S02 - Solicitation - 36C77625R0047.pdf

PDF 732 KB Posted

Attached to
36C77625R0047 - Expand & Renovate New MRI - Providence, RI - Solicitation
Solicitation number
36C77625R0047
Issued by

About this file

This document is a Solicitation (Request for Proposal) for a construction project to expand and renovate the MRI suite at the Providence Veterans Affairs Medical Center. The solicitation (No. 36C77625R0047) is a total small business set-aside with a project magnitude between $10,000,000 and $20,000,000. The contract requires the contractor to provide all necessary labor, materials, equipment, and supervision to complete the MRI suite renovation, with a mandatory performance period of 600 calendar days from the notice to proceed.

Key details include a proposal submission deadline of July 25, 2025 at 3:00 PM EDT, with proposals to be submitted electronically to Christopher Yong. The project will use a Lowest Price Technically Acceptable (LPTA) evaluation method, with contractors required to demonstrate prior experience in multi-story medical facility construction and high-tech medical equipment installations. The solicitation includes multiple bid line items with deductive alternates, allowing the government flexibility in awarding the contract based on available funding. The project is located at 830 Chalkstone Avenue in Providence, Rhode Island, and has a NAICS code of 236220 for Commercial and Institutional Building Construction.

View the file

Other files

File Type Posted
36C77625R0047 0004.pdf PDF
36C77625R0047_r2.pdf PDF
E2-02.1-001 SECTION Reg Roll in 5113 Pkt Tile Support 1.pdf PDF
261116 - Secondary Unit Substations 1.pdf PDF
E2-01.1-003 SECTION Regular Roll with Fascia Wall Moun 1.pdf PDF
19026-VA Medical Center Geotech Rpt 1.pdf PDF
Magnetom Sola Tech Specs 1.pdf PDF
19.0158 - RGB - VAMC - MRI 3-24-23-SKC-1 1.pdf PDF
36C77625R0047_r1.pdf PDF
00 Rescue SR frame 1.pdf PDF
Sola 1.PDF PDF
Vida XT Typical Final Drawings 1.PDF PDF
Sola XQ Typical Final Drawings 1.PDF PDF
36C77625R0047 0003.pdf PDF
Technical Questions and Answers - Volume 1.docx DOCX document
E1-01.1-00220Regular20with20Wall 20 Mount.pdf PDF
190316.01 - VAMC Providence - MRI Expan-Add - 04.03.2023 1.pdf PDF
Technical Questions and Answers - Volume 2.docx DOCX document
Vida 1.PDF PDF
107316 - Canopies 1.pdf PDF
MagnetomVida Tech Specs 1.pdf PDF
S06 - 36C77625R0047 0002.pdf PDF
S06 - Attachment 01 - Site Visit Sign in Sheet - Original.pdf PDF
S06 - Attachment 02 - Site Visit Sign in Sheet - VA Reproduced.pdf PDF
S06 - Attachment 01 - Providence Campus Map.pdf PDF
S06 - 36C77625R0047 0001.pdf PDF
100 VAMC MRI - Full Set IFC 1 of 5.pdf PDF
100 VAMC MRI - Full Set IFC 2 of 5.pdf PDF
Limitations on Subcontracting - Construction.docx DOCX document
Specifications.pdf PDF
100 VAMC MRI - Full Set IFC 3 of 5.pdf PDF
100 VAMC MRI - Full Set IFC 5 of 5.pdf PDF
19026-VA Medical Center Geotech Rpt.pdf PDF
100 VAMC MRI - Full Set IFC 4 of 5.pdf PDF
Wage Rates - Providence County.pdf PDF
650-345 Expand and Renovate MRI SOW Synopsis-FINAL.doc DOC document
Contractor Safety - Environmental Form.docx DOCX document
Show all 37

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

1. SOLICITATION NUMBER 2. TYPE OF SOLICITATION 3. DATE ISSUED PAGE OF PAGES

4. CONTRACT NUMBER 5. REQUISITION/PURCHASE REQUEST NUMBER 6. PROJECT NUMBER

7. ISSUED BY CODE 8. ADDRESS OFFER TO

a. NAME b. TELEPHONE NUMBER (Include area code) (NO COLLECT CALLS)

10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS (Title, identifying number, date)

12a. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?

(If "YES," indicate within how many calendar days after award in Item 12B.)

12b. CALENDAR DAYS

13. ADDITIONAL SOLICITATION REQUIREMENTS:

STANDARD FORM 1442 (REV. 8/2014) STANDARD FORM 1442

Prescribed by GSA-FAR (48 CFR) 52.236-1(d)

SOLICITATION, OFFER,

AND AWARD

(Construction, Alteration, or Repair)

SOLICITATION SOLICITATION

IMPORTANT - The "offer" section on the reverse must be fully completed by offeror.

9. FOR INFORMATION

CALL:

NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid" and "bidder".

SEALED BID (IFB)

NEGOTIATED (RFP)

11. The Contractor shall begin performance within ____________ calendar days and complete it within ____________ calendar days after receiving award, notice to proceed. This performance period is mandatory negotiable. (See _____________________________).

YES NO

a. Sealed offers in original and ___________________copies to perform the work required are due at the place specified in Item 8 by _____________ (hour) local time _____________________ (date). If this is a sealed bid solicitation, offers must be publicly opened at that time. Sealed envelopes containing offers shall be marked to show the offeror's name and address, the solicitation number, the date and time offers are due.

b. An offer guarantee is, is not required.

c. All offers are subject to the (1) work requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.

d. Offers providing less than _______________________ calendar days for Government acceptance after the date offers are due will not be considered and will be rejected.

36C77625R0047

X

05-01-2025

TBD

650-345

36C776

Department of Veterans Affairs Program Contracting Activity Central

6100 Oak Tree Blvd, Suite 490 Independence OH 44131

Department of Veterans Affairs Program Contract Activity Central 6100 Oak Tree Blvd, Suite 490

Independence OH 44131

Christopher Yong 561-422-1456

This project is a competitive, total small business set-aside.

Contractor shall provide all tools, equipment, materials, labor, supervision, personnel, and shall perform IAW SOW and technical drawings necessary that will result in the completion of the Expansion and Renovation of the Providence VAMC, MRI suite.

This project is located at the Providence VAMC 830 Chalkstone Avenue Providence, RI 02908

NAICS: 236220

PSC: YIDA

Firms submitting a proposal acknowledge the submitted proposal price is guaranteed for 90 days from submission.

The magnitude of this construction project is between $10,000,000 and $20,000,000.

10 600 x x 52.211-10

X 10

3:00 PM EDT

07-25-2025

X

14. NAME AND ADDRESS OF OFFEROR 15. TELEPHONE NUMBER

16. REMITTANCE ADDRESS

CODE FACILITY CODE

17. The offeror agrees to perform the work required at the prices specified below in strict accordance with the terms of the solicitation, if this offer is accepted by the Government in writing within __________ calendar days after the date offers are due.

AMOUNTS

18. The offeror agrees to furnish any required performance and payment bonds.

19. ACKNOWLEDGMENT OF AMENDMENTS

AMENDMENT

NUMBER

DATE.

20a. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN OFFER 20b. SIGNATURE 20c. OFFER DATE

21. ITEMS ACCEPTED:

22. AMOUNT 23. ACCOUNTING AND APPROPRIATION DATA

24. SUBMIT INVOICES TO ADDRESS SHOWN IN ITEM 25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO 10 U.S.C. 2304(c)( ) 41 U.S.C. 3304(a) ( )

26. ADMINISTERED BY 27. PAYMENT WILL BE MADE BY

PHONE: FAX:

28. NEGOTIATED AGREEMENT 29. AWARD Your Contractor agrees offer on this solicitation is hereby accepted as to the items listed. This to furnish and deliver all items or perform all work requirements identified award consummates the contract, which consists of (a) the Government on this form and any continuation sheets for the consideration stated in solicitation and your offer, and (b) this contract award. No further cont-this contract. The rights and obligations of the parties to this contract ractual document is necessary.

shall be governed by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, certifications, and specifications incorporated by reference in or attached to this contract.

30a. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED 31a. NAME OF CONTRACTING OFFICER

TO SIGN

30b. SIGNATURE 30c. DATE 31b. UNITED STATES OF AMERICA 31c. AWARD DATE

BY

OFFER

AWARD

STANDARD FORM 1442 (REV. 8/2014) BACK

(Include ZIP Code) (Include area code)

(Include only if different than Item 14.)

(Insert any number equal to or greater than the minimum requirement stated in Item 13d. Failure to insert any number means the offeror accepts the minimum in Item 13d.)

(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each)

(Type or print)

(4 copies unless otherwise specified)

(Type or print) (Type or print)

(Contractor is required to sign this document and return _______ copies to issuing office.)

(Contractor is not required to sign this document.)

(Must be fully completed by offeror)

(To be completed by Government)

CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE

36C776

Department of Veterans Affairs Program Contracting Activity Central

6100 Oak Tree Blvd, Suite 490 Independence OH 44131

VAFSC

Department of Veterans Affairs Financial Services Center Invoices to be Submitted Electronically https://www.fsc.va.gov/einvoice.asp e-Invoice Setup Info Phone 877-489-6135 877-353-9791 512-460-5429 x x

Nicholas Sparks

Table of Contents

PART I - THE SCHEDULE

SECTION A - SOLICITATION/CONTRACT FORM

A.1 SF 1442 SOLICITATION, OFFER, AND AWARD (Construction, Alteration, or Repair)

A.2 SF 1442 SOLICITATION, OFFER, AND AWARD (CONSTRUCTION,

ALTERATION, OR REPAIR)– BACK

A.3 PRICE/COST SCHEDULE

ITEM INFORMATION

INFORMATION REGARDING PROPOSAL MATERIAL, BID GUARANTEE AND BONDS

1.1 BID MATERIAL:

1.2 BID GUARANTEE:

1.3 PAYMENT & PERFORMANCE BONDS:

1.4 TAXES:

INSTRUCTIONS, CONDITIONS, AND OTHER STATEMENTS TO OFFERORS

2.1 AVAILABILITY OF SOLICITATION DOCUMENTS

2.2 REQUEST FOR PROPOSAL:

2.3 SMALL BUSINESS SET-ASIDE

2.4 PRE-PROPOSAL SITE VISIT:

2.5 TECHNICAL QUESTIONS:

2.6 AMENDMENTS

2.7 PREPARATION OF PROPOSALS

2.8 PROPOSAL REQUIREMENTS

2.9 EVALUATION FACTORS

2.10 EVALUATION OF OFFERORS

2.11 RESPONSIBILITY DETERMINATION

2.12 VETS 4212

2.13 SYSTEM FOR AWARD MANAGEMENT (SAM)

2.14 REFERENCES TO BIDS/BIDDERS

2.15 REVIEW REQUIRED REGISTRATION WITH CONTRACTOR PERFORMANCE

ASSESSMENT REPORTING SYSTEM (CPARS)

2.16 BACKGROUND INVESTIGATIONS AND SPECIAL AGREEMENT CHECKS

2.17 REFERENCES TO VA ENGINEER, RESIDENT ENGINEER, OR PROJECT

MANAGER

2.18 52.201-1 ACQUISITION 360: VOLUNTARY SURVEY (SEP 2023)

2.19 52.216-1 TYPE OF CONTRACT (APR 1984)

2.20 52.222-5 CONSTRUCTION WAGE RATE REQUIREMENTS—SECONDARY

SITE OF THE WORK (MAY 2014)

2.21 52.228-1 BID GUARANTEE (SEP 1996)

2.22 52.228-17 INDIVIDUAL SURETY—PLEDGE OF ASSETS (BID GUARANTEE)

(FEB 2021)

2.23 52.233-2 SERVICE OF PROTEST (SEP 2006)

2.24 52.236-27 SITE VISIT (CONSTRUCTION) (FEB 1995) ALTERNATE I (FEB

1995)

2.25 52.252-1 SOLICITATION PROVISIONS INCORPORATED BY REFERENCE

(FEB 1998)

2.26 VAAR 852.219-75 VA NOTICE OF LIMITATIONS ON SUBCONTRACTING—

CERTIFICATE OF COMPLIANCE FOR SERVICES AND CONSTRUCTION (JAN 2023)

(DEVIATION)

2.27 VAAR 852.228-72 ASSISTING SERVICE-DISABLED VETERAN-OWNED AND

VETERAN-OWNED SMALL BUSINESSES IN OBTAINING BONDS (DEC 2009)

2.28 VAAR 852.233-71 ALTERNATE PROTEST PROCEDURE (OCT 2018)

2.29 VAAR 852.233-70 PROTEST CONTENT/ALTERNATIVE DISPUTE

RESOLUTION (OCT 2018)

2.30 VAAR 852.236-92 NOTICE TO BIDDERS—ADDITIVE OR DEDUCTIVE BID LINE

ITEMS (APR 2019)

2.31 VAAR 852.239-75 INFORMATION AND COMMUNICATION TECHNOLOGY

ACCESSIBILITY NOTICE (FEB 2023)

REPRESENTATIONS AND CERTIFICATIONS

3.1 52.204-8 ANNUAL REPRESENTATIONS AND CERTIFICATIONS (JAN 2025)

(DEVIATION FEB 2025)

3.2 52.204-24 REPRESENTATION REGARDING CERTAIN TELECOMMUNICATIONS

AND VIDEO SURVEILLANCE SERVICES OR EQUIPMENT (NOV 2021)

3.3 52.204-29 FEDERAL ACQUISITION SUPPLY CHAIN SECURITY ACT ORDERS—

REPRESENTATION AND DISCLOSURES (DEC 2023)

3.4 52.209-7 INFORMATION REGARDING RESPONSIBILITY MATTERS (OCT 2018)

3.5 52.209-13 VIOLATION OF ARMS CONTROL TREATIES OR AGREEMENTS—

CERTIFICATION (NOV 2021)

3.6 52.229-11 TAX ON CERTAIN FOREIGN PROCUREMENTS—NOTICE AND

REPRESENTATION (JUN 2020)

GENERAL CONDITIONS

4.1 52.211-10 COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK

(APR 1984)

4.2 52.225-11 BUY AMERICAN—CONSTRUCTION MATERIALS UNDER TRADE

AGREEMENTS (NOV 2023) ALTERNATE I (NOV 2023)

4.3 52.219-28 POSTAWARD SMALL BUSINESS PROGRAM REREPRESENTATION

(JAN 2025)

4.4 52.222-35 EQUAL OPPORTUNITY FOR VETERANS (JUN 2020)

4.5 52.222-40 NOTIFICATION OF EMPLOYEE RIGHTS UNDER THE NATIONAL

LABOR RELATIONS ACT (DEC 2010)

4.6 52.229-3 FEDERAL, STATE, AND LOCAL TAXES (FEB 2013)

4.7 52.236-4 PHYSICAL DATA (APR 1984)

4.8 SUPPLEMENTAL INSURANCE REQUIREMENTS

4.9 MANDATORY WRITTEN DISCLOSURES

4.10 52.252-2 CLAUSES INCORPORATED BY REFERENCE (FEB 1998)

4.11 VAAR 852.201-70 CONTRACTING OFFICER'S REPRESENTATIVE (DEC 2022)

4.12 VAAR 852.203-70 COMMERCIAL ADVERTISING (MAY 2018)

4.13 VAAR 852.204-70 PERSONAL IDENTITY VERIFICATION OF CONTRACTOR

PERSONNEL (MAY 2020)

4.14 VAAR 852.211-72 TECHNICAL INDUSTRY STANDARDS (NOV 2018)

4.15 VAAR 852.215-71 EVALUATION FACTOR COMMITMENTS (OCT 2019)

4.16 VAAR 852.228-70 BOND PREMIUM ADJUSTMENT (JAN 2008)

4.17 VAAR 852.232-70 PAYMENTS UNDER FIXED-PRICE CONSTRUCTION

CONTRACTS (WITHOUT NAS– CPM) (NOV 2018)

4.18 VAAR 852.232-72 ELECTRONIC SUBMISSION OF PAYMENT REQUESTS (NOV

2018)

4.19 VAAR 852.236-71 SPECIFICATIONS AND DRAWINGS FOR CONSTRUCTION

(APR 2019)

4.20 VAAR 852.236-79 CONTRACTOR PRODUCTION REPORT (APR 2019)

4.21 VAAR 852.236-80 SUBCONTRACTS AND WORK COORDINATION (APR 2019)

4.22 VAAR 852.242-70 GOVERNMENT CONSTRUCTION CONTRACT

ADMINISTRATION (OCT 2020)

4.23 VAAR 852.242-71 ADMINISTRATIVE CONTRACTING OFFICER (OCT 2020) ..63

4.24 VAAR 852.243-70 CONSTRUCTION CONTRACT CHANGES—SUPPLEMENT

(SEP 2019)

4.25 IT CONTRACT SECURITY

4.26 LIST OF ATTACHMENTS

A.3 PRICE/COST SCHEDULE

ITEM INFORMATION

ITEM

NUMBER

DESCRIPTION OF

SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT

1.00 JB __________________ __________________

Line Item 0001, (General Construction): Work includes general construction, electrical, mechanical, structural, architectural and civil work to be performed consistent with the attached Specifications and Drawings.

The contractor shall complete the entire project no later than 600 calendar days after receipt of the NOTICE TO PROCEED.

Contract Period: Base POP Begin:

POP End:

PRINCIPAL NAICS CODE: 236220 - Commercial and Institutional Building Construction PRODUCT/SERVICE CODE: Y1DA - Construction of Hospitals and Infirmaries

Line Item 0002, Deduct Alternate No. 1: Base Bid minus:

a. Provide PVC roofing membrane in lieu of PVC "Sure-Flex Kee HP" roofing membrane.

b. Existing chiller to remain in its temporary location, Re: MEP Drawings.

c. Omit pre-fab canopy at ground floor egress exit (Corridor #B051/Door #B051.3)

Line Item 0003, Deduct Alternate No. 2: Base Bid minus deduct alternate No. 1 and

a. Omit ceiling-mounted Sky Factory panels (2x2, quantity 21) and replace with ACT ceiling panels.

b. Omit "Light Boxes" at the ground, first and second floors. Existing Building #1 window infill/"Light Box", Quantity 10. Sub-waiting room (RM #B058) "Light Box" Quantity 1. Existing E-Wing waiting room (RM#E201) "Light Box" Quantity 1. First floor corridor (RM #B100) Quantity 1.

c. Omit ground floor roof screen and structural supports.

Line Item 0004, Deduct Alternate No. 3: Base Bid Minus Deduct

Alternate No. 1 and 2 and

a. Omit first floor roof screen and structural supports.

b. Omit the Mobile MRI Trailer canopy. Provide a 12-inch-deep band in lieu of the full-size canopy.

c. Omit ground floor roof screen and structural supports.

Line Item 0005, Deduct Alternate No. 4: Base Bid minus Deduct

Alternate No. 1, 2 and 3 and

a. Island Modifications: Remove, salvage and reuse all items within the perimeter of island modifications.

b. Omit the second-floor elevator lobby reconfiguration.

GRAND TOTAL __________________

NOTICE

1. Line Item 0001, Base Bid (General Construction) contains all the work for this project. Each

Line Item (Deduct) is listed in descending order of importance and removes a portion of the work.

2. The intent is to award Line Item 0001, Base Bid (General Construction). However, if the bid price exceeds the funds available for Line Item 0001, Base Bid (General Construction), then Line Item 0002 (Deduct No. 1) will be applied. If the bid price exceeds the funds available for Line Item 0002 (Deduct No. 1), then Line Item 0003 (Deduct No. 2) will be applied. If the bid price exceeds the funds available for Line Item 0003 (Deduct No. 2), then Line Item 0004 (Deduct No. 3) will be applied. If the bid price exceeds the funds available for Line Item 0004 (Deduct No. 3), then Line Item 0005 (Deduct No. 4) will be applied.

3. Please reference VAAR 852.236-92 Notice to Bidders–Additive or Deductive Bid Line Items in the solicitation for additional details.

4. Bidders must provide a lump sum price for each of the Line Items. Failure to do so may render their bid as nonresponsive.

5. Pricing should be submitted in whole dollar values. Please do NOT include pricing in cents.

6. Contractor is required to fill in their Unique Entity Identifier number associate with SAM.gov in Block No. 14 on Standard Form (SF) 1442.

7. PLEASE NOTE: The Contractor agrees to attend any Post Award conference convened by the contracting activity or contract administration in accordance with Federal Acquisition Regulation subpart 42.5.

INFORMATION REGARDING PROPOSAL MATERIAL, BID

GUARANTEE AND BONDS

1.1 BID MATERIAL:

Proposal materials consisting of drawings, specifications, and contract forms are included and/or attached as part of this Request for Proposal (RFP). The VA will not provide printed copies of drawings or specifications. It is the responsibility of the offeror to obtain the proposal materials in a time and manner sufficient to respond to this solicitation by the specified due date.

1.2 BID GUARANTEE:

A Bid Guarantee, Standard Form 24 (SF 24), is required in an amount not less than 20 percent of the proposal price but shall not exceed $3,000,000. Failure to furnish the required bid guarantee in the proper form and amount, by the time set for receipt of proposals, may result in the proposal being deemed unacceptable. Copies of the SF 24 may be obtained from https://www.gsa.gov/forms.

1.3 PAYMENT & PERFORMANCE BONDS:

The offeror to whom award is made will be required to furnish two bonds. A Payment Bond shall be provided on Standard Form 25A (SF 25A) and a Performance Bond shall be provided on Standard Form 25 (SF 25). Both bonds shall be submitted in accordance with FAR 52.228-15 Performance and Payment Bonds - Construction. Copies of SFs 25A and 25 may be obtained from https://www.gsa.gov/forms.

1.4 TAXES:

Contractor must take into account FAR 52.229-3; “Federal, State and Local Taxes” and its Special Note in their pricing. The FAR clause and its Special Note provide guidance on taxes being applied to pricing.

https://gcc02.safelinks.protection.outlook.com/?url=https%3A%2F%2Fwww.gsa.gov%2Fforms&data=05%7C02%7C%7C7197924ab06b4510c2cb08dd1867cd0b%7Ce95f1b23abaf45ee821db7ab251ab3bf%7C0%7C0%7C638693556286629207%7CUnknown%7CTWFpbGZsb3d8eyJFbXB0eU1hcGkiOnRydWUsIlYiOiIwLjAuMDAwMCIsIlAiOiJXaW4zMiIsIkFOIjoiTWFpbCIsIldUIjoyfQ%3D%3D%7C0%7C%7C%7C&sdata=MT5QogE1p45j8KY7G3NL%2BRIn0UgyKEY8mmn8Lp5c5oQ%3D&reserved=0 https://gcc02.safelinks.protection.outlook.com/?url=https%3A%2F%2Fwww.gsa.gov%2Fforms&data=05%7C02%7C%7C7197924ab06b4510c2cb08dd1867cd0b%7Ce95f1b23abaf45ee821db7ab251ab3bf%7C0%7C0%7C638693556286629207%7CUnknown%7CTWFpbGZsb3d8eyJFbXB0eU1hcGkiOnRydWUsIlYiOiIwLjAuMDAwMCIsIlAiOiJXaW4zMiIsIkFOIjoiTWFpbCIsIldUIjoyfQ%3D%3D%7C0%7C%7C%7C&sdata=MT5QogE1p45j8KY7G3NL%2BRIn0UgyKEY8mmn8Lp5c5oQ%3D&reserved=0

INSTRUCTIONS, CONDITIONS, AND OTHER STATEMENTS TO

OFFERORS

2.1 AVAILABILITY OF SOLICITATION DOCUMENTS

All solicitation-related documents will be published to Contract Opportunities at https://sam.gov/.

2.2 REQUEST FOR PROPOSAL:

This is a Request for Proposal (RFP) in accordance with FAR Part 15. Award will be made to the offeror whose proposal represents the “best value” to the Government Utilizing the Lowest Price Technically Acceptable (LPTA) method of evaluation.

2.3 SMALL BUSINESS SET-ASIDE

This procurement is a 100% set-aside for Small Business concerns. Offers received from other than small business concerns will not be considered.

2.4 PRE-PROPOSAL SITE VISIT:

A formal site visit has been scheduled for this project. This will be the only opportunity for potential offerors to visit the site. All potential offerors, subcontractors, and suppliers are strongly encouraged to attend this site visit. See FAR 52.236-27 of this solicitation for further information.

NOTE: Although not required, it is highly recommended that those who attend the pre-proposal site visit for this project, review the drawings ahead of time. Due to the continued care of our veterans, there may be areas that cannot be accessed during the pre-proposal site visit. Any questions regarding these areas can be addressed during the technical question period of the solicitation.

2.5 TECHNICAL QUESTIONS:

Questions of a technical nature must be provided in writing and shall be submitted by the prospective offerors to Christopher Yong. Questions shall be submitted only via e-mail to:

christopher.yong@va.gov. The subject line must read: Expand and Renovate New MRI – Providence, RI. Oral questions of a technical nature are not acceptable due to the possibility of misunderstanding or misinterpretation. THE CUT-OFF DATE AND TIME FOR RECEIPT OF QUESTIONS IS 7/7/2025 at 3:00PM EST.

2.6 AMENDMENTS

Amendments to this solicitation will be posted at https://sam.gov/. Paper copies of the amendments will NOT be individually mailed. No other notification of amendments will be provided. Potential offerors are advised that they are responsible for obtaining and acknowledging any amendments to the solicitation. Failure to acknowledge an amendment may result in your proposal being considered unacceptable and ineligible for award.

2.7 PREPARATION OF PROPOSALS

The Government will not pay for any costs incurred in the preparation and submission of proposals.

https://sam.gov/ mailto:christopher.yong@va.gov

2.8 PROPOSAL REQUIREMENTS

A. General:

1. Proposal Submission: Offerors shall submit their proposals via email to:

christopher.yong@va.gov. Proposals shall be based on solicitation documents issued for RFP number 36C77625R0047. Proposals will be in the format stipulated in this document. There will be no public opening of the proposals.

Only e-mail proposals will be accepted. Hard-copy proposals will not be accepted.

B. Proposal Format:

1. Technical, Price and Administrative sections of the Offerors proposals will be evaluated independently; therefore, the Offeror shall submit the proposal in three

(3) Volumes: Volume I Technical, Volume II Price and Volume III Administrative.

In order that the Volume I Technical may be evaluated strictly on the merit of the material submitted, the contractor shall include NO price information in Volume I.

Offeror shall separate Volumes I, II and III. Each volume must be labeled with the Offeror's organization, business address, and VA Solicitation Number. The volumes shall be submitted in electronic format as searchable PDF documents.

The proposal, in its entirety, shall not exceed three emails (one email for each volume) of 20MB each. Include page numbers and the company name in the header or footer of each page.

2. Volume I Technical: Offerors shall format the Volume I Technical proposal as listed below.

a. The offer, including title page, detailed table of contents, preface shall be submitted in one (1) PDF document for Volume I Technical and shall not exceed a total of Fifty (50) pages (title page, table of contents and preface are excluded from the page limits) in Microsoft Times New Roman 12 font. The Offeror shall not include any price or price related material in the Volume I proposal. Use graphic presentations where such use will contribute to the compactness and clarity of the proposal.

b. A page is defined as each face of an 8.5 X 11-inch sheet of paper with 1-inch margins around the page perimeter containing information. All information (except for document numbers, page numbers, etc.) shall be provided in an image area of 7 X 9 inches.

The background color of each page of the submission shall be white or ivory stock only and each page shall count as one (1) page.

Excess pages will not be evaluated. Text lines will be single-spaced, and proposals shall be submitted using Times New Roman, with font no smaller than 12 point with normal proportional spacing. A smaller font size for any graphics presented in a proposal is permitted as long as the information is legible to the human eye.

Fonts other than Times New Roman are permissible in the presentation of graphic material only.

c. The Offeror’s responses shall clearly address each evaluation factor listed in this solicitation. Failure to submit in the format required and clearly address those factors may result in this offer being rated unacceptable.

3. Volume II Price: Offerors shall format the Volume II Price proposal as listed below.

a. Volume II Price shall not exceed a total of TWENTY (20) pages.

mailto:christopher.yong@va.gov

b. Offerors shall complete the Price Schedule contained in the solicitation.

The Offeror shall submit separate pricing for all items listed.

c. Offerors shall ensure the Signed Standard Form (SF 1442) is included with Volume II price. The Offeror shall complete & sign the “OFFER” section of the SF 1442. Please include your company’s Unique Entity Identifier number associate with SAM.gov in Block 14. Offerors shall also acknowledge receiving amendments by filling out section 19 of the SF 1442. Failure to acknowledge all amendments shall result in the rejection of the proposal.

d. Bid Guarantee is included with Volume II Price: The bid bond must be submitted electronically as part of the proposal package. In accordance with Class Deviation from the Federal Acquisition Regulation to Eliminate Hard Copy Original Documents, Signatures, Notarization, Seals on Bonds, and Other Seals for Certain Contract Requirements issued by the VA Executive Director, Office of Acquisition and Logistics, and the Senior Procurement Executive on May 11, 2020, the requirement for a hard copy original bond with the original signatures, notarization, and seals has been eliminated.

Failure to furnish the required bid guarantee in the proper form and amount, by the time set for receipt of proposals, shall result in the rejection of the proposal.

4. Volume III Administrative Information: Offerors shall include the following in Volume III. Information concerning Items a. through h. must be provided. An Offeror may be considered unacceptable if Items a. through h. are not provided in the proposal.

a. Representations & Certifications:

The offeror shall provide their Representations and Certifications or their response to FAR 52.204-8 (2) (i) or (ii) Annual Representations and Certifications.

b. Representation Regarding Certain Telecommunications and Video Surveillance Services or Equipment:

Offeror shall provide their response to FAR 52.204-24 (d) Representation.

c. Information Regarding Responsibility Matters:

Offeror shall provide their response to FAR 52.209-7 (b) Information Regarding Responsibility Matters.

d. Violation of Arms Controls Treaties or Agreements:

Offeror shall provide their response to FAR 52.209-13 (b) (1) or (2) Violation of Arms Controls Treaties or Agreements.

e. Tax on Certain Foreign Procurements – Notice and Representation:

The offeror shall provide their response to FAR 52.229-11 (d).

f. Post Award Small Business Program Representations:

Offeror shall provide their response to FAR 52.219-28 (h), if applicable.

g. Limitations on Subcontracting:

The offeror shall complete and sign the VA Notice of Limitations on Subcontracting - Certificate of Compliance for Services and Construction required in VAAR 852.219-75 and return it with their proposal submission as a separate document (see attachment Limitations on Subcontracting - Construction). The completed and signed form will become part of the official award documentation.

2.9 EVALUATION FACTORS

A. Technical Proposal Requirements: The proposal shall address the following submission requirements for Factor 1 Prior Experience (Technical).

Factor 1 Prior Experience (Technical):

Offerors shall provide a minimum of three (3), but no more than five (5) prior projects that provide experience in similar size, scope, and complexity of the subject project. The proffered projects must have been completed within the last ten (10) years and the offeror must have acted as the prime contractor. Project experience where the offeror acted as a subcontractor may not be used to supplement experience necessary to fulfil this requirement. Further, experience of proposed subcontractors may not be used to supplement experience necessary to fulfill this requirement. The Government requires extensive prior experience directly related to new construction of multi-story building projects within an active hospital environment. Example projects must have been constructed for the use of high tech/high-cost medical equipment. Example projects should demonstrate the contractor’s ability to coordinate the construction of the shell, the coordination and integration of whatever shielding the particular equipment requires, and the coordination of the equipment installation.

Proffered projects must demonstrate:

One (1) addition or new construction of a multi-story facility

One (1) addition or new construction project of high tech / high cost medical and or diagnostic equipment OR one (1) addition or new construction project of an MRI

Further, an offeror need not submit example projects that each individually demonstrate all of the above-mentioned criteria. Offerors may submit separate projects that individually demonstrate one or more of the above-mentioned qualifications. For example, “Offeror A” may submit one (1) project that demonstrates both an addition or new construction of a multi-story facility and an addition or new construction project of an MRI and two (2) additional projects of similar size scope and complexity that are relevant but do not necessarily exemplify the above-mentioned qualifications. “Offeror A” may also submit one (1) example project that demonstrates an addition or new construction of a multi-story facility; another example project of an addition or new construction project of an MRI; and one (1) additional project of similar size, scope and complexity.

B. Volume II – Price Proposal Requirements

a. Complete the Price Schedule contained in the solicitation and provide separate pricing for all items listed.

b. Complete the SF 1442 as outlined in 2.8 Proposal Requirements Volume II Price.

c. Submit a bid guarantee as stipulated in the solicitation.

d. Prices shall be Firm Fixed Price. The Offeror shall take care not to include remarks that take exception to the Government’s Specifications/Drawings or pricing requirements or otherwise preclude the Government from evaluating the offer, which will render the offer unacceptable.

2.10 EVALUATION OF OFFERORS

Proposals will be evaluated using the LPTA source selection process. The evaluation will be conducted as follows:

All offers shall be evaluated on the basis of the same deductive line items. The Source Selection Team (SST) will subsequently evaluate the offerors for the non-price factors. The Contracting Officer will use the list of priorities in the price schedule only to determine the lowest price.

Prior to the opening of proposals, the Government will determine the amount of funds available for the project. Deductive line items in the price schedule will be evaluated to determine the lowest price offeror and the line items to be awarded. The lowest price will be the offeror that is otherwise eligible for award and offers the lowest aggregate amount for the first or base line item, minus (in the order of priority stated in the price schedule) those deductive line items that provide the most features within the funds determined available. This amount will be the total evaluated price.

The SST will subsequently determine the acceptability of the offerors for the non-price factor. All offerors are advised that, in the interest of efficiency, the Government reserves the right to conduct the evaluation in the most effective manner. Specifically, the Government may first evaluate the total proposed price of all offerors, then evaluate the proposal of the lowest price offeror only.

If the lowest price offeror’s proposal is determined to be Acceptable, the Government may make award to that offeror without further evaluation of the remaining offerors’ proposals, provided its price is determined to be fair and reasonable. If the lowest price offeror’s proposal is determined to be Unacceptable, then the Government may evaluate the next lowest priced proposal, and so forth and so on, until the Government reaches the lowest priced proposal that is determined to be Acceptable with fair and reasonable pricing.

However, the Government reserves the right to evaluate all offerors’ proposals should it desire to conduct discussions, or otherwise determine it to be in the Government’s best interest. If discussions are deemed necessary, the Contracting Officer will establish a competitive range and proposal revisions will be requested.

To receive consideration for award, a rating of ACCEPTABLE must be achieved Factor 1 Prior Experience.

ACCEPTABLE is defined as: the Offeror provided examples that meet all of the Government’s minimum requirements as identified in the solicitation.

UNACCEPTABLE is defined as: the Offeror failed to provide examples that meet all of the Government’s minimum requirements as identified in the solicitation.

Factor 1 Prior Experience (Technical):

The minimum requirements for an Acceptable Rating include all of the following:

• Acceptability is determined when the offeror submits at least three (3), but no more than five (5) recent (completed within the last ten (10) years) example projects of similar size, scope and complexity.

• Acceptability is determined when the offeror’s example projects demonstrate experience where the offeror acted as the prime contractor for an addition or new construction of a multi-story facility AND an addition or new construction project of high tech / high cost medical and or diagnostic equipment OR an addition or new construction project of an

MRI.

Factor 2 Price: The total evaluated price will be determined by the Offeror's price provided on the Price Schedule. The Offeror who provides the lowest price will be determined to be the lowest priced Offeror.

Note: If none of the offerors are within the available funding limitation or is otherwise determined to be other than fair and reasonable, the VA reserves the right to enter into discussions with those offerors who are determined to be within the competitive range.

If the Offeror communicates in its proposal any qualifications, exceptions, exclusions, or conditions to the proposed prices in the Offerors proposal documents, the Contracting Officer may reject the proposal and exclude the Offeror from further discussions.

2.11 RESPONSIBILITY DETERMINATION

In accordance with FAR subpart 9.1, Responsible Prospective Contractors, a responsibility determination will be made for the apparent awardee prior to processing the award. The Contracting Officer reserves the right to request information to assist the Government in determining the apparent successful offeror responsible, including information regarding the offeror’s previous experience (including points of contact), organization (including company officers), technical qualifications, financial resources, and other information deemed necessary.

These requests for information do not constitute discussions. NOTE: Any information received by the Government that would be cause for a negative responsibility determination may deem the offeror ineligible for award.

2.12 VETS 4212

Title 38, USC Section 4212(d), codified at 41 CFR Section 61-300, requires that federal contractors report, at least annually, the number and category of veterans who are within their workforce. Submission of the VETS-4212 reporting information can be done electronically at:

http://www.dol.gov/vets/vets4212.htm. Award cannot be made unless the awardee has filed their VETS-4212 report. Therefore, all offerors are encouraged to file every year. The Contracting Officer may request a copy of the email confirmation of receipt notification prior to awarding the project. Failure to comply with this section will result in removal from award consideration.

2.13 SYSTEM FOR AWARD MANAGEMENT (SAM)

Federal Acquisition Regulations require that federal contractors register in the System for Award Management (SAM) database at https://sam.gov/ and enter all mandatory information into the system. Offerors are required to be registered in SAM.gov at the time an offer is submitted and at the time of award in order to comply with the annual representations and certifications requirements (see FAR 52.204-7). Failure to be registered in SAM.gov at any point during the solicitation period will result in removal from the competition. The initial screening of proposals includes reviewing SAM.gov for compliance with this section.

http://www.dol.gov/vets/vets4212.htm

2.14 REFERENCES TO BIDS/BIDDERS

Within the solicitation/contract specifications and/or drawings, any reference to “bid” must be replaced with “proposal” and any reference to “bidder” must be replaced with “offeror.”

2.15 REVIEW REQUIRED REGISTRATION WITH CONTRACTOR

PERFORMANCE ASSESSMENT REPORTING SYSTEM (CPARS)

As prescribed in Federal Acquisition Regulation (FAR) Part 42.1502(e), the Department of Veterans Affairs (VA) evaluates contractor past performance on all construction contracts that exceed $750,000 and shares those evaluations with other Federal Government contract specialists and procurement officials. The FAR requires that the contractor be provided an opportunity to comment on past performance evaluations prior to each report closing. To fulfill this requirement, VA uses an online database, CPARS, which is maintained by the Naval Sea Logistics Center in Portsmouth, New Hampshire. CPARS is available to all Federal agencies and is the system used to collect and retrieve performance assessment reports used in source selection determinations. CPARS also includes access to the federal awardee performance and integrity information system (FAPIIS). FAPIIS is a web-enabled application accessed via CPARS for contractor responsibility determination information.

Each contractor whose contract award is estimated to exceed $750,000 is required to register with CPARS database at the following web address: http://www.cpars.gov/. Help in registering can be obtained by contacting Customer Support Desk @ DSN: 684-1690 or COMM: 207- 438- 1690. Registration should occur no later than thirty days after contract award and must be kept current should there be any change to the contractor’s registered representative.

For contracts with a period of one year or less, the contracting officer will perform a single evaluation when the contract is complete. For contracts exceeding one year, the contracting officer will evaluate the contractor’s performance annually. Interim reports will be filed each year until the last year of the contract, when the final report will be completed. The report shall be assigned in CPARS to the contractor’s designated representative for comment. The contractor representative will have thirty days to submit any comments and re-assign the report to the VA contracting officer.

Failure to have a current registration in the CPARS database, or to re-assign the report to the VA contracting officer within those thirty days, will result in the Government’s evaluation being placed on file in the database with a statement that the contractor failed to respond.

2.16 BACKGROUND INVESTIGATIONS AND SPECIAL AGREEMENT

CHECKS

All contractor employees are subject to the same level of investigation as VA employees who have access to VA Sensitive Information. The level of background investigation is commensurate with the level of access needed to perform all work as identified in the solicitation documents. This requirement is applicable to all subcontractor personnel requiring the same access. As per VA Directive 0710, costs of background investigations will be borne by the contractor. Please be advised that the awardee will need to coordinate with the VA Medical Center concerning badging requirements. If the site requires an investigation, the contractor shall follow VA Directive 0710.

http://www.cpars.gov/

2.17 REFERENCES TO VA ENGINEER, RESIDENT ENGINEER, OR

PROJECT MANAGER

Any reference contained within the solicitation/contract specifications and/or drawings to the “VA Engineer,” “Resident Engineer,” or “Project Manager,” or their abbreviations shall be replaced with “Contracting Officer’s Representative (COR).”

2.18 52.201-1 ACQUISITION 360: VOLUNTARY SURVEY (SEP 2023)

(a) All actual and potential offerors are encouraged to provide feedback on the preaward and debriefing processes, as applicable. Feedback may be provided to agencies up to 45 days after award. The feedback is anonymous, unless the participant self-identifies in the survey. Actual and potential offerors can participate in the survey by selecting the following link: https:// www.acquisition.gov/360.

(b) The Contracting Officer will not review the information provided until after contract award and will not consider it in the award decision. The survey is voluntary and does not convey any protections, rights, or grounds for protest. It creates a way for actual and potential offerors to provide the Government constructive feedback about the preaward and debriefing processes, as applicable, used for a specific acquisition.

(End of Clause)

2.19 52.216-1 TYPE OF CONTRACT (APR 1984)

The Government contemplates award of a Firm-Fixed-Price contract resulting from this solicitation.

(End of Provision)

2.20 52.222-5 CONSTRUCTION WAGE RATE REQUIREMENTS—

SECONDARY SITE OF THE WORK (MAY 2014)

(a)(1) The offeror shall notify the Government if the offeror intends to perform work at any secondary site of the work, as defined in paragraph (a)(1)(ii) of the FAR clause at 52.222-6, Construction Wage Rate Requirements, of this solicitation.

(2) If the offeror is unsure if a planned work site satisfies the criteria for a secondary site of the work, the offeror shall request a determination from the Contracting Officer.

(b)(1) If the wage determination provided by the Government for work at the primary site of the work is not applicable to the secondary site of the work, the offeror shall request a wage determination from the Contracting Officer.

(2) The due date for receipt of offers will not be extended as a result of an offeror's request for a wage determination for a secondary site of the work.

(End of Provision)

2.21 52.228-1 BID GUARANTEE (SEP 1996)

(a) Failure to furnish a bid guarantee in the proper form and amount, by the time set for opening of bids, may be cause for rejection of the bid.

(b) The bidder shall furnish a bid guarantee in the form of a firm commitment, e.g., bid bond supported by good and sufficient surety or sureties acceptable to the Government, postal money order, certified check, cashier's check, irrevocable letter of credit, or, under Treasury Department regulations, certain bonds or notes of the United States. The Contracting Officer will return bid guarantees, other than bid bonds—

(1) To unsuccessful bidders as soon as practicable after the opening of bids; and

(2) To the successful bidder upon execution of contractual documents and bonds (including any necessary coinsurance or reinsurance agreements), as required by the bid as accepted.

(c) The amount of the bid guarantee shall be 20 percent of the bid price or $3,000,000.00, whichever is less.

(d) If the successful bidder, upon acceptance of its bid by the Government within the period specified for acceptance, fails to execute all contractual documents or furnish executed bond(s) within 10 days after receipt of the forms by the bidder, the Contracting Officer may terminate the contract for default.

(e) In the event the contract is terminated for default, the bidder is liable for any cost of acquiring the work that exceeds the amount of its bid, and the bid guarantee is available to offset the difference.

(End of Provision)

2.22 52.228-17 INDIVIDUAL SURETY—PLEDGE OF ASSETS (BID

GUARANTEE) (FEB 2021)

(a) Offerors shall obtain from each person acting as an individual surety on a bid guarantee—

(1) A pledge of assets that meets the eligibility, valuation, and security requirements described in the Federal Acquisition Regulation (FAR) 28.203–1; and

(2) Standard Form 28, Affidavit of Individual Surety.

(b) The Offeror shall include with its offer the information required at paragraph (a) of this provision within the timeframe specified in the provision at FAR 52.228–1, Bid Guarantee, or as otherwise established by the Contracting Officer.

(c) The Contracting Officer may release the security interest on the individual surety’s assets in support of a bid guarantee based upon evidence that the offer supported by the individual surety will not result in contract award.

2.23 52.233-2 SERVICE OF PROTEST (SEP 2006)

Protests, as defined in section 33.101 of the Federal Acquisition Regulation, that are filed directly with an agency, and copies of any protests that are filed with the Government Accountability Office (GAO), shall be served on the Contracting Officer (addressed as follows) by obtaining written and dated acknowledgment of receipt from:

Hand-Carried Address:

Nicholas Sparks

Department of Veterans Affairs Program Contracting Activity Central 6100 Oak Tree Blvd, Suite 490

Mailing Address:

Nicholas Sparks

Department of Veterans Affairs Program Contracting Activity Central 6100 Oak Tree Blvd, Suite 490 Independence, OH 44131

(b) The copy of any protest shall be received in the office designated above within one day of filing a protest with the GAO.

(End of Provision)

2.24 52.236-27 SITE VISIT (CONSTRUCTION) (FEB 1995) ALTERNATE I

(FEB 1995)

(a) The clauses at 52.236-2, Differing Site Conditions, and 52.236-3, Site Investigations and Conditions Affecting the Work, will be included in any contract awarded as a result of this solicitation. Accordingly, offerors or quoters are urged and expected to inspect the site where the work will be performed.

(b) An organized site visit has been scheduled for—

June 30th, 2025 at 10AM local time

(c) Participants will meet at—

Providence VAMC, 830 Chalkstone Ave, Providence, RI 02908

2.25 52.252-1 SOLICITATION PROVISIONS INCORPORATED BY

REFERENCE (FEB 1998)

This solicitation incorporates one or more solicitation provisions by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. The offeror is cautioned that the listed provisions may include blocks that must be completed by the offeror and submitted with its quotation or offer. In lieu of submitting the full text of those provisions, the offeror may identify the provision by paragraph identifier and provide the appropriate information with its quotation or offer. Also, the full text of a solicitation provision may be accessed electronically at this/these address(es):

https://www.acquisition.gov/browse/index/far https://www.va.gov/oal/library/vaar/

FAR

Number

Title Date

52.204-7 SYSTEM FOR AWARD MANAGEMENT NOV 2024

52.204-16 COMMERCIAL AND GOVERNMENT ENTITY CODE

REPORTING

AUG 2020

52.204-22 ALTERNATIVE LINE ITEM PROPOSAL JAN 2017

52.215-1 INSTRUCTIONS TO OFFERORS—COMPETITIVE

ACQUISITION

NOV 2021

52.236-28 PREPARATION OF PROPOSALS—CONSTRUCTION OCT 1997

2.26 VAAR 852.219-75 VA NOTICE OF LIMITATIONS ON

SUBCONTRACTING—CERTIFICATE OF COMPLIANCE FOR SERVICES AND

CONSTRUCTION (JAN 2023) (DEVIATION)

(a) Pursuant to 38 U.S.C. 8127(l)(2), the offeror certifies that—

(1) If awarded a contract (see FAR 2.101 definition), it will comply with the limitations on subcontracting requirement as provided in the solicitation and the resultant contract, as follows:

(i) [] Services. In the case of a contract for services (except construction), the contractor will not pay more than 50% of the amount paid by the government to it to firms that are not certified SDVOSBs listed in the SBA certification database as set forth in 852.219–73 or certified VOSBs listed in the SBA certification database as set forth in 852.219–74. Any work that a similarly situated certified SDVOSB/VOSB subcontractor further subcontracts will count towards the 50% subcontract amount that cannot be exceeded. Other direct costs may be excluded to the extent they are not the principal purpose of the acquisition and small business concerns do not provide the service as set forth in 13 CFR 125.6.

(ii) [] General construction. In the case of a contract for general construction, the contractor will not pay more than 85% of the amount paid by the government to it to firms that are not certified SDVOSBs listed in the SBA certification database as set forth in 852.219–73 or certified VOSBs listed in the SBA certification database as set forth in 852.219–74. Any work that a similarly situated certified SDVOSB/VOSB subcontractor further subcontracts will count towards the 85% subcontract amount that cannot be exceeded. Cost of materials are excluded and not considered to be subcontracted.

(iii) [] Special trade construction contractors. In the case of a contract for special trade contractors, the contractor will not pay more than 75% of the amount paid by the government to it to firms that are not certified SDVOSBs listed in the SBA certification database as set forth in 852.219–73 or certified VOSBs listed in the SBA certification database as set forth in 852.219–

74. Any work that a similarly situated certified SDVOSB/VOSB subcontractor further subcontracts will count towards the 75% subcontract amount that cannot be exceeded. Cost of materials are excluded and not considered to be subcontracted.

(2) The offeror acknowledges that this certification concerns a matter within the jurisdiction of an Agency of the United States. The offeror further acknowledges that this certification is subject to Title 18, United States Code, Section 1001, and, as such, a false, fictitious, or fraudulent certification may render the offeror subject to criminal, civil, or administrative penalties, including prosecution.

(3) If VA determines that an SDVOSB/ VOSB awarded a contract pursuant to 38 U.S.C. 8127 did not act in good faith, such SDVOSB/VOSB shall be subject to any or all of the following:

(i) Referral to the VA Suspension and Debarment Committee;

(ii) A fine under section 16(g)(1) of the Small Business Act (15 U.S.C. 645(g)(1)); and

(iii) Prosecution for violating 18 U.S.C. 1001.

(b) The offeror represents and understands that by submission of its offer and award of a contract it may be required to provide copies of documents or records to VA that VA may review to determine whether the offeror complied with the limitations on subcontracting requirement specified in the contract. Contracting officers may, at their discretion, require the contractor to demonstrate its compliance with the limitations on subcontracting at any time during performance and upon completion of a contract if the information regarding such compliance is not already available to the contracting officer. Evidence of compliance includes, but is not limited to, invoices, copies of subcontracts, or a list of the value of tasks performed.

(c) The offeror further agrees to cooperate fully and make available any documents or records as may be required to enable VA to determine compliance with the limitations on subcontracting requirement. The offeror understands that failure to provide documents as requested by VA may result in remedial action as the Government deems appropriate.

(d) Offeror completed certification/fill-in required. The formal certification must be completed, signed and returned with the offeror’s bid, quotation, or proposal. The Government will not consider offers for award from offerors that do not provide the certification, and all such responses will be deemed ineligible for evaluation and award.

Certification

I hereby certify that if awarded the contract, [insert name of offeror] will comply with the limitations on subcontracting specified in this clause and in the resultant contract. I further certify that I am authorized to execute this certification on behalf of [insert name of offeror].

Printed Name of Signee: ___________

Printed Title of Signee: _____________

Signature: ____________

Date: ______________

Company Name and Address: _______________

(End of Clause)

2.27 VAAR 852.228-72 ASSISTING SERVICE-DISABLED VETERAN-OWNED

AND VETERAN-OWNED SMALL BUSINESSES IN OBTAINING BONDS (DEC

2009) Prime contractors are encouraged to assist service-disabled veteran-owned and veteran-owned small business potential subcontractors in obtaining bonding, when required. Mentor firms are encouraged to assist protégé firms under VA's Mentor-Protégé Program in obtaining acceptable bid, payment, and performance bonds, when required, as a prime contractor under a solicitation or contract and in obtaining any required bonds under subcontracts.

(End of Clause)

2.28 VAAR 852.233-71 ALTERNATE PROTEST PROCEDURE (OCT 2018)

(a) As an alternative to filing a protest with…

This is the start of the file's text. The full file is on GovTribe.