SOLICITATION-DESCRIPTION.docx
DOCX document 274 KB Posted
- Solicitation number
- 36C25227B0001
About this file
This is a Solicitation Description and Bid Schedule for construction services related to replacing boilers at a VA Medical Center facility.
The Department of Veterans Affairs seeks qualified contractors to replace Boilers 4 and 5 at the Clement J. Zablocki VA Medical Center in Milwaukee, Wisconsin (Building 112 Boilerhouse). The solicitation number is 36C25227B0001, with a project number of 695-24-107. This is a 100% set-aside for Service-Disabled Veteran-Owned Small Business (SDVOSB) firms verified by CVE, as authorized under 38 U.S.C. 8127. The NAICS code is 238220 (Plumbing, Heating, and Air Conditioning Contractors) with a $19.0 million size standard. Sealed bids are due via email by 11:00 AM CST on November 18, 2026, with virtual bid opening at 1:00 PM CST the same day. The expected project cost range is between $2,000,000 and $5,000,000. All work must be completed within 455 calendar days after receipt of the Notice to Proceed, encompassing preconstruction (90 days), construction (275 days), and post-completion phases (90 days). A site visit is scheduled for October 14, 2026, at 1:30 PM at the facility (5000 West National Avenue, Milwaukee, WI 53295). Bidders must submit proof of current SAM and DSBS registration, complete certification per VAAR 852.219-75, provide a bid bond of 20% of bid price (not to exceed $3,000,000), evidence of general liability insurance without asbestos exclusions, Experience Modification Rate information, and OSHA/EPA safety records documentation. The contract will be firm-fixed-price, and performance and payment bonds equal to the contract value will be required upon award. Questions must be submitted in writing to the Contract Specialist (Kristine.Sutton@va.gov) and Contracting Officer (Ryan.McMillin@va.gov) by 11:00 AM CST on October 22, 2026. A single award will be made based on the lowest responsive bid, subject to available funding; if base bid funding is insufficient, award may be made on Alternate Bid Item 1 (demo/removal of Boiler #5 only).
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
36C25227B0001 Replace Boilers 4 and 5, 695-24-107
Replace Boilers 4 and 5, 695-24-107
F
1. SOLICITATION NUMBER
2. TYPE OF SOLICITATION
3. DATE ISSUED
PAGE OF PAGES
4. CONTRACT NUMBER
5. REQUISITION/PURCHASE REQUEST NUMBER
6. PROJECT NUMBER
7. ISSUED BY
CODE
8. ADDRESS OFFER TO
a. NAME
b. TELEPHONE NUMBER (Include area code) (NO COLLECT CALLS)
10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS (Title, identifying number, date) 12a. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?
(If "YES," indicate within how many calendar days after award in Item 12B.)
12b. CALENDAR DAYS
13. ADDITIONAL SOLICITATION REQUIREMENTS:
STANDARD FORM 1442 (REV. 8/2014)
STANDARD FORM 1442
Prescribed by GSA-FAR (48 CFR) 52.236-1(d)
SOLICITATION, OFFER,
AND AWARD
(Construction, Alteration, or Repair)
SOLICITATION
SOLICITATION
IMPORTANT - The "offer" section on the reverse must be fully completed by offeror.
9. FOR INFORMATION
CALL:
NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid" and "bidder".
SEALED BID (IFB)
NEGOTIATED (RFP)
11. The Contractor shall begin performance within ____________ calendar days and complete it within calendar days after receiving award, notice to proceed. This performance period is mandatory negotiable. (See _____________________________).
YES
NO
a.
Sealed offers in original and ___________________copies to perform the work required are due at the place specified in Item 8 by _____________ (hour) local time _____________________ (date). If this is a sealed bid solicitation, offers must be publicly opened at that time. Sealed envelopes containing offers shall be marked to show the offeror's name and address, the solicitation number, the date and time offers are due.
b.
An offer guarantee is, is not required.
c.
All offers are subject to the (1) work requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.
d.
Offers providing less than _______________________ calendar days for Government acceptance after the date offers are due will not be considered and will be rejected.
X
695-24-107
Department of Veterans Affairs 36C252 115 South 84th Street, Suite 101
Milwaukee WI 53214-1476 Department of Veterans Affairs 36C252 115 South 84th Street, Suite 101
Milwaukee WI 53214-1476 Kristine Sutton, Contract Specialist 414-844-4876 Project 695-24-107 Replace Boilers 4 and 5 at the Clement J. Zablocki, VA Medical Center Milwaukee, WI 53295.
Contractor shall provide for and furnish all labor, materials, equipment, qualified supervision and other items designated in this contract in accordance with the specifications and drawings to complete project 695-24-107 Replace Boilers 4 and 5 at the Clement J. Zablocki, VA Medical Center Milwaukee, WI
The North American Industry Classification Code (NAICS) for this procurement is 238220 (Plumbing, Heating, and Air Conditioning Contractors); size standard $19.0 Million applies.
This procurement is a 100% set-aside for CVE verified Service-Disabled Veteran-Owned Small Business Firms (SDVOSB) per the authority 38 U.S.C 8127 (Public Law 109-461). In accordance with VAAR 819.7003(b), at the time of submission of bid, and prior to award of any contract, the bidder must represent to the CO that it is: (1) an SDVOSB eligible under VAAR Subpart 819-70; (2) a Small Business concern under the NAICS assigned to this acquisition; and (3) certified SDVOSB listed in the SBA Small Business Search database at https://search.certifications.sba.gov/ (see 13 CFR 128).
Site Visit: See Contracting Officer’s Special Instructions.
Ensure to complete and include the certification for VAAR 852.219-75 in bid package submission; failure to do so will result in the bid being non-responsive and ineligible for evaluation and award. See Attachment.
Submit all questions regarding the solicitation, specifications, and/or drawings in writing:
See Contracting Officer’s Special Instructions Questions received after this date/time may not be addressed. NO TELEPHONE INQUIRIES WILL BE ACCEPTED.
Notice: VA and/or third party (support contractor) will require access to VA contractor records to access contract compliance with the limitations on subcontracting requirements included in VAAR 852.219-75 LIMITATIONS ON SUBCONTRACTING If submitting a joint-venture, bidders must include a copy of the joint-venture agreement within the bid package.
Joint Ventures (JVs) submitting an offer shall also submit printed proof of their SBA DSBS and / or SBA SDVOSB certification with their offer. JV offerors failing to submit this proof shall be rendered non-responsive outright and shall not be eligible for award.
All potential bidders are responsible for monitoring and downloading all amendments from Contract Opportunities at:
https://sam.gov/contracting.
ZERO (0)
11AM
CST
11-18-2026
14. NAME AND ADDRESS OF OFFEROR
15. TELEPHONE NUMBER
16. REMITTANCE ADDRESS
CODE
FACILITY CODE
17. The offeror agrees to perform the work required at the prices specified below in strict accordance with the terms of the solicitation, if this offer is accepted by the Government in writing within __________ calendar days after the date offers are due.
AMOUNTS
18. The offeror agrees to furnish any required performance and payment bonds.
19. ACKNOWLEDGMENT OF AMENDMENTS
AMENDMENT
NUMBER
DATE.
20a. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN OFFER 20b. SIGNATURE 20c. OFFER DATE
21. ITEMS ACCEPTED:
22. AMOUNT
23. ACCOUNTING AND APPROPRIATION DATA
24. SUBMIT INVOICES TO ADDRESS SHOWN IN
ITEM
25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO
10 U.S.C. 2304(c)( 41 U.S.C. 3304(a) (
26. ADMINISTERED BY
27. PAYMENT WILL BE MADE BY
PHONE:
FAX:
28. NEGOTIATED AGREEMENT
29. AWARD
Your Contractor agrees offer on this solicitation is hereby accepted as to the items listed. This to furnish and deliver all items or perform all work requirements identified award consummates the contract, which consists of (a) the Government on this form and any continuation sheets for the consideration stated in solicitation and your offer, and (b) this contract award. No further cont-this contract. The rights and obligations of the parties to this contract ractual document is necessary.
shall be governed by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, certifications, and specifications incorporated by reference in or attached to this contract.
30a. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED 31a. NAME OF CONTRACTING OFFICER
TO SIGN
30b. SIGNATURE 30c. DATE 31b. UNITED STATES OF AMERICA 31c. AWARD DATE
BY
OFFER
AWARD
STANDARD FORM 1442 (REV. 8/2014) BACK
(Include ZIP Code) (Include area code) (Include only if different than Item 14.)
(Insert any number equal to or greater than the minimum requirement stated in Item 13d. Failure to insert any number means the offeror accepts the minimum in Item 13d.)
(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each) (Type or print) (4 copies unless otherwise specified) (Type or print) (Type or print) (Contractor is required to sign this document and return _______ copies to issuing office.)
(Contractor is not required to sign this document.)
(Must be fully completed by offeror) (To be completed by Government)
CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE
CLIN 0001: BASE BID LUMP SUM. Alternate Bid Item 1.
36C252 Great Lakes Acquisition Center - HC 115 South 84th Street, Suite 101 Milwaukee WI 53214-1476
Financial Services Center PO Box 149971
RYAN MCMILLIN
CONTRACTING OFFICER
BID SCHEDULE
VA Construction Project# 695-24-107 to Replace Boilers 4 and 5 Expected project range is between $2,000,000 and $5,000,000.
0001 – All-Inclusive Base Bid: Contractor shall provide for and furnish all labor, materials, equipment, qualified supervision, and other items designated in this contract in accordance with the specifications and drawings to complete Project 695-24-107, “Replace Boilers 4 and 5,” at the Clement J. Zablocki VA Medical Center, Milwaukee WI. That is, demo and removal of existing Boilers #4 and #5 and the installation of one new Boiler #5.
All work, starting with preconstruction phase through construction, ending in post-substantial completion is to be accomplished within FOUR hundred and FIFTY-FIVE days (455) calendar days after receipt of the notice to proceed.
The contractor must submit proof of current (as of time of bid) SAM and DSBS registries with their bid and any bidder that is not current shall be rendered non-responsive outright and shall not be considered for award.
Base Bid LUMP SUM: CLIN 0001 $___________________________
Alternate Bid Item 1 – Demo/Removal of One Boiler (#5) instead of both (#4 and #5) Base Bid general construction minus the following:
Alternate Bid Item #1 includes the demo and removal of just existing Boiler #5, allowing the VA to utilize existing Boiler #4 as a back-up summertime boiler. This Bid Alternate also includes ancillary piping and controls adjustments to maintain feeders, discharge piping, and controls for the remaining Boiler #4. See plans and specifications for further information.
All work, starting with preconstruction phase through construction, ending in post-substantial completion is to be accomplished within FOUR hundred and FIFY-FIVE days (455) calendar days after receipt of the notice to proceed.
Price for Alternate Bid Item 1: $__________________________
NOTICE TO BIDDERS: Award will be made on Base Bid, subject to available funding. In the event bids on the Base Bid exceed available funding, a single award will be made exclusively on the amount of funding available for Alternate Bid Item 1. Award will be made to the responsible bidder who submitted the lowest responsive bid.
A single award will be made on Base Bid or Alternate Bid, subject to available funding at time of award.
NOTICE TO BIDDERS: The contractor will be working in a very active and often-congested operating hospital. The contractor will be sharing roadways with patients, visitors, staff, vendors, delivery vehicles and other contractors during the normal workday. The contractor shall coordinate delivery schedules with the COR to minimize congestion and interference with facility operations. Delivery times may be adjusted, including outside normal working hours, when approved by the Government.
The contractor will be required to keep all other non-impacted roads, walks and entrances to grounds, parking, and to occupied areas of buildings clear of construction materials, debris and standing construction equipment and vehicles. Submittals regarding staging of equipment, storage of supplies, etc. are required. Off-hours and/or weekend deliveries of construction equipment or materials may be required.
NOTICE TO BIDDERS: An approved cost-loaded, Critical Path Method (CPM) construction schedule is required prior to commencement of construction. See specifications for details. CPM schedule shall be approved by the Contracting Officer or the Contracting Officer’s Representative. See specifications for details.
NOTICE TO BIDDERS: This BID SCHEDULE is in addition to and augments the specifications and drawings. BIDDERS MUST BID ON ALL BID ITEMS. ONLY ONE AWARD WILL BE MADE AS A RESULT OF THIS SOLICITATION.
FAR DEVIATION FEB 2026 INSTRUCTIONS: System updates may lag policy updates. The System for Award Management (SAM) may continue to require entities to complete representations based on provisions that are not included in agency solicitations. Examples include 52.222-25, Affirmative Action Compliance, and paragraph (d) of 52.212-3, Offeror Representations and Certifications—Commercial Products and Commercial Services. Contracting officers will not consider these representations when making award decisions or enforce requirements. Entities are not required to, nor are they able to, update their entity registration to remove these representations in SAM.
COMPLIANCE WITH VHA DIRECTIVE 1192.01
VHA Directive 1192.01 issued August 10, 2020, requires all contractor personnel to receive annual seasonal influenza vaccinations or obtain an exemption for medical or religious reasons. Compliance with this directive is a requirement of this contract. A copy of VHA Directive 1192.01 is available at this link:
https://www.google.com/url?sa=t&rct=j&q=&esrc=s&source=web&cd=&ved=2ahUKEwi0t7CAj_DrAhXDgnIEHbVSCwgQFjAAegQIBRAB&url=https%3A%2F%2Fwww.va.gov%2Fvhapublications%2FViewPublication.asp%3Fpub_ID%3D8948&usg=AOvVaw1Rwijbc9Z5WL5ilsgWoagN
Contracting Officer’s Special Instructions as follows:
After compiling all required information, submit the information in accordance with Block 13 of the SF 1442 (page 1 of this solicitation). Return the original and specified number of copies to the issuing office listed in Block 8 of the SF 1442 (page 1 of this solicitation).
INQUIRIES:
Accordingly, offerors may Inspect the Site where the work will be performed.
· An organized Site Visit scheduled: Wednesday, October 14, 2026, at 1:30PM
· Participants meet in the parking lot between Bldgs. 112 and 43. See ATT F for map. The address of the VA facility is 5000 W. National Ave, Milwaukee, WI 53295. ALL contractors must park in the contractor parking lot shown in map and walk to meeting point. Do NOT Park in the lots up by Bldg. 43.
Written Requests for Information (RFI) or clarifications to solicitation documents are requested to be submitted as soon as possible to the Contract Specialist at Kristine.Sutton@va.gov AND Contracting Officer at Ryan.McMillin@va.gov but, no later than 11am local time October 22, 2026. Requests received after this deadline may not be addressed. Telephone inquiries will not be accepted.
NOTE: Inquiries and all correspondence concerning this solicitation document should be submitted in writing to the Contract Specialist and Contracting Officer.
YOU ARE INSTRUCTED SPECIFICALLY TO CONTACT ONLY THE CONTRACT SPECIALIST AND CONTRACTING OFFICER ISSUING THE SOLICITATION ABOUT ANY ASPECT OF THIS REQUIREMENT PRIOR TO CONTRACT AWARD.
VIRTUAL BID OPENING INFORMATION:
1) There will be no in-person public bid opening process. This will be conducted as a public virtual activity.
2) The virtual bid opening will be available to the public via Microsoft Teams at the following link and/or phone number:
Join the meeting now
a) (Meeting will be available to be accessed 15 min prior to bid opening)
b) Meeting ID: 247 074 689 067 769
c) Passcode: Zs6gN2Sm
d) Dial-in by phone: +1 872-701-0185,,234797034#; United States, CST Phone conference ID: 234 797 034#
3) IAW FAR 52.214-5 Submission of Bids and FAR 14.202-8 Electronic Bids; Bids shall be provided via email to the Contracting Specialist at Kristine.Sutton@va.gov AND Ryan.McMillin@va.gov as follows:
BIDS DUE: Vendor bids are due via email as shown above at 11AM local time on November 18, 2026.
The virtual public bid opening will be held at 1:00PM local time on November 18, 2026, at the link and/or the phone # provided above.
A hard copy submission is not required. Any bids received after the date and time specified for receipt of bids will be processed in accordance with FAR 52.214-7 Late Submissions, Modifications, and Withdrawals of Bids (Nov 1999).
It is highly recommended that Bidders submit their bid NLT COB the day before bid due date to avoid any transmission issues and request notice that bid was received to ensure receipt. Please refer to FAR 52.214-7 for further guidance. Please note: Transmission issues can happen unexpectedly at any time, it is the responsibility of the bidder to ensure bids are received before the bid due date and time.
4) Bidders shall submit a bid bond with their bid in accordance with FAR 52.228-1. Noncompliance with this requirement will result in rejection of the bid, except that such noncompliance must be waived under the circumstances identified at FAR 28.101-4(c). The apparent successful low bidder shall furnish an executed bid bond, within ten (10) calendar days after notification by the Contracting Officer, or as otherwise directed in the solicitation.
5) Ensure your bid includes the completed VAAR 852.219-75 VA NOTICE OF LIMITATIONS ON SUBCONTRACTING—CERTIFICATE OF COMPLIANCE FOR SERVICES AND CONSTRUCTION (JAN 2023) (DEVIATION). See Solicitation Attachment. Bidders that fail to do so will be rendered non-responsive outright and shall not be considered for award.
“VAAR 852.219-73 was included in this solicitation and references the SBA certification database at https://veterans.certify.sba.gov/. However, the website portal at the foregoing link is now static and is no longer being updated as of August 2024. To be eligible for award, a vendor must be listed as SDVOSB certified in the SBA’s Small Business Search (formerly Dynamic Small Business Search) website: https://search.certifications.sba.gov/
CONTRACTOR'S SIGNATURE:
In accordance with Federal Acquisition Regulations Part 4, contractual documents (e.g. bids, proposals, awards, modifications, etc.) shall be completed and signed by the Contractor as follows:
(a) Individuals. A contract with an individual shall be signed by that individual. A contract with an individual doing business as a firm shall be signed by that individual, and the signature shall be followed by the individual’s typed, stamped, or printed name and the words “, an individual doing business as _________” [insert name of firm].
(b) Partnerships. A contract with a partnership shall be signed in the partnership name. Before signing for the Government, the contracting officer shall obtain a list of all partners and ensure that the individual(s) signing for the partnership have authority to bind the partnership.
(c) Corporations. A contract with a corporation shall be signed in the corporate name, followed by the word “by” and the signature and title of the person authorized to sign. The contracting officer shall ensure that the person signing for the corporation has authority to bind the corporation.
(d) Joint venturers. A contract with joint venturers may involve any combination of individuals, partnerships, or corporations. The contract shall be signed by each participant in the joint venture in the manner prescribed in paragraphs (a) through (c) of this section for each type of participant. When a corporation is participating, the contracting officer shall verify that the corporation is authorized to participate in the joint venture.
(e) Agents. When an agent is to sign the contract, other than as stated in paragraphs (a) through (d) of this section, the agent’s authorization to bind the principal must be established by evidence satisfactory to the contracting officer.
CONTRACTOR INFORMATION:
Name of Company: _____________________________
Name: ___________________________________________
Title: _______________________________________________
Address: _________________________________________ _______
| E-Mail Address: | ____________________________ | |
| Phone No: | _______________________________________________ | |
| Fax No: | _______________________________________________________ |
TAX ID Number: ___________________
SAM UEI Number: _________________________________________________________________________
DUNS NUMBER: ________________________________________________________
Past Performance Point of Contact (within your company), include name and email address:
INFORMATION REGARDING BIDDING MATERIAL, BID GUARANTEE AND BONDS
(a) This solicitation & all associated bid documents are available to interested parties in electronic file format from www.sam.gov. No hard copy documents will be provided by the government.
(b) A bid guarantee is required in an amount not less than 20 percent of the bid price but shall not exceed $3,000,000. Failure to furnish the required bid guarantee on form SF24, in the proper amount, by the time set for opening of bids, will result in rejection of the bid in all cases except those listed in FAR 28.101-4, and may be cause for rejection even then.
(c) The bidder to whom a contract is awarded will be required to furnish a Payment Bond, on form SF25A, and a Performance Bond, on form SF25. Each bond shall be issued for a penal sum equal to the value of the awarded contract. Copies of forms SF25 and SF25A may be obtained from the Contracting Officer upon request.
(d) Bidders are to ensure the most current version of SF24, SF25, and SF25A bond forms are used. Current versions of these forms can be found and downloaded from the GSA Forms Library (https://www.gsa.gov/portal/forms/type/TOP).
Safety or Environmental Violations and Experience Modification Rate All Bidders/Offerors shall submit information pertaining to their past Safety and Environmental record. The information must contain a certification that the bidder/offeror has no more than three (3) serious, or one (1) repeat or one (1) willful OSHA or any EPA violation(s) in the past three years. If such certification cannot be made, a Bidder/Offeror shall explain why and submit as much information as possible regarding the circumstances of its past safety and environmental record, including the number of EPA violations and/or the number of serious, repeat, and/or willful OSHA violations, along with a detailed description of those violations.
All Bidders/Offerors shall submit information regarding their current Experience Modification Rate (EMR). This information shall be obtained from the Bidder’s/Offeror’s insurance carrier and be furnished on the insurance carrier’s letterhead. If a Bidder/Offeror’s EMR is above 1.0, Bidder/Offeror must submit a written explanation of the EMR from its insurance carrier furnished on the insurance carrier’s letterhead, describing the reasons for the EMR, and the anticipated date the EMR may be reduced to 1.0 or below.
Self insured contractors or other contractors that cannot provide their EMR rating on insurance letterhead must obtain a rating from the National Council on Compensation Insurance, Inc. (NCCI) by completing/submitting form ERM-6 and providing the rating on letterhead from NCCI. Note: Self insured contractors or other contractors that cannot provide EMR rating on insurance letterhead from the states or territories of CA, DE, MI, NJ, ND, OH, PA, WA, WY, and PR shall obtain their EMR rating from their state run worker’s compensation insurance rating bureau.
If the NCCI cannot issue an EMR because the Bidder/Offeror lacks insurance history, Bidder/Offeror shall submit a letter indicating so from its insurance carrier furnished on the insurance carrier’s letterhead, and include a letter from the NCCI indicating that is has assigned Bidder/Offeror a Unity Rating of 1.0.
The above information, along with other information obtained from Government systems, such as the OSHA and EPA online inspection history databases, will be used to make an initial Determination of Responsibility.
This requirement is applicable to all subcontracting tiers, and prospective prime contractors are responsible for determining the responsibility of their prospective subcontractors.
Pre-Award Contractor Safety and Environmental Record Evaluation Form Company Name: ______________________________________________ Address: _____________________________________________________ Telephone: ______________________ Fax: ________________________ Email: _______________________________________________________ Contact: ______________________________________________________
1. Utilizing your OSHA 300 Forms, please complete the following information:
| Category |
| 2024 |
| 2025 |
| 2026 |
Number of man hours (jobsite and office).
Number of cases involving days away from work, restricted activity, or both (Column H and I of OSHA 300).
Days away, restricted, or transferred rate (# of days away, restricted, or transferred cases x 200,000/# of man hours) (DART Rate).
Number of serious, willful, or repeat violations from OSHA within the last 3 years. Please attach explanation for any violations.
Please attach copies of the following documents: OSHA 300 and 300a Forms. These forms can be accessed through the OSHA publications search page: http://www.osha.gov/pls/publications/publication.html.
| 2. | Provide your six-digit North American Industrial Classification System (NAICS) Code for this acquisition: _______________________________________________________________ |
| 3. | Who administers your company’s Safety and Health Program? _________________________________________________________________________ |
4. Company’s Insurance Experience Modification Rate (EMR): ______________________
STATEMENT OF WORK
I General Description:
Provide Construction Services for Project# 695-24-107 to Replace Boilers 4 and 5 at VAMC Milwaukee Building 112 (Boilerhouse).
II Project Scope:
1. Contractor shall provide for and furnish all labor, materials, equipment, qualified supervision, and other items designated in this contract in accordance with the specifications and drawings to complete Project# 695-24-107 to Replace Boilers 4 and 5 at Building 112 (Boilerhouse) at Clement J. Zablocki VA Medical Center, 5000 West National Avenue Milwaukee, WI. This project will replace Boilers #4 & #5 at the VAMC Milwaukee Building 112 (Boiler House) with a new Boiler #5 (single new firetube boiler).
2. All work shall be completed within 455 calendar days after receiving Notice to Proceed.
III Project Duration/Phase:
· Phase 1: Pre-Construction Period. That period of time from Notice to Proceed (NTP) to the end of the pre-construction submittal period. Phase 1 shall be 90 days, and shall not exceed NTP + 90 calendar days: 60 days for the Contractor to assemble and submit his preconstruction submittals and 30 days for COR and CO reviews and approvals. GC shall ensure all contractors attain their badging this period. COR will schedule a NTP meeting early in this period (could be same day as NTP, or shortly thereafter). Construction kick-off meeting will be scheduled by COR late in this period, once all pre-construction submittals are in and approved. The table below lists the required pre-construction submittals (see Specification 01 33 23):
| Preconstruction Submittal |
| Reference |
| Due |
Surety Bonds & Certificates of Ins
To CO prior to NTP
SF 1413s (Subcontractor List)
To CO re: FAR 52.222-11
| Schedule Consultant Qualification Proposal |
| 01 32 16.15 |
| Within 15d of award |
Project Management Team Memo (PM, Supt, QCM/CPM, SSHO) 01 00 00/ 01 35 26 Within 60d of NTP
| Construction Site Security Plan |
| 01 00 00 |
| Within 60d of NTP |
| Logistics Plan |
| 01 00 00 |
| Within 60d of NTP |
| Construction Phasing Plan(s) * |
| 01 00 00 |
| Within 60d of NTP |
| Existing Conditions Survey |
| 01 00 00 |
| Within 60d of NTP |
| Construction Schedule (Initial) |
| 01 32 16.15 |
| Within 30d of NTP |
| Schedule of Values |
| 01 32 16.15 |
| Within 60d of NTP |
| Construction Baseline Schedule (Final) |
| 01 32 16.15 |
| Within 30d of VA approval of Initial Schedule and Schedule of Values |
| Submittal Register |
| 01 33 23 |
| Within 60d of NTP |
| Accident Prevention Plan |
| 01 35 26 |
| Within 60d of NTP |
| Activity Hazard Analyses |
| 01 35 26 |
| With APP or Within 60d of NTP, or 15d prior to Activity |
| OSHA Certificates and Applicable Training Documents |
| 01 35 26 |
| Within 60d of NTP |
| Infection Control Plan(s) * |
| 01 35 26 |
| Within 60d of NTP |
| Fire Safety Plan |
| 01 35 26 |
| Within 60d of NTP |
| Environmental Protection Plan |
| 01 57 19 |
| Within 60d of NTP |
| Construction Waste Management Plan |
| 01 74 19 |
| Within 60d of NTP |
| Sustainable Construction Spreadsheet |
| 01 81 13 |
| Within 30d of Kickoff |
· Phase 2: Construction Period. That period of time from General Contractor mobilization to VA substantial completion and/or beneficial occupancy (acceptance). Phase 2 shall be 275 days (9 months) and shall not exceed NTP + 365 calendar days. All applicable documentation listed in Phase 1 and any necessary submittals required to mobilize must be approved by the COR prior to commencing work. No demolition or construction shall be started without COR review and approval of those items listed in the Pre-Construction Period unless authorized in writing by the COR or the CO. Should naturally occurring weather delays occur, the contractor shall restart construction immediately once conditions permit.
· Phase 3: Post-Substantial Completion Period. That period of time from beneficial occupancy (acceptance) to final payment and release of claims. Phase 3 shall be 90 days and shall not exceed NTP + 455 calendar days. The Contractor shall provide the following documentation within 60 days, (NTP + 425 calendar days), of the beginning of this period:
| Punchlist Resolution Documentation |
| Warranty Documentation |
| Redlines and As-builts drawings |
| O&M Manuals |
| Training |
| Final Waste Manifests |
-- End SOW --
Records Management
1. Citations to pertinent laws, codes and regulations such as 44 U.S.C chapters 21, 29, 31 and 33; Freedom of Information Act (5 U.S.C. 552); Privacy Act (5 U.S.C. 552a); 36 CFR Part 1222 and Part 1228.
2. Contractor shall treat all deliverables under the contract as the property of the U.S. Government for which the Government Agency shall have unlimited rights to use, dispose of, or disclose such data contained therein as it determines to be in the public interest.
3. Contractor shall not create or maintain any records that are not specifically tied to or authorized by the contract using Government IT equipment and/or Government records.
4. Contractor shall not retain, use, sell, or disseminate copies of any deliverable that contains information covered by the Privacy Act of 1974 or that which is generally protected by the Freedom of Information Act.
5. Contractor shall not create or maintain any records containing any Government Agency records that are not specifically tied to or authorized by the contract.
6. The Government Agency owns the rights to all data/records produced as part of this contract.
7. The Government Agency owns the rights to all electronic information (electronic data, electronic information systems, electronic databases, etc.) and all supporting documentation created as part of this contract. Contractor must deliver sufficient technical documentation with all data deliverables to permit the agency to use the data.
8. Contractor agrees to comply with Federal and Agency records management policies, including those policies associated with the safeguarding of records covered by the Privacy Act of 1974. These policies include the preservation of all records created or received regardless of format [paper, electronic, etc.] or mode of transmission [e-mail, fax, etc.] or state of completion [draft, final, etc.].
9. No disposition of documents will be allowed without the prior written consent of the Contracting Officer. The Agency and its contractors are responsible for preventing the alienation or unauthorized destruction of records, including all forms of mutilation. Willful and unlawful destruction, damage or alienation of Federal records is subject to the fines and penalties imposed by 18 U.S.C. 2701. Records may not be removed from the legal custody of the Agency or destroyed without regard to the provisions of the agency records schedules.
10. Contractor is required to obtain the Contracting Officer's approval prior to engaging in any contractual relationship (sub-contractor) in support of this contract requiring the disclosure of information, documentary material and/or records generated under, or relating to, this contract. The Contractor (and any sub-contractor) is required to abide by Government and Agency guidance for protecting sensitive and proprietary information.
INSTRUCTIONS, CONDITIONS AND OTHER STATEMENTS TO BIDDERS/OFFERORS
2.1 52.216-1 TYPE OF CONTRACT (NOV 2025) (DEVIATION)
The Government contemplates award of a Firm-Fixed-Price contract resulting from this solicitation.
(End of Provision)
2.2 52.222-5 CONSTRUCTION WAGE RATE REQUIREMENTS—SECONDARY SITE OF THE WORK (NOV 2025) (DEVIATION) (a)(1) The offeror must notify the Government if the offeror intends to perform work at any secondary site of the work, as defined in paragraph (a)(1)(ii) of the FAR clause at 52.222-6, Construction Wage Rate Requirements, of this solicitation.
(2) If the offeror is unsure if a planned work site satisfies the criteria for a secondary site of the work, the offeror must request a determination from the Contracting Officer.
(b)(1) If the wage determination provided by the Government for work at the primary site of the work is not applicable to the secondary site of the work, the offeror must request a wage determination from the Contracting Officer.
(2) The due date for receipt of offers will not be extended as a result of an offeror's request for a wage determination for a secondary site of the work.
(End of Provision)
2.3 52.225-10 NOTICE OF BUY AMERICAN REQUIREMENT—CONSTRUCTION MATERIALS (MAY 2014)
(a) Definitions. "Commercially available off-the-shelf (COTS) item," "construction material," "domestic construction material," and "foreign construction material," as used in this provision, are defined in the clause of this solicitation entitled "Buy American—Construction Materials" (Federal Acquisition Regulation (FAR) clause 52.225-9).
(b) Requests for determinations of inapplicability. An offeror requesting a determination regarding the inapplicability of the Buy American statute should submit the request to the Contracting Officer in time to allow a determination before submission of offers. The offeror shall include the information and applicable supporting data required by paragraphs (c) and (d) of the clause at FAR 52.225-9 in the request. If an offeror has not requested a determination regarding the inapplicability of the Buy American statute before submitting its offer, or has not received a response to a previous request, the offeror shall include the information and supporting data in the offer.
(c) Evaluation of offers.
(1) The Government will evaluate an offer requesting exception to the requirements of the Buy American statute, based on claimed unreasonable cost of domestic construction material, by adding to the offered price the appropriate percentage of the cost of such foreign construction material, as specified in paragraph (b)(3)(i) of the clause at FAR 52.225-9.
(2) If evaluation results in a tie between an offeror that requested the substitution of foreign construction material based on unreasonable cost and an offeror that did not request an exception, the Contracting Officer will award to the offeror that did not request an exception based on unreasonable cost.
(d) Alternate offers.
(1) When an offer includes foreign solicitation in paragraph (b)(2) of the clause at FAR 52.225-9, the offeror also may submit an alternate offer based on use of equivalent domestic construction material.
(2) If an alternate offer is submitted, the offeror shall submit a separate Standard Form 1442 for the alternate offer, and a separate price comparison table prepared in accordance with paragraphs (c) and (d) of the clause at FAR 52.225-9 for the offer that is based on the use of any foreign construction material for which the Government has not yet determined an exception applies.
(3) If the Government determines that a particular exception requested in accordance with paragraph (c) of the clause at FAR 52.225-9 does not apply, the Government will evaluate only those offers based on use of the equivalent domestic construction material, and the offeror shall be required to furnish such domestic construction material. An offer based on use of the foreign construction material for which an exception was requested—
(i) Will be rejected as nonresponsive if this acquisition is conducted by sealed bidding; or
(ii) May be accepted if revised during negotiations.
(End of Provision)
2.4 52.228-1 BID GUARANTEE (SEP 1996)
(a) Failure to furnish a bid guarantee in the proper form and amount, by the time set for opening of bids, may be cause for rejection of the bid.
(b) The bidder shall furnish a bid guarantee in the form of a firm commitment, e.g., bid bond supported by good and sufficient surety or sureties acceptable to the Government, postal money order, certified check, cashier's check, irrevocable letter of credit, or, under Treasury Department regulations, certain bonds or notes of the United States. The Contracting Officer will return bid guarantees, other than bid bonds—
(1) To unsuccessful bidders as soon as practicable after the opening of bids; and
(2) To the successful bidder upon execution of contractual documents and bonds (including any necessary coinsurance or reinsurance agreements), as required by the bid as accepted.
(c) The amount of the bid guarantee shall be 20% percent of the bid price or $3,000,000.00, whichever is less.
(d) If the successful bidder, upon acceptance of its bid by the Government within the period specified for acceptance, fails to execute all contractual documents or furnish executed bond(s) within 10 days after receipt of the forms by the bidder, the Contracting Officer may terminate the contract for default.
(e) In the event the contract is terminated for default, the bidder is liable for any cost of acquiring the work that exceeds the amount of its bid, and the bid guarantee is available to offset the difference.
(End of Provision)
| FAR Number |
| Title |
| Date |
| 52.228-17 |
| INDIVIDUAL SURETY—PLEDGE OF ASSETS (BID GUARANTEE) |
| FEB 2021 |
2.5 52.233-2 SERVICE OF PROTEST (SEP 2006)
Protests, as defined in section 33.101 of the Federal Acquisition Regulation, that are filed directly with an agency, and copies of any protests that are filed with the Government Accountability Office (GAO), shall be served on the Contracting Officer (addressed as follows) by obtaining written and dated acknowledgment of receipt from:
Hand-Carried Address:
Kristine Sutton/Ryan McMillin Department of Veterans Affairs 36C252 115 South 84th Street, Suite 101 Milwaukee WI 53214-1476
Mailing Address:
Kristine Sutton/Ryan McMillin Department of Veterans Affairs 36C252 115 South 84th Street, Suite 101 Milwaukee WI 53214-1476
(b) The copy of any protest shall be received in the office designated above within one day of filing a protest with the GAO.
(End of Provision)
2.6 52.240-90 SECURITY PROHIBITIONS AND EXCLUSIONS REPRESENTATIONS AND CERTIFICATIONS (NOV 2025) (DEVIATION)
(a) Definitions. As used in this provision— Backhaul, covered article, covered telecommunications equipment or services, critical technology, FASCSA order, Intelligence community, interconnection arrangements, national security system, roaming, sensitive compartmented information, sensitive compartmented information system, source, and substantial or essential component have the meanings provided in the clause 52.240-91, Security Prohibitions and Exclusions.
Business operations means engaging in commerce in any form, including by acquiring, developing, maintaining, owning, selling, possessing, leasing, or operating equipment, facilities, personnel, products, services, personal property, real property, or any other apparatus of business or commerce.
Marginalized populations of Sudan means—
(1) Adversely affected groups in regions authorized to receive assistance under section 8(c) of the Darfur Peace and Accountability Act (Pub. L. 109-344) (50 U.S.C. 1701 note); and
(2) Marginalized areas in Northern Sudan described in section 4(9) of such Act.
Restricted business operations means business operations in Sudan that include power production activities, mineral extraction activities, oil-related activities, or the production of military equipment, as those terms are defined in the Sudan Accountability and Divestment Act of 2007 (Pub. L. 110-174). Restricted business operations do not include business operations that the person (as that term is defined in Section 2 of the Sudan Accountability and Divestment Act of 2007) conducting the business can demonstrate—
(1) Are conducted under contract directly and exclusively with the regional government of southern Sudan;
(2) Are conducted under specific authorization from the Office of Foreign Assets Control in the Department of the Treasury, or are expressly exempted under Federal law from the requirement to be conducted under such authorization;
(3) Consist of providing goods or services to marginalized populations of Sudan;
(4) Consist of providing goods or services to an internationally recognized peacekeeping force or humanitarian organization;
(5) Consist of providing goods or services that are used only to promote health or education; or
(6) Have been voluntarily suspended.
Sensitive technology—
(1) Means hardware, software, telecommunications equipment, or any other technology that is to be used specifically—
(i) To restrict the free flow of unbiased information in Iran; or
(ii) To disrupt, monitor, or otherwise restrict speech of the people of Iran; and
(2) Does not include information or informational materials the export of which the President does not have the authority to regulate or prohibit pursuant to section 203(b)(3) of the International Emergency Economic Powers Act (50 U.S.C. 1702(b)(3)).
(b) Procedures.
(1) Covered telecommunications and video surveillance. The Offeror shall review the list of excluded parties in the System for Award Management (SAM) at https://www.sam.gov for entities excluded from receiving federal awards for “covered telecommunications equipment or services.”
(2) FASCSA Orders.
(i) The Offeror shall search in SAM for the phrase “FASCSA order” for any covered article, or any products or services produced or provided by a source, if there is an applicable FASCSA order described in paragraph (e) of FAR 52.240-91, Security Prohibitions and Exclusions.
(ii) The Offeror shall review the solicitation for any FASCSA orders that are not in SAM but are effective and apply to the solicitation and resultant contract (see FAR 40.204-1(c)(2)).
(iii) FASCSA orders issued after the date of solicitation do not apply unless added by an amendment to the solicitation.
(c) Covered telecommunications equipment or services representations. By submission of its offer, the Offeror represents that, after conducting a reasonable inquiry (that looks at any information in the Offeror’s possession but does not need to include an internal or third-party audit)—
(1) It will not provide covered telecommunications equipment or services to the Government in the performance of any contract, subcontract or other contractual instrument resulting from this solicitation, except as waived by the solicitation, or as disclosed in paragraph (g); and
(2) It does not use covered telecommunications equipment or services, or use any equipment, system, or service that uses covered telecommunications equipment or services, except as waived by the solicitation, or as disclosed in paragraph (g).
(d) FASCSA Representation. By submission of this offer, the offeror represents that it has conducted a reasonable inquiry, and that the offeror does not propose to provide or use in response to this solicitation any covered article, or any products or services produced or provided by a source, if the covered article or the source is prohibited by an applicable FASCSA order in effect on the date the solicitation was issued, except as waived by the solicitation, or as disclosed in paragraph (g). A reasonable inquiry will look at any information in the offeror’s possession but does not need to include an internal or third-party audit.
(e) Sudan certification. By submission of its offer, the offeror certifies, after conducting a reasonable inquiry (that looks at any information in the offeror’s possession but does not need to include an internal or third-party audit), that the offeror does not conduct any restricted business operations in Sudan.
(f) Iran Representation and Certifications.
(1) Except as provided in paragraph (f)(2) of this provision or if a waiver has been granted in accordance with FAR 40.203-3, the offeror, after conducting a reasonable inquiry (that looks at any information in the offeror’s possession but does not need to include an internal or third-party audit), by submission of its offer—
(i) Represents, to the best of its knowledge and belief, that the offeror does not export any sensitive technology to the government of Iran or any entities or individuals owned or controlled by, or acting on behalf or at the direction of, the government of Iran;
(ii) Certifies that the offeror, or any person (as defined at section 15 of the Iran Sanctions Act of 1996, Pub. L. 104-172, 50 U.S.C. 1701 note) owned or controlled by the offeror, does not engage in any activities for which sanctions may be imposed under section 5 of the Act. These sanctioned activities are in the areas of development of the petroleum resources of Iran, production of refined petroleum products in Iran, sale and provision of refined petroleum products to Iran, and contributing to Iran’s ability to acquire or develop certain weapons or technologies; and
(iii) Certifies that the offeror, and any person owned or controlled by the offeror, does not knowingly engage in any transaction that exceeds $15,000 with Iran’s Revolutionary Guard Corps or any of its officials, agents, or affiliates, the property and interests in property of which are blocked pursuant to the International Emergency Economic Powers Act (50 U.S.C. 1701 et seq.) (see OFAC’s Specially Designated Nationals and Blocked Persons List at https://www.treasury.gov/resource-center/sanctions/SDN-List/Pages/default.aspx)
(2) Exception for trade agreements. The representation and certification requirements of paragraph (f)(1) of this provision do not apply if—
(i) This solicitation includes a trade agreements notice or certification (e.g., 52.225-6, Trade Agreements Certificate); and
(ii) The offeror has certified that all the offered products to be supplied are designated country end products or designated country construction material.
(iii) The offeror shall email questions concerning sensitive technology to the Department of State at CISADA106@state.gov.
(g) Disclosure.
(1) If the Offeror is not able to represent compliance with the prohibitions in paragraphs (c) or (d), then the Offeror shall disclose within 72 hours to the contracting office identified in paragraph (g)(2) the following information for each product or service not compliant:
(i) Contract number and order number, if applicable;
(ii) Identification of whether this disclosure relates to paragraph (c) on covered telecommunication equipment or services, or to paragraph (d) on FASCSA orders;
(iii) A description of the products or services that the Contractor identifies or has reason to suspect is prohibited (include brand; model number, such as the original equipment manufacturer (OEM) number, manufacturer part number, or wholesaler number; and item description, as applicable);
(iv) The entity that produced the product or service (include entity name, unique entity identifier, Contractor and Government Entity (CAGE) code, facilities responsible for design, fabrication, assembly, packaging, and test of the product, and whether the entity was the OEM or a distributor (provide manufacturer codes and distributor codes used for the product));
(v) Description of the functionality of the product or service and how that functionality impacts the risk to the product or service;
(vi) An explanation of any factors relevant to determining if the product or service should be permitted by an applicable exception, exemption, or waiver (if the offeror would like the Government to consider a waiver);
(vii) Whether alternative products or services are available that would be compliant with the prohibition;
(viii) If the product or service is related to item maintenance, include the following information on the item being maintained:
(A) Brand;
(B) Model number, OEM number, manufacturer part number, or wholesaler number; and
(C) Item description, as applicable.
(ix) Any readily available information about mitigation actions undertaken or recommended.
(2) If a disclosure is required to be submitted to a contracting office, the offeror shall submit the disclosure as follows:
(i) If a Department of Defense contracting office, the offeror shall submit the disclosure to the website at https://dibnet.dod.mil.
(ii) For all other contracting offices, the Offeror shall submit the disclosure to the Contracting Officer.
(3) If the disclosure provided does not contain any of the information required by paragraph (1), and the Offeror later discovers new information that is required by paragraph (1), then the Offeror shall submit a subsequent disclosure within 72 hours of discovering the new information.
(h) Executive agency review of disclosures. The Contracting Officer will review disclosures provided in paragraph (g) to determine if any applicable waiver may be sought. The Contracting Officer may choose not to pursue a waiver and may instead make an award to an Offeror that does not require a waiver.
(End of Provision)
2.7 52.252-1 SOLICITATION PROVISIONS INCORPORATED BY REFERENCE (FEB 1998)
This solicitation incorporates one or more solicitation provisions by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. The offeror is cautioned that the listed provisions may include blocks that must be completed by the offeror and submitted with its quotation or offer. In lieu of submitting the full text of those provisions, the offeror may identify the provision by paragraph identifier and provide the appropriate information with its quotation or offer. Also, the full text of a solicitation provision may be accessed electronically at this/these address(es):
https://www.acquisition.gov/browse/index/far https://www.va.gov/oal/library/vaar/
(End of Provision)
| FAR Number |
| Title |
| Date |
| 52.204-7 |
| SYSTEM FOR AWARD MANAGEMENT—REGISTRATION (DEVIATION) |
| NOV 2025 |
| 52.214-3 |
| AMENDMENTS TO INVITATIONS FOR BIDS (DEVIATION) |
| NOV 2025 |
| 52.214-4 |
| FALSE STATEMENTS IN BIDS |
| APR 1984 |
| 52.214-5 |
| SUBMISSION OF BIDS (DEVIATION) |
| NOV 2025 |
| 52.214-6 |
| EXPLANATION TO PROSPECTIVE BIDDERS |
| APR 1984 |
| 52.214-7 |
| LATE SUBMISSIONS, MODIFICATIONS, AND WITHDRAWALS OF BIDS (DEVIATION) |
| NOV 2025 |
| 52.214-18 |
| PREPARATION OF BIDS—CONSTRUCTION |
| APR 1984 |
| 52.214-19 |
| CONTRACT AWARD—SEALED BIDDING—CONSTRUCTION |
| AUG 1996 |
| 52.214-34 |
| SUBMISSION OF OFFERS IN THE ENGLISH LANGUAGE |
| APR 1991 |
| 52.214-35 |
| SUBMISSION OF OFFERS IN U.S. CURRENCY |
| APR 1991 |
| 52.223-4 |