Scenario 2_SOW_CoolingTowerRebuild.pdf
PDF 369 KB Posted
- Attached to
- Task Order Agreement for Cooling Tower Maintenance & Repair Services at Brookhaven National Laboratory
- Solicitation number
- SJ453282
- Issued by
-
Department of Energy Office of Science
About this file
This Statement of Work details requirements for demolition and replacement of components for a 275-ton Marley TQ8304E-1GM cooling tower at Building 488 of Brookhaven National Laboratory. The cooling tower, installed in 2005, supports the facility's cafeteria and meeting rooms by rejecting heat from water-cooled chillers in the basement.
The contractor must provide safety barriers, scaffolding, rigging plans, demolition, and installation services between November 2024 and February 2025 during normal working hours (8:00am-4:30pm). Specific tasks include replacing the 15HP fan motor, gear reducer assembly, fill/drift eliminators, hot water basin, nozzles, horizontal control valves, hanging probe, fill valve, and tower fan. The contractor must attend pre-bid walkthrough, complete required safety training (including fall protection, LOTO, confined space), and return the area to original condition upon completion. BNL will directly purchase the manufacturer parts, while the contractor is responsible for procuring ancillary materials. The cooling tower is classified as a 2A confined space requiring proper safety protocols and lockout/tagout procedures.
View the file
Other files
Show all 16
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
P.O. Box 5000
Upton, NY 11973-5000 managed by Brookhaven Science Associates for the U.S. Department of Energy
STATEMENT OF WORK
I. TITLE – STATEMENT OF WORK FOR THE REBUILD OF BUILDING 488’S 275 TON
COOLING TOWER
II. SCOPE
Under this contract BNL expects the selected vendor to provide service to complete full demolition and replacement of the following components already for a 275 ton Marley TQ8304E-1GM cooling tower; S/N 805496X. The cooling tower is located outside of the facility at ground level, with ample access for maintenance, photos below.
Actual cooling tower and parts storage location
- 2 -
Ground view of tower, noting ground obstruction (red)
The vendor shall provide all safety barriers, scaffolding, a rigging detailed rigging plan, demolition, and installation work to complete the cooling tower maintenance, while conforming to the requirements of BNL safety work package that is develop with the selected vendor upon award of the contract.
Work is expected to be performed during normal BNL working hours 8:00am to 4:30pm.
Work will not be permitted, nights, weekends, or holidays unless vendor receives written permission from BNL Energy and Utilities division. The work is expected to be completed during the tower’s off season between November 2024 and February of 2025.
III. Background
B488, the Berkner Hall facility is a staff support facility supporting BNL’s cafeteria, and several large meeting rooms. The water cooled chillers are located in the basement of B488, heat is rejected at a single cell Trane-branded, Marley model induced draft cooling tower located on the west side of the building.
The cooling tower was installed in 2005, since installation there have been no major overhauls or fill replacements. After almost 20 years this critical service is necessary for the continued operation of the chiller. The cooling tower is assessed as a predetermined 2A confined space, with a LOTO in place and no hazards introduced (Chemicals, sprays, solvents, torch work, grinding) no atmospheric testing is required.
- 3 -
IV. TASKS AND REQUIREMENTS
The scope includes the execution of the following tasks:
1) All vendors are required to attend a pre-bid walkthrough, date and time to be determined.
2) Vendor Access/Training Required
a) All team members requiring site access shall register with the GUV center, and attend, at minimum a remote 2-hr Contractor/Vendor Orientation training.
3) Perform Site Safety Walkthrough with BNL Safety and complete a Job Hazard Analysis
a) Any training requirements identified during the safety walk through, and job hazard analysis are required to be completed prior to any worker performing work. Trainings are likely to include:
i) Fall Protection
ii) LOTO
iii) Confined Space
iv) Ladder Safety
v) Scaffold User Safety
4) Set up safety barriers around sky lights and building edge
5) Install scaffolding around tower work areas to facilitate all required work
6) Perform all demolition work required to execute the cooling tower rehabilitation, including the removal of construction debris.
7) Install the cooling tower rebuild kits purchased by BNL directly from the manufacturer per manufacturer assembly instructions, and industry best practices, including all necessary rigging of equipment. All expected subtask descriptions, including parts procured by BSA are shown in the following table, any materials ancillary to the parts list below shall be the responsibility of the contractor to procure.
Subtask Description Marley Part Qty Description 1 75 Ton 15 HP Fan
Motor Removal Replacement, Balancing and Start-up
041574 1 AC Electric Motor, Horsepower: 15, Phase: 3, Cycle: 60, Voltage: 230/460, Speed: 1800, Service factor: 1.15, Enclosure: TEFC, Frame size: 254T Horizontal foot mounted, Premium efficiency
2 275 Ton Cooling Tower Gear Reducer Assembly Removal Replacement, Balancing and Start-up
C68400 1 Geareducer assembly, 2000 Series, 4.80 ratio, CC2 fan shaft, Marley gray epoxy paint
C24687 1 Series 22.1T, 22.2, 22.3, 2200, 2250 and 2400, hardware and shims for securing gear box to mounting base. This kit also works for the series 20, 20T, 20.1, 20.2, 1800 and 2000.
A76772 3 Oil Synthetic, ISO 150, 1 Gallon container 3 275 Ton Cooling Tower
Fill/Drift Eliminator Overhaul (removal and replacement of fill partitions, fill, splice tubes, telescopic rods / fill hanging assembly, and all hardware)
FAPBRANDED1 1 Tower Model:NC8304 Replacement galv fill partition, pricing includes find#B13, B15, and all attaching hardware to install, per cell.
FAPBRANDED1 1 Tower Model NC8304, MX75 20mil fill replacement includes 20mil fill sheets, splice tubes(to splice cut tubes back together) and all hardware to install, per cell.
- 4 -
Subtask Description Marley Part Qty Description 4 275 Ton Cooling Tower
Hot Water Basin Removal and Replacement (including covers)
D45479 1 Tower Model (box size) NC8304, Galvanized Hot Water Basin replacement includes 2 unassembled basins, sealer, and hardware to install, per cell. Nozzles, gaskets and basin covers are not included, but nozzles are required.
D45725 1 Tower Model (box size) NC8304, Galvanized Hot Water Basin Covers with hardware to install, per cell.
5 275 Ton Cooling Tower Nozzle Removal and Replacement
D44542 152 Spiral Target Crossflow Nozzle 68-3738-45
6 275 Ton Cooling Tower Horizontal Control Valve Removal and Replacement
778738 2 Gasket for 6-inch Diameter HC Valves (1 req'd per valve). Located between valve and pipe. Note:
8600 through 210 towers, 2 Gaskets are required.
221481 2 Full-Face Gasket for 6-inch Diameter HC Valves (1 req'd per valve). Located between valve and top of basin.
03834 2 Hardware to attach 6" flanged HC valve to inlet piping. Each quantity includes hardware for 1 HC valve.
7 275 Ton Cooling Tower Hanging Probe and Fill Valve Removal and Replacement
378554 1 VALVE 1"DIA VALVE
2088585 1 VALVE 16" STEM - Replaces 378752 Bronze version that was used previously.
045302 1 VALVE 8"DIA COPPER FLOAT
2065269 1 CONTROL LLC+c HANGING PROBE SET 30
FEET, MU 14 15 REF 13
8 275 Ton Cooling Tower
Fan Removal, Replacement, Balancing and Start-up
N/A 1 Tower Fan
8) Return surrounding area to original condition at start of project.
V. SIGNATURE AND DATE
____________________________ October 29, 2024
| Description |
| Qty |
| Marley Part |
| Description |
| Subtask |
| AC Electric Motor, Horsepower: 15, Phase: 3, Cycle: 60, Voltage: 230/460, Speed: 1800, Service factor: 1.15, Enclosure: TEFC, Frame size: 254T Horizontal foot mounted, Premium efficiency |
| 1 |
| 041574 |
| 75 Ton 15 HP Fan Motor Removal Replacement, Balancing and Start-up |
| 1 |
| Geareducer assembly, 2000 Series, 4.80 ratio, CC2 fan shaft, Marley gray epoxy paint |
| 1 |
| C68400 |
| 275 Ton Cooling Tower Gear Reducer Assembly Removal Replacement, Balancing and Start-up |
| 2 |
| Series 22.1T, 22.2, 22.3, 2200, 2250 and 2400, hardware and shims for securing gear box to mounting base. This kit also works for the series 20, 20T, 20.1, 20.2, 1800 and 2000. |
| 1 |
| C24687 |
| Oil Synthetic, ISO 150, 1 Gallon container |
| 3 |
| A76772 |
| Tower Model:NC8304 Replacement galv fill partition, pricing includes find#B13, B15, and all attaching hardware to install, per cell. |
| 1 |
| FAPBRANDED1 |
| 275 Ton Cooling Tower Fill/Drift Eliminator Overhaul (removal and replacement of fill partitions, fill, splice tubes, telescopic rods / fill hanging assembly, and all hardware) |
| 3 |
| Tower Model NC8304, MX75 20mil fill replacement includes 20mil fill sheets, splice tubes(to splice cut tubes back together) and all hardware to install, per cell. |
| 1 |
| FAPBRANDED1 |
| Tower Model (box size) NC8304, Galvanized Hot Water Basin replacement includes 2 unassembled basins, sealer, and hardware to install, per cell. Nozzles, gaskets and basin covers are not included, but nozzles are required. |
| 1 |
| D45479 |
| 275 Ton Cooling Tower Hot Water Basin Removal and Replacement (including covers) |
| 4 |
| Tower Model (box size) NC8304, Galvanized Hot Water Basin Covers with hardware to install, per cell. |
| 1 |
| D45725 |
| Spiral Target Crossflow Nozzle 68-3738-45 |
| 152 |
| D44542 |
| 275 Ton Cooling Tower Nozzle Removal and Replacement |
| 5 |
| Gasket for 6-inch Diameter HC Valves (1 req'd per valve). Located between valve and pipe. Note: 8600 through 210 towers, 2 Gaskets are required. |
| 2 |
| 778738 |
| 275 Ton Cooling Tower Horizontal Control Valve Removal and Replacement |
| 6 |
| Full-Face Gasket for 6-inch Diameter HC Valves (1 req'd per valve). Located between valve and top of basin. |
| 2 |
| 221481 |
| Hardware to attach 6" flanged HC valve to inlet piping. Each quantity includes hardware for 1 HC valve. |
| 2 |
| 03834 |
| VALVE 1"DIA VALVE |
| 1 |
| 378554 |
| 275 Ton Cooling Tower Hanging Probe and Fill Valve Removal and Replacement |
| 7 |
| VALVE 16" STEM - Replaces 378752 Bronze version that was used previously. |
| 1 |
| 2088585 |
| VALVE 8"DIA COPPER FLOAT |
| 1 |
| 045302 |
| CONTROL LLC+c HANGING PROBE SET 30 FEET, MU 14 15 REF 13 |
| 1 |
| 2065269 |
| Tower Fan |
| 1 |
| N/A |
| 275 Ton Cooling Tower Fan Removal, Replacement, Balancing and Start-up |
| 8 |
File details come from the government source that posted it. Updated .