This document contains a request for proposal for construction services. The solicitation seeks proposals to renovate approximately 4,750 square feet of an existing main laboratory and construct a new 6,900 square foot addition at a Veterans Affairs medical center in Lebanon, Pennsylvania. Work will be completed in phases and includes construction of floors, walls, ceilings, mechanical and electrical systems. Offerors must submit details on up to three relevant past performance examples and identify any subcontractors to be used. Proposals are due by the date specified in Amendment 0007 to the solicitation. The selected contractor will provide all labor, materials and equipment to complete the project in accordance with drawings and specifications for the Department of Veterans Affairs Veterans Health Administration Veterans Integrated Service Network 4.

View the file

Other files

File Type Posted
36C24421R0018 0007_1.docx DOCX document
SITE-01.pdf PDF
Section 221100 - Facility Water Distribution.pdf PDF
SITE-02.pdf PDF
Addendum 01 with Attachments to Specifications and Drawings.pdf PDF
RFI document for Amendment 0007.pdf PDF
36C24421R0018 0006_1.docx DOCX document
36C24421R0018 0005_1.docx DOCX document
36C24421R0018 0004_1.docx DOCX document
RFI Questions and Answers.pdf PDF
36C24421R0018 0003.pdf PDF
Pre-proposal Roster of Attendees for 12-14 and 12-30 Visits.pdf PDF
36C24421R0018 0003_1.docx DOCX document
36C24421R0018 0002_1.docx DOCX document
Sign In Roster from Pre-Bid 12-14-2020 595-667- Construct New Lab.pdf PDF
36C24421R0018 0001_1.docx DOCX document
100 Specifications - Full Set.pdf PDF
Solicitation Attachment Specification100 Vol.1.pdf PDF
Solicitation Attachment EXHIBIT B - Subcontractor Information and Consent Form Expand Lab 595-667.pdf PDF
Solicitation Attachment Specification 100 Vol.2.pdf PDF
36C24421R0018_2.docx DOCX document
Solicitation Attachment JA - Fire Alarms Signed.pdf PDF
Solcitation Attachment JA - Security System Signed.pdf PDF
Solicitation Attachment EXHIBIT D -Transmittal Letter for Past Performance Evaluation Questionnaire 595-667 Expand Lab.pdf PDF
Solicitation Attachment EXHIBIT C - Calculation of Self-Performed Expand Lab.pdf PDF
Solicitation Attachment EXHIBIT E - Past Performance Questionnaire Expand Lab.pdf PDF
36C24421R0018.pdf PDF
Solcitation Attachment JA - HVAC Controls Signed.pdf PDF
Solicitation Attachment JA - Locksets Signed.pdf PDF
Solcitation Attachment Drawings 595-667 FULL SET.pdf PDF
Solicitation Attachment Wage Determination.pdf PDF
Show all 31

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Request for Proposal, Solicitation 36C24420R0084 Expand Laboratory Construction, Project 595-667

PART 1: Prepare no more than three (3) Part 1 forms:

Provide the following information requested in this format for each of the projects/contracts being described. Projects may be on going and cannot have been completed any later than 5 years prior to the solicitation issue date. Provide frank, concise comments regarding YOUR PERFORMANCE on the contracts you identify. Use additional space as required.

A. Offeror (Your) Name (Company/Division):

B. Project/Contract Title:

C. Contract Specifics:

1. Description of Effort as Prime or _Subcontractor

2. Contract Number

3. Original Contract $ Value Current/Final Contract $ Value

4. If amounts in 3 above are different, provide a brief description of the reason:

5. Completion Date:

1. Original Date:

2. Current Schedule: _____________________

3. Estimate/Final Completion Date:

4. Primary cause for Contract Modifications

D. Provide detailed description of the work performed under the contract and describe why you believe the work is very relevant, relevant or semi-relevant to this solicited project.

(Use as much space as necessary)

In addition, address the following

1. Describe the specific elements of the work performed by your firm.

2. Indicate what elements of work were performed by your major subcontractors and indicate if those same subcontractors will be used on projects awarded under this solicitation. Should you intend to use these same subcontractors, please list their company names and described their principal areas of work that they will perform.

3. Address any technical areas about this project you consider uniquely relevant to this solicitation.

E. Point of Contact for Owner/Government agency Contracting Officer and or inspector (COR / COTR); include a current phone number and email address for each.

End of Part 1- Questionnaire Requirements – Prepare and send Exhibit C Package to the reference(s) for each of the no more than three Construction Projects, or Specialty Trade if applicable provided in Exhibit A, Part 1. See below for Exhibit A, Part 2.

Part 2: Additional offeror information required.

A. Name subcontractors and/or Teaming Partners to be utilized on this contract. Multiple subcontractors may be named for the same discipline but are limited to a maximum of three (3) subcontractors per discipline. As a minimum, provide the name(s) of subcontractors to be utilized in the following areas:

(Specialty Trades will address their specific trade for any major subcontractor or Teaming partner)

Request for Proposal, Solicitation 36C24420R0084 Expand Laboratory Construction, Project 595-667
PART 1: Prepare no more than three (3) Part 1 forms:
End of Part 1- Questionnaire Requirements – Prepare and send Exhibit C Package to the reference(s) for each of the no more than three Construction Projects, or Specialty Trade if applicable provided in Exhibit A, Part 1. See below for Exhibit A, Part 2.