36C25227B0001 0003.docx
DOCX document 209 KB Posted
- Solicitation number
- 36C25227B0001
About this file
This is Amendment 0003 to Solicitation 36C25227B0001 for the replacement of Boilers 4 and 5 at Clement J. Zablocki VA Medical Center in Milwaukee, Wisconsin. The amendment, issued by the Department of Veterans Affairs Great Lakes Acquisition Center on November 19, 2026, adds updated specifications and drawings with Addendum 02 and 03 designations, incorporates new attachments including lightning protection plans and PIV badging procedures, and updates the Pre-Award Contractor Safety and Environmental Record Evaluation Form to reflect years 2023, 2024, and 2025. The amendment also provides clarifications on 111 questions and answers submitted by bidders addressing critical project scope items including boiler specifications, project duration (455 calendar days: 90 days preconstruction + 275 days construction + 90 days closeout), staffing requirements (dedicated full-time Site Safety and Health Officer and Superintendent as separate individuals), Quality Control Manager qualifications, commissioning responsibilities, utility outages, temporary equipment provisions, and asbestos abatement scope. The bid due date remains December 9, 2026 at 11:00 AM local time, with the government having 90 days after bid receipt to make an award, anticipated award within the stated acceptance period.
Key project specifications clarifications include: Boilers 1, 2, and 3 provide sufficient steam capacity during construction with no temporary boiler required; the contractor must complete all required safety device testing, commissioning, and minimum 89 hours of training; construction and safety signage are required; a six-foot tall temporary construction fence is acceptable; temporary power will be provided by VA with contractor responsible for connections; contractor shall provide third-party schedule consultant, third-party commissioning agent (funded by VA), and third-party independent safety professional (CHST/CSP); AISC certification for structural steel may be waived with documented relevant experience and AWS-certified welding personnel; no asbestos-containing materials are identified for abatement; contaminated soils are assumed present and disposal costs are contractor responsibility unless testing proves otherwise; and badging, fingerprinting, and influenza vaccinations are required for all contractor personnel.
View the file
Other files
Show all 19
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
36C25227B0001 0003 Continuation Page
5. PROJECT NUMBER (if applicable)
CODE
7. ADMINISTERED BY
2. AMENDMENT/MODIFICATION NUMBER
CODE
6. ISSUED BY
8. NAME AND ADDRESS OF CONTRACTOR
4. REQUISITION/PURCHASE REQ. NUMBER
3. EFFECTIVE DATE
9A. AMENDMENT OF SOLICITATION NUMBER
9B. DATED
PAGE OF PAGES
10A. MODIFICATION OF CONTRACT/ORDER NUMBER
10B. DATED
BPA NO.
1. CONTRACT ID CODE
FACILITY CODE
CODE
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers
E. IMPORTANT:
is extended,
(a) By completing Items 8 and 15, and returning __________ copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY is not extended.
12. ACCOUNTING AND APPROPRIATION DATA
(REV. 11/2016)
is required to sign this document and return ___________ copies to the issuing office.
is not, A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER NO. IN ITEM 10A.
15C. DATE SIGNED
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER
Contractor
16C. DATE SIGNED
14. DESCRIPTION OF AMENDMENT/MODIFICATION
16B. UNITED STATES OF AMERICA
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER
16A. NAME AND TITLE OF CONTRACTING OFFICER
15B. CONTRACTOR/OFFEROR
STANDARD FORM 30
PREVIOUS EDITION NOT USABLE
Prescribed by GSA - FAR (48 CFR) 53.243 (Type or print) (Type or print) (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
(Number, street, county, State and ZIP Code) (If other than Item 6) (Specify type of modification and authority) (such as changes in paying office, appropriation date, etc.)
(If required)
(SEE ITEM 11)
(SEE ITEM 13)
(X)
CHECK
ONE
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS,
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
(Signature of person authorized to sign) (Signature of Contracting Officer)
11-19-2026
695-27-1-6845-0001
695-24-107
Department of Veterans Affairs 36C252 115 South 84th Street, Suite 101
Milwaukee WI 53214-1476
Department of Veterans Affairs 36C252 Great Lakes Acquisition Center - HC 115 South 84th Street, Suite 101 Milwaukee WI 53214-1476 To all Offerors/Bidders
36C25227B0001
X
See Continuation Page.
Kristine Sutton Contracting Officer
Replace Boilers 4 and 5, Project# 695-24-107 36C25227B0001 0003 Clement J. Zablocki VA Medical Center, Milwaukee, WI
I. The following changes are to be made to the solicitation:
1. Added Attachment: A0003 - 695-22-106 Bldg. 112 Lightning Protection PLAN (construction of which is in progress),
2. Added Attachment: A0003 - PIV procedure for KTRs PDF, New Procedure
3. Added Attachment: A0003 - Blr 4-5 nameplates: Existing Boiler #4 and #5 nameplate information/pictures.
4. UPDATED Attachment: A0003 - Page 11_UPDATED. This replaces page 11, Pre-Award Contractor Safety and Environmental Record Evaluation Form, in solicitation to read now: 2023, 2024, 2025.
II. The following changes are made to project specifications:
Note – all specifications were updated with the header “Addendum 02” and dated 11/04/26. These are the specifications for the project and are issued with Amendment 03. Please consider the “Addendum 02” specifications as the correct specifications issued with the “Addendum 03” drawings and part of the Amendment 03.
See Attachment: A0003 - VA 695-24-107 Addendum 02 Combined Specifications
SPECIFICATIONS:
1. 01 35 26 – Updated spec includes QCM and CHST/CSP requirements
2. 01 45 29 – Updated tests required section re: quantities
3. 23 05 10 – Monitoring period changed from 21-days to 30-days
4. 23 10 00 – Added requirements for fuel piping secondary containment and leak detection
5. 26 05 11 – Removed arc flash study requirements
6. 31 20 11 – Fill material requirements were updated III. The following changes are made to project drawings:
Note – the new drawings have “Addendum 03” in the bottom left REVISION BLOCK. Please note that “Addendum 03” drawings are issued as part of Amendment 03. Revision #1 of “Addendum 03” is dated 11/04/26 and Revision #2 of “Addendum 03” is dated 11/16/26.
See Attachment: A0003 - VA 695-24-107 Addendum 03 Combined Drawings setPart-1 See Attachment: A0003 - VA 695-24-107 Addendum 03 Combined Drawings setPart-2 See Attachment: A0003 - VA 695-24-107 Addendum 03 Combined Drawings setPart-3
DRAWINGS:
1. Sheet GI001 – drawing index updated (3 new sheets)
2. Sheet GC101 – note #5 added
3. Sheet GC501 – new sheet (signage)
4. Sheet A-001 – added door schedule
5. Sheet AE101 – added roll up door tag
6. Sheet AE105 – added roll up door tag
7. Sheet AE121 – keynote #3 change
8. Sheet AE125 – keynote #3 change
9. Sheet AE201 – added roll up door tag; dimensions updated
10. Sheet AE205 – added roll up door tag; dimensions updated
11. Sheet AE301 – dimensions updated
12. Sheet AE501 – detail #5 and #9 edits
13. Sheet AE502 – detail #4 edit
14. Sheet D-611 – edited the legend at right
15. Sheet D-631 – edited the legend at right
16. Sheet D-643 – added 8x6 reducer to PID for Blr #4
17. Sheet M-601 – edit to VORTEX FLOW METER schedule
18. Sheet MD101 – edited the legend at right
19. Sheet MD105 – edited the legend at right
20. Sheet MP101 – change to steam header piping
21. Sheet MP102 – change to steam header piping
22. Sheet MP103 – added keynote #1 for fuel oil double-wall piping
23. Sheet MP105 – change to steam header piping
24. Sheet MP106 – change to steam header piping
25. Sheet MP107 – added keynote #1 for fuel oil double-wall piping
26. Sheet MP501 – detail #1 edit
27. Sheet MP901 – new sheet (isometric)
28. Sheet MP905 – new sheet (isometric)
29. Sheet MK101 – change to steam header piping
30. Sheet MK105 – change to steam header piping
31. Sheet MK201 – change to steam header piping
32. Sheet MK202 – change to steam header piping
33. Sheet MK205 – change to steam header piping
34. Sheet MK206 – change to steam header piping
35. Sheet E-001 – changes to GENERAL ELECTRICAL NOTES; LIGHTING FIXTURE SCHEDULE
36. Sheet ED101 – changes to keynotes #1 and #3
37. Sheet ED105 – changes to keynotes #1 and #2
38. Sheet ED601 – one line changes BLR #5 fan and MCC-2
39. Sheet ED605 – one line changes BLR #5 fan and MCC-2
40. Sheet EP601 – one line changes BLR #5 O2 analyzer
41. Sheet EP602 – panel schedule change
42. Sheet EP605 – one line changes BLR #4 and BLR #5 O2 analyzers
43. Sheet EP606 – panel schedule change EPL-SB-BLG112-2
44. Sheet EG121 – add roof grounding directions
45. Sheet EG125 – add roof grounding directions
46. Sheet EG501 – detail #2 edit
IV. The following Questions and Answers / Clarifications are the result of bidder’s request(s) for information:
| No. |
| Date Submitted |
| SUBJECT/COMMENT |
| Response |
| Included in Amendment # |
| 1 |
| 10/21/2026 |
| Reference: Pre-Award Contractor Safety and Environmental Record Evaluation Form, Item 1 (page 11 of the solicitation) |
The form requests the number of man hours (jobsite and office) for calendar years 2024, 2025, and 2026. As calendar year 2026 is not yet complete, please clarify how bidders should report 2026 man hours:
1. Should bidders report year-to-date actual man hours through a specific date (e.g., the most recent month-end prior to bid submission)?
2. Or should bidders provide an estimate of total man hours for the full 2026 calendar year?
| The form is updated to read 2023, 2024 and 2025, see Page 11 attached |
| A0003 |
| 2 |
| 10/21/2026 |
| Will the facility require any work to be completed off-hours? |
a. If so, can these tasks / scopes of work be completed in evenings and/or weekends?
| Outages and shutdowns must be accomplished off shift. Review the 01 00 00 specification (paragraph 1.6) regarding impacts to utilities. |
| A0003 |
| 3 |
| 10/21/2026 |
| Is temporary power and water available for a Construction Trailer at the laydown/storage area? |
| VA will make power available for a construction (job) trailer. Water is not available. Review the 01 00 00 specification (paragraph 1.23). |
| A0003 |
| 4 |
| 10/21/2026 |
| Will this project be Sales Tax Exempt? |
| MKE bids shall be all inclusive. |
| A0003 |
| 5 |
| 10/21/2026 |
| Can the site visit list please be provided. |
| See Amendment 01 which has already been posted to SAM.gov. |
| A0003 |
| 6 |
| 10/21/2026 |
| Please confirm whether one individual can ‘triple-hat’ and perform the duties of SSHO, CP and Superintendent roles, so long as they are qualified for each position and able to adequately perform responsibilities of all such roles; or if two individuals will be required to perform the duties of these three roles? |
| SSHO and Superintendent are two separate individuals, and they are dedicated to THIS PROJECT ALONE. They are both full-time onsite people during work on the contract. They may not act as QCM or PM, either. "CP" refers to competent people and there will be many CPs this project. SSHO and Superintendent shall not be CPs because they are in project management positions and not laborers or performers of actual work. For further clarification, this is directly communicated in the 01 00 00 specification (paragraph 1.4). |
| A0003 |
| 7 |
| 10/22/2026 |
| Please provide weight of existing Boilers 4 and 5. |
| Reliable information on the existing D-type boilers from 2010 is not available. The manufacturer has since been sold and the new owner provides very little reference information. When the VA was originally pursuing one-for-one replacements, the "like" watertube boilers that were being used as a basis for design have a shipping weight of 27,400 lb and a flooded weight of 42,400 lb. Nameplate data for the existing boilers is also attached separately. |
| A0003 |
| 8 |
| 10/22/2026 |
| For the alternate Boiler #4 is going to remain in place and be reconnected to the steam header. So for the base a new boiler will go into space #4 but there are no prints showing the new piping for new boiler #4. All of the deduct sheets show deduct for new boiler #5. What is correct? |
| Please review the Statement of Bid Item(s) again in the specification 01 00 00 (paragraph 1.3). The Alternate Bid includes demo of one boiler only (#5). The Alternate Bid means boiler #4 stays in place and will need to remain connected to the steam header. The new boiler goes where the old boiler #5 was removed. The revised Amendment 03 drawings show this more clearly. |
| A0003 |
| 9 |
| 10/22/2026 |
| Reference: Specification Sections 01 01 10 (Special Notes) Para. 3.2, 23 05 10, 23 07 11, and 07 01 50.19 |
The specifications reference asbestos abatement in several sections. Section 01 01 10, Para. 3.2 states that inspection reports are available from Facilities Management and refers bidders to Division 2 for abatement requirements. Sections 23 05 10 and 23 07 11 require asbestos insulation removal in accordance with Sections 02 82 11, Traditional Asbestos Abatement, and 02 82 13.13, Glove bag Asbestos Abatement. However, neither Section 02 82 11 nor 02 82 13.13 is included in the specification book, and no asbestos survey, locations, or quantities were provided with the solicitation.
Please clarify the following:
1. Can the VA provide the asbestos inspection/survey report(s) for Building 112, including the boiler plant piping insulation, breeching, stacks, and roofing within the project area?
| There are no asbestos containing materials (ACM) identified for abatement on this project. There may be specification remnants that mention "asbestos" or "ACM", but again there was no expectation for abatement in this contract. The following specification sections/paragraphs do not apply: 01 01 10SN/3.2; 07 01 50.19/1.6A2; 23 05 10/3.6E; and 23 07 11/1.1A3. There are no asbestos inspection or survey reports for Building 112. Boilers #4 and #5 were installed in 2010 and ACM were not allowed. |
| A0003 |
| 10 |
| 10/22/2026 |
| Continue from question 9: |
2. Is asbestos abatement part of the Contractor's scope for this project? If so, please provide the locations and quantities of ACM to be abated, along with Specification Sections 02 82 11 and 02 82 13.13.
See RFI #9 response. There is no ACM abatement expected this project. That being said, if the Contractor believes they come across any material that could be ACM, they should follow their internal safety procedures and immediately notify the VA for testing. Ensure a RFI is filed to track the administration of the issue as well.
There are no asbestos containing materials (ACM) identified for abatement on this project. There may be specification remnants that mention "asbestos" or "ACM", but again there was no expectation for abatement in this contract. The following specification sections/paragraphs do not apply: 01 01 10SN/3.2; 07 01 50.19/1.6A2; 23 05 10/3.6E; and 23 07 11/1.1A3. There are no asbestos inspection or survey reports for Building 112. Boilers #4 and #5 were installed in 2010 and ACM were not allowed.
A0003
| 11 |
| 10/22/2026 |
| Continue from question 9 and 10: |
3. If abatement is required but quantities cannot be confirmed prior to bid, please advise how bidders should account for this work in their bid pricing.
See RFI #9 and #10 response.
There is no ACM abatement expected this project. That being said, if the Contractor believes they come across any material that could be ACM, they should follow their internal safety procedures and immediately notify the VA for testing. Ensure a RFI is filed to track the administration of the issue as well.
There are no asbestos containing materials (ACM) identified for abatement on this project. There may be specification remnants that mention "asbestos" or "ACM", but again there was no expectation for abatement in this contract. The following specification sections/paragraphs do not apply: 01 01 10SN/3.2; 07 01 50.19/1.6A2; 23 05 10/3.6E; and 23 07 11/1.1A3. There are no asbestos inspection or survey reports for Building 112. Boilers #4 and #5 were installed in 2010 and ACM were not allowed.
A0003
| 12 |
| 10/22/2026 |
| Please advise if sales / use taxes are to be included in the bid? |
| MKE bids shall be all inclusive. |
| A0003 |
| 13 |
| 10/22/2026 |
| Please confirm the Site Superintendent CANNOT be the SSHO as well. Dual Hatting will not be permitted on this project? |
| SSHO and Superintendent are two separate individuals, and they are dedicated to THIS PROJECT ALONE. They are both full-time onsite people during work on the contract. They may not act as QCM or PM, either. "CP" refers to competent people and there will be many CPs this project. SSHO and Superintendent shall not be CPs because they are in project management positions and not laborers or performers of actual work. For further clarification, this is directly communicated in the 01 00 00 specification (paragraph 1.4). |
| A0003 |
| 14 |
| 10/22/2026 |
| What is the anticipated award date for this project? |
| Bid states the Government has 90 days after receipt of your bid to make an award. It is anticipated that the award date for this project will be made within the Government’s stated acceptance period. Under certain circumstances, an extension can be requested. |
| A0003 |
| 15 |
| 10/22/2026 |
| When is the “Notice to Proceed” anticipated to be issued? |
| COR will work with GC on mutually agreed upon date after award. |
| A0003 |
| 16 |
| 10/22/2026 |
| When is the anticipated “Start of Construction” for this project? |
| Date of NTP. |
| A0003 |
| 17 |
| 10/22/2026 |
| The solicitation says the contract duration is 455 days (90 for Phase 1 (Pre-Construction) + 275 Phase 2 (Construction) + 90 for Phase 3 (Closeout) = 455 days. Yes Section 01 00 00, section 1.3.E states the POP will be 12 months, EXCLUDING Preconstruction submittals, Pre-construction administration, equipment order / delivery, AND close out administration. See snapshot below. If you add 365 to the 90 days for Phase 1 and the 90 days for Phase 3, the contract duration would be 545 days. Please advise what the contract duration should be? 455 or 545 days? |
| The duration in specification 01 00 00 paragraph 1.3E is incorrect. The full period of performance for this contract is indeed 455 calendar days: 90 + 275 + 90. Paragraph 1.3E has been changed from "12 months" to "275 days". |
| A0003 |
| 18 |
| 10/22/2026 |
| Current economic conditions have resulted in extended lead times on equipment. How will these extended lead times on necessary equipment be accounted for in the contract? |
i. Will all materials be required to be on site prior to starting the project?
ii. Will the contract duration be extended to account for long lead time items?
i. All materials for each task should be on hand before starting work, unless coordinated with the COR. Exceptions may be possible if work can proceed without impacting staff.
ii. Long lead time items have been considered when establishing this project’s period of performance. If the period of performance in this solicitation is not realistic, the bidder shall bring this to the COR and CO’s attention.
A0003
| 19 |
| 10/22/2026 |
| Can you please provide specific procedures for Contractor / Subcontractor badging? It appears there may be a new process and procedures, and timelines for this process. Please provide instructions along anticipated approval process for this to be accounted for by all parties. |
| COR will provide separate badging procedure as appendix to this RFI document. Yes - the process has changed SIGNIFICANTLY. 1) there will be three forms required from each individual contractor person. 2) no more emailing of forms from GC's PM to COR because of full SSNs. 3) VA is issuing PIV badges going forward (the one with the "chip") and not access badges as in the past. Refer to the additional information attached (File named "PIV procedure for KTRs"). |
| A0003 |
| 20 |
| 10/22/2026 |
| It is noted in the specifications that all OSHA 10-hour AND 30-hour training must be completed in the last 5 years. Since the OSHA cards do not expire from OSHA, can the 5-year requirement be waived for the OSHA 10 hr. training? |
| OSHA-10 is good indefinitely. OSHA-30 requires a course certificate showing completion within the past five years. |
| A0003 |
| 21 |
| 10/22/2026 |
| Specification Section 01 32 13.15 does not list the GC as having the option to produce the schedule “in house”. Please confirm this is the case and the contractor must hire a 3rd party schedule consultant? |
| That is correct. The new schedule specification no longer allows the GC to produce or maintain the construction schedule "in house". A 3rd party schedule contractor must be retained by the GC and that 3rd party schedule contractor must have their qualifications vetted by the VA. Refer to paragraph 1.2 of the 01 32 16.15 specification. |
| A0003 |
| 22 |
| 10/22/2026 |
| In Specification Section 01 35 26, section 1.8.E, references a FULL time QCM/Communication Project Manager and references lead telecommunications subcontractor. This conflicts with the CQM as defined in section 01 00 00 Section 1.4.D. Please confirm 01 00 00, 1.4.D is to correct application and that 01 35 26, 1.8.E in N/A to this project. |
| The QCM requirements are correctly identified in the paragraph 1.4D of specification 01 00 00. QCM may be the PM. QCM may be an employee of the GC or the lead mechanical subcontractor. QCM shall have 10 years experience in quality control. The Superintendent or SSHO may not act as the QCM. The QCM (and PM, for that matter) do NOT have to on the project site at all times. And they do NOT need to be dedicated to this project alone. |
The paragraph identified here (01 35 26; 1.8E) has been corrected.
A0003
| 23 |
| 10/22/2026 |
| Section 01 35 26, section 1.8.F notes the CHST / CSP MUST be a 3rd Party? Can the CHST / CSP be an employee of the GC as long as it’s not the SSHO, or the Superintendent, or the Project Manager / QCM? |
| No. CHST/CSP must be an independent 3rd party safety professional that meets the specification requirements. |
| A0003 |
| 24 |
| 10/22/2026 |
| Please confirm a “Construction Sign” and / or a “Safety Sign” are NOT required for this project as they are NOT shown on the drawings. |
| Construction and Safety signs are required. These signage details are reflected correctly in the Amendment 03 drawings sheet GC501. |
| A0003 |
| 25 |
| 10/22/2026 |
| Please confirm the construction fence can be 6’ tall as sated on the drawings and is not required to be 7’ tall as referenced in 01 00 00, section 1.6.K |
| VA will accept a 6ft tall fence. |
| A0003 |
| 26 |
| 10/22/2026 |
| Specification section 01 45 29, section 3.18 lists a significant number of tests that seem to be not applicable to this project. Please advise if this section is correct or needs to be revised to reflect the required tests for this project? If revision is needed – please provide revised section. |
| The majority of the tests designated within 01 45 29 are related to the placement of the exterior concrete pad, as detailed on the Civil drawings. Quantities have been re-evaluated and a revised specification 01 45 29 is included in Amendment 03. |
| A0003 |
| 27 |
| 10/22/2026 |
| Will crane picks for the rigging of HVAC equipment and materials be restricted to federal holidays and weekends? |
| Depending upon the critical details of the lift, most likely they may be accomplished during regular working hours at Bldg. 112. Government reserves the right to shift from regular working hours to off shift, however, if the criticality of the lift makes it safer for off shift. But for bidding/labor purposes, the GCs may use regular working hours for crane work. |
| A0003 |
| 28 |
| 10/22/2026 |
| Do both the Steel Fabricator and the Steel erector need to be AISC certified for this project? |
| See RFI #62 and #63. VA will consider waiving the AISC certification for the steel fabricator and erector. |
| A0003 |
| 29 |
| 10/22/2026 |
| Please confirm the scope of the roofing work is related to patching area at the removed stacks thru the roof as well as patching at the new Guy wire installation and that the whole roof is NOT being removed and replaced. |
| Correct - the whole roof is NOT being removed/replaced. |
| A0003 |
| 30 |
| 10/22/2026 |
| Is the contractor required to hire a Third Party Fire stopping inspector? Or will the VA complete all necessary firestopping inspections on this project? |
| Yes. The GC shall meet the requirements of specification 07 84 00 FIRESTOPPING paragraph 1.5B and 1.5C. Review paragraph 3.5 same specification. Submittals noted in paragraphs 1.3B and 1.3C require qualifications for installers and inspectors. |
| A0003 |
| 31 |
| 10/22/2026 |
| How will existing penetrations in Fire Rated Walls be remediated if they are not fire stopped adequately? |
| There are no identified fire-rated walls that will be impacted on this project in the way this RFI infers. |
| A0003 |
| 32 |
| 10/22/2026 |
| Will the VA shops repair / remediate any existing penetrations that are not properly sealed? |
| Yes, if required, however not expected |
| A0003 |
| 33 |
| 10/22/2026 |
| Please confirm the Commissioning Agent(CxA) and all associated costs for commissioning are being provided and paid for by the VA? |
| There will be a 3rd party commissioning agent on this project funded by the VA and not the GC. That CX agent is already under contract and has participated in the design process. The GC has the responsibility to follow the 01 91 00 specification and the detailed commissioning requirements in the MEP specifications as well. |
| A0003 |
| 34 |
| 10/22/2026 |
| Do the MEPF contractors need to include a specific number of hours for training? If so please advise the number of hours required? |
| Yes. The GENERAL REQUIREMENTS specification 01 00 00 paragraph 1.26 goes into great detail regarding training; a minimum of one 8-hour day is specified for full system training to the entire boiler plant staff. Also, a detailed specification for DEMONSTRATIONS AND TESTS FOR BOILER PLANT exists - 23 08 11 - specifically paragraph 3.6 (28 hrs. min). The GENERAL COMMISSIONING REQUIREMENTS specification 01 91 00 goes into great detail about the Contractor's responsibilities with regards to training and coordination with the Commissioning Agent (CxA) but does not quantify hours. The COMMISSIONING OF HVAC SYSTEMS specification 23 08 00 applies to all Div 23 equipment being commissioned and the training requirements are called out in paragraphs 1.5A and 3.5 but does not quantify hours. The COMMISSIONING OF ELECTRICAL SYSTEMS specification 26 08 00 applies to all Div 26 equipment being commissioned and the training requirements are called out in paragraphs 1.5A and 3.5 but does not quantify hours. Furthermore, refer to the following specifications/paragraphs as well: 07 08 00/3.5; 22 05 11/1.4N and 3.13 (4 hrs min); 22 13 00/1.4G and 3.7 (4 hrs min); 23 05 10/1.4T and 3.15 (4 hrs min); 23 05 12/1.4I and 3.5 (1 hr min); 23 05 51/1.4D; 23 09 11/1.4O and 1.5A and 3.10 (min 16 hrs); 23 10 00/1.4P and 1.5D and 3.16 (4 hrs min); 23 11 23/1.4G and 3.6 (4 hrs min); 23 21 11/1.4F and 3.30 (4 hrs min); 23 50 11/1.4I and 3.5 (4 hrs min); 23 51 00/1.4L and 3.2B3 and 3.7 (4 hrs min); 23 52 39/1.4P and 3.6 (4 hrs min); 26 05 11/1.17. In total, the specifications require at least 89 hours of training. |
| A0003 |
| 35 |
| 10/22/2026 |
| Historically all soils on campus are considered contaminated, are any soils to be removed from the site? If so, are they to be hauled to Orchard Ridge? Is the contractor to include disposal fees (Tipping Fees) in their bid? |
| Any soils removed from the VA grounds shall be assumed to be contaminated with low levels of PAHs and disposed of accordingly. The Contractor may test the soils himself (his cost) to prove via submittal that they are clean if desired. Clean soils do not have to be landfilled at a regulated site (like Orchard Ridge). If the Contractor does not test the soils, they shall be assumed contaminated and will need to be appropriately disposed of at a licensed landfill (like Orchard Ridge). Those are the GC's costs and should be included in the bid. |
The Clement J. Zablocki VA Medical Center (5000 W. National Ave. Milwaukee, WI 53295) is listed on the Wisconsin Department of Natural Resources (DNR) Bureau for Remediation and Redevelopment Tracking System (BRRTS) [BRRTS No. 02-41-563846]. Soils excavated at the Medical Center are typically contaminated with low levels of lead, petroleum volatile organic compounds (PVOCs), and polycyclic aromatic hydrocarbons (PAHs). All soil spoils are assumed to be contaminated unless an exemption is approved. If an exemption from the landfill requirement is desired, the contractor is responsible for all expenses related to sample collection, laboratory analysis, reporting, interpretation of the results, coordinating with the DNR to obtain permission to dispose of soils at a non-licensed landfill or other site. For soil spoils that must be disposed of offsite without an approved exemption from the DNR, the contractor is responsible for obtaining approval from a licensed landfill prior to disposal. The contractor must consult with the Milwaukee VAMC Green Environmental Management System (GEMS) Coordinator at least four weeks prior to shipment of soil spoils offsite so as not to cause any project delays.
A0003
| 36 |
| 10/22/2026 |
| Can any contaminated soils be stockpiled on site for re-use as fill in green space? |
If so, are there any special preparations needed for storage of these materials on site?
Contaminated soils may be temporarily stockpiled for re-use. Temporary is defined as 15-days or less. Stockpiled soils shall be protected with silt fencing at a minimum to prevent washout.
Transport surplus satisfactory soil that will be reused onsite to a designated temporary stockpile on Medical Center property as directed by COR. In accordance with Wis. Admin. Code § NR 718.05(3):
1) Up to 2,500 cubic yards of contaminated soil may be stored in a temporary stockpile.
2) The entire contaminated soil pile shall be located within the project boundaries no more than 1,000 feet from the excavation from which the contaminated soil was removed.
3) The same contaminated soil shall not be stored for more than 15 days.
4) All contaminated soil shall be placed on base material impervious to contaminants in the soil and to water, such as concrete, asphalt, plastic sheeting, or impervious construction fabrics.
5) Surface water contact with the contaminated soil shall be prevented, including the construction of berms, if necessary, to control surface water movement.
6) The contaminated soil shall be covered when it is not being moved, with a cover material sufficient to prevent infiltration of precipitation and to inhibit volatilization of soil contaminants.
A0003
| 37 |
| 10/22/2026 |
| Is the intention to haul nothing off site and re-use all excavated materials on site? |
| This is a means/methods question and the VA will not respond. See response to RFIs # 35 and 36. |
| A0003 |
| 38 |
| 10/22/2026 |
| RFI 1 - Drawing Issue Status |
1. The drawing sets are identified as "100% Construction Documents" dated April 6, 2026; however, multiple sheets are also stamped "PRELIMINARY NOT FOR CONSTRUCTION." Please confirm that Attachments A and B dated April 6, 2026 are the final drawings upon which contractors are to base their bids and subsequent construction. If not, please provide the final IFC/bid set.
| A more current BID SET was prepared by the AE on 4/20/26 and was unfortunately NOT originally uploaded to SAM.gov. Between 4/6/26 (uploaded set) and 4/20/26 the government made a few administrative changes (adjustments to the steam header, overhead door nomenclature, key notes for double-wall new fuel oil piping, roof detail edits, etc.) and added a three sheets (GC501 for signage and two new isometric sheets). That 4/20/26 set will be uploaded as part of the Amendment 03 and the changes from the original 4/6/26 set are clouded to aid the Contractor in quickly identifying where the drawings were changed. Additional changes required as part of this RFI document are also clouded. |
| A0003 |
| 39 |
| 10/22/2026 |
| RFI 2 - Utility Shutdown Durations and Work Hours |
2. Please provide the maximum allowable duration and permitted work hours for shutdowns of steam, boiler feedwater, condensate/return, natural gas, fuel oil, compressed air, electrical power, and boiler plant controls required to execute the work. Identify any shutdowns that must occur nights, weekends, or during specific seasonal operating conditions, and state the required advance notification period for each.
| The expectation is that the crux of the connection and outage work would be in the summer cooling months when steam demand is at its lowest. VA will not allow any steam outages during the winter season (roughly mid Oct thru mid Apr). Other utilities can be rotated to accommodate outages (i.e., the operating boilers can run on fuel oil while the Contractor is working on the natural gas lines). Recent projects upgraded panels and power is separated enough that we should not have any electrical issues that would impact this project. If a full steam outage and boiler plant shut down is required it would have to be coordinated to a holiday like Juneteenth day or Labor Day. |
| A0003 |
| 40 |
| 10/22/2026 |
| RFI 3 - Boiler Plant Capacity and Temporary Steam |
3. Please confirm whether the remaining existing boilers provide sufficient capacity and redundancy during all phases of construction. If temporary steam generation, temporary piping, temporary controls, temporary fuel connections, or other temporary utility services are required to maintain plant operation during any shutdown or cutover, identify the required capacity, pressure, connection points, and responsibility for providing that equipment.
| See also RFI #111. Boilers #1/#2/#3 will provide sufficient steam capacity during the work on Boilers #4 and #5. Temporary steam generation to include piping, controls, fuel connections, utilities or other temporary provisions are NOT required in the GC's bid. |
| A0003 |
| 41 |
| 10/22/2026 |
| RFI 4 - Emergency Boiler Connections |
4. Drawing GC101 requires the Contractor to maintain 24/7 access to emergency boiler connections throughout construction. Please identify the emergency boiler connection location(s), required clearances, and access route that must be maintained 24/7.
5. Please confirm whether the Contractor is required only to maintain physical access or whether temporary piping, connections, utilities, or provisions for hookup of a temporary boiler are also required.
| The Contractor shall ensure the VA has 24/7 access to the emergency boiler connections at the north side of the Bldg. 112. In the event that temporary boilers are needed, VA would just need to be able to get a temp boiler around the Contractor through the grass to get to that location at the rear of the building. Temporary piping, controls, fuel connections, utilities or other temporary provisions by the GC are NOT required. |
| A0003 |
| 42 |
| 10/22/2026 |
| RFI 5 - Steam Piping Hydrostatic and Operational Testing |
6. The specifications require boiler external steam piping to receive a hydrostatic test at 1.5 times design pressure and require steam piping, prior to insulation, to be exposed to steam at final operating pressure. Please identify which portions of new steam piping are considered "boiler external steam piping" requiring hydrostatic testing at 1.5 times design pressure.
7. For each new or modified steam system, please confirm the required hydrostatic and operational test limits, test medium, test pressure, duration, witnessing requirements, and required documentation.
| Boiler external steam piping requiring hydrostatic testing extends from the boiler steam outlet nozzle through the new steam header to the 8-inch HPS connection at the existing valve shown on the drawings. As the design pressure of the piping to be tested is 100 psig, hydrostatically test the new boiler external steam piping with water at 150 psig, in accordance with the applicable ASME requirements and specification 23 21 11. Maintain test pressure for at least 10 minutes, then reduce pressure to design pressure for leak inspection. Before insulation, perform the operational test by exposing the steam piping to steam at final operating pressure and inspecting all joints and connections for leaks and workmanship. |
| A0003 |
| 43 |
| 10/22/2026 |
| RFI 6 - Weld Examination and NDE Requirements |
8. Specification Section 23 21 11 requires piping fabrication and installation in accordance with ASME B31.1 and references inspection of piping welds. Please confirm whether nondestructive examination (NDE) beyond the examinations required by ASME B31.1 is required for field or shop welds on this project.
9. If additional NDE is required, please identify the applicable piping systems, examination method, percentage of welds to be examined, and acceptance criteria.
| In addition to examinations required by ASME B31.1, specification 23 21 11 requires radiographic examination of 50% of the first ten (10) piping welds made by each welder and 10% of all additional welds made by each welder on Steam and Condensate Piping. Welds shall also be visually inspected by the COR or the COR’s representative in the presence of the Superintendent. The specification does not distinguish between shop and field welds. An ASNT Certified Level III radiographer employed by the GC or mechanical contractor shall interpret and sign the reading report. Acceptance shall comply with ASME B31.1. |
| A0003 |
| 44 |
| 10/22/2026 |
| RFI 7 - 30-Day Monitoring Period |
10. Please define the requirements of the 30-day monitoring period, including whether continuous Contractor or controls-vendor personnel are required onsite, required trending and reporting, response-time requirements, permitted system interruptions, criteria for restarting the 30-day period following a failure, and the point at which substantial completion may be achieved.
| GC shall complete startup, safety device testing, training, and required backup fuel and emergency generator tests before this 30-day monitoring period begins. Continuous GC or controls vendor staffing onsite is not required. VA operators may operate the boiler under the conditions in specification 23 05 10, paragraph 3.12.F. The Contractor shall respond onsite within four hours of a reported fault. The boiler plant systems shall operate for 30 continuous days without contractor attributable faults or shutdowns. Correct faults and retest affected safety devices before restarting the period. The VA will determine whether interruptions beyond the Contractor’s control require a restart. Submit an operating and event log at the end of the period. A revised specification is included in Amendment 03 to change the monitoring period from 21-days to 30-days. |
| A0003 |
| 45 |
| 10/22/2026 |
| RFI 8 - Scrap-Value Credit |
11. The mechanical demolition drawings instruct the Contractor to coordinate with the VA to provide scrap-value credit to the Owner for removed equipment. Please clarify the required method for determining and crediting scrap value for removed boilers, piping, and equipment.
12. Please confirm whether bidders should deduct an estimated scrap value in the bid or whether actual documented scrap proceeds will be credited after demolition.
| Before removing equipment, coordinate with the COR. The COR will coordinate with VA Boiler Plant Staff regarding items to be retained, the scrap disposition process and how to handle credits. Do NOT deduct an estimated scrap value from the bid. Include demolition and removal in the bid. |
| A0003 |
| 46 |
| 10/22/2026 |
| RFI 9 - Boiler Startup, Testing and Commissioning Responsibilities |
13. Please clarify responsibility for providing manufacturer and controls-vendor representatives, technicians, instrumentation, temporary connections, equipment, and other services necessary to complete required boiler startup, burner tuning, safety-device testing, pretesting, performance testing, and final commissioning.
14. Please also clarify how the required boiler operating loads will be established for testing and identify any testing or commissioning services furnished directly by the VA.
| The Contractor shall provide the manufacturer’s and controls vendor representatives, qualified technicians, calibrated instruments, special tools, temporary connections, and other labor, materials, and equipment required for boiler startup, burner tuning, safety device testing, pretesting, and VA-required commissioning by the third party CxA. Establish boiler test loads using the hospital steam system, the steam silencer vent, or a combination of both, as per specification 23 52 39. The COR and CxA will witness final tests. The CxA will observe selected startup activities and contractor testing as planned. |
| A0003 |
| 47 |
| 10/22/2026 |
| RFI 10 - Existing Structural and Miscellaneous Steel |
15. Existing structural and miscellaneous steel framing, platforms, grating, ladders, and supports are located around Boilers 4 and 5 and the associated venting/stack systems. Please clarify which existing steel is to be removed, reused, modified, or remain in place as part of the new work. If any existing steel is intended for reuse, please identify the components and their intended use.
| None of the existing steel associated with support of the current boilers 4 & 5 stack and/or economizers is intended for reuse on the new boilers. Additionally, none of the existing catwalks/access platforms for boilers 4 & 5 are intended for reuse on the new boilers. Modifications have previously been made to the support steel on the underside of the roof, allowing for the existing stack penetration; that steel is intended to remain in place. |
| A0003 |
| 48 |
| 10/22/2026 |
| Please confirm this is not a sales tax-exempt project. |
A. If sales tax-exempt, will the government provide the prime contractor with a tax-exempt certificate for use by subcontractors and vendors?
| MKE bids shall be all inclusive. |
| A0003 |
| 49 |
| 10/22/2026 |
| If a Prime Contractor is awarded multiple projects at the same VA Medical Center location: |
Can the Superintendent be shared across multiple projects at the same site/location, or should they only be dedicated full-time to this project only?
| Please refer to the 01 00 00 specification. The Superintendent for this project MAY NOT superintend anywhere else on the campus. The Superintendent must be 100% for this construction contract. |
| A0003 |
| 50 |
| 10/22/2026 |
| Is a Quality Control Manager a requirement for this project? |
A.If a QCM is required, please provide specification 01 45 00.
B.Can the Superintendent also serve as the QCM?
C.Can the SSHO also serve as the QCM?
D.Is the QCM required to be onsite full-time, or can they make site visits as required for inspections?
E.If the QCM is required to be onsite full-time, should they be assigned to this project only, or can they be assigned to another project as well on the same property?
F.Section 01 00 00, 1.4D, permits a qualified Project Manager to serve as QCM, while Section 01 35 26, 1.8E, requires separate personnel. Please confirm whether the PM may also serve as QCM.
Please refer to the 01 00 00 specification. This was also answered previously in RFIs #6, #13, and #22. A QCM is required but VA has opted to not include the 01 45 00 specification. Meet QCM requirements as noted in 01 00 00. It is the government's position that most Project Managers can fulfill the role of QCM. The QCM (and PM, for that matter) do NOT have to on the project site at all times. And they do NOT need to be dedicated to this project alone. The Superintendent and the QCM are two different individuals. The SSHO and the QCM are two different individuals.
SSHO and Superintendent are two separate individuals. They are both full-time onsite persons during work on the contract. SSHO and Superintendent shall not be CPs because they are in project management positions and not laborers or performers of actual work. For further clarification, this is directly communicated in the 01 00 00 specification (paragraph 1.4).
The QCM requirements are correctly identified in the paragraph 1.4D of specification 01 00 00. QCM may be the PM. The QCM (and PM, for that matter) do NOT have to on the project site at all times. And they do NOT need to be dedicated to this project alone. QCM may be an employee of the GC or the lead mechanical subcontractor. QCM shall have 10 years experience in quality control. The Superintendent or SSHO may not act as the QCM. The paragraph identified here (01 35 26; 1.8E) has been corrected.
A0003
| 51 |
| 10/22/2026 |
| Can the Superintendent also serve as the SSHO? |
A. Is the SSHO required to be on-site full-time, or can they visit the site daily for safety inspections?
B. Please confirm the SSHO shall be dedicated to this project alone.
Please refer to the 01 00 00 specification. This was also answered previously in RFIs #6 and #13.
SSHO and Superintendent are two separate individuals, and they are dedicated to THIS PROJECT ALONE. They are both full-time onsite people during work on the contract. SSHO and Superintendent shall not be CPs because they are in project management positions and not laborers or performers of actual work. For further clarification, this is directly communicated in the 01 00 00 specification (paragraph 1.4).
The Superintendent or SSHO may not act as the QCM.
A0003
| 52 |
| 10/22/2026 |
| Section 01 00 00, 1.4C, permits the Superintendent to be employed by the lead mechanical subcontractor, while Section 01 35 26, 1.8B, requires a GC employee. Please confirm which requirement governs. |
| The paragraph identified here (01 35 26; 1.8B) has been corrected. It is the government's position that the Superintendent can be an employee of the General Contractor OR the lead Mechanical Contractor as long as the qualifications are met per the 01 00 00 specification paragraph 1.4C. |
| A0003 |
| 53 |
| 10/22/2026 |
| Is badging required for the project? |
| Yes. Refer to RFI #19. The government will include a thorough and new badging procedure as part of the Amendment 03 (see "PIV procedure for KTRs" PDF file included in Amendment 03). |
| A0003 |
| 54 |
| 10/22/2026 |
| Are fingerprinting and background checks required for this project? |
| Yes. Refer to RFI #19 and #53. The government will include a thorough and new badging procedure as part of the Amendment 03 which included fingerprinting and background checks (see "PIV procedure for KTRs" PDF file included in Amendment 03). |
| A0003 |
| 55 |
| 10/22/2026 |
| Please confirm if influenza vaccines are required for all contractors and subcontractors’ employees who work on the site or if masks will be required. |
| Yes - influenza vaccines are required. If there are medical exceptions, documented by a physician, or deeply held religious beliefs, verified by a supervisor, we would allow masked at all times through influenza season per VHA Directive 1192.01. |
| A0003 |
| 56 |
| 10/22/2026 |
| Given the complexity of the required submittals, will the VA consider extending the 90-day preconstruction period if additional time is needed for review and approval? |
| POP timeframes have considered time for complex submittals. It is in the GC's best interest and responsibility to communicate any issues with due dates. Extension may be granted. |
| A0003 |
| 57 |
| 10/22/2026 |
| Given the anticipated long lead times for the new boiler and associated equipment, will the VA consider extending the 455-day POP to accommodate procurement and delivery following submittal approval? |
| Yes. If the GC can make a strong case after submittal approval that more time is required after conferring with the supplier/vendor. |
| A0003 |
| 58 |
| 10/22/2026 |
| Once awarded, will the VA provide an Administrative NTP to allow time for subcontracts to be executed, GC & Subs to work together to develop a project schedule, provide SF1413s, and prepare other Division 1 submittals? |
| No Administrative NTP. |
| A0003 |
| 59 |
| 10/22/2026 |
| Once awarded, if the VA will not provide an Administrative NTP, will the VA allow up to 90 days between the kickoff meeting and the NTP? |
| NTP will be a day/time that GLAC, GC and COR can agree to as soon after award as practical. POP starts at NTP. Formal construction kickoff meeting will be scheduled late in the pre-construction period. |
| A0003 |
| 60 |
| 10/22/2026 |
| Please provide the point of contact information for the BMS integration contractor. |
| BMS (Building Management System) integrator is Johnson Controls, Inc for HVAC controls (Metasys). Point of contact is Scott R Galaszewski <scott.r.galaszewski@jci.com>. |
| A0003 |
| 61 |
| 10/22/2026 |
| Please provide the point of contact information for the Fire Alarm integration contractor. |
| Fire Alarm integrator is Systec. Point of contract is Scott Wrenn <scottw@systecltd.com>. |
| A0003 |
| 62 |
| 10/22/2026 |
| Given the limited structural steel scope, will the VA consider waiving the AISC certification requirements for structural steel fabrication and erection? These requirements significantly limit subcontractor participation and increase costs. |
| See RFI #28 and #63. VA will consider waiving the AISC certification for the steel fabricator and erector. |
| A0003 |
| 63 |
| 10/22/2026 |
| If AISC certification is required, will the VA accept alternative qualifications, such as documented relevant experience and AWS-certified welding personnel, in lieu of AISC certification? |
| See RFIs #28 and #62. yes, VA COR will accept alternate qualifications, such as documented relevant experience and AWS-certified welding personnel in lieu of the AISC certification. These qualifications, experiences, and certifications will be reviewed by the AE and VA to determine acceptability. |
| A0003 |
| 64 |
| 10/22/2026 |
| Please confirm the required ICRA levels for each phase and area of construction. If ICRA barriers are required, please provide drawings identifying the locations, extents, and required barrier types. |
| Although Building 112 is not a patient-care area and is not routinely occupied by Veterans or visitors, the project should undergo a documented, multidisciplinary Infection Control plan before demolition begins. The absence of patients in the immediate work area may reduce the infection-control risk; however, it does not automatically eliminate the need for an ICRA or establish that barriers, dust controls, or airflow controls are unnecessary. The assessment will consider: (1) The extent of demolition and removal of the north wall; (2) Potential migration of dust and debris into occupied areas or adjacent buildings; (3) Air intakes, exhausts, doors, penetrations, and shared or interconnected HVAC systems; (4) Protection of existing-to-remain boiler systems, controls, piping, valves, pumps, and other equipment; (5) Staff access and exposure during each phase; (6) Construction traffic and debris-removal routes; (7) Required cleaning and inspection before areas or equipment are returned to service; (8) Potential asbestos, lead, mold, or other regulated materials, as applicable; and (9) Coordination with Facilities Management, Safety/Industrial Hygiene, Fire/Life Safety, Environmental Management Service, and the General Contractor. Infection Prevention cannot preassign an ICRA level or approve the absence of controls without reviewing the contractor’s complete phasing and infection-control plan. The Infection control requirements should be based on the project scope, work practices, adjacency, airflow, duration, and identified risks. Controls may be less stringent than those required for construction adjacent to patient-care areas, but they must be clearly documented. At a minimum, the contractor’s plan should address dust and debris containment, protection of existing equipment, controlled access, worker and material movement, debris removal, cleaning, and procedures for responding to an unanticipated release of dust or debris. Fans should not be used in a manner that disperses contaminants toward occupied spaces, air intakes, or existing equipment. Any proposed negative-air or ventilation strategy should be reviewed with Facilities/HVAC and Safety. |
| A0003 |
| 65 |
| 10/22/2026 |
This is the start of the file's text. The full file is on GovTribe.