Scenario 1 _SOW_CoolingTowerRebuild.pdf

PDF 525 KB Posted

Attached to
Task Order Agreement for Cooling Tower Maintenance & Repair Services at Brookhaven National Laboratory
Solicitation number
SJ453282
Issued by

About this file

This Statement of Work outlines requirements for rebuilding Cell 4 of the B600 North Cooling Tower (1700 ton BAC S3E-1424-14T-4/E) at Brookhaven National Laboratory, to be completed between November 2024 and February 2025 during normal working hours (8:00am-4:30pm). The work requires full demolition and replacement of multiple cooling tower components including a 100HP fan motor, gear reducer assembly, fill/drift eliminators, hot water basin, nozzles, control valves, hanging probe, and fan. The contractor must provide safety barriers, scaffolding, rigging plans, and handle all demolition and installation while following BNL safety protocols.

The work involves 8 major tasks including required safety training, site preparation, component replacement, and site restoration. Specific parts and materials have been pre-purchased by BNL directly from the manufacturer, though ancillary materials are the contractor's responsibility. The cooling tower, installed in 2007, requires this maintenance due to continuous operation, poor water quality, and chemical treatment issues that shortened component life. The work supports the Department of Energy's Brookhaven National Laboratory central chilled water facility, which operates four water-cooled centrifugal Trane chillers on an isolated condenser water loop.

View the file

Other files

Show all 16

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

P.O. Box 5000

Upton, NY 11973-5000 managed by Brookhaven Science Associates for the U.S. Department of Energy

STATEMENT OF WORK

I. TITLE – STATEMENT OF WORK FOR THE REBUILD OF B600 NORTH COOLING

TOWER CELL 4 – 1700 TON

II. SCOPE

Under this contract BNL expects the selected vendor to provide service to complete full demolition and replacement of the following components already for a 1700 ton BAC S3E-1424-14T-4/E cooling tower cell; S/N U163944204-01-04. The cooling tower is located outside of the facility elevated above ground level and may required scaffolding on the east face to complete, due to soft terrain limiting the mobility of lifts.

Arial view of cooling tower and parts storage location

North

- 2 -

Ground view of tower (cell is furthest to the right)

The vendor shall provide all safety barriers, scaffolding, a rigging detailed rigging plan, demolition, and installation work to complete the cooling tower maintenance, while conforming to the requirements of BNL safety work package that is develop with the selected vendor upon award of the contract.

Work is expected to be performed during normal BNL working hours 8:00am to 4:30pm.

Work will not be permitted, nights, weekends, or holidays unless vendor receives written permission from BNL Energy and Utilities division. The work is expected to be completed during the towers low load season between November 2024 and February of 2025.

III. Background

The central chilled water facility is the primary chilled water facility supporting BNL’s central cooling system. On the ground floor of the North side of the plant, four water cooled centrifugal Trane chillers are operate on a condenser water loop isolated from the loop serving the south towers. Heat is rejected at a four cell BAC cooling tower, elevated off the ground to increase the NPSH for pumping.

- 3 -

The cooling tower cells were installed in 2007, since installation there have been no major overhauls or fill replacements but continuous (all-season) operation, poor water quality, and chemical treatment issues have shortened the life of all of the critical components. After only 8 years this critical service is necessary for the continued operation of Cell-4. The cooling tower is assessed as a predetermined 2A confined space, with a LOTO in place and no hazards introduced (Chemicals, sprays, solvents, torch work, grinding) no atmospheric testing is required.

IV. TASKS AND REQUIREMENTS

The scope includes the execution of the following tasks:

1) All vendors are required to attend a pre-bid walkthrough, date and time to be determined.

2) Vendor Access/Training Required

a) All team members requiring site access shall register with the GUV center, and attend, at minimum a remote 2-hr Contractor/Vendor Orientation training.

3) Perform Site Safety Walkthrough with BNL Safety and complete a Job Hazard Analysis

a) Any training requirements identified during the safety walk through, and job hazard analysis are required to be completed prior to any worker performing work. Trainings are likely to include:

i) Fall Protection

ii) LOTO

iii) Confined Space

iv) Ladder Safety

v) Scaffold User Safety

4) Set up safety barriers around sky lights and building edge

5) Install scaffolding around tower work areas to facilitate all required work

6) Perform all demolition work required to execute the cooling tower rehabilitation, including the removal of construction debris.

7) Install the cooling tower rebuild kits purchased by BNL directly from the manufacturer per manufacturer assembly instructions, and industry best practices, including all necessary rigging of equipment. All expected subtask descriptions, including parts procured by BSA are shown in the following table, any materials ancillary to the parts list below shall be the responsibility of the contractor to procure.

Subtask Description Part No. Qty Description 1 1700 Ton tower cell

100 HP Fan Motor Removal Replacement, Balancing and Start-up

N/A 1 AC Electric Motor, Horsepower: 100, Phase: 3, Cycle: 60, Voltage: 230/460, Speed: 1800, Service factor: 1.15, Enclosure: TEFC, Frame size: 254T Horizontal foot mounted, Premium efficiency

2 1700 Ton Cooling Tower cell Gear Reducer Assembly

N/A 1 Geareducer assembly N/A 1 Hardware and shims for securing gear box to mounting base.

- 4 -

Subtask Description Part No. Qty Description Removal Replacement, Balancing and Start-up

N/A 3 Oil Synthetic, ISO 150, 1 Gallon container

3 1700 Ton Cooling Tower Cell Fill/Drift Eliminator Overhaul (removal and replacement of fill partitions, fill, splice tubes, telescopic rods / fill hanging assembly, and all hardware)

RK2047M5 1 BACross III PVC Fill Kit (14x224) GLV 281564L 2 Plastic Louver End-Cap (Top LH) 281564P2 62 Plastic Louver Support End 281564R 2 Plastic Louver End-Cap (Top RH) CF5126M5 2 Inlet Louver (8-1/64" X 160-3/4") Galv CF5127M5 30 Inlet Louver (10-11/16" X 160-3/4") Galv CW5343M5 6 Bottom Louver Hook, Galv CW5368M5 6 Center Louver Support Lower Section (112")

Galv TF4700M5 6 Center Louver Support Upper Section (112")

Galv TF4G00M5 6 Top Louver Support Bracket, Galv TF4M00M5 2 Louver Bottom Support (14') Galv TF7KBMM5 2 Inlet Tie Rod Kit, Lower Section (14' X 112")

Galv 4 1700 Ton Cooling

Tower Cell Hot Water Basin Removal and Replacement (including covers)

N/A 1 Tower Model (box size) Galvanized Hot Water Basin replacement includes unassembled basins, sealer, and hardware to install, per cell. Nozzles, gaskets and basin covers are not included, but nozzles are required.

N/A 1 Tower Model (box size), Galvanized Hot Water Basin Covers with hardware to install, per cell.

5 1700 Ton Cooling Tower Cell Nozzle Removal and Replacement

RK0441 3 Metering Orifices (Size XF-2, qty of 25) RK0442 3 Metering Orifices (Size XF-3, qty of 25) RK0443 2 Metering Orifices (Size XF-4, qty of 25) RK0446 9 Metering Orifices (Size XF-7, qty of 25)

6 1700 Ton Cooling Tower Cell Horizontal Control Valve Removal and Replacement

N/A 2 Gasket for HC Valves (1 req'd per valve).

Located between valve and pipe.

N/A 2 Full-Face Gasket for HC Valves (1 req'd per valve). Located between valve and top of basin.

N/A 2 Hardware to attach HC valve to inlet piping.

7 1700 Ton Cooling

Tower Cell Hanging Probe and Fill Valve Removal and Replacement

N/A 1 VALVE

N/A 1 VALVE STEM

N/A 1 VALVE COPPER FLOAT

N/A 1 CONTROL LLC+c HANGING PROBE SET 30

FEET,

8 1700 Ton Cooling

Tower Cell Fan Removal, Replacement, Balancing and Start-up

N/A 1 Tower Fan

8) Return surrounding area to original condition at start of project.

V. SIGNATURE AND DATE

____________________________ October 29, 2024

Description
Qty
Part No.
Description
Subtask
AC Electric Motor, Horsepower: 100, Phase: 3, Cycle: 60, Voltage: 230/460, Speed: 1800, Service factor: 1.15, Enclosure: TEFC, Frame size: 254T Horizontal foot mounted, Premium efficiency
1
N/A
1700 Ton tower cell 100 HP Fan Motor Removal Replacement, Balancing and Start-up
1
Geareducer assembly
1
N/A
1700 Ton Cooling Tower cell Gear Reducer Assembly Removal Replacement, Balancing and Start-up
2
Hardware and shims for securing gear box to mounting base.
1
N/A
Oil Synthetic, ISO 150, 1 Gallon container
3
N/A
BACross III PVC Fill Kit (14x224) GLV
1
RK2047M5
1700 Ton Cooling Tower Cell Fill/Drift Eliminator Overhaul (removal and replacement of fill partitions, fill, splice tubes, telescopic rods / fill hanging assembly, and all hardware)
3
Plastic Louver End-Cap (Top LH)
2
281564L
Plastic Louver Support End
62
281564P2
Plastic Louver End-Cap (Top RH)
2
281564R
Inlet Louver (8-1/64" X 160-3/4") Galv
2
CF5126M5
Inlet Louver (10-11/16" X 160-3/4") Galv
30
CF5127M5
Bottom Louver Hook, Galv
6
CW5343M5
Center Louver Support Lower Section (112") Galv
6
CW5368M5
Center Louver Support Upper Section (112") Galv
6
TF4700M5
Top Louver Support Bracket, Galv
6
TF4G00M5
Louver Bottom Support (14') Galv
2
TF4M00M5
Inlet Tie Rod Kit, Lower Section (14' X 112") Galv
2
TF7KBMM5
Tower Model (box size) Galvanized Hot Water Basin replacement includes unassembled basins, sealer, and hardware to install, per cell. Nozzles, gaskets and basin covers are not included, but nozzles are required.
1
N/A
1700 Ton Cooling Tower Cell Hot Water Basin Removal and Replacement (including covers)
4
Tower Model (box size), Galvanized Hot Water Basin Covers with hardware to install, per cell.
1
N/A
Metering Orifices (Size XF-2, qty of 25)
3
RK0441
1700 Ton Cooling Tower Cell Nozzle Removal and Replacement
5
Metering Orifices (Size XF-3, qty of 25)
3
RK0442
Metering Orifices (Size XF-4, qty of 25)
2
RK0443
Metering Orifices (Size XF-7, qty of 25)
9
RK0446
Gasket for HC Valves (1 req'd per valve). Located between valve and pipe.
2
N/A
1700 Ton Cooling Tower Cell Horizontal Control Valve Removal and Replacement
6
Full-Face Gasket for HC Valves (1 req'd per valve). Located between valve and top of basin.
2
N/A
Hardware to attach HC valve to inlet piping.
2
N/A
VALVE
1
N/A
1700 Ton Cooling Tower Cell Hanging Probe and Fill Valve Removal and Replacement
7
VALVE STEM
1
N/A
VALVE COPPER FLOAT
1
N/A
CONTROL LLC+c HANGING PROBE SET 30 FEET,
1
N/A
Tower Fan
1
N/A
1700 Ton Cooling Tower Cell Fan Removal, Replacement, Balancing and Start-up
8

File details come from the government source that posted it. Updated .