RFQ27006992 Murray Center HVAC Project Manual.pdf
PDF 10 MB Posted
- Attached to
- RIC Murray Center Gym HVAC Improvements
- Solicitation number
- RFQ27006992
- Issued by
- Providence County, Rhode Island
About this file
This is a Project Manual for HVAC improvements at Rhode Island College's Murray Center, prepared by RGB Architects for the State of Rhode Island Board of Education. The project involves the addition of air conditioning to the gymnasium at 600 Mount Pleasant Avenue, Providence, RI, including the installation of two new air handling units, replacement of existing HVAC equipment (units #2-1 and #2-2), new insulated ductwork, two 80-ton air-cooled condensers with aluminum enclosure screening, and associated piping, electrical, and controls integration. The work encompasses both exterior work (concrete pad and condenser installation) and interior modifications to existing systems. Three addenda have been issued as of the publication date of March 2026, with bid due dates revised to May 26, 2026, and subsequent contract start date targeted for June 23, 2026. A non-mandatory pre-bid meeting was scheduled for September 17, 2026. The project includes specific liquidated damages provisions and establishes a critical path schedule with final completion targeted for June 7, 2027, with interior gym work allocated for a six-week window from April 19, 2027 to May 28, 2027.
The contract is structured as a single prime contract based on stipulated price under AIA Document A101-2017, as amended by the State of Rhode Island. The General Conditions follow AIA Document A201-2007, as amended by the state. The contract requires prevailing wage compliance in accordance with Rhode Island Department of Labor rates updated July 1 annually. Performance and payment bonds are required per AIA A312 documents. The Contractor must provide schedule of values, monthly applications for payment on AIA G702/G703 forms, certified payroll records, and lien waivers. A testing and inspection allowance is included, with regular testing costs incorporated into the base bid and additional testing covered by separate allowance. The project requires coordination with an occupied facility, with strict working hour restrictions (7:00 AM to 4:00 PM Monday through Friday as regular hours, with off-hours work permitted only with advance coordination). The Contractor is responsible for all permits, licensing fees, temporary facilities, waste management, and site restoration, with costs of coordination and any premium time wages included in the base bid price.
View the file
Other files
Show all 14
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
PROJECT MANUAL
RHODE ISLAND COLLEGE
Murray Center HVAC Updates
600 Mt Pleasant Ave Providence, RI 02908
RGB #6963
March 2026
SECTION 00 01 01 Murray Center HVAC Updates, RIC
TITLE PAGE
© THE ROBINSON GREEN BERETTA CORPORATION – 6963 Section 00 01 01 - Page 1 of 1
00 01 01 – TITLE PAGE
Owner:
State of Rhode Island Board of Education, Rhode Island College, and State of Rhode Island
User Agency:
Capital Projects Administration
Rhode Island College
600 Mount Pleasant Avenue
Welcome Center Suite 300
Providence, RI 02908
Phone: (401) 456-9885
Design Agent:
RGB Architects
50 Holden Street
Providence, Rhode Island 02908
(401) 272-1730
Structural:
C.A. Pretzer Associates, INC.
50 Freeway Drive, Cranston, RI 02920
(401) 785-2690
Mechanical and Electrical:
DM Engineering
225 Dyer Street
Providence, Rhode Island 02908
(929) 333-2339
TABLE OF CONTENTS Murray Center HVAC Updates, RIC
TABLE OF CONTENTS
© THE ROBINSON GREEN BERETTA CORPORATION – 6963 Section 00 01 10 Page 1 of 3
Division ........ Section Title .................................................................................................................... Pages
SPECIFICATIONS GROUP
General Requirements Subgroup
DIVISION 00 - PROCUREMENT AND CONTRACTING REQUIREMENTS
00 00 00 ....... COVER
00 01 01 ....... TITLE PAGE
00 01 10 ....... TABLE OF CONTENTS
00 01 15…….LIST OF DRAWINGS
00 40 00 ....... STATE PROCUREMENT DOCUMENTS
00 43 00 ....... BID BOND
00 50 00…….CONTRACTING FORMS
00 51 00 ....... NOTICE OF AWARD
00 52 00 ....... AGREEMENT FORM
00 55 00 ....... NOTICE TO PROCEED
00 61 00…….BOND FORMS
00 62 00 ....... CERTIFICATES AND OTHER FORMS
00 65 00 ....... CLOSEOUT FORMS
00 72 00 ....... GENERAL CONDITIONS
00 73 43…. PREVAILING WAGE RATES
00 91 13 ....... ADDENDA AND MODIFICATIONS
DIVISION 01 - GENERAL REQUIREMENTS
01 00 50 ....... GENERAL REQUIREMENTS
01 02 00 ....... CONTRACT LIST OF DRAWINGS
01 10 00 ....... SUMMARY OF THE WORK
01 14 00…….COORDINATION OF WORK
01 17 90 ....... UTILITY PLANNING AND INTERRUPTIONS
01 20 00 ....... PRICES AND PROCEDURES
01 21 00 ....... ALLOWANCES
01 22 00 ....... UNIT PRICES
01 23 00 ....... ALTERNATES
01 25 00 ....... SUBSTITUTION PROCEDURES
01 26 00…….CONTRACT MODIFICATION PROCEDURES
01 29 00 ....... PAYMENT PROCEDURES
01 30 00 ....... ADMINISTRATIVE REQUIREMENTS
01 31 00 ....... PROJECT MANAGEMENT AND COORDINATION
01 32 00…….CONSTRUCTION PROGRESS DOCUMENTATION
01 33 00 ....... SUBMITTAL PROCEDURES
01 35 23 ....... HOT WORK PROCEDURE
01 35 24 ....... MANAGING FIRE PROTECTION SYSTEM IMPAIRMENT
01 40 00 ....... QUALITY REQUIREMENTS
01 42 00 ....... REFERENCES
01 45 35…. SPECIAL INSTRUCTIONS
01 50 00 ....... TEMPORARY FACILITIES AND CONTROLS
01 60 00…….PRODUCT REQUIREMENTS ……………………………………………………………………. .. 3
01 71 00…….EXAMINATION AND EXECUTION
01 73 00…….EXECUTION
01 74 13…….CLEANING
01 74 20 ....... CONSTRUCTION WASTE MANAGEMENT AND DISPOSAL
01 78 00 ....... CLOSEOUT PROCEDURES
TABLE OF CONTENTS Murray Center HVAC Updates, RIC
TABLE OF CONTENTS
© THE ROBINSON GREEN BERETTA CORPORATION – 6963 Section 00 01 10 Page 2 of 2
DIVISION 02- EXISTING CONDITIONS/SITEWORK
02 41 20 ....... SELECTIVE DEMOLITIONS
DIVISION 03 – CONCRETE
03 30 00 ....... CAST IN PLACE CONCRETE
DIVISION 05 – METALS
05 50 00 ....... METAL FABRICATIONS
DIVISION 07 - THERMAL AND MOISTURE PROTECTION
07 72 00 ....... ROOF ACESSORIES
07 92 00 ....... JOINT SEALANTS
DIVISION 09 - FINISHES
09 91 00 ....... PAINTING INTERIOR & EXTERIOR
DIVISION 31 – EARTHWORK
31 50 05 ....... EARTHWORK FOR SMALL PROJECT
DIVISION 32 – SITE IMPROVEMENT
32 35 00 ...... SCREENING DEVICES
DIVISION 23 – MECHANICAL
23 05 00 ....... BASIC MECHANICAL MATERIAL AND METHODS
23 05 13 ....... MOTOR AND CONTROLLERS
23 05 29 ...... HANGERS AND SUPPORTS
23 05 48 ....... MECHANICAL VIBRATION CONTROLS AND SEISMIC RESTRAINTS
23 05 53 ....... MECHANICAL IDENTIFICATION
23 05 93 ....... TESTING, ADJUSTING, AND BALANCING
23 07 13 ....... DUCT INSULATION
23 07 19 ....... HVAC PIPING INSULATION
23 21 13 ....... HYDRONIC PIPING
23 21 16 ....... HYDRONIC PIPING SPECIALTIES
23 31 00 ....... SHEET METAL WORK AND ACCESSORIES
23 37 00 ....... REGISTERS, GRILLES AND DIFFUSERS
23 39 00 ....... FANS AND ACCESSORIES
23 73 23 ....... FACTORY BUILT-UP AIR HANDLING UNITS
23 81 13 ....... PACKAGED TERMINAL AIR CONDITIONERS
25 05 00 ....... BASIC MATERIALS AND METHODS
25 10 00 ....... DIRECT DIGITAL/AUTOMATIC TEMPERATURE CONTROLS
DIVISION 26 – ELECTRICAL
26 05 00 ....... COMMON WORK RESULTS FOR ELECTRICAL
26 05 19 ....... LOW-VOLTAGE ELECTRICAL POWER CONDUCTORS AND CABLES
26 05 26 ....... GROUNDING AND BONDING FOR ELECTRICAL SYSTEMS
26 05 29 ....... HANGERS AND SUPPORTS FOR ELECTRICAL SYSTEMS
26 05 33 ....... RACEWAYS AND BOXES FOR ELECTRICAL SYSTEMS
26 05 44 ....... SLEEVES AND SLEEVE SEALS FOR ELECTRICAL RACEWAYS AND CABLING
26 05 53 ....... IDENTIFICATIONS FOR ELECTRICAL SYSTEMS
26 20 01 ....... FEEDERS AND BRANCH CIRCUITRY
26 20 10 ....... LOW VOLTAGE DISTRIBUTION
26 28 13 ....... FUSES
END TABLE OF CONTENTS
SECTION 00 01 15 Murray Center HVAC Updates, RIC
LIST OF DRAWINGS
© THE ROBINSON GREEN BERETTA CORPORATION – 6963 Sec�on 00 01 15 - Page 1 of 2
00 01 15 – LIST OF DRAWINGS
GENERAL
G000 COVER SHEET
ARCHITECTURAL
C 100 SITE PLAN
STRUCTURAL
S100 ENLARGED PLAN OF MECHANICAL ENCLOSURE PAD
FIRE PROTECTION
FA001 FIRE ALARM COVER SHEET
FA100 FIRE ALARM PLANS
MECHANICAL
M001.00 MECHANICAL SYMBOLS, LEGEND & NOTES
M002.00 MECHANICAL EQUITMENT SCHEDULE
DM101.00 DEMOLLITION PLAN MECHANICAL DUCTWORK/PIPING
M101.00 MECHANICAL DUCTWORK
M201.00 MECHANICAL PIPING
M301.00 ELEVATION VIEW
M401.00 MECHANICAL CONTROLS
M501.00 MECHANICAL DETAILS
M1.2 MECHANICAL 2ND FLOOR PLAN DUCT SYSTEM (EXISTING PLAN)
SECTION 00 01 15 Murray Center HVAC Updates, RIC
LIST OF DRAWINGS
© THE ROBINSON GREEN BERETTA CORPORATION – 6963 Sec�on 00 01 15 - Page 2 of 2
M5.0 MECHANICAL: EQUIPMENT SCHEDULES
ELECTRICAL
E001 ELECTRICAL SYMBOLS AND NOTES
E200 ELECTRICAL PLANS
E300 ELECTRICAL RISER
END OF SECTION
SECTION 00 40 00 Murray Center HVAC Updates, RIC
STATE PROCURMENT DOCUMENTS
© THE ROBINSON GREEN BERETTA CORPORATION – 6963 Section 00 40 00 - Page 1 of 1
00 40 00 – STATE PROCURMENT DOCUMENTS
Procurement documents are provided under separate cover.
SECTION 00 43 00 Murray Center HVAC Updates, RIC
BID BOND
© THE ROBINSON GREEN BERETTA CORPORATION – 6963 Sec�on 00 43 00 - Page 1 of 4
00 43 00 – BID BOND
See AIA Document A310-2010, example attached as the following page.
BID BOND
© THE ROBINSON GREEN BERETTA CORPORATION – 6963 Sec�on 00 43 00 - Page 2 of 4
BID BOND
© THE ROBINSON GREEN BERETTA CORPORATION – 6963 Sec�on 00 43 00 - Page 3 of 4
BID BOND
© THE ROBINSON GREEN BERETTA CORPORATION – 6963 Sec�on 00 43 00 - Page 4 of 4
SECTION 00 50 00 Murray Center HVAC Updates, RIC
CONTRACTING FORMS
© THE ROBINSON GREEN BERETTA CORPORATION – 6963Section 00 50 00 - Page 1 of 1
00 50 00 – CONTRACTING FORMS
PART 1 - GENERAL
COPYRIGHT
A. Contractor is responsible for obtaining a valid license to use all copyrighted documents specified or included in the Project Manual.
AGREEMENT AND CONDITIONS OF THE CONTRACT
A. See Section 00 5200 for the Agreement form to be executed.
B. See Section 00 7200 for the General Conditions.
FORMS
A. Use the following forms for the specified purposes unless otherwise indicated elsewhere in the Contract Documents.
B. Bond Forms:
1. Performance Bond and Payment Bond Forms: AIA A312
C. Release of Lien:
1. Release of Liens Form: AIA G706A
2. RIC Waiver of Liens Form 01 20 00
D. Insurance certificate, supplementary attachment:
1. ACORD Certificate of Insurance Form: AIA G715
REFERENCE STANDARDS
A. AIA G706A – Release of Liens: 1994.
B. AIA A312 - Performance Bond: 2010 and Payment Bond: 2010.
C. AIA G715 – ACORD Certificate of Insurance: 1991.
PART 2 - PRODUCTS (NOT USED)
PART 3 - EXECUTION (NOT USED)
SECTION 00 51 00 Murray Center HVAC Updates, RIC
NOTICE OF AWARD
© THE ROBINSON GREEN BERETTA CORPORATION – 6963 Sec"on 00 51 00 - Page 1 of 1
00 51 00 – NOTICE OF AWARD
RI State Purchasing shall issue the Notice of Tentative Award.
SECTION 00 52 00 Murray Center HVAC Updates, RIC
AGREEMENT FORM PART
© THE ROBINSON GREEN BERETTA CORPORATION – 6963 Section 00 52 00 - Page 1 of 1
00 52 00 – AGREEMENT FORM PART
1 - GENERAL
AGREEMENT FORM
A. The Agreement Form to be utilized on this project is AIA Document A101-2017 as amended by the state https://ridop.ri.gov/vendor-resources/public-works-aia-custom-state-rhode-islanddocuments.
B. Agreement made as of the date of issue of the Purchase Order for this Work.
C. This Agreement is entered into as of the date of the applicable Purchase Order and is assumed as executed once the Purchase Order is issued.
PART 2 - PRODUCTS (NOT USED)
PART 3 - EXECUTION
EXECUTION OF THE AGREEMENT
A. Following the issuance of the Notice of Tentative Award, the user Agency, Design Team and
Contractor shall convene a Pre-Award Conference. Meeting minutes from the Pre-Award
Conference and acceptance of the minutes by the Contractor shall be incorporated into the
Contract.
B. The User Agency will transmit the A101-2017 to the Contractor for signature. The Contractor will sign and return the contract to the User Agency, who then transmits it to the RI State
Purchasing Office for final signatures.
SECTION 00 55 00 Murray Center HVAC Updates, RIC
NOTICE TO PROCEED
© THE ROBINSON GREEN BERETTA CORPORATION – 6963 Sec�on 00 55 00 - Page 1 of 1
00 55 00 – NOTICE TO PROCEED
RI State Purchasing shall issue the Purchase Order. The User Agency shall issue the Notice to Proceed, per
AIA A101-2017 as amended by the state §3.1.
SECTION 00 61 00 Murray Center HVAC Updates, RIC
BOND FORMS
© THE ROBINSON GREEN BERETTA CORPORATION – 6963 Sec�on 00 61 00 - Page 1 of 1
00 61 00 – BOND FORMS
The RI State Purchasing Notice of Tentative Award indicates the required bonding forms for this project.
SECTION 00 62 00 Murray Center HVAC Updates, RIC
CERTIFICATES AND OTHER FORMS
© THE ROBINSON GREEN BERETTA CORPORATION – 6963 Sec�on 00 62 00 - Page 1 of 1
00 62 00 – CERTIFICATES AND OTHER FORMS
PART 1 - GENERAL
1.1 ARCHITECT PROVIDED CERTIFICATES AND PROJECT FORMS (NOT USED)
1.1 USER AGENCY PROVIDED FORMS (NOT USED)
PART 2 - PRODUCTS (NOT USED)
SECTION 00 65 00 Murray Center HVAC Updates, RIC
CLOSEOUT FORMS
© THE ROBINSON GREEN BERETTA CORPORATION – 6963 Sec on 00 65 00 - Page 1 of 1
00 65 00 – CLOSEOUT FORMS
PART 1 - GENERAL
CLOSEOUT FORMS
A. The following forms are required as part of the closeout documentation:
1. Transmittal on Contractor’s letter head for each package of documents transmitted.
2. Upon Substantial Completion, the User Agency shall provide copies of the AIA Documents indicated in Section 01 74 19.
PART 2 - PRODUCTS (NOT USED)
SECTION 00 72 00 Murray Center HVAC Updates, RIC
GENERAL CONDITIONS PART
© THE ROBINSON GREEN BERETTA CORPORATION – 6963 Section 00 72 00 - Page 1 of 1
00 72 00 – GENERAL CONDITIONS PART
1 - GENERAL
GENERAL CONDITIONS
A. The General Conditions to be utilized on this project are AIA Document A201-2007 as amended by the state. https://ridop.ri.gov/vendor-resources/public-works-aia-custom-state-rhode-island-documents
PART 2 - PRODUCTS (NOT USED)
PART 3 - EXECUTION
EXECUTION OF THE GENERAL CONDITIONS
A. The User Agency will transmit the A201-2007 as amended by the state to the Contractor. The contractor shall initial and return to the User Agency, who then transmits it to the RI State
Purchasing Office.
B. Any conflicts with the general provisions included in the project manual, and the A201-2007 as amended by the state, the provisions in form A201-2007 as amended by the state will take precedence.
SECTION 00 73 43 Murray Center HVAC Updates, RIC
PREVAILING WAGE RATES
© THE ROBINSON GREEN BERETTA CORPORATION – 6963 Section 00 73 43 - Page 1 of 1
00 73 43 – PREVAILING WAGE RATES
The State of Rhode Island Department of Labor, Division of Professional Regulation General Decision
Modification document is an integral part of the Bid Documents for use in fulfilling prevailing wage rate requirements. A copy is available linked to the web site of the State of Rhode Island Department of
Administration, Division of Purchases. Contractors working on RI Prevailing Wage projects must adjust employee hourly rates every July 1 in accordance with updated Davis Bacon rates. These rates may be obtained at the following website:
https://sam.gov/content/wage-determinations
The Division of Purchases Web Site Address is: http://www.purchasing.ri.gov/RIVIP/Info.asp
The link for the US Government prevailing wage tables is:
http://www.purchasing.ri.gov/bidinfo/geninfo/geninfo.aspx
Applicable Rhode Island labor laws may be found at: http://www.dlt.ri.gov/pw/
SECTION 00 91 13 Murray Center HVAC Updates, RIC
ADDENDA AND MODIFICATIONS
© THE ROBINSON GREEN BERETTA CORPORATION – 6963 Sec�on 00 91 31 - Page 1 of 1
00 91 13 – ADDENDA AND MODIFICATIONS
PART 1 - GENERAL
A. As of the time of publication of this Project Manual, 3 Addenda had been issued.
B. Addenda issued during the Bid Period, will augment this Document and become a part of the Project
Manual.
C. Such Addenda and Modifications when issued, with reference to the Project Manual, the General
Conditions, Supplemental General Conditions, Drawings or Specifications, shall be inserted following this page and become integral parts of the Contract Documents.
MURRAY CENTER, HVAC UPDATES
PROVIDENCE, RHODE ISLAND
ADDENDUM NO. 1
May 8, 2026
The attention of Bidders submitting proposals for the above-mentioned project in at Rhode Island College in Providence, RI, is called to the following addendum to the Contract Documents. The following additions, clarifications, and/or deletions are hereby to be included in their entirety with the scope of the Contract Documents, and shall, in turn, form a part of the proposals submitted for Bid.
CHANGES/CLARIFICATIONS TO THE STATE OF RHODE ISLAND RFQ – REQUEST FOR
QUOTE OF PUBLIC WORKS
Addendum 1.1 DELETED from Section F: ALTERNATES: “Add Alternate 1” in its entirety, and “Deduct Alternate #2” in its entirety.
CHANGES/CLARIFICATIONS TO THE PROJECT MANUAL & SPECIFICATIONS
Addendum 1.2 ADD specification Section 013000 “RIC Administrative Requirements” to the project manual.
Addendum 1.3 ADD specification Section 013100 “Project Management & Coordination” to the project manual.
Addendum 1.4 ADD specification Section 013200 “Construction Progress Documentation” to the project manual.
Addendum 1.5 ADD specification Section 013300 “RIC Submittal Procedures” to the project manual.
Addendum 1.6 ADD specification Section 013523 “RIC Hot Work Procedures” to the project manual.
Addendum 1.7 ADD specification Section 013524 “RIC Managing Fire Protection Systems” to the project manual.
Addendum 1.8 ADD specification Section 015000 “RIC Temporary Facilities & Controls” to the project manual.
Addendum 1.9 REPLACE specification Section 232113 “Hydronic Piping” in its entirety with the attached new Section 232113 “Hydronic Piping”
Addendum 1.10 REPLACE specification Section 232116 “Hydronic Piping Specialties” in its entirety with the attached new Section 232116 “Hydronic Piping Specialties”
Addendum 1.11 REPLACE specification Section 237323 “Factory Built-up Air Handling Units” in its entirety with the attached new Section 237323 “Factory Built-up Air Handling Units”
QUESTIONS & ANSWERS
1. This project has liquidated damages. At time of award will the owner work with the contractor to establish an agreeable schedule based on long lead items, and the contractor will not be penalized by liquidated damages for any long lead items that we cannot control delivery on?
Please see the new critical path schedule proposed by Rhode Island College.
Liquidated damages will remain in effect as specified.
• 5/19/26 Bids due
• 6/16/26 Contract start (target)
• ASAP Long lead Submittals begin
• ASAP Long Lead items order released
• 12/15/27 (or earlier) HVAC equipment on-site.
• 12/15/27 Interior Gym work starts (to be finalized with AD)
• 1/8/27 Interior Gym work complete (4 weeks)
• 1/15/27 Final completion (hard deadline)
The GC shall coordinate the other required work (electrical, exterior, snow guards, etc.) along this critical path with the majority of non-gym area work to be completed prior to 12/15/26.
2. Has the lead time of the equipment been verified with the manufacturer to meet the project schedule?
No. The schedule has been adjusted. Please see the answer to question #1.
3. Has the fire review been completed, and if so, will the cost be paid by the owner or the GC?
Drawings were submitted on 4/3/26. The review is in progress. The General Contractor shall pay all permit fees.
4. Does the project have RIBCC approval
The project has been submitted and approval is pending. 5. Please confirm alternates on bid are correct?
The alternates on the bid are incorrect and are hereby removed as part of Addendum 1, item 1.1.
6. Please confirm there will be a staging area available for contractor parking, storage containers, dumpster.
A staging area will be provided in the Physical Plant parking lot to the rear (west) of the Murray Center.
7. Please provide existing FA system manufacturer?
The existing fire alarm panel is Gamewell FCI Model E3 series by Honeywell.
8. Please confirm we are painting all new duct work and HVAC equipment?
All new and existing ductwork in the gym shall be painted, color to match existing.
9. Please confirm gym floor can support lift for work to be completed in ceiling of gym?
The General Contractor shall submit the lift(s) intended for use to the College for review and approval by the floor manufacturer. Additionally, the GC will need to protect the wood floor as to not damage during work. This protection method shall be submitted for review as well. The GC will be responsible to repair any damage done to the wood floor due to construction
10. Spec section 012000 mentions a testing & inspection allowance, but we do not see one on the bid form. Please confirm.
Testing & Inspections of the concrete will be carried by the College under a separate contract. No additional testing is anticipated.
11. What contractor currently holds the roof warranty?
The current roof warranty is serviced by Capeway Roofing Systems.
12. Spec sections 013000 – 015000 seem to be missing from the manual, please provide?
Specification Sections 013000 – 015000 have been added to the Project Manual by this addendum as listed above.
13. Please confirm once contractor is mobilized, they will have complete access to the entire gym for the duration of the work during normal workings hours? The contractor will not have to turn over the work area certain days during construction?
The Contractor will have complete access to the Gym for four (4) weeks.
14. Please confirm we are not to include off hours work in our bid?
The General Contract shall provide the mean & methods to meet the revised schedule in the answer to question #1.
END OF DOCUMENT
RFQ26006544 - RIC HVAC IMPROVEMENTS MURRAY CENTER GYM
ADDENDUM NO. 2
May 15, 2026
The attention of Bidders submitting proposals for the above-mentioned project in at Rhode Island College in Providence, RI, is called to the following addendum to the Contract Documents. The following additions, clarifications, and/or deletions are hereby to be included in their entirety with the scope of the Contract Documents, and shall, in turn, form a part of the proposals submitted for Bid.
The number of this Addendum, Addendum No. 2, must be entered in the space provided on the Bid Form.
REVISION TO QUESTIONS AND ANSWERS:
1. This project has liquidated damages. At time of award will the owner work with the contractor to establish an agreeable schedule based on long lead items, and the contractor will not be penalized by liquidated damages for any long lead items that we cannot control delivery on?
Please see the new critical path schedule proposed by Rhode Island College.
Liquidated damages will remain in effect as specified.
• 5/26/26 Bids due
• 6/23/26 Contract start (target)
• 6/29/26 Long lead Submittals begin (or ASAP)
• 7/6/26 (week of) Long Lead items order released (ASAP)
• 10/23/26 (or earlier) HVAC equipment on-site.
• 4/19/2027 Interior Gym work starts (to be finalized with AD)
• 5/28/27 Interior Gym work complete (6 weeks)
• 6/7/27 Final completion (hard deadline)
This schedule is for bidding purposes. The only fixed dates are for the availability of the gym. The GC shall be responsible for the final schedule and coordinate the other required work (electrical, exterior, snow guards, etc.) along this critical path.
It is the intent of this contract to have all work that does not occur inside the gym be complete prior to start of winter.
MURRAY CENTER, HVAC UPDATES
PROVIDENCE, RHODE ISLAND
ADDENDUM NO. 3
May 28, 2026
The attention of Bidders submitting proposals for the above-mentioned project in at Rhode Island College in Providence, RI, is called to the following addendum to the Contract Documents. The following additions, clarifications, and/or deletions are hereby to be included in their entirety with the scope of the Contract Documents, and shall, in turn, form a part of the proposals submitted for Bid.
The number of this Addendum, Addendum No. 3, must be entered in the space provided on the Bid Form.
REVISION TO SCOPE OF WORK:
3.1 The scope of work added in Addendum #3 shall include demolition and removal of the existing units (#2-1 and #2-2 that feed the class room areas); rigging and installation of two new Trane Performance Climate Changer air-handling units (used as basis of design see attached cut sheets of units); reconnection to the existing ductwork, chilled water, hot water, condensate, electrical power, and controls; conversion from the existing arrangement to a 4-pipe coil configuration with external 6-way valves in lieu of face-and-bypass dampers; associated electrical modifications for power reconnection, disconnects, controls power, and coordination with the new fan/VFD arrangement; startup, controls integration, and final testing and balancing / air-system rebalancing to restore the intended air distribution to the adjacent areas served by these units.
The selected replacement units are both provided with 15 HP supply fans. Air handlers HVAC Unit #2-1 and Unit #2-2 are in the Gym as indicated in the attached drawing M1.2 (6/14/93) and drawing M5.0 (6/14/93). The work shall include all sheet metal work to be painted to match existing duct work in the gym; as required for complete, operable, and warrantable installation.
SECTION 01 00 50 Murray Center HVAC Updates, RIC
GENERAL REQUIREMENTS AT EXISTING FACILITIES
© THE ROBINSON GREEN BERETTA CORPORATION – #6963 Section 01 00 50 - Page 1 of 8
SECTION 01 00 50 - GENERAL REQUIREMENTS AT EXISTING FACILITIES
PART 1 - GENERAL
1.1 RELATED DOCUMENTS
A. The General Conditions, Supplementary Conditions and applicable portions of Division 1 of the Specification are a part of this Section, which shall consist of all labor, materials, equipment, tools, construction equipment and machinery, water, heat, utilities, transportation and other facilities and services necessary for the proper execution and completion of the work, whether temporary or permanent and whether or not incorporated or to be incorporated in the work; and as related to the project or projects defined in the Bidding Requirements.
B. The specification format used herein is in accordance with MASTERFORMAT, CSI (2004 Format) and in no way intends to restrict this Contractor from expediting his work as he sees fit, nor is there any intention of segregating the units of work as related to specific trades involving jurisdictional problems.
1.2 CONTRACTOR'S DUTIES
A. The Contractor is responsible for all personnel involved in the work, including those of his direct employ, his sub-contractors and suppliers of materials and equipment and/or labor. The Technical Specifications have been divided for convenience only to cover the scope of work, and where reference to a particular contractor is noted, it is for convenience only. The Owner and Architect only recognize one Contractor as party to this Contract.
B. As it is impractical to enumerate every piece of equipment, device and/or accessory required for proper operation of the indicated systems specified within their respective Sections or Divisions of the Project Manual; it is intended that all materials, systems, and/or equipment, required to insure proper operation of the equipment, device, and/or accessory, be provided as a part of the Work of this Project so the specified work or system functions, and/or performs as required by the specification. To infer the intent is otherwise, is to render the specified work or system less than required.
C. Except as specifically noted, provide and pay for:
1. Labor, materials and equipment.
2. Tools, construction equipment and machinery.
3. Other facilities and services necessary for proper execution and completion of the Work.
D. Pay sales, consumer, use and similar taxes for the Work or portions thereof.
E. Secure and pay for, as necessary for proper execution and completion of the Work, and as applicable at time of receipt of Bids:
1. Permits.
2. Government fees.
3. Licenses.
F. Give required notices.
SECTION 01 00 50 Murray Center HVAC Updates, RIC
© THE ROBINSON GREEN BERETTA CORPORATION – #6963 Section 01 00 50 - Page 2 of 8
G. Comply with codes, ordinances, rules, regulations, orders and other legal requirements of public authorities which bear on the performance of the Work.
H. Promptly submit written notice to the Architect of observed variance of Contract Documents from legal requirements.
I. Lay out all work and be responsible for all lines, elevations, measurements of the building, utilities and site work executed under the Contract. Verify the figures shown before laying out the Work and be responsible for any error resulting from failure to do so. Employ a competent registered engineer or registered land surveyor, approved by the Architect, for establishing all lines, levels and dimensions, and place at the disposal of the Architect, as required for checking purposes.
J. Enforce strict discipline and good order among employees. Do not employ persons not skilled in assigned task.
K. Notify all trades, sub-contractors and suppliers of all designated alternatives and be responsible for their coordination.
L. At your option, certain indicated materials and/or procedures are specified herein to be used in lieu of other indicated materials and/or procedures, at no change in Contract Price. Such options should be analyzed and coordinated during the bidding period, so that the selection of any may immediately be brought to the Architect's attention, once the Contract is awarded (within thirty days thereafter).
1.3 SCOPE OF THE WORK: Includes but is not limited to:
A. EXTERIOR:
1. Furnishing and installing a new concrete pad, (2) 80-ton air cooled condensers, and 10’ height aluminum encloser with gates.
B. INTERIOR:
1. Removing the existing Gym duct work and HVAC units (HV2-1, 2-2). Adding structural reinforcing to existing joists to accommodate the new insulated duct work and AHU as required. Paint existing and new duct work in gym.
1.4 SPECIAL CONDITIONS
A. The Contractor must schedule the Work, in the various rooms with the Owner, a minimum of seven days in advance.
B. The Owner will make available to the Contractor requested spaces, to be determined during the course of the Work. Upon substantial completion of the work in these areas and a minimal punch list, the Owner will make additional spaces available to the Contractor. Punch list completion must be scheduled to permit notification of tenants.
C. Miscellaneous work in other areas of the building must be scheduled seven (7) days in advance and approved by the Owner.
D. The Contractor is responsible to physically isolate all work areas, to protect residents, while maintaining safe egress.
SECTION 01 00 50 Murray Center HVAC Updates, RIC
© THE ROBINSON GREEN BERETTA CORPORATION – #6963 Section 01 00 50 - Page 3 of 8
E. The Contractor shall maintain a professional relationship with all tenants, employees and other occupants. All incidents with the residents must be promptly reported to the Owner or the Owner's Representative. The Owner will resolve all issues with all employees and other occupants.
F. Use of premises:
1. No storage of materials in the building. (Locate trailer in area designated by the Owner, and repair all damaged areas upon completion of the work.)
2. Provide office trailer and toilet facilities for work force. Do not use building facilities.
3. No smoking on the site or within the buildings.
4. Daily clean-up required.
5. Use of on-site utilities, electric and water permitted. Do not overtax existing systems.
6. Major movement of materials must be scheduled so as to minimize inconvenience of the tenants. Coordinate with the Owner.
7. Notify the Owner of utility interruptions a minimum of thirty-six (36) hours in advance.
1.5 HEALTH AND SAFETY PRECAUTIONS
A. HAZARDOUS BUILDING MATERIALS:
1. Prior to commencing any removal or demolition operations, coordinate with the Owner/Operator to ensure that an asbestos survey has been conducted, in accordance with National Emission Standard for Hazardous Air Pollutants (NESHAP), 40 CFR, Part M, Section 61.145, of the Clean Air Act.
2. Notify the EPA prior to demolition/renovation operations in which more than 260 L.F. or 160 S.F. of regulated asbestos-containing material (RACM) is to be stripped or removed from facility components.
3. If during the course of the Work hazardous materials are encountered, or suspicion exists that such may be prevalent, including, but not limited to asbestos and/or lead paint, immediately and prior to any removal, contact the governing agency for testing and removal procedures.
B. OSHA:
1. These construction documents, and the joint and several phases of construction hereby contemplated, are to be governed, at all times, by the applicable portions of the Federal Laws, including but not limited to, the latest amendments of the following:
a. Williams-Steiger Occupational Safety and Health Act of 1970, Public Law 91-956;
b. Part 1910 - Occupational Safety and Health Standards, Title 29, Code of Federal
Regulations, as amended to date;
c. Part 1926 - Safety and Health Regulations for Construction, Title 29, Code of Federal Regulations, as amended to date.
2. This Project, the Contractor and his sub-contractors shall, at all times, be governed by applicable Chapters of Title 29, Code of Federal Regulations, Part 1926 - Safety and Health Regulations for Construction, as amended to date.
a. Note: Furnish the Owner and Architect copies of all accident reports.
C. Dig Safe:
SECTION 01 00 50 Murray Center HVAC Updates, RIC
© THE ROBINSON GREEN BERETTA CORPORATION – #6963 Section 01 00 50 - Page 4 of 8
1. All excavations near underground public utility facilities shall be performed in accordance with Connecticut State Law.
D. Emergencies:
1. Should tornado, hurricane, gale or heavy wind warnings be issued, take precautions to minimize the danger to persons, to the work, and to the adjacent property. Damage caused to any part of the work shall be rectified or replaced to the complete satisfaction of the Architect and at no expense to the Owner. Injury to personnel or damage to adjacent property because of the work shall be the complete responsibility of the Contractor, and he accepts exclusive responsibility for same.
E. Loading:
1. Do not load any part of the work involved in this Contract, during construction, with a load greater than it is calculated to carry with safety. Should any accidents or damage occur through any violation of this requirement, the Contractor shall be held responsible under his Contract and Bond. When, in the opinion of the Architect, portions of the structure appear to be overloaded, it shall be the Contractor's responsibility to prove otherwise, or the Contractor shall follow the instructions of the Architect in connection with reduction of the loads.
1.6 PROJECT RECORD DOCUMENTS
A. Maintain at job site, one copy of:
1. Contract Drawings.
2. Specifications.
3. Addenda.
4. Reviewed Shop Drawings.
5. Record Drawings.
6. Change Orders.
7. Other modifications to Contract.
8. Field Test Reports.
9. Approved materials, samples and colors.
B. Store documents in approved field construction office, apart from documents used for construction.
1. Provide files and racks for storage of documents.
2. File documents in accordance with Project Filing Format of MASTERFORMAT.
3. Maintain documents in clean, dry, legible condition.
4. Do not use record documents for construction purposes.
5. Make documents available at all times for inspection by Architect and Owner.
C. Recording changes:
1. Provide red pen or pencil for all marking.
2. Keep record documents current.
3. Do not permanently conceal any work until required information has been recorded.
4. Contract Drawings: Legibly mark to record actual construction and the following:
a. Record various elements of foundations in relation to lowest floor elevation.
SECTION 01 00 50 Murray Center HVAC Updates, RIC
© THE ROBINSON GREEN BERETTA CORPORATION – #6963 Section 01 00 50 - Page 5 of 8
b. Reference horizontal and vertical location of underground utilities and appurtenances to permanent surface improvements.
c. Reference location of internal utilities and appurtenances concealed in construction to visible and accessible features of structure.
d. Record field changes of dimensions and details.
e. Record changes made by Change Order or Field Order.
f. Record details not on original Contract Drawings.
5. Specifications and Addenda: Legibly mark up each Section to record the following:
a. Manufacturer, trade name, catalog number, and supplier of each product and item of equipment actually installed.
b. Changes made by Change Order and Field Order.
c. Other matters and materials not previously specified.
6. Shop Drawings: Maintain as record documents; legibly annotate drawings to record changes after review.
1.7 TRANSPORTATION AND HANDLING
A. Transport all materials and equipment on legally approved conveyances as required or recommended by the respective manufacturer or supplier.
B. Receive and handle all materials and equipment, at the project site, by conveyances or methods as recommended by the respective manufacturer or supplier.
C. Coordinate delivery of equipment and materials when two or more trades, contractors or suppliers are involved.
D. Remove from the site any material or item of equipment damaged during the transportation or handling process, and immediately replace at no additional cost to the Owner.
1.8 STORAGE AND PROTECTION
A. Store all materials and equipment as recommended by the respective manufacturer or supplier, including the following minimum requirements.
B. Upon receipt of such materials and equipment, check, distribute, store and safeguard in a clean, dry, ventilated location.
C. Elevate off the ground, items which can be stored in exterior locations, and completely cover with approved tarpaulins. Protect against the elements at all times.
D. Maintain all storage areas in a clean and orderly condition at all times.
E. Immediately replace any material or item of equipment damaged, due to inadequate storage protection, at no additional cost to the Owner.
1.9 CUTTING AND PATCHING
A. Execute cutting, including excavating, fitting or patching work required to:
SECTION 01 00 50 Murray Center HVAC Updates, RIC
© THE ROBINSON GREEN BERETTA CORPORATION – #6963 Section 01 00 50 - Page 6 of 8
B. Make several parts fit properly.
C. Uncover work to provide for installation of ill-timed work.
D. Remove and replace defective work.
E. Remove and replace work not conforming to the Contract Documents.
F. Remove samples of installed work, as specified, for testing.
G. Install specified work in existing construction.
1. In addition to the Contract requirements, upon written instructions from Architect:
a. Uncover work to provide for Architect's observation of covered work, as required by General Conditions.
b. Remove samples of installed materials for testing; as required by the General Conditions.
2. Do not endanger any work by cutting or altering work, or any part of it.
3. Do not cut or alter work of another Contractor without written permission of the Architect.
4. Prior to cutting which affects structural safety of Project, or work of another Contractor, submit written notice to Architect requesting consent to proceed with cutting.
5. Prior to cutting and patching, done on instruction of the Architect, submit cost estimate.
6. Should conditions of work, or schedule, indicate change of materials or methods, submit written recommendations to the Architect including:
a. Conditions indicating change.
b. Recommendations for alternative materials or methods.
c. Submittals required for Substitutions.
H. Submit written notice, to the Architect, designating time work will be uncovered, to provide for observation.
I. Payment for costs caused by ill-timed or defective work, or work not conforming to the Contract Documents, including costs for additional services of Architect will be borne by the Contractor.
J. Contractor Inspection:
1. Inspect existing conditions of work, including elements subject to movement or damage during:
a. Cutting and patching.
b. Excavating and backfilling.
2. After uncovering work, inspect conditions affecting installation of new products.
K. Preparation: (prior to cutting)
1. Provide shoring, bracing and support as required to maintain structural integrity of the Project.
2. Provide protection for other portions of the Project.
3. Provide protection from the elements.
SECTION 01 00 50 Murray Center HVAC Updates, RIC
© THE ROBINSON GREEN BERETTA CORPORATION – #6963 Section 01 00 50 - Page 7 of 8
L. Performance: Perform all work of fitting, adjustment, cutting, patching, finishing, and restoration to perfectly match the quality as specified throughout these specifications.
1.10 CONNECTING TO AND USE OF EXISTING
A. Demolish and remove from site all existing construction work as indicated. Do such work in a neat and orderly manner so as not to endanger the lives of the working force nor cause damage to adjacent surfaces indicated to remain.
B. Remove portions of existing work as indicated or required, and perfectly patch, match and tie into the new work.
C. Repair existing walls, floors, ceilings, partitions, doors, frames, etc., where required for tieing into, including existing systems such as electrical or mechanical, etc.
D. If existing conditions, indicated to remain, include defective work, deteriorated or rotted materials, immediately notify the Architect. Do not conceal such materials.
E. Relocate and remove certain existing items, facilities and equipment, as indicated. Items designated to be removed, and not be re-used, shall remain the property of the Owner and placed on the site where directed by the Owner.
F. Quality of Work/Responsibility to Match Existing:
1. Perfectly match the existing building finishes for all new work, unless otherwise specified or shown. Such matching includes quality, style, character, finish and color. Likewise, repair or replace, in exact likeness to the existing, any existing surfaces, materials, fixtures, or items damaged by the process of completing the new work.
1.11 CONTRACTOR USE OF PREMISES
A. Confine operations at site to areas permitted by:
1. Law.
2. Ordinances.
3. Permits.
4. Contract Documents.
B. Do not unreasonably encumber the site with materials and equipment.
C. Do not load structure with weight that will endanger structure.
D. Assume full responsibility for protection and safekeeping of products stored on the premises.
E. Move any stored products which interfere with operations of Owner or other Contractor.
F. Obtain and pay for use of additional storage or work areas needed for operations.
G. Limit use of site for work and storage within confines of the Project Limit Line.
SECTION 01 00 50 Murray Center HVAC Updates, RIC
© THE ROBINSON GREEN BERETTA CORPORATION – #6963 Section 01 00 50 - Page 8 of 8
1.12 PARTIAL OWNER OCCUPANCY
A. Schedule early completion of designated areas for Owner's usage prior to Substantial Completion of the entire Project.
B. Contractor provide:
1. Access for Owner personnel.
2. Operation of mechanical and electrical systems.
C. Prior to occupancy, execute Certificate of Substantial Completion for designated areas.
PART 2 - PRODUCTS (Not Applicable)
PART 3 - EXECUTION (Not Applicable)
END OF SECTION 01 00 50
SECTION 01 10 00 Murray Center HVAC Updates, RIC
SUMMARY
© THE ROBINSON GREEN BERETTA CORPORATION – 6963 Section 01 10 00 - Page 1 of 2
01 10 00 – SUMMARY
PART 1 - GENERAL
1.1 PROJECT
A. The Project consists of the construction of the following types of work:
1. New addition of air conditioning to the gym area. Which includes new concrete pad, aluminum enclosure and (2) air cooled condensers to the rear West of the exterior. Interi-or work to include (2) air handler units and new insulated duct work in the gym, paint to match existing.
1.2 CONTRACT DESCRIPTION
A. Contract Type: A single prime contract based on a Stipulated Price as described in Document
00 50 00 – Contracting Forms.
1.3 DESCRIPTION OF WORK
A. Scope of demolition and removal work is shown on drawings plus as specified in Section
020600
B. Scope of alterations work is shown on drawings and/or as specified herein.
C. Site modifications as shown on drawings and/or as specified herein.
1.4 SCHEDULE
A. The date of commencement of the Work shall be the latter of: (i) the issuance of the Purchase
Order by the Owner; and (ii) the date set forth in a notice to proceed issued by the User
Agency.
B. Ordering of products, Building Permit, coordination and preparatory work shall commence immediately upon receipt of Purchase Order.
C. Construction at the site can commence immediately upon receipt of PO and building permit and shall be agreed upon with the User Agency.
D. The substantial completion date is August 1st . This is the date to which liquidated damages may apply and may only be adjusted as provided for in the Contract Documents. Contractor shall be responsible for completing the submittals required for issue of a Purchase Order in a timely manner. No extension will be granted for purchasing delays. Contractor shall account for any premium time required to meet the substantial completion date of August 1st,2026 in their base bid.
E. Final Completion is September 1st,2026. This date represents the completion of all outstand-ing punch list items and complete demobilization of the site.
F. Cooperate with User Agency to minimize conflict and to facilitate the facility’s operations.
1.5 ITEMS TO BE SALVAGED
No items removed and not identified for reinstallation shall be salvaged
SECTION 01 10 00 Murray Center HVAC Updates, RIC
SUMMARY
© THE ROBINSON GREEN BERETTA CORPORATION – 6963 Section 01 10 00 - Page 2 of 2
1.6 SUBCONTRACTOR CERTIFICATION REQUIREMENTS
A. Installation certification from the roof manufacturer for the roofing subcontractor for both the asphalt shingle roofing and membrane roofing. Refer to roofing specification section for clar-ification specifics.
PART 2 - PRODUCTS (NOT USED)
SECTION 01 14 00 Murray Center HVAC Updates, RIC
COORDINATION OF WORK WITH USER AGENCY
© THE ROBINSON GREEN BERETTA CORPORATION – 6963 Section 01 14 00 - Page 1 of 5
01 14 00 – COORDINATION OF WORK WITH USER AGENCY
PART 1 - GENERAL
1.1 SECTION INCLUDES
A. Contractor Use of Site and Premises.
B. Utility and Building Services Outages and Shutdowns.
C. Construction Requirements in Occupied Buildings.
D. Construction Activities in Occupied Spaces.
E. Time Restrictions and Working Hours.
F. Schedule Coordination.
1.2 CONTRACTOR USE OF SITE AND PREMISES
A. User Agency intends to continuously occupy the facility. Work areas will be made available as mutually agreed to during project scheduling.
B. Construction Operations: Limited to areas noted on Drawings. Coordinate with Site Utilization Requirements. Include in the Base Bid all costs of this coordination, including all premium time wages that may be required to meet these requirements and project schedule. Cost of all work done during second or third shifts or on weekends and holidays shall be included in the bid price. Contractor is responsible for protection and restoration of existing conditions in-cluding, but not limited to hardscape, landscape and lawns.
C. Arrange use of site and premises to allow:
1. Adjacent projects to progress as planned for the User Agency.
2. Use of street and adjacent properties by the Public.
3. Continued operation of the facility.
D. For activities requiring closure of parking lots, roadways and/or walkways, seven (7) days’ no-tice is required. Refer to Section 01 50 00 Temporary Facilities and Controls for further infor-mation.
E. Provide access to and from site as required by law and by User Agency:
1. Maintain appropriate egress for workforce and users of the facility.
2. Do not obstruct roadways, sidewalks, or other public ways without permit. Provide neces-sary signage and barriers to direct pedestrians around work areas.
3. Barriers and signage must be provided by the contractor to the satisfaction of the User Agency to separate the work area from occupied areas. Efforts must be taken to limit dust, noise and odors from escaping the work area. Proper separation and protection of interior spaces shall be established and maintained during the project, to the satisfaction of the User Agency.
4. Contractor is responsible for cleaning construction dust and/or debris from public areas and daily or at the request of the User Agency. Work areas within the building shall be kept tidy at all times.
SECTION 01 14 00 Murray Center HVAC Updates, RIC
© THE ROBINSON GREEN BERETTA CORPORATION – 6963 Section 01 14 00 - Page 2 of 5
5. Contractor shall provide and maintain walk-off mats at all entrances to the work site from occupied areas.
1.3 UTILITY AND BUILDING SERVICES OUTAGES AND SHUTDOWN:
A. Prevent accidental disruption of utility services to other facilities. Contractor is responsible for restoration and damages resulting from unplanned disruptions to utilities.
B. For life safety systems interruptions or shutdowns, including but not limited to fire sprinklers and fire alarm system, seven (7) days’ written notice to User Agency and authorities having jurisdiction shall be provided. Contractor to utilize Fire Sprinkler and Alarm System Impair-ment Notification Forms found in Section 00 73 02. Contractor is responsible for providing Fire Alarm Technician or support personal to provide the necessary bypassing or fire watch as required for fire sprinkler or other life safety shutdowns.
C. Electrical, plumbing, network and other utility shutdowns shall be scheduled off hours. Con-tractor shall provide written request for utility shutdown at least 72 hours in advance.
D. When construction activities impact ventilation, heating or air conditioning to occupied build-ing spaces, the contractor shall provide the necessary equipment to maintain proper ventila-tion rates and a temperature of 68° heating and 72° cooling. Prior to the decommissioning of equipment, the contractor shall submit a plan for temporary HVAC services, including unit lo-cation, utility connection, ductwork tie in and other logistical considerations.
1.4 CONSTRUCTION REQUIREMENTS FOR OCCUPIED BUILDINGS:
A. User Agency intends to continuously occupy the facility. Work areas will be made available as mutually agreed to during project scheduling.
B. The building and surrounding areas will be occupied during construction. The Contractor shall be solely responsible for initiating, maintaining and supervising safety, security and protection programs and shall comply with all applicable laws, ordinances, rules and regulations con-cerning safety of people and the protection of property.
C. Barriers and signage must be provided by the contractor to the satisfaction of the User Agen-cy to separate the work area from occupied areas. Appropriate signage, approved by the Us-er Agency, shall be placed at all potential entrances to the Project Site and maintained throughout the project.
D. Efforts must be taken to limit dust, noise and odors from escaping the work area. Proper sep-aration and protection of interior spaces shall be established and maintained during the pro-ject, to the satisfaction of the User Agency. Contractor shall provide and maintain walk-off mats and plastic barriers at work site entries.
E. Contractor shall provide appropriate masking of building supply air intakes to protect indoor air quality and limit transfer of odors. Contractor to coordinate with User Agency regarding shut down of appropriate units as work continues.
F. Contractor to provide air scrubbing and/or negative air machines to prevent odors from es-caping the Project Site.
G. During the progress of the Work, the Contractor shall so conduct his work that as little incon-venience as possible is caused to the occupants. At the close of the work each day, the Con-tractor shall pick up and stow all equipment and miscellaneous material leaving the site in a neat and safe condition.
SECTION 01 14 00 Murray Center HVAC Updates, RIC
© THE ROBINSON GREEN BERETTA CORPORATION – 6963 Section 01 14 00 - Page 3 of 5
H. The Contractor shall repair or replace, at his own expense, with new any item, surface, or ob-ject that is damaged by the Contractor or damaged because of the Contractor's actions dur-ing the course of the Work and during any guarantee period.
I. Site and building conditions shall be restored to their condition as they were at the start of the Work. Before commencing work, the Contractor shall report any existing damage to the Ar-chitect in writing to assure that the Contractor will not be liable for preexisting damage.
J. Contractor is responsible for cleaning construction dust and/or debris from public areas and daily or at the request of the User Agency. Work areas within the building shall be kept tidy at all times.
K. Refer to Section 01 50 00 – TEMPORARY FACILITIES AND CONTROLS for more infor-mation.
1.5 CONSTRUCTION ACTIVITIES IN OCCUPIED SPACES
A. The Project Site is defined as the immediate rooms under construction at a given time. Any work in vertically or horizontally adjacent classrooms, hallways, MEP/IT/FP spaces and grounds outside the footprint indicated on the Site Utilization Plan shall be considered as be-ing outside the Project Site.
This is the start of the file's text. The full file is on GovTribe.