Sample ATS 13 VA Commissioning.pdf

PDF 974 KB Posted

Attached to
N041--626-24-201 - Replace Chiller #2 Tennessee Valley Healthcare System, Nashville Campus
Solicitation number
36C24923B0023
Issued by

About this file

This document outlines acceptance checks and tests for an automatic transfer switch. It details visual inspections and electrical tests to verify the physical condition, electrical condition, mechanical condition, lubrication, anchorage, clearances, alignment, connections, grounding, ratings of sensors, cleaning, exercising of active components, manual transfer warning signs, sensing devices, alarms, indicating devices, insulation resistance, simulation of power failures from normal and emergency sources, low phase-to-ground voltage, pickup voltage, dropout voltage, bypass isolation functions, and prevention of nuisance trips or alarms. Follow-up is scheduled. Demonstration of operational function is documented in a report from a third-party testing company.

The related federal contract opportunity is a solicitation to replace Chiller #2 at the Tennessee Valley Healthcare System Nashville Campus. The solicitation number is 36C24923B0023 for project 626-24-201 under the Department of Veterans Affairs Veterans Health Administration Veterans Integrated Service Network 9.

View the file

Other files

File Type Posted
36C24923B0023 0003.pdf PDF
PCRA Memorandum 7-11.doc DOC document
626-23-201 Replace Chiller 2 Layout_Rev1.pdf PDF
Switch Gear Location.pdf PDF
Painting Standards.pdf PDF
36C24923B0023 0002.docx DOCX document
Pre-Bid Site Walk Sign In_Replace Chiller2_28SEP23.pdf PDF
36C24923B0023 0001.docx DOCX document
Calculation of Self Performance Work.pdf PDF
VA Provided Chiller Cutsheets.pdf PDF
UEI _ TAX ID.docx DOCX document
626-24-201 Chiller 2 Specs.pdf PDF
RFI Form.docx DOCX document
DBA wage determination TN20230178 modification 4 last revised 06302023.pdf PDF
General Conditions Breakout.xlsx XLSX spreadsheet
One Line Diagram 8-3-23.pdf PDF
VA Chiller Details.pdf PDF
626-23-201 Replace Chiller 2 Layout.pdf PDF
36C24923B0023_1.docx DOCX document
Current 650 Ton Chiller 160-73-o2 Operating and Maintenance Manual.pdf PDF
Contractor EMR Certification Form.docx DOCX document
Sample Chiller Installation Checklist.docx DOCX document
Show all 22

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Date:

Manufacturer's Representative:

Contractor's Representative:

Contracting Officer's Representative:

Nameplate:

Catalog Number:

Serial Number:

Accessories:

Physical Condition OK? YES NO

Electrical Condition OK? YES NO

Mechanical Condition OK? YES NO

Lubricant OK? YES NO

Appropriate Anchorage? YES NO

Clearance acceptable per NEC 110.26? YES NO

Correct Alignment? YES NO

All Bolted Electrical Connections Torqued? YES NO

If not torqued Thermographic Survey

Verified Grounding Connections YES NO

Verified Ratings of Sensors YES NO

Vacuum/Clean all debris from Equipment YES NO

Exercise all active components YES NO

26 36 23 - Automatic Transfer Switches Part 3.2 - Acceptance Checks and Tests

Visual Inspections & Tests

Attach Photo of Thermograph

THVS Upgrade Paralleling System Project 626-18-203

Verify manual transfer warning signs in place YES NO

Verify operation of sening devices YES NO

Verify operation of alarms YES NO

Verify operation of indicating devices YES NO

Perform Insulation Resistance Tests

Test Bypass-isolation YES NO

Simulate Power Failure of Normal Source YES NO

Simulate Power Failure of EM Source YES NO

Simulate Low Phase-to-Ground Voltage YES NO

Verify Settings & Document: YES NO

a. Override Time Delay

b. Transfer Time Delay

c. Return Time Delay

d. Engine Shutdown Time Delay

e. Exerciser

f. Aux Contacts

g. Supplemental Features

Verify & Document Pickup Voltage

Verify & Document Dropout Voltage

NOVerify bypass isolation functions by removing ATS in Bypass YES

Verify ATS will not cause nuisance trips or alarms of Grounds YES NO

Notes:

Follow-up Scheduled:

Electrical Tests:

Demonstration of Operational Function:

See report from 3rd Party NETA testing company