are located to ensure that they are not disturbed. If the suspected materials have already been disturbed, secure and post signs in the area where the material was originally located, any areas to which materials have been moved, and any containers that suspect materials may have been placed in. Take all necessary steps to ensure that materials are not further disturbed, moved, or disposed of until directed to do so by the CO. Failure to notify the Government promptly or failure to comply with state and federal regulations will be grounds for termination of the contract and may result in other appropriate civil and/or criminal actions. "The contractor will be fully responsible for any and all fines or other penalties resulting from acts and/or omissions pursuant to law and regulation. At the preconstruction meeting, the contractor will be required to sign the "Contractor's Safety and Hazardous Materials Requirements".

4.21.4. If at any time, an authorized inspector for 75 CEG/CEIE feels that regulatory requirements listed above are not being followed, 75 CEG/CEIE reserves the right to notify the CO, and recommend corrective action.

4.22. Storm Water Permitting:

4.22.1. The contractor shall obtain a Utah Pollutant Discharge Elimination System (UPDES) storm water permit or waiver if the project disturbs more than 1 acre of soil surface area. To obtain the permit a contractor must prepare a Storm Water Pollution Prevention Plan (SWPPP) and then submit a Notice of Intent (NOI), and the required fee to the State of Utah, Department of Environmental Quality (DEQ); Division of Water Quality (DWQ). The contractor shall submit and receive approval of the UPDES permit before starting excavation (for work outside the State of Utah area, the contractor shall comply with the requirements of the agency having jurisdiction).

4.22.2. Projects disturbing a soil surface area greater than 1 acre will require submission of a sediment and erosion control plan to the project manager for subsequent review and approval by the Environmental Compliance Office (75 CEG/CEIE). The contractor shall receive approval of the plan and best management practices before starting excavation.

15 | P a g e

4.22.3. Projects disturbing more than 1 acre of soil surface area require submission of a plan for permanent stabilization of disturbed area to the project manager for subsequent review and approval by the Environmental Compliance Office (75 CEG/CEIE). The contractor shall receive approval of the plan and best management practices before contract closeout.

Examples of best management practices are available at the following websites:

https://www.epa.gov/npdes/stormwater-discharges-construction-activities#resources https://www.epa.gov/npdes/national-menu-best-management-practices-bmps-stormwater#edu

4.22.4. Projects with a footprint area greater than 5,000 square feet (sq ft) shall maintain or restore, to the maximum extent technically feasible, the predevelopment hydrology of the property with regard to the temperature, rate, volume, and duration of flow. Use of Low Impact Development (LID) techniques in accordance with the Energy Independence and Security Act (EISA) Section 438 Guidance shall be implemented. The contractor shall comply with general provisions entitled Low Impact Development under UFC 3-210-10.

4.22.5. The contractor is prohibited from pouring or washing water into the storm drain system.

4.22.6. All items of geological or archeological interest such as fossils, articles of value or antiquity and structures or other remains or relics discovered during excavation or surface work are and will remain the property of the Air Force. Upon discovery of an historical artifact or human remains, all work shall cease and the CE PM and CO shall be immediately notified. Work shall only continue when the contractor is authorized to proceed by the CO. The contractor shall take all reasonable precautions to prevent unauthorized removal of or damage to any such discovery.

4.22.7. The contractor shall comply with all applicable local, state, and federal regulations pertaining to environmental and workplace management and protection. In the event of a conflict between any laws or regulations, the most stringent shall apply. These items include, but are not limited, to the following:

4.22.7.1. The contractor shall adhere to the most recent version of the HAFB Fugitive Dust Control Plan and document all measures used to control fugitive dust from construction and demolition activities.

4.22.7.2. The contractor shall provide a fugitive dust control plan to the CE PM, transferring all records documenting measures to control fugitive dust control from construction…