Sample Chiller Installation Checklist.docx

DOCX document 37 KB Posted

Attached to
N041--626-24-201 - Replace Chiller #2 Tennessee Valley Healthcare System, Nashville Campus
Solicitation number
36C24923B0023
Issued by

About this file

This document is a construction checklist for a water cooled chiller installation project. The checklist details inspections that must be completed for the installation and operation of a chiller, including reviews of documentation received, installation checks, operational checks, and sensor and actuator calibrations. It relates to solicitation number 36C24923B0023 from the Department of Veterans Affairs for replacing chiller number two at the Tennessee Valley Healthcare System Nashville campus. The checklist requires sign off from mechanical, controls, electrical, general, and TAB contractors, as well as commissioning provider and owner approval.

View the file

Other files

File Type Posted
36C24923B0023 0003.pdf PDF
PCRA Memorandum 7-11.doc DOC document
626-23-201 Replace Chiller 2 Layout_Rev1.pdf PDF
Switch Gear Location.pdf PDF
Painting Standards.pdf PDF
36C24923B0023 0002.docx DOCX document
Pre-Bid Site Walk Sign In_Replace Chiller2_28SEP23.pdf PDF
36C24923B0023 0001.docx DOCX document
Calculation of Self Performance Work.pdf PDF
VA Provided Chiller Cutsheets.pdf PDF
UEI _ TAX ID.docx DOCX document
626-24-201 Chiller 2 Specs.pdf PDF
Sample ATS 13 VA Commissioning.pdf PDF
RFI Form.docx DOCX document
DBA wage determination TN20230178 modification 4 last revised 06302023.pdf PDF
General Conditions Breakout.xlsx XLSX spreadsheet
One Line Diagram 8-3-23.pdf PDF
VA Chiller Details.pdf PDF
626-23-201 Replace Chiller 2 Layout.pdf PDF
36C24923B0023_1.docx DOCX document
Current 650 Ton Chiller 160-73-o2 Operating and Maintenance Manual.pdf PDF
Contractor EMR Certification Form.docx DOCX document
Show all 22

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Water Cooled Chiller Construction Checklist (rev. 12/1/2015) Project

Date

Location

Service Area

Submittal The above equipment and systems integral to them are complete and ready for functional testing. The checklist items are complete and have been checked off only by parties having direct knowledge of the event, as marked below, respective to each responsible contractor. This construction checklist is submitted for approval, subject to an attached list of outstanding items yet to be completed. A Statement of Correction will be submitted upon completion of any outstanding areas. None of the outstanding items preclude safe and reliable functional tests being performed.

List attached

Mechanical Contractor
Date
Controls Contractor
Date
Electrical Contractor
Date
General Contractor
Date
TAB Contractor
Date

Construction checklist items are to be completed as part of startup and initial checkout, before functional testing.

· This checklist augments, but is not meant to replace recommendations or requirements for installation, checkout and startup from standards, manufacturers, codes or governing bodies.

· If this form is not used for documenting, a CxP approved form of similar rigor may be used.

· Contractors assigned responsibility for sections of the checklist shall be responsible to see that checklist items by their subcontractors are completed and checked off.

· In the Trade column, indicate the contractor responsible for verifying the completion of this item:

A/E = architect/engineerAll = all contractorsCxP = commissioning provider
CC = controlsEC = electricalGC = general
MC = mechanicalPC = plumbingSC = sheet metal

TAB = test and balance CxP Approval This filled-out checklist has been reviewed. Its completion is approved with the exceptions noted below.

Commissioning provider
Date
Owner’s Representative
Date

Chiller 1 Information Make

Model

Serial Number

Capacity

GPM

Volts/Phase

Refrigerant

Charge

Label

Label

Comments

Requested Documentation Mark checkbox if the document was received. If not, indicate the number of an applicable explanatory note.

Requested Documentation Submitted
Rec’d
Note #
Manufacturer’s Cut Sheets
|_|
Performance Data
|_|
Installation and Startup Manual
|_|
O&M Manuals
|_|
Factory Test Results
|_|
Sequences and Control Strategies
|_|
Warranty Certificate
|_|
Startup Report
|_|

Comments:

Installation Checks If acceptable, mark the check box. If unacceptable, indicate the number of the applicable explanatory note attached to this form.

General
OK?
Note #
General appearance good, no apparent damage
|_|
Proper vibration isolators installed and adjusted
|_|
Seismic restraints in place
|_|
Pipe fittings and accessories complete
|_|
Hydronic system flushing complete and strainers cleaned
|_|
Evaporator air vent provided
|_|
Condenser air vent provided
|_|
Refrigerant relief pipe extended to outside
|_|
Test plugs (P/T) installed near all control sensors and as per spec
|_|
Flow switch installed as required
|_|
Proper refrigerant level
|_|
Proper oil level
|_|
Purge unit installed, if specified
|_|
Equipment labels affixed
|_|
Oil heater installed properly
|_|
Oil filter clean
|_|
No leaking apparent
|_|
Adequate maintenance access to all components
|_|
Piping
OK?
Note #
Piping installation checked against the drawings and all devices gages and appurtenances are in place
|_|
Piping supported independently of the chiller
|_|
Piping type and flow direction labeled on piping
|_|
Isolation valves, balancing valves and piping specialties installed
|_|
System flushing complete and strainers cleaned
|_|
Hydronic system flushing complete and strainers cleaned
|_|
Electrical and Controls
OK?
Note #
Power disconnect is located within site of the unit it controls and labeled
|_|
All electric connections tight
|_|
Grounding installed for components and unit
|_|
Safeties installed and operational
|_|
Starter overload breakers installed and correct size
|_|
All control devices and wiring complete
|_|
Control system interlocks connected and functional
|_|
Size of overcurrent heater in motor starter correct (where applicable)
|_|
HOA Switch installed per manufacturer’s instructions (if applicable)
|_|
Operation of HOA switch checked in all positions
|_|
Proper safeties in control when HOA switch in Hand position
|_|
Sensors and Gages
OK?
Note #
Temperature, pressure and flow gages and sensors installed
|_|
Piping gages, BAS and associated panel temperature and pressure readouts match
|_|
TAB
OK?
Note #
Installation of system and balancing devices allowed balancing to be completed following specified NEBB or AABC procedures and contract documents
|_|

Comments:

Operational Checks If acceptable, mark the check box. If unacceptable, indicate the number of the applicable explanatory note attached to this form.

OK?
Note #

Measure line to line voltage phase imbalance for compressor:

(%Imbalance = 100 x (avg. - lowest) / avg.)

Record imbalance of compressor. Imbalance less than 2%?

Record full load running amps for compressor. _____rated FL amps x ______srvc factor = _______ (Max amps). Running less than max?

No unusual noise and vibration when running
|_|
Compressor interlocking with oil pressure
|_|
Adequate oil pressure when compressor shaft is turning
|_|
Specified sequences of operation and operating schedules have been implemented with all variations documented
|_|
Specified point-to-point checks have been completed and documentation record submitted for this system
|_|
Startup report completed with this checklist attached. (Includes full listing of all internal settings with notes as to which settings are BAS controlled or monitored and which are integral
|_|
Startup report includes written certification from chiller manufacturer that all specified features, controls and safeties have been installed and are functioning properly and that the installation and application comply with the manufacturer’s recommendations
|_|
Piping gages, BAS and chiller panel temperature and pressure readouts match (see calibration section below)
|_|

Comments:

Sensor and Actuator Calibration

All field-installed sensors and gages, and all actuators (dampers and valves) on this piece of equipment shall be calibrated in accordance with Specification Section[_____________]
All test instruments shall have had a certified calibration within the last 12 months?Y/N

Sensors installed in the unit at the factory with calibration certification provided with no additional wire being added to the controller need not be field calibrated.

NOTE: This form need not be filled in if the information is in the control contractor’s checkout forms.

Sensor or Actuator Tag & Location
Location OK?
First Gage or BAS Value
Instrument-Measured Value
Final Gage or BAS Value
Pass?

Y/N

Y/N

Y/N

Y/N

Y/N

Y/N

Y/N

Y/N

Y/N

Y/N

Y/N

Y/N

General Comments:

End of Checklist

2.6.3.1 Water Cooled Chiller Construction Checklist.docx (rev. 12/1/2015) p.4 of 4