RFQ27006912 A1.pdf
PDF 2 MB Posted
- Attached to
- RIC Murray Center Gym HVAC Improvements
- Solicitation number
- RFQ27006992
- Issued by
- Providence County, Rhode Island
About this file
This is Addendum No. 1 to the contract documents for HVAC improvements at Rhode Island College's Murray Center in Providence, Rhode Island, issued by the State of Rhode Island Division of Purchases. The addendum provides critical revisions to the mechanical drawings and clarifications regarding the scope of work for replacement of two existing air handling units (AHU-1, AHU-2, AHU-2-1, and AHU-2-2) with new refrigerant-based systems and modifications to the existing hydronic loop. Key changes include updated mechanical drawings (M-001.00 through M-501.00) with revision clouds indicating scope modifications, confirmation that the glycol system requires no rebalancing as AHU-1 and AHU-2 are refrigerant-based while AHU-3 and AHU-4 reuse the existing chilled-water system, clarification that no masonry work is required for duct modifications, confirmation that equipment will be provided in shipping splits to facilitate installation through double doors, and verification that all low-voltage cabling for the building management system will be provided by the contractor. Additionally, the addendum clarifies that no structural reinforcement of existing steel joists is required, as a structural engineer has confirmed the new equipment loading does not necessitate reinforcement. The equipment specifications include AHU-1 and AHU-2 units measuring 191.90 inches long by 112.50 inches wide by 70.75 inches high, each divided into four shipping sections with weights ranging from 1,020 to 1,970 pounds per section, and AHU-2-1 and AHU-2-2 units measuring 173.96 inches long by 93.50 inches wide by 65 inches high, also in four shipping sections with weights from 540 to 1,750 pounds per section.
The addendum establishes comprehensive general notes and mechanical specifications requiring contractors to provide complete and operational HVAC systems in accordance with 2021 Rhode Island Building and Mechanical Codes and 2024 Rhode Island Energy Code, with all work executed in a neat and workmanlike manner per manufacturer recommendations. Contractors must obtain all permits and inspections prior to construction and conduct a pre-bid site visit to verify field conditions and investigate installation requirements. The contractor bears responsibility for all costs associated with equipment substitutions, structural modifications, relocation of existing conduits and junction boxes, selective ceiling demolition and restoration, vibration isolation, flexible ductwork connections, and contingency costs for conflicts between design and existing conditions. A one-year warranty on all materials, equipment, and installations is required from the date of acceptance by the owner, and contractors must provide shop drawings for architect/engineer review prior to purchasing or installing equipment, along with final as-built drawings in AutoCAD format upon project completion. The scope explicitly excludes work related to flood mitigation or flood damages, and the contract documents reference associated electrical, plumbing, fire alarm, and structural drawings that must be reviewed and coordinated by all subcontractors.
View the file
Other files
Show all 14
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
RHODE ISLAND COLLEGE
MURRAY CENTER, HVAC UPDATES
PROVIDENCE, RHODE ISLAND
ADDENDUM NO. 1
September 24, 2026
The attention of Bidders submitting proposals for the above-mentioned project in at Rhode Island College in Providence, RI, is called to the following addendum to the Contract Documents. The following additions, clarifications, and/or deletions are hereby to be included in their entirety with the scope of the Contract Documents, and shall, in turn, form a part of the proposals submitted for Bid.
The number of this Addendum, Addendum No. 1, must be entered in the space provided on the Bid Form.
CHANGES/CLARIFICATIONS TO THE DRAWINGS
Addendum 1.1 REPLACE the following drawings in the bid set with the drawings in the attached. The revisions are identified with revision clouds/bubbles to clearly indicate the updated scope.
Please also note the updated equipment selection and shipping splits.
M-001.00 Mechanical Symbols, Legends & Notes M-002.00 Mechanical Equipment Schedules MD-101.00 Second Floor Mechanical Demolition Plan Ductwork/Piping Plan M-101.00 Lower Floor Mechanical Ductwork Plan M-102.00 First Floor Mechanical Ductwork Plan M-103.00 Second Floor Mechanical Ductwork Plan M-201.00 Second Floor Mechanical Piping Plan M-301.00 Elevation Views
QUESTIONS & ANSWERS
1. Will glycol system need rebalancing?
No. AHU-1 and AHU-2 are refrigerant-based systems and are not connected to the hydronic loop. AHU-3 and AHU-4 will reuse the existing indoor DTS/DTR chilled-water system, which does not contain glycol. The contractor shall balance the new AHU-3 and AHU-4 coil water flows to the scheduled design values.
2. What is the required floor protection system to protect the gym flooring?
See attached Addendum 01 sheet MD-101.00 dated 9/23/2026
3. Please confirm there is no masonry work for any duct work modifications?
See attached Addendum 01 sheet MD-101.00 dated 9/23/2026.
Also, new units can be provided in shipping splits to allow the equipment to be brought into the gym through the available double doors and assembled in place. The design team has coordinated revised equipment selections accordingly. Please see the attached updated selections, along with the shipping split summary, which identifies the approximate dimensions of each individual section for rigging and access coordination.
4. Drawing C100, please confirm how many rows of snow guard are to be installed. Plans show double row at each location.
The snow guards have (2) bars on a single retention bar, (8) rows total.
5. Please confirm that all low voltage cabling for the BMS system will be handled by contractor.
Confirmed. All low-voltage wiring and cabling required for the BMS controls and integration shall be provided by the contractor.
6. Per the specifications, the existing steel joists are required to be reinforced. However, the drawings do not indicate the required reinforcement details, quantities, or existing conditions of the joists.
Please clarify.
The design team has had a structural engineer check the loading for the new units, and confirmed that there will not be any reinforcement needed.
END OF DOCUMENT
PROJECT:
SUBMITTED BY:
EQUIPMENT:
Tag Qty Description Dimensions Shipping
Sections AHU-1 1 AHU-1 191.90"L x 112.50"W x 70.75"H 4 AHU-2 1 AHU-1 191.90"L x 112.50"W x 70.75"H 4
SHIPPING SECTION INFO:
Tag Section Section
Length Section Weight
Module Module Length Module Width Module Height Module Weight
AHU-1 1 48 1020 Air mixing section 48 70.75 112.50 1013.72 2 39.98 1020 Coil section 39.98 70.75 112.50 1018.79 3 57.83 1480 Coil section 43.83 70.75 112.50 1188.19
Access section 14 70.75 112.50 282.20 4 45.71 1970 Fan section 45.71 70.75 112.50 1969.25
AHU-2 1 48 1020 Air mixing section 48 70.75 112.50 1013.72 2 39.98 1020 Coil section 39.98 70.75 112.50 1018.79 3 57.83 1480 Coil section 43.83 70.75 112.50 1188.19
Access section 14 70.75 112.50 282.20 4 45.71 1970 Fan section 45.71 70.75 112.50 1969.25
Shipping Split Report
PROJECT:
SUBMITTED BY:
EQUIPMENT:
Tag Qty Description Dimensions Shipping
Sections AHU-2-1 1 AHU-2-1 173.96"L x 93.50"W x 65"H 4 AHU-2-2 1 AHU-2-2 173.96"L x 93.50"W x 65"H 4
SHIPPING SECTION INFO:
Tag Section Section
Length Section Weight
Module Module Length Module Width Module Height Module Weight
AHU-2-1 1 46 620 Air mixing section 46 65 93.50 616.08 2 38.35 540 Coil section 38.35 65 93.50 530.97 3 42.92 970 Coil section 42.92 65 93.50 969.93 4 46.69 1750 Fan section 46.69 65 93.50 1743.90
AHU-2-2 1 46 620 Air mixing section 46 65 93.50 616.08 2 38.35 540 Coil section 38.35 65 93.50 530.97 3 42.92 960 Coil section 42.92 65 93.50 957.73 4 46.69 1750 Fan section 46.69 65 93.50 1743.90
Shipping Split Report
POINT OF DISCONNECTION
POINT OF NEW CONNECTION
DUCT SYMBOLS
PIPING SYMBOLS
REFRIGERANT LIQUID GAS LINE
RISER, WATER, STEAM AND/OR RETURN
FLOOR CONNECTION
CEILING CONNECTION TO FLOOR ABOVE
DROP
RISE
TEE TAKEOFF
INDICATES SUPPLY AIR
INDICATES EXHAUST AIR
ACCESS DOOR (SIZES VARY AS SHOWN
ON DRAWINGS)
A.A.D. - AUTOMATIC AIR OPERATED LOUVER DAMPER
C.F.M. - CUBIC FEET PER MINUTE
C.C. - COOLING COIL
C.O.D. - CLEAN OUT DOOR
EF. - EXHAUST FAN
F.D. - FIRE DAMPER
GR. - GRILLE (WITH VOLUME DAMPER)
M.A.D. - MANUAL AIR OPERATED LOUVER DAMPER
O.A.I. - OUTSIDE AIR INTAKE (FRESH AIR INLET)
ABBREVIATIONS
A.D.- ACCESS DOOR
REMOVE EXISTING PIPING
REMOVE EXISTING DUCTWORK
COMBINATION OF BALANCING
AND SHUT OFF VALVE
CONTROL SYMBOLS
CONTROL VALVE
PNEUMATIC THERMOSTAT
ELECTRO-PNEUMATIC SWITCH
MANUAL SWITCH
S
DUCT SMOKE DETECTOR
VOLUME DAMPER VD
FD FIRE DAMPER
EQUIPMENT TO REMAIN
EXISTING PIPING, DUCTWORK,
NEW WORK
RETURN DUCTWORK
NEW WORK
REFRIGERANT GAS PIPE LINE
D.N. - DRAIN
HMI - HUMAN MACHINE INTERFACE
(E) - EXISTING
DIGITAL THERMOSTAT
AND ACCESS DOOR
CARBON DIOXIDE SENSOR
FSD COMBINATION FIRE-SMOKE DAMPER
SMOKE DAMPER
SD
VENT. - VENTILATION
WMS - WIRE MESH SCREEN
MECHANICAL GENERAL NOTES
CONDENSATE PIPE LINE
COMBUSTION VENT
EA. - EXHAUST AIR (CFM)
RA. - RETURN AIR (CFM)
SA. - SUPPLY AIR (CFM)
SUMMER:
WINTER:
SUMMER:
WINTER:
78°F(DB)/50% RH
89°F(DB)/73°F(WB)
OUTSIDE AMBIENT DESIGN PARAMETERS:
INSIDE AMBIENT DESIGN PARAMETERS:
72°F(DB)
13°F(DB)
MOTORIZED DAMPER MD
AND ACCESS DOOR
DOOR UNDERCUT
HEATING AND COOLING SYSTEM CAPACITY IS BASED ON THE FOLLOWING DESIGN CONDITIONS.(AS PER
THE LATEST ASHRAE CODE).
1. THE WORK TO BE DONE UNDER THESE SPECIFICATIONS AND THE DRAWINGS CONSISTS OF PROVIDING ALL EQUIPMENT, MATERIALS, LABOR AND SERVICES AND PERFORMING ALL OPERATIONS TO COMPLETE THE MECHANICAL CONSTRUCTION WORK FOR THIS PROJECT. ANY WORK NOT SPECIFICALLY COVERED BY THESE SPECIFICATIONS OR INDICATED ON THE MECHANICAL/ELECTRICAL/PLUMBING PLANS, BUT NECESSARY TO COMPLETE OR PERFECT ANY PART OF THIS INSTALLATION IN A SUBSTANTIAL MANNER, SHALL BE PROVIDED WITHOUT EXTRA COST TO THE OWNER.
2. THE TERM "FURNISH" SHALL MEAN TO OBTAIN AND SUPPLY TO THE JOB SITE. THE TERM "INSTALL" SHALL MEAN TO FIX IN POSITION AND CONNECT FOR USE. THE TERM "PROVIDE" SHALL MEAN TO FURNISH AND INSTALL. THE TERM "MECHANICAL WORK" OR “WORK" SHALL MEAN ALL LABOR, MATERIAL, EQUIPMENT, SCAFFOLDING, RIGGING, TOOLS, SUPERVISION, SERVICES AND OTHER INCIDENTALS NECESSARY FOR COMPLETE AND
OPERABLE INSTALLATION.
3. THE CONTRACTOR SHALL FURNISH AND INSTALL ALL EQUIPMENT, MATERIALS AND LABOR TO PROVIDE A COMPLETE AND OPERATIONAL SYSTEM AS
INDICATED ON THE DESIGN DOCUMENTS.
4. ALL WORK SHALL BE EXECUTED IN A NEAT AND WORKMANLIKE MANNER AND SHALL BE DONE IN ACCORDANCE WITH GOOD TRADE PRACTICE AND IN
CONFORMANCE WITH APPLICABLE MANUFACTURERS RECOMMENDATIONS.
5. THE DRAWINGS INDICATE DIAGRAMMATICALLY THE EXTENT, GENERAL CHARACTER, LOCATION AND ARRANGEMENT OF THE WORK UNDER THIS CONTRACT. WHERE JOB CONDITIONS REQUIRE MINOR CHANGES OR ADJUSTMENTS IN THE INDICATED LOCATIONS OR ARRANGEMENT OF THE WORK, SUCH CHANGES SHALL BE PROVIDED WITHOUT EXTRA COST THE CONTRACTOR SHALL RE-INSTALL EQUIPMENT THAT HAS INADEQUATE OR
UNSAFE ACCESSIBILITY.
6. CONTRACTOR SHALL VERIFY FIELD CONDITIONS AT THE SITE AND NOTIFY THE OWNER/ENGINEER OF ANY DISCREPANCIES PRIOR TO AWARDING OF
BID.
7. COORDINATE HVAC SYSTEM INSTALLATION WITH EXISTING CONDITIONS. VISIT SITE PRIOR TO BID AND INVESTIGATE REQUIREMENTS FOR HVAC
SYSTEM INSTALLATION. SEE THE SPECIFICATIONS FOR ADDITIONAL REQUIREMENTS.
8. ALL CHANGES MADE IN THE FIELD SHALL BE RECORDED ON AS-BUILT DRAWINGS, SHOP DRAWINGS, AND MAINTENANCE MANUALS. PROVIDE FINAL
AS-BUILT CONDITIONS IN AUTOCAD FORMAT.
9. CONTRACTOR SHALL PROVIDE SHOP DRAWINGS PER SPECS PRIOR TO PURCHASING OR INSTALLING EQUIPMENT AND SYSTEMS INDICATED ON CONTRACT DOCUMENTS. PRIOR TO SUBMITTAL, CONTRACTOR SHALL VERIFY THAT ADEQUATE SPACE EXISTS FOR THE
SUBMITTED EQUIPMENT. SHOP DRAWINGS MUST BE REVIEWED BY ARCHITECT/ENGINEER.
10. CONTRACTOR SHALL OBTAIN ALL PERMITS, INSPECTIONS AND APPROVALS PRIOR TO CONSTRUCTION, AND PAY ALL RELATED FEES. OWNER WILL
HIRE AND PAY FOR EXPEDITOR FEES. ALL PERMIT FEES ARE BY CONTRACTOR.
11. ALL MATERIALS, EQUIPMENT AND INSTALLATIONS SHALL BE IN STRICT ACCORDANCE WITH APPLICABLE BUILDING AND MECHANICAL CODES, SMACNA, UL, MANUFACTURERS' RECOMMENDATIONS, AND TO THE REQUIREMENTS OF FEDERAL, STATE AND LOCAL REGULATORY AGENCIES AND
AUTHORITIES HAVING JURISDICTION.
12. IN THE ABSENCE OF OTHER SPECIFIC INSTRUCTIONS, ALL WORK AND MATERIALS SUPPLIED SHALL BE GUARANTEED FOR A PERIOD OF ONE (1)
YEAR FROM THE DATE OF THEIR ACCEPTANCE BY THE OWNER.
13. CONTRACTOR SHALL NOT CONCEAL ANY WORK UNTIL INSPECTED BY MECHANICAL INSPECTOR AND/OR ARCHITECT /ENGINEER. CONTRACTOR
SHALL NOTIFY A/E OF A SCHEDULED INSPECTION TIME WITHIN 72 HOURS.
14. GENERAL CONTRACTOR SHALL NOT CONCEAL WORK UNTIL APPROVED, REGARDLESS OF SCHEDULE.
15. REFER TO SPECIFICATIONS ON DRAWINGS, DETAILS AND EQUIPMENT SCHEDULES FOR ADDITIONAL INFORMATION.
16. ALL EQUIPMENT, PIPING AND VALVES SHALL HAVE SPECIFIED IDENTIFICATION LABELS AND AS INDICATED.
17. CONTRACTOR AND HIS SUBCONTRACTORS SHALL WORK WITH A FULL SET OF LATEST MECHANICAL DRAWINGS. IT IS CONTRACTOR'S RESPONSIBILITY TO OBTAIN THESE DRAWINGS FROM GENERAL CONTRACTOR OR CONSTRUCTION MANAGER.
18. THE CONTRACTOR SHALL BE RESPONSIBLE FOR ALL COSTS INCURRED BY OTHER TRADES DUE TO SUBSTITUTION OF OTHER THAN SCHEDULED EQUIPMENT. WHEN EQUIPMENT FURNISHED IS DIFFERENT THAN INDICATED, THE COST OF ADDITIONAL ELECTRICAL SERVICE, STRUCTURAL AND
RELATED WORK SHALL BE PAID BY THIS CONTRACTOR.
19. EACH TRADE CONTRACTOR SHALL RECEIVE ALL DRAWINGS AND SPECIFICATION SECTIONS ISSUED AS PART OF THE OVERALL BID PACKAGE. ALL CONTRACTORS ARE TO RECEIVE, REVIEW, AND COORDINATE ALL OF THEIR WORK AS SHOWN OR REFERENCED ON THE OTHER TRADE DOCUMENTS.
ALL WORK SHOWN OR REFERENCED ON THE OTHER
TRADE DOCUMENTS SHALL BE INCLUDED AS PART OF THE OVERALL PROJECT SCOPE FOR THAT PARTICULAR DISCIPLINE AND TRADE.
20. SCHEDULE THE WORK UNDER THIS CONTRACT WITH WORK OF OTHER TRADES AS NOT TO DELAY THE OVERALL PROGRESS OF THE PROJECT.
21. PRIOR TO EQUIPMENT STARTUP, CONTRACTOR SHALL PERFORM THE SPECIFIED STARTUP AND COMMISSIONING PROCEDURES.
22. NOTIFY ARCHITECT/ENGINEER OF ANY CONFLICTS PRIOR TO PURCHASING EQUIPMENT AND PRIOR TO CUTTING OPENINGS.
23. REVIEW ALL DISCIPLINES DRAWINGS INCLUDING ARCHITECTURAL AND STRUCTURAL, AND COORDINATE IN FIELD ALL WORK WITH OTHER TRADES AND WITH EXISTING CONDITIONS PRIOR TO INSTALLATION OF ANY WORK. REPORT ALL CONFLICTS IMMEDIATELY TO ARCHITECT AND/OR ENGINEER.
24. VERIFY THE ACTUAL LOCATIONS AND EXACT DIMENSIONS OF ALL EQUIPMENT, CASEWORK, DEVICES, FIXTURES, SWITCHES, SENSORS, ETC. DURING FIELD VISITS AND PRIOR TO PERFORMING ANY ROUGH-IN WORK FOR THE UTILITIES AND DUCTWORK. REPORT DISCREPANCIES IMMEDIATELY TO
ARCHITECT AND/OR ENGINEER.
25. ALL ADJUSTABLE THERMOSTATS AND TEMPERATURE SENSORS SHALL BE MOUNTED 46" ABOVE FINISHED FLOOR.
26. COORDINATE LOCATION OF ALL WALL, FLOOR AND ROOF OPENINGS WITH STRUCTURAL AND OTHER TRADES.
27. COORDINATE THE LOCATIONS OF ALL EQUIPMENT AND REGISTERS WITH THE LATEST ARCHITECTURAL DRAWINGS PRIOR TO PERFORMING AND
ROUGH-IN WORK FOR THE UTILITIES.
28. SCHEDULE ALL WORK, CUTTING AND BUILDING SERVICE INTERRUPTIONS WITH BUILDING OWNER AND CONSTRUCTION MANAGER PRIOR TO
COMMENCING WITH THE WORK.
29. ANY CHANGES AND/OR MODIFICATIONS MUST BE REVIEWED AND APPROVED BY THE ENGINEER AND/OR OWNER'S REPRESENTATIVE PRIOR TO
CONSTRUCTION.
30. PROVIDE ALL ROOFING OPENINGS AND FLASHINGS REQUIRED FOR THE INSTALLATION OF ROOF MOUNTED EQUIPMENT.
31. ALL MATERIALS AND EQUIPMENT INSTALLED IN RETURN AIR PLENUMS SHALL BE NON-COMBUSTIBLE AND UL APPROVED FOR USE IN A RETURN AIR PLENUM SPACE. ALL WIRING SHALL BE NON COMBUSTIBLE OR SHALL BE ENCLOSED IN METAL CONDUIT OR PROTECTED BY A SHEET METAL COVER
SECURED WITH METAL FASTENERS.
32. INSULATION, FITTINGS, COVERS AND FINISHES IN RETURN AIR PLENUM SHALL HAVE A MAXIMUM FLAME SPREAD RATING OF 25 AND A MAXIMUM
SMOKE DEVELOPED RATING OF 50.
33. PROVIDE ACCESS PANELS AS REQUIRED FOR ALL VALVES, DAMPERS, CONTROLS, OR OTHER EQUIPMENT.
34. ALL ROOFING WORK SHALL BE PERFORMED BY AUTHORIZED ROOFING CONTRACTOR TO MAINTAIN ROOF WARRANTY.
35. SUPPORT ALL EQUIPMENT, PIPING AND DUCTWORK FROM BUILDING STRUCTURE TO PROVIDE A VIBRATION FREE INSTALLATION. OTHERWISE ADHERE TO THE DETAILS IN THE CONTRACT DOCUMENTS. NOTIFY ARCHITECT AND/OR STRUCTURAL ENGINEER OF ALL WEIGHTS AND METHODS OF SUPPORT. PROVIDE DETAILS TO COORDINATE CONCRETE PADS AND STEEL PLATFORMS REQUIRED FOR MECHANICAL WORK.
36. CUTTING AND PATCHING AS REQUIRED AND WHERE NECESSARY TO ACCOMMODATE NEW WORK AND THE REPAIR OF EXISTING WORK.
37. CONTRACTOR SHALL PROTECT ALL SURFACES DURING RIGGING AND CONSTRUCTION INCLUDING BUT NOT LIMITED TO THE LOBBY AND HALLWAY FLOORS AND WALLS. CONTRACTOR SHALL RESTORE ALL SURFACES (WALLS, CEILINGS, FLOORS AND ROOFS) THAT ARE DAMAGED BY THE WORK
OF THIS CONTRACT TO THEIR ORIGINAL CONDITION AT NO EXTRA COST TO THE OWNER.
38. REMOVE ALL TRASH, DEBRIS AND DEMOLITION MATERIAL FROM PREMISES AT THE END OF EACH DAY.
39. PROVIDE ACCESS PANELS IN NON LAY-IN-CEILINGS FOR SERVICE AND MAINTENANCE OF ALL CONCEALED EQUIPMENT AND DEVICES, SUCH AS HEAT
PUMPS, ELECTRIC DUCT HEATERS, COILS, SMOKE DETECTORS, BALANCING DAMPERS
AND FIRE DAMPERS.
40. ALL DUCT DIMENSIONS ARE INSIDE CLEAR DIMENSIONS.
41. COORDINATE LOCATION OF NEW DUCTWORK, AIR DEVICES AND EQUIPMENT WITH LIGHT FIXTURES, SPRINKLER PIPING AND HYDRONIC PIPING.
42. SHEETMETAL FITTINGS SHOWN SHALL BE PROVIDED. NO SUBSTITUTES WILL BE ALLOWED WITHOUT PRIOR CONSENT FROM ENGINEER.
43. PROVIDE BALANCING DAMPERS IN ALL DUCT BRANCHES TO AIR DEVICES.
44. EQUIPMENT INDICATED ON THE DRAWINGS, TOGETHER WITH ITS BASE AND /OR SUPPORT, DUCTWORK CONNECTIONS, SERVICE CLEARANCES, WALL, FLOOR AND ROOF PENETRATIONS, AND ELECTRICAL REQUIREMENTS IS BASED ON THE MODEL INDICATED IN THE SCHEDULES. IF CONTRACTOR FURNISHES AN EQUIVALENT SUBSTITUTION, THE CONTRACTOR SHALL MAKE THE REQUIRED MODIFICATIONS IN THE WORK WITHOUT
THE CHANGE IN CONTRACT AMOUNT.
45. DUCTWORK SHALL NOT BE ROUTED ABOVE ELECTRICAL PANELS. COORDINATE WITH ELECTRICAL CONTRACTOR DUCTWORK SHALL NOT COVER
OR LIMIT ACCESS TO EXISTING J-BOXES.
46. INSTALLATION OF WORK SHALL PROVIDE REASONABLE ACCESSIBILITY FOR OPERATION, INSPECTION AND MAINTENANCE OF EQUIPMENT AND
ACCESSORIES. PROVIDE CLEARANCES REQUIRED BY MANUFACTURERS AND APPLICABLE CODES.
47. VERIFY ALL EQUIPMENT CONNECTIONS WITH MANUFACTURER'S CERTIFIED DRAWINGS. VERIFY AND PROVIDE DUCT AND PIPE TRANSITIONS TO FURNISHED EQUIPMENT. FIELD VERIFY AND COORDINATE ALL DIMENSIONS BEFORE FABRICATION.
48. PROVIDE VIBRATION ISOLATION FOR ROTATING, REVOLVING OR RECIPROCATING EQUIPMENT, INCLUDING DUCTWORK CONNECTIONS TO THIS EQUIPMENT TO PREVENT TRANSMISSION OF NOISE AND VIBRATION TO BUILDING STRUCTURE AND OCCUPIED SPACES. VIBRATION ISOLATION DEVICES SHALL INCLUDE SPRING VIBRATION ISOLATORS, NEOPRENE PADDING AND DUCT /PIPE FLEXIBLE CONNECTIONS.
49. PROVIDE FLEXIBLE CONNECTIONS AT ALL FANS INLET AND OUTLET CONNECTIONS.
50. EFFECTIVELY PROTECT ALL MATERIALS AND EQUIPMENT FROM DUST, DIRT AND DAMAGE UNTIL FINAL ACCEPTANCE CLOSE ALL DUCT AND EQUIPMENT OPENINGS DURING CONSTRUCTION WITH SUITABLE PROTECTIVE COVERING BEFORE, DURING AND FOLLOWING INSTALLATION.
51. REMOVE TEMPORARY AIR FILTERS AND PROVIDE NEW FLLTERS IN ALL AIR CONDITIONING EQUIPMENT WITHIN THE SCOPE OF WORK UPON
COMPLETION OF CONSTRUCTION AND BEFORE BALANCING.
52. CONTROL WIRE AND CONDUIT SHALL COMPLY WITH NEC AND ELECTRICAL SPECIFICATIONS.
53. ALL SERVICES TO EXISTING BUILDINGS SHALL BE MAINTAINED DURING CONSTRUCTION UNLESS OTHERWISE INDICATED.
54. PROVIDE SELECTIVE CEILING DEMOLITION TO PLACE NEW DUCTWORK AND DIFFUSERS. REPLACE DAMAGED CEILING TILES AND GRIDS RESULTING
FROM DEMOLITION. NEW CEILING TILES SHALL MATCH WITH EXISTING.
55. MECHANICAL CONTRACTOR SHALL BE RESPONSIBLE FOR FIELD VERIFICATION OF EXISTING CONDITIONS AND COORDINATION WITH ALL OTHER TRADES, INCLUDING BUT NOT LIMITED TO STRUCTURAL, LIGHTING, ELECTRICAL, PLUMBING, AND OTHER EXISTING AND NEW WORK. VERIFY ALL EXISTING CONDITIONS IN FIELD PRIOR TO PURCHASING EQUIPMENT. ALL DISCREPANCIES OR POTENTIAL PROBLEMS SHALL BE BROUGHT TO THE ATTENTION OF THE ARCHITECT/ENGINEER PRIOR TO BIDDING. PROVIDE ADDITIONAL MATERIALS AND LABOR TO RELOCATE OR REPLACE
MECHANICAL WORK AS REQUIRED TO ALLOW SPACE FOR THE WORK OF ALL TRADES.
56. THE WORK INCLUDES CONNECTION TO AN EXISTING MECHANICAL, ELECTRICAL, FIRE ALARM, AND CONTROL SYSTEMS ON THE PROJECT.
CONTRACTOR SHALL INCLUDE IN HIS BID PRICE ANY LABOR AND MATERIALS NECESSARY TO UNCOVER, TRACE, TEST, FIELD VERIFY, AND MEASURE ANY EXISTING EQUIPMENT OR SYSTEMS THAT ARE AFFECTED BY THE WORK UNDER THIS CONTRACT.
57. THE DRAWINGS INDICATE APPROXIMATE LOCATIONS BASED UPON INFORMATION OBTAINED WITHOUT REMOVING CEILING TILES OR WALLS.
THEREFORE, THE CONTRACTOR SHALL INCLUDE IN THEIR BID CONTINGENCY COSTS TO ADDRESS CONFLICTS BETWEEN DESIGN AND EXISTING
CONDITIONS.
58. THE CONTRACTOR SHALL INCLUDE IN HIS BID ALL COSTS RELATED TO REMOVING AND REPLACING ALL CEILINGS AS REQUIRED FOR THE
MECHANICAL AND ELECTRICAL WORK ON THIS PROJECT.
59. THE CONTRACTOR SHALL INCLUDE IN THE BID THE RELOCATION OF ANY EXISTING JUNCTION BOXES (OF ANY KIND) THAT WILL BE INACCESSIBLE
DUE TO THE WORK IN THIS PROJECT.
60. PRIOR TO DEMOLITION, THE CONTRACTOR SHALL LOG ALL EXISTING EQUIPMENT AND TRACE ELECTRICAL, FIRE ALARM, AND CONTROL CIRCUITS
THAT SERVE SUCH EQUIPMENT.
61. THE CONTRACTOR SHALL INCLUDE IN THEIR BID COSTS REQUIRED TO RELOCATE EXISTING CONDUITS OF ANY KIND IN ORDER TO INSTALL NEW
EQUIPMENT, DUCTWORK, AND PIPING. .
62. SEISMIC REQUIREMENTS AS SPECIFICATIONS.
SUMMARY OF WORK:
THE WORK SHALL BE AS SHOWN AND CALLED FOR IN THE CONTRACT DOCUMENTS AND SHALL INCLUDE, BUT NOT BE LIMITED TO, THE
FOLLOWING GENERAL ITEMS OF WORK:
REPLACEMENT OF EXISTING HEATING & VENTILATION UNITS (H&V 2-1 AND H&V 2-2) WITH NEW AIR HANDLING UNITS.
EXISTING DUCTWORK, PIPING, CONTROLS, AND ELECTRICAL CONNECTIONS ASSOCIATED WITH THE UNITS TO BE DEMOLISHED SHALL BE
REMOVED AND REPLACED.
NO CHANGE IN BULK, EGRESS, USE OR OCCUPANCY UNDER THIS APPLICATION.
*SCOPE OF WORK IS NOT RELATED TO FLOOD MITIGATION OR DAMAGES DUE TO FLOOD.
HVAC DESIGN CRITERIA
GRAVITY DAMPER GD
C.P. - CONDENSATE PUMP
ACCU - AIR COOLED CONDENSING UNIT
SF. - SUPPLY FAN
TEF. - TOILET EXHAUST FAN
LDS. - LINEAR DIFFUSER SUPPLY
LDR. - LINEAR DIFFUSER RETURN
GENERAL CONTRACTOR SHALL OBTAIN ALL SIGNOFFS, PERMITS, AND FINAL C.O. FROM THE BUILDING DEPARTMENT:
1. ALL WORK SHALL COMPLY WITH APPLICABLE LOCAL AND MUNICIPAL BUILDING CODES. AS WELL AS ANY AND ALL REGULATORY AGENCIES, INCLUDING BUT NOT LIMITED TO OSHA, ETC. GENERAL NOTES SHALL APPLY TO ALL DRAWINGS:
· RHODE ISLAND BUILDING CODE 2021 (IBC 2021 AMENDED).
· RHODE ISLAND MECHANICAL CODE 2021 (IBC 2021 AMENDED).
· RHODE ISLAND ENERGY CODE 2024.
2. ALL WORK, WHETHER SHOWN OR IMPLIED, UNLESS SPECIFICALLY QUESTIONED SHALL BE CONSIDERED FULLY UNDERSTOOD IN ALL RESPECTS BY THE GENERAL CONTRACTOR AND HE WILL BE RESPONSIBLE FOR ANY MISREPRESENTATIONS OR CONSEQUENCES
THEREOF FOR ALL WORK ON ALL DRAWINGS.
3. DRAWINGS ARE NOT TO BE SCALED, DIMENSIONS GOVERN.
4. ALL WORK IS TO CONFORM TO THE ARCHITECT'S DRAWINGS AND SPECIFICATIONS AND SHALL BE NEW AND BEST QUALITY OF THE
KINDS SPECIFIED.
5. NO MATERIAL SUBSTITUTIONS SHALL BE MADE. THE ARCHITECT WILL CONSIDER MATERIAL CHANGE REQUESTS ON AN INDIVIDUAL BASIS. THE CONTRACTOR SHALL SUBMIT SAMPLES AND CUTS FOR WRITTEN APPROVAL FROM THE ARCHITECT PRIOR TO THE START
OF ANY WORK.
6. THE CLIENT AND/OR ARCHITECT RESERVES THE RIGHT TO LET OTHER CONTRACTS IN CONNECTION WTH THE WORK OF THE PROJECT. THE GENERAL CONTRACTOR SHALL BE RESPONSIBLE FOR COORDINATION OF WORK AND ESTABLISHING SCHEDULES FOR ALL TRADES, HE/SHE SHALL AFFORD OTHER CONTRACTORS REASONABLE OPPORTUNITY FOR THE INTRODUCTION AND STORAGE OF
THEIR MATERIALS, EQUIPMENT AND THE EXECUTION OF THEIR WORK.
7. ALL MANUFACTURED ARTICLES, MATERIALS, AND EQUIPMENT SHALL BE SUPPLIED, INSTALLED, CONNECTED, ERECTED, USED, CLEANED AND CONDITIONED AS DIRECTED BY THE MANUFACTURER UNLESS OTHERWISE SPECIFIED ON THE DRAWINGS.
8. EACH SUBTRADE WILL BE RESPONSIBLE FOR REVIEWING THE ENTIRE SET OF DRAWINGS AND NOTING HIS/HER SCOPE OF WORK.
WORK INDICATED OR INFERRED ON THE DRAWINGS IS TO BE INCLUDED IN THE SUBCONTRACTOR'S COST. THE SAME SHALL HOLD
TRUE FOR THE GENERAL CONTRACTOR.
9. ALL SURFACES OR FINISHES TO REMAIN, IF DAMAGED DURING DEMOLITION OR ANY STAGE OF THE WORK, SHALL BE REPAIRED BY
THE GENERAL CONTRACTOR AT HIS/HER EXPENSE TO "LIKE NEW" CONDITION.
10. THE GENERAL CONTRACTOR SHALL SUBMIT IN WRITING ALL PROPOSALS FOR ADDITIONAL WORK TO THE CLIENT FOR REVIEW AND APPROVAL. NO WORK IS TO PROCEED UNTIL A SIGNED PROPOSAL IS RETURNED TO THE GENERAL CONTRACTOR.
11. THE CONTRACTOR SHALL IN ALL RESPECTS COMPLY WITH ALL REGULATIONS OF THE BUILDING MANAGEMENT. THIS SHALL INCLUDE BUT NOT BE LIMITED TO DEMOLITION, CORE DRILLING, ALL NOISE-CREATING WORK, AND CARTING RUBBISH THROUGH THE BUILDING.
IT SHALL BE THE RESPONSIBILITY OF THE CONTRACTOR TO OBTAIN SUCH REGULATIONS FROM THE BUILDING OWNER. IN THE EVENT OF CONFLICT BETWEEN BUILDING REGULATIONS AND OTHER CONTRACT DOCUMENTS THE ARCHITECT SHALL BE CONSULTED PRIOR
TO PROCEEDING.
12. THE CONTRACTOR SHALL BE RESPONSIBLE FOR ARRANGING WITH THE BUILDING MANAGEMENT THE USE OF ELEVATORS OR OTHER HOISTING FACILITIES FOR HANDLING THE DELIVERY OF MATERIALS. ANY AND ALL FEES, WHETHER DURING NORMAL WORKING HOURS OR OVERTIME, FOR THE USE OF THE HOISTING FACILITIES WILL BE THE RESPONSIBILITY OF THE GENERAL CONTRACTOR.
13. THE CONTRACTOR SHALL HAVE HAD EXPERIENCE ON AT LEAST THREE PROJECTS INVOLVING QUALITIES AND COMPLEXITIES AT LEAST EQUAL TO THOSE REQUIRED UNDER ALL DIVISIONS DETAILED IN THESE DRAWINGS. ALL WORKMEN PERFORMING UNDER
THIS WORK SHALL BE SKILLED WORKMEN IN THEIR RESPECTIVE TRADES.
14. THE GENERAL CONTRACTOR SHALL BE RESPONSIBLE FOR PICKING UP AND PAYING FOR ALL PERMITS FROM THE BUILDING
DEPARTMENT.
15. UPON COMPLETION OF THE WORK THE GENERAL CONTRACTOR SHALL SUBMIT CERTIFICATES OF INSPECTION, CERTIFICATE OF
OCCUPANCY AND A CERTIFICATE OF SUBSTANTIAL COMPLETION (A.I.A. DOCUMENT #G-704).
16. THE GENERAL CONTRACTOR IS RESPONSIBLE FOR CLEANING UP AND REMOVING FROM THE PREMISES ALL WASTE MATERIALS, RUBBISH, WRAPPINGS, AND SELVAGES AS GENERATED BY THE CONSTRUCTION, DEMOLITION AND/OR DELIVERY AND INSTALLATION
OF CARPET, MILLWORK, FURNITURE, OR OTHER TRADES EMPLOYED BY THE OWNER.
17. THE GENERAL CONTRACTOR SHALL MAINTAIN AN OPERATING ONSITE FIELD OFFICE TELEPHONE AT ALL TIMES DURING THE COURSE
OF CONSTRUCTION.
18. CONTRACTOR SHALL SCHEDULE ALL WORK TO CONFORM TO THE GENERAL CONSTRUCTION SCHEDULE AND SHALL COOPERATE WITH OTHER CONTRACTORS IN THE REQUIRED SEQUENTIAL INSTALLATION SCHEDULE AS APPROVED BY THE ARCHITECT.
19. THE GENERAL CONTRACTOR SHALL BE RESPONSIBLE FOR PROVIDING AND ASSUMING ALL COSTS ASSOCIATED WITH ALL
CONTROLLED INSPECTIONS AND AMENDMENTS (AS REQUIRED) AT THE BUILDING DEPARTMENT.
20. THE GENERAL CONTRACTOR MUST PROVIDE AND ASSUME ALL COST, INCLUDING ANY OVERTIME TO MEET THE REQUIREMENTS OF THE PROJECT AND ANY SCHEDULE WHICH IS SUBMITTED AS PART OF THE CONTRACT DOCUMENTS.
21. THE GENERAL CONTRACTOR AND ALL APPROPRIATE SUB-CONTRACTORS MUST VISIT THE SITE PRIOR TO SUBMITTING A BID.
22. THE GENERAL CONTRACTOR SHALL BECOME FAMILIAR WITH A.D.A. STANDARDS & MINIMUM CLEARANCES AND SHALL INFORM THE ARCHITECT OF ANY AND ALL CONFLICTS WITH COMPLYING WITH THOSE MINIMUM CLEARANCES AND STANDARDS.
23. THE GENERAL CONTRACTOR AND ALL SUB-CONTRACTORS SHALL REVIEW THE ENTIRE SET OF CONSTRUCTION DOCUMENT DRAWINGS TOGETHER WITH THE INVITATION TO BID AND ANY OTHER ITEMS WHICH CONSTITUTE THE CONTRACT DOCUMENTS.
24. THE CLIENT SHALL NOT BE RESPONSIBLE FOR ANY DELAYS OR COSTS ASSOCIATED WITH DOWN TIME DUE TO FAILURES CAUSED BY
THE CONTRACTOR.
GENERAL NOTES:
GENERAL CONTRACTOR SHALL OBTAIN ALL SIGN-OFFS, PERMITS, AND FINAL C.O. FROM THE BUILDING DEPARTMENT.
THE CONTRACTOR IS RESPONSIBLE FOR FORWARDING ALL CONTRACT DOCUMENTS (ARCHITECTURAL, STRUCTURAL, MECHANICAL, ELECTRICAL, FIRE ALARM, FIRE PROTECTION, PLUMBING DRAWINGS AND SPECIFICATIONS) TO ALL OF ITS SUBCONTRACTORS. DURING THE BIDDING PROCESS THE SUB-CONTRACTORS SHALL ASSUME WHERE DIRECTED ON ANY DRAWINGS AS "CUSTOMER PROVIDED" OR "OWNER PROVIDED", THE SUB CONTRACTOR SHALL PROVIDE THE SPECIFIED ITEM. NO ADDED PAYMENT ABOVE THE CONTRACT SUM WILL BE PAID TO THE CONTRACTOR FOR ANY WORK WHICH MAY BE REQUIRED AS A RESULT OF THE CONTRACTORS FAILURE TO COORDINATE
THIS INFORMATION DURING THE PRICING PROCESS.
NOTE TO THE CONTRACTOR:
GENERAL CONSTRUCTION NOTES:
MECHANICAL DRAWING LIST
Dwg. No. Drawing Title
M-201.00 SECOND FLOOR MECHANICAL PIPING PLAN 7
M-301.00 ELEVATION VIEWS 8
M-401.00 MECHANICAL CONTROLS 9
M-001.00 MECHANICAL SYMBOLS, LEGENDS & NOTES 1
M-002.00 MECHANICAL EQUIPMENT SCHEDULES 2
MD-101.00 DEMOLITION PLAN - MECHANICAL DUCTWORK/PIPING 3
M-101.00 LOWER FLOOR MECHANICAL DUCTWORK PLAN 4
Sheet No.
M-501.00 MECHANICAL DETAILS 10
M-102.00 FIRST FLOOR MECHANICAL DUCTWORK PLAN 5
M-103.00 SECOND FLOOR MECHANICAL DUCTWORK PLAN 6
This drawing is copyrighted and is subject to copyright protection as an "architectural work" under 17 U. S. C. Sec. 101 et seq. The protection includes but is not limited to the overall form as well as the arrangement and composition of spaces, materials, color and elements in the design. Under such protection, unauthorized use of this drawing may result in the cessation of construction or buildings being seized and/or monetary compensation being awarded to The Robinson Green Beretta Corporation (RGB).
Any reproduction, possession, or use of this drawing or any part thereof without the express written permission of RGB, is prohibited. Violators will be prosecuted to the full extent of the law.
© RGB 2025
Drawn by
Checked by
Revised on
PP
MM
E-mail: rgbinfo@rgb.net www.rgb.net
Project
Drawing Status
Issued On
Sheet Contents
Project Number.
Drawing No.
Sheet of
Certification
Phone: (401) 272-1730 Fax: (401) 273-7156
50 Holden Street Providence, Rhode Island 02908
BID SET
12/19/2025
Architecture · Project Management · Interior Design
RHODE ISLAND
COLLEGE
600 MOUNT PLEASANT AVE,
PROVIDENCE, RI 02908
RECRETION
CENTER
RENOVATION
225 DYER ST, PROVIDENCE, RI 02903
SUNNYSIDE, NY, 11104
WWW.DM-ENGINEERS.COM
#1 BID - Addendum 01 09/23/2023
MECHANICAL SYMBOLS,
LEGENDS & NOTES
1 10
M-001.00
CA
MM, PE
SG-2
SG-1
TAGS
2. CONTRACTOR SHALL COORDINATE REGISTER'S COLOR WITH ARCHITECT AND/OR CLIENT.
1. CONTRACTOR SHALL COORDINATE REGISTER'S BORDER TYPE WITH ARCHITECT AND/OR CLIENT.
NOTES:
24x121.830-920
MODEL NO.
10/L
MAX.
RATING.
NOISE
INCHES
SPACINGANGLE OF
(DEGREES)
DEFLECTION
NOMINAL
SIZE
DUCTCORE
AREA
SQ.FT.
CFM RANGE
ANEMOSTAT200.7522.5°
NCINCHES
MANUFACTURER
20x120-760 1.52
SUPPLYAIR GRILLES SCHEDULE
RG-1
TAGS MODEL NO.
E30
MAX.
RATING.
NOISE
INCHES
SPACINGANGLE OF
(DEGREES)
DEFLECTION
NOMINAL
SIZE
DUCTCORE
AREA
SQ.FT.
CFM RANGE
-20-40°
NCINCHES
MANUFACTURER
42X360-4,990 9.98
RETURN AIR GRILLES SCHEDULE
10/LANEMOSTAT200.7522.5°
REFRIG. TYPE
R-454B80x90x178 53517595 460 RAU-C80-200OUTDOOR 974,490 3 60 178 16.3 10.6 -
NET
WEIGHT
(LBS)
APPROX.
PHYSICAL
EXTERNAL
DIMENSIONS
(HxWxD)
MODEL
No. REMARKS
SOUND
POWER
RATING
(dB)CO P
EE
RMOCP
WBDB
SERVICE
UNIT
TAG LOCATION
1. CONTRACTOR TO FIELD VERIFY ACTUAL LENGTHS AND NUMBER OF FITTINGS AND CONFIRM
WITH UNIT MANUFACTURER.
2. PROVIDE UNIT WITH FACTORY MOUNTED DISCONNECT SWITCH.
3. PROVIDE SPRING NEOPRENE VIBRATOR ISOLATORS, SIMILAR TO MASON OR APPROVED
EQUAL.
4. VERIFY THE FINAL LAYOUT AND SIZING OF REFRIGERANT PIPING WITH THE UNIT
MANUFACTURER PRIOR TO INSTALLATION.
5. REFRIGERANT LINE SIZING TO BE CALCULATED BY APPROVED AIR CONDITIONING UNIT
MANUFACTURER IN ACCORDANCE WITH ACTUAL INSTALLATION AND LATEST COORDINATED
SHOP DRAWINGS.
6. MOUNT AIR SOURCE ACCU UNITS ACCORDING TO UNIT MANUFACTURER'S SPECIFIC WRITTEN
INSTRUCTIONS.
7. TESTS FOR REFRIGERANT LINES ARE TO BE COMPLETED PRIOR TO INSULATION AND
ENCLOSURE.
8. VERIFY EXACT AMOUNT OF REFRIGERANT WITH UNIT MANUFACTURER BASED ON ACTUAL
INSTALLED LENGTH OF PIPING.
9. PROVIDE UNITS WITH FACTORY CONTROLLERS FOR INTEGRATION INTO THE BUILDING
MANAGEMENT SYSTEM (BMS). SYSTEM SHALL HAVE A TOUCH SCREEN USER INTERFACE.
NOTES:
BASIS OF DESIGN: TRANE
IE
ERMCA
AIR COOLED CONDENSING OUTDOOR UNIT SCHEDULE
ELECTRICAL DATA
Hz
PH
AS
E
VO
LT
S
EAT (°F)
COOLING CAPACITY
TOTAL
BTU/HR
GYM 5448113x71x192 --INDOORAHU-1 960 CSAAA040
NET
WEIGHT
(LBS)
APPROX. PHYSICAL
EXTERNAL
DIMENSIONS
(WxHxD)
ASSOCIATED
OUTDOOR UNIT
REMARKS
SOUND
POWER
RATING
(dB)
SERVICEUNIT
TAG LOCATION MODEL
No.
AIR CONDITIONING UNIT SCHEDULE
COOLING
CAPACITY
(MBTU/HR)
1. CONTRACTOR TO FIELD VERIFY ACTUAL LENGTHS AND NUMBER OF FITTINGS AND
CONFIRM WITH UNIT MANUFACTURER.
2. PROVIDE UNIT WITH FILTER AS PER MANUF. RECOMMENDATIONS, INCLUDE TWO SPARE
FILTERS PER UNIT.
3. VERIFY THE FINAL LAYOUT AND SIZING OF REFRIGERANT PIPING WITH THE UNIT
MANUFACTURER PRIOR TO INSTALLATION.
4. REFRIGERANT LINE SIZING TO BE CALCULATED BY APPROVED AIR CONDITIONING UNIT
MANUFACTURER IN ACCORDANCE WITH ACTUAL INSTALLATION AND LATEST
COORDINATED SHOP DRAWINGS.
5. MOUNT AIR SOURCE AC INDOOR UNITS ACCORDING TO UNIT MANUFACTURER'S SPECIFIC
WRITTEN INSTRUCTIONS.
6. TESTS FOR REFRIGERANT LINES ARE TO BE COMPLETED PRIOR TO INSULATION AND
ENCLOSURE.
7. VERIFY EXACT AMOUNT OF REFRIGERANT WITH UNIT MANUFACTURER BASED ON ACTUAL
INSTALLED LENGTH OF PIPING.
9. PROVIDE UNITS WITH FACTORY CONTROLLERS FOR FUTURE INTEGRATION INTO THE
BUILDING MANAGEMENT SYSTEM (BMS).
NOTES:
No. OF
COILS
PD AIR
(IN H2O)
COOLING COIL PERFORMANCE
SYSTEM TYPE
EAT
(dbF/wbF)
LAT
(dbF/wbF)
SUPPLY FAN DATA
CFM
TSP
(IN WG)
ESP
(IN WG) RPM
INPUT
POWER (kW) BHP MOP MCA
ELECTRICAL
SUPPLY
(V/P/F)
QTY. OF
FANS
HEATING COIL PERFORMANCE
1,225
HEATING
CAPACITY
(MBTU/HR)
EAT
(dbF)
LAT
(dbF)
No. OF
COILS
PD AIR
(IN H2O) SYSTEM TYPE
EWT
(F)
LWT
(F)
FLOW RATE
(GPM)
160180122.34HOT WATER10.12993.7034.2554.03/52.7682.40/68.98
REFRIGERANT
(R-454B)10.761460/3/6031.5-17.62314.92,07421.503.6119,000
RG-2 E30-20-40°40X400-5,280 10.57
FLUID OPERATING TEMP.
RANGE AND USAGE (°F)
INSULATION
CONDUCTIVITY
BTU.IN/HRFT²°F
INSULATION
CONDUCTIVITY MEAN
RATING TEMPERATURE °F
NOM.
DIA.<1"
NOM. DIA.
1"TO <1.5"
NOM. DIA.
1.5" TO <4"
NOM. DIA.
4" TO 8"
NOM. DIA.
>=8"
201-250 0.27-0.3 150 2.5 2.5 2.5 3.0 3.0 141-200 0.25-0.29 125 1.5 1.5 2.0 2.0 2.0 105-140 0.21-0.28 100 1.0 1.0 1.5 1.5 1.5
40-60 0.21-0.27 75 0.5 0.5 1.0 1.0 1.0
PIPING INSULATION
BASIS OF DESIGN: TRANE
AHU-1
ACCU-1
TOTAL
POWER
(KW)
99.66
GYM 383194x65x175 --INDOORAHU-3 401.4 CSAAA030461.04 16018046.04HOT WATER10.06874.574560.07/58.2980/67CHILLED WATER10.406460/3/6026.9-12.29010.21,724113.3414,375-
GYM 381994x65x175 --INDOORAHU-4 373.1 CSAAA030455.67 16018045.51HOT WATER10.06574.894560.89/58.7580/67CHILLED WATER10.36460/3/6026.9-11.6579.681,692113.2614,055-
FLA
21.65
21.65
FLOW RATE
(GPM)
74.36
ACCU-1
CFM
OA
10,500
14,375
14,055
REFRIG. TYPE
R-454B80x90x178 53517595 460 RAU-C80-200OUTDOOR 974,490 3 60 178 16.3 10.6 -AHU-2 99.66ACCU-2
GYM 5448113x71x192 --INDOORAHU-2 960 CSAAA0401,225 160180122.34HOT WATER10.12993.7034.2554.03/52.7682.40/68.98
REFRIGERANT
(R-454B)10.761460/3/6031.5-17.62314.92,07421.503.6119,000ACCU-2 28 -10,500
This drawing is copyrighted and is subject to copyright protection as an "architectural work" under 17 U. S. C. Sec. 101 et seq. The protection includes but is not limited to the overall form as well as the arrangement and composition of spaces, materials, color and elements in the design. Under such protection, unauthorized use of this drawing may result in the cessation of construction or buildings being seized and/or monetary compensation being awarded to The Robinson Green Beretta Corporation (RGB).
Any reproduction, possession, or use of this drawing or any part thereof without the express written permission of RGB, is prohibited. Violators will be prosecuted to the full extent of the law.
© RGB 2025
Drawn by
Checked by
Revised on
PP
MM
E-mail: rgbinfo@rgb.net www.rgb.net
Project
Drawing Status
Issued On
Sheet Contents
Project Number.
Drawing No.
Sheet of
Certification
Phone: (401) 272-1730 Fax: (401) 273-7156
50 Holden Street Providence, Rhode Island 02908
BID SET
12/19/2025
Architecture · Project Management · Interior Design
RHODE ISLAND
COLLEGE
600 MOUNT PLEASANT AVE,
PROVIDENCE, RI 02908
RECRETION
CENTER
RENOVATION
225 DYER ST, PROVIDENCE, RI 02903
SUNNYSIDE, NY, 11104
WWW.DM-ENGINEERS.COM
#1 BID - Addendum 01 09/23/2023
MECHANICAL EQUIPMENT
SCHEDULES
2 10
M-002.00
CA
MM, PE
"Ø
S A
"Ø
S A
48"Ø SA 48"Ø SA
48"Ø SA48"Ø SA
"Ø
S A
"Ø
S A
"Ø
S A
"Ø
S A
"Ø
S A
"Ø
S A
36"Ø SA36"Ø SA
"Ø
S A
"Ø
S A
4"Ø
3"Ø
3"Ø
4"Ø
3"Ø
3"Ø
36"Ø SA
3"Ø DTS
4"Ø DTS
3"Ø DTS
3"Ø DTR
3"Ø DTR
3"Ø DTS
4"Ø DTR
3"Ø DTS
3"Ø DTR
3"Ø DTR
1-1/4"Ø CD1-1/4"Ø CD
HWS
HWR
HWS
HWR
RF 2-1 RF 2-2
HVAC
2-1
HVAC
2-2
H&V 2-2
5 5
3 3
FD FD FD FD
H&V 2-1
EXISTING H&V 2-1 TO BE REMOVED ALONG WITH ALL ASSOCIATED ACCESSORIES.
REMOVE THE EXISTING SUPPORTS AND FRAMING AS REQUIRED FOR INSTALLATION FOR
THE NEW UNITS.
EXISTING H&V 2-2 TO BE REMOVED ALONG WITH ALL ASSOCIATED ACCESSORIES.
REMOVE THE EXISTING SUPPORTS AND FRAMING AS REQUIRED FOR INSTALLATION FOR
THE NEW UNITS.
REMOVE EXISTING SA DUCT.
REMOVE EXISTING OA/RA DUCT.
REMOVE THE EXISTING HWS&R, DTS&R AND CONDENSATE DRAIN(CD) PIPING FROM THE
UNIT UP TO DISCONNECTION POINT/CLOSEST SHUT-OFF VALVE.
EXISTING LOUVER 72" x 120" TO REMAIN.
EXISTING RETURN AIR GRILLES AND ASSOCIATED DAMPERS FROM THE H&V UNITS TO BE
REPLACED. PROTECT EXISTING RETURN AIR DUCTWORK IN PLACE TO BE REUSED. DO
NOT DEMOLISH OR DAMAGE THE EXISTING CMU WALL STRUCTURE.
EXHAUST FAN EXISTING TO REAMIN.
1. PRIOR TO SUBMISSION OF BID, VISIT THE AND VERIFY AND BECOME FAMILIAR WITH RELATIVE LOCATIONS AND EXISTING CONDITIONS. SUBMITTED BIDS WILL BE INTERPRETED TO MEAN THE CONTRACTOR VISITED THE SITE, AND ALL COST AND
CHARGES MADE NECESSARY BY THE EXISTING CONDITIONS ARE INCLUDED.
2. PROVIDE ALL LABOR, MATERIAL, EQUIPMENT, AND SERVICES FOR THE PROPER EXECUTION OF DEMOLITION WORK. ANY LABOR, MATERIAL, EQUIPMENT AND SERVICE NECESSARY SHALL BE PROVIDED AS IF CALLED FOR.
3. PROVIDE LADDERS, TOOLS AND OTHER EQUIPMENT AND SERVICES FOR THE MECHANICAL WORK. REMOVE IT UPON
COMPLETION OF WORK.
4. WORK SHALL CONFORM TO THE LATEST EDITION OF ALL APPLICABLE LAWS, CODES AND REGULATIONS HAVING
JURISDICTION.
5. SECURE ALL PERMITS, INSPECTIONS AND CERTIFICATED REQUIRED, AND PAY ALL FEES OR CHARGES FOR THE SAME.
6. WHEN WORK INVOLVES ASBESTOS, PCB OR OTHER TOXIC MATERIALS, CONTRACTOR SHALL NOTIFY OWNER WHO WILL
RETAIN AN INDUSTRIAL HYGIENIST TO ESTABLISH STANDARD PROCEDURES FOR WORKING WITH/OR REMOVING TOXIC
MATERIALS.
7. PROVIDE SUITABLE WRAPPING AND OTHER PROTECTION NECESSARY TO PREVENT DAMAGE TO MECHANICAL EQUIPMENT AND MATERIAL. REMOVE ALL SUCH PROTECTIVE DEVICES WHEN THEIR USE BECOMES UNNECESSARY.
8. IT SHALL BE THE RESPONSIBILITY OF THE CONTRACTOR TO TAKE ALL NECESSARY PRECAUTIONS TO ENSURE THE SAFETY
OF ALL EXISTING STRUCTURAL ELEMENTS DURING ALL PHASES OF HIS/HER WORK.
9. PROVIDE WEATHER TIGHT AND SECURE CLOSURES FOR ANY BUILDING OPENING LEFT OVERNIGHT. THE CONTRACTOR IS RESPONSIBLE FOR ANY BREACHED OF SECURITY OR DAMAGE CAUSED AS A RESULT OF INSUFFICIENT PROTECTION.
10. PROVIDE APPROPRIATE SEPARATION BETWEEN THE CONSTRUCTION AREA AND ADJACENT OCCUPIED SPACES TO
PREVENT MIGRATION OF DUST, ODORS AND SUBSTANCES HAZARDOUS TO HUMAN HEALTH.
11. AT ALL TIMES KEEP PREMISES FREE FROM ACCUMULATION OF WASTE MATERIAL AND RUBBISH CAUSED BY AGENTS AND EMPLOYEES OF THE CONTRACTOR. RUBBISH IS TO BE REMOVED FROM THE SITE BY THE GENERAL CONTRACTOR; THE MECHANICAL CONTRACTOR SHALL ON A WEEKLY BASIS GATHER THE RUBBISH HE CREATED AND PILE IT AT THE LOCATION DESIGNATED BY THE GENERAL CONTRACTOR. IN THE EVENT OF DISPUTE OR REFUSAL TO COMPLY WITH REQUIREMENTS OF THE ABOVE PARAGRAPHS, THE OWNER SHALL HAVE THE OPTION OF REMOVING SUCH RUBBISH FROM THE PREMISES, AND BACK-CHARGING THE CONTRACTOR FOR DOING SUCH WORK.
12. REMOVED EQUIPMENT AND MATERIAL NOT DESIRED BY THE OWNER SHALL BECOME THE PROPERTY OF THE CONTRACTOR AND SHALL PROMPTLY REMOVED FROM THE SITE. EQUIPMENT AND MATERIAL DESIRED BY THE OWNER SHALL BE DELIVERED BY THE CONTRACTOR TO LOCATION DESIGNATED BY THE OWNER. OWNER WILL TAG OR OTHERWISE INDICATE
THE EQUIPMENT AND MATERIAL HE DESIRES TO KEEP.
13. PROVIDE SUITABLE FIRE RATED PATCHING FOR MECHANICAL SYSTEMS AND EQUIPMENT OPENINGS CREATED BY
DEMOLITION.
14. EXISTING MECHANICAL WORK THAT IS TO REMAIN, WHEN EXISTING STRUCTURE IN WHICH IT IS INSTALLED IS TO BE
REMOVED, SHALL BE TEMPORARY SUPPORTED IN PLACE.
15. ALL EXISTING DEVICES AND CONTROLS INDICATED TO BE RELOCATED SHALL BE REMOVED WITH CARE AND STORED UNTIL
RE-INSTALLATION.
16. REMOVAL OF EQUIPMENT, DUCTWORK, AND PIPING SHALL INCLUDE REMOVAL OF ALL ASSOCIATED VALVES, FITTINGS, HANGERS, SUPPORTS, CONTROLS, AND APPURTENANCES.
17. INFILL ALL OPENINGS LEFT BY REMOVED DUCTWORK AND PIPING. COORDINATE THIS WORK WITH GENERAL CONTRACTOR.
18. CAN AND SEAL AIR TIGHT, OPENINGS IN EXISTING DUCTWORK TO REMAIN LEFT BY REMOVAL OF DUCT BRANCHES. CAP
FLUSH TO EDGE OF MAIN DUCT. REMOVAL OF ALL EXISTING DUCT COLLARS FROM EXISTING DUCTS TO REMAIN AND CAP
FLUSH TO EDGE OF MAIN DUCT.
19. PLUG ALL TAPS AT MAINS WHERE BRANCH PIPING HAS BEEN REMOVED. WHERE EXISTING VALES ARE TO REMAIN, THE
VALVES SHALL BE CLOSED AND CAPPED.
20. THE CONTRACTOR IS TO PROTECT THE FLOOR WITH POLYETHYLENE SHEET OR FILM AND 34" PLYWOOD.
KEY NOTES
GENERAL DEMOLITION NOTES
7 7RA PLENUM
144" x 54"
RA PLENUM
144" x 54"
This drawing is copyrighted and is subject to copyright protection as an "architectural work" under 17 U. S. C. Sec. 101 et seq. The protection includes but is not limited to the overall form as well as the arrangement and composition of spaces, materials, color and elements in the design. Under such protection, unauthorized use of this drawing may result in the cessation of construction or buildings being seized and/or monetary compensation being awarded to The Robinson Green Beretta Corporation (RGB).
Any reproduction, possession, or use of this drawing or any part thereof without the express written permission of RGB, is prohibited. Violators will be prosecuted to the full extent of the law.
© RGB 2025
Drawn by
Checked by
Revised on
PP
MM
E-mail: rgbinfo@rgb.net www.rgb.net
Project
Drawing Status
Issued On
Sheet Contents
Project Number.
Drawing No.
Sheet of
Certification
Phone: (401) 272-1730 Fax: (401) 273-7156
50 Holden Street Providence, Rhode Island 02908
BID SET
12/19/2025
Architecture · Project Management · Interior Design
RHODE ISLAND
COLLEGE
600 MOUNT PLEASANT AVE,
PROVIDENCE, RI 02908
RECRETION
CENTER
RENOVATION
225 DYER ST, PROVIDENCE, RI 02903
SUNNYSIDE, NY, 11104
WWW.DM-ENGINEERS.COM
#1 BID - Addendum 01 09/23/2023
SECOND FLOOR
MECHANICAL DEMOLITION
DUCTWORK/PIPING PLAN
3 10
MD-101.00
CA
MM, PE
SECOND FLOOR MECHANICAL DEMOLITION PLAN
SCALE: 1/8"=1'-0"
FIRST FLOOR MECHANICAL DEMOLITION PART PLAN - H&V 2-1
SCALE: 1/8"=1'-0"
FIRST FLOOR MECHANICAL DEMOLITION PART PLAN - H&V 2-2
SCALE: 1/8"=1'-0"
(E)18x12SA UP(E)36x12RA
UP(E)48x16RA (2050)
(E)TA
8x4(E)TA
32x6
(E)TA
10x10
(E)TA
10x10
(E)TA
10x10
(E)8x8SA
(E)6"ØSA
(E)TA
12x12
(E)18x10SA
(E)10x10SA
(E)TA
10x10
(E)8"ØSA
(E)6"ØSA
(E)22x12SA
(E)48x16RA (2840) (E)24x12SA UP
(E)36x12RA UP
(E)VAV
L-1
(E)VAV
L-2
(E)VAV
L-3
(E)VAV
L-4
(E)VAV
L-5
(E)VAV
L-6
(E)VAV
L-7
(E)VAV
L-8
(E)VAV
L-9
(E)VAV
L-10
(E)VAV
L-11
(E)VAV
L-12
(E)SA
(270)
(E)SA
(205)
(E)SA
(205)
(E)SA
(85)
(E)SA
(50)
SA
(210)
(E)SA
(120)
(E)SA
(120)
(E)SA
(165)
(E)SA
(120)
(E)SA
(120)
SA
(300)
SA
(300)
(E)SA
(180)
(E)SA
(220)
(E)SA
(50)
(E)LSA
(450)
(E)LSA
(450)
(E)SA
(80)
(E)SA
(170)
(E)EA
(170)
(E)RA
(205)
RA
(205)
(E)RA
(270)
(E)RA
(50)
(E)RA
(85)
(E)LRA
(450)
(E)RA
(165)
(E)RA
(210)
(E)RA
(50)
(E)LRA
(450)(E)RA
(120)
(E)RA
(120)
(E)RA
(120)
(E)RA
(120)
(E)RA
(220)
(E)RA
(180)
(E)10"x10"SA (E)12"x8"SA
(E)10"x10"SA (E)6"x8"SA
(E)12"x12"SA
(E)9"ØSA
(E)8"x6"SA
(E)9"ØSA
(E)8"ØSA
(E)10"x10"
(E)9"ØSA
(E)8"x6"SA
(E)10"x10"SA
(E)8"x6"SA
(E)10"x10"SA
(E)6"ØSA (E)6"ØSA
(E)6"x8"SA
(E)8"x8"SA
(E)9"ØSA
(E)6"x6"SA
(E)10"x10"SA
(E)6"x6"SA
(E)12"x12"SA
(E)10"x10"SA
(E)6"ØSA (E)6"ØSA
(E)10"x10"SA
(E)8"ØSA
(E)6"x8"SA (E)12"x12"SA
(E)12x20EA UP
(E)16x12EA (920) →
(E)EA
(300)
(E)EA
(300)
(E)16"x12"EA (E)18"x12"EA (E)20"x12"EA
(E)12"x8"EA (E)12"x8"EA
FD FD FDFD
FD
(E)10"ØSA
(E)10"ØSA
(E)32"x6"SA
(E)10"x10"SA
(E)6"x6"SA
(E)8"x4"SA
(E)12"x12"SA
(E)32"x6"SA
EXISTING DUCTWORK SYSTEM SHALL REMAIN AND BE REUSED.
THE CONTRACTOR SHALL PERFORM A COMPLETE AIR BALANCE FOR THE EXISTING
DUCTWORK SYSTEM SERVED BY AHU-3 AND AHU-4.
THE CONTRACTOR MUST TAKE AIRFLOW READINGS (CFM) AT ALL EXISTING SUPPLY AND
RETURN GRILLES, ADJUST DAMPERS, AND BALANCE THE SYSTEM TO MATCH THE
ORIGINAL DESIGN FLOW RATES.
EXISTING AHU-3 & AHU-4 DUCTWORK DISTRIBUTION SYSTEMS
NOTES
This drawing is copyrighted and is subject to copyright protection as an "architectural work" under 17 U. S. C. Sec. 101 et seq. The protection includes but is not limited to the overall form as well as the arrangement and composition of spaces, materials, color and elements in the design. Under such protection, unauthorized use of this drawing may result in the cessation of construction or buildings being seized and/or monetary compensation being awarded to The Robinson Green Beretta Corporation (RGB).
Any reproduction, possession, or use of this drawing or any part thereof without the express written permission of RGB, is prohibited. Violators will be prosecuted to the full extent of the law.
© RGB 2025
Drawn by
Checked by
Revised on
PP
MM
E-mail: rgbinfo@rgb.net www.rgb.net
Project
Drawing Status
Issued On
Sheet Contents
Project Number.
Drawing No.
Sheet of
Certification
Phone: (401) 272-1730 Fax: (401) 273-7156
50 Holden Street Providence, Rhode Island 02908
BID SET
12/19/2025
Architecture · Project Management · Interior Design
RHODE ISLAND
COLLEGE
600 MOUNT PLEASANT AVE,
PROVIDENCE, RI 02908
RECRETION
CENTER
RENOVATION
225 DYER ST, PROVIDENCE, RI 02903
SUNNYSIDE, NY, 11104
WWW.DM-ENGINEERS.COM
#1 BID - Addendum 01 09/23/2023
LOWER FLOOR MECHANICAL
DUCTWORK PLAN
4 10
M-101.00
CA
MM, PE
LOWER FLOOR MECHANICAL DUCTWORK PLAN
SCALE: 1/8"=1'-0"
RG-2
(5000)
RG-2
(5000)
RARA → ←RA
RA
92" x 26" RA UP
(E)40" x 30" RA
(E)40x18SA UP / (E)18x12SA DN
(E)46x18RA UP / (E)36x12RA DN
(E)40x18SA UP / (E)24x12SA DN
(E)46x18RA UP / (E)36x12RA DN
(E)TA
10x10
(E)TA
10x10
(E)TA
10x10
(E)TA
10x10
(E)TA
10x10
(E)TA
10x10
(E)TA
10x10
(E)64x18RA (4680)
(E)TA
10x10
(E)TA
20x12
(E)TA
20x12
(E)TA
14x12
(E)TA
14x12
(E)TA
20x6
(E)TA
28x12(E)TA
28x12
(E)TA
10x10
(E)TA
10x10
(E)TA
10x10 (E)TA
10x10
(E)TA
10x10 (E)TA
12x12
(E)TA
10x10
(E)TA
10x10
(E)TA
18x12
(E)TA
18x12
(E)64x18RA (4540)
(E)VAV
1-1
(E)VAV
1-2
(E)VAV
1-3
(E)VAV
1-4 (E)VAV
1-5
(E)VAV
1-6
(E)VAV
1-7
(E)VAV
1-8
(E)VAV
1-9
(E)VAV
1-10
(E)VAV
1-11
(E)VAV
1-12
(E)VAV
1-13
(E)VAV
1-14
VAV
1-15
(E)VAV
1-16
(E)VAV
1-17
(E)VAV
1-18
(E)VAV
1-19
(E)VAV
1-20
(E)VAV
1-21
(E)VAV
1-22
(E)VAV
1-23
(E)VAV
1-24
(E)VAV
1-25
(E)VAV
1-26
(E)VAV
1-27
(E)VAV
1-28
(E)VAV
1-29
(E)VAV
1-30
(E)VAV
1-31
(E)SA
(130)
(E)SA
(245)
(E)SA
(245)
(E)SA
(170)
(E)SA
(105)
(E)SA
(80)
(E)SA
(130)
(E)SA
(285)
SA
(285)
(E)SA
(140)
(E)SA
(300)
(E)SA
(300)
(E)SA
(205)
(E)SA
(390)
(E)SA
(220)
(E)SA
(430)
(E)SA
(395)
(E)SA
(395)
(E)SA
(335)
(E)SA
(335)
(E)SA
(395)
(E)SA
(395)
(E)SA
(90)
(E)SA
(300)
(E)SA
(300)
(E)SA
(360)
(E)SA
(405)
(E)SA
(230)
(E)SA
(230)
(E)SA
(80) (E)SA
(105) (E)SA
(170)
(E)SA
(135)
(E)SA
(200)
SA
(160)
(E)SA
(140)
SA
(220)
(E)SA
(80)
(E)RA
(200)
(E)RA
(135)
(E)RA
(170)
(E)RA
(105)(E)RA
(80)
(E)SA
(230)
(E)SA
(230)
(E)RA
(360)
(E)SA
(405)
(E)RA
(80)
(E)RA
(335)
(E)SA
(335)
(E)RA
(395)
(E)RA
(395)
(E)RA
(395)
(E)RA
(395)
(E)RA
(100)(E)RA
(100)
(E)RA
(430)
(E)RA
(220)
(E)RA
(205)
(E)RA
(390)
(E)RA
(170)
(E)RA
(105)
(E)RA
(80)
(E)RA
(130)
(E)RA
(285)
(E)RA
(285)
(E)RA
(140)
(E)RA
(245)
(E)RA
(245)
(E)RA
(140)
(E)RA
(130)
(E)10"x10"SA
(E)8"ØSA
(E)6"x6"SA
(E)8"x12"SA
(E)8"x12"SA
(E)10"x8"SA (E)12"x8"SA
(E)10"x10"SA
(E)6"x6"SA
(E)40"x12"SA
(E)18"x12"SA
(E)12"x8"SA
(E)8"x6"SA
(E)6"x6"SA
(E)10"ØSA (E)10"ØSA
(E)8"x8"SA (E)12"x12"SA
(E)12"ØSA
(E)8"x6"SA(E)6"x6"SA
(E)10"x10"SA(E)10"x10"SA(E)10"x10"SA(E)10"x10"SA
(E)6"x6"SA
(E)TA
14x10
(E)6"x6"SA
(E)18"x10"SA (E)12"x10"SA (E)10"x8"SA (E)14"x14"SA
(E)8"x14"SA
(E)6"x20"SA
(E)8"x8"SA (E)8"x8"SA
(E)12"x12"SA
(E)8"x12"SA(E)8"x12"SA
(E)10"ØSA(E)10"ØSA
(E)8"x14"SA
(E)12"ØSA
(E)12"ØSA
(E)20"x6"SA
(E)8"x8"SA (E)10"x10"SA (E)14"x10"SA (E)16"x10"SA
(E)18"x10"SA
(E)6"x6"SA (E)6"x6"SA
(E)8"x6"SA
(E)10"x10"SA
(E)10"x10"SA
(E)10"ØSA
(E)10"x10"SA (E)10"x10"SA
(E)6"ØSA (E)6"ØSA
(E)10"x10"SA
(E)10"ØSA
(E)10"x10"SA
(E)12"x8"SA
(E)10"ØSA
(E)12"x10"SA
(E)8"ØSA
(E)18"x12"SA
(E)6"x6"SA
(E)10"x10"SA
(E)12"x12"SA
(E)8"x8"SA
(E)12"x12"SA
(E)8"x12"SA(E)8"x12"SA(E)6"x8"SA
(E)6"ØSA
(E)10"x8"SA
(E)8"x14"SA
(E)8"x14"SA
(E)40"x12"SA
(E)14x20EA UP
(E)EA
(300)
(E)EA
(300)
(E)16"x12"EA
(E)14"x12"EA
(E)EA
(300)
(E)EA
(300)(E)EA
(90)
(E)20x14EA
(E)14"x8"SA
(E)12x20EA UP/DN
SD
(E)8"ØSA
(E)10"ØSA
(E)10"ØSA
(E)8"ØSA (E)6"ØSA (E)6"ØSA (E)8"ØSA
(E)10"x10"SA
(E)6"x6"SA
(E)10"x10"SA
(E)8"ØSA
(E)10"x10"SA
(E)10"ØSA
(E)12"x12"SA
(E)12"ØSA
(E)12"ØSA
(E)12"ØSA
(E)12"ØSA
(E)12"ØSA
(E)12"x12"SA
(E)12"ØSA
(E)12"x12"SA
(E)12"ØSA
(E)6"ØSA
(E)6"x6"SA
(E)10"x10"SA
(E)8"x8"SA
(E)10"ØSA
(E)10"ØSA
(E)14"x14"SA (E)6"x6"SA
(E)6"x6"SA
(E)10"ØSA
(E)10"x10"SA
(E)6"x6"SA
(E)8"ØSA
(E)10"x10"SA
(E)10"x10"SA
(E)10"ØSA (E)10"ØSA
FD
(E)46"x18"SA
FD
FD
FD
FD
(E)46"x18"SA
FD FD
RG-1
(4500) RG-1
(4500)
(E)RA PLENUM
144" x 54"
1 1
(E)RA PLENUM
144" x 54"
SD
RG-2
(5000)
RG-2
(5000)
RARA → ←RA
RA
92" x 26" RA UP
(E)40" x 30" RA
RG-1
(4500)
RG-1
(4500)
KEY NOTES
1 PROVIDE NEW RETURN AIR GRILLES AND ASSOCIATED DAMPERS.
RECONNECT THE RA DUCTWORK OF THE UNIT TO THE EXISTING RA PLENUM. CLEAN THE
EXISTING RA PLENUM PRIOR TO RECONNECTION.
EXISTING DUCTWORK SYSTEM SHALL REMAIN AND BE REUSED.
THE CONTRACTOR SHALL PERFORM A COMPLETE AIR BALANCE FOR THE EXISTING
DUCTWORK SYSTEM SERVED BY AHU-3 AND AHU-4.
THE CONTRACTOR MUST TAKE AIRFLOW READINGS (CFM) AT ALL EXISTING SUPPLY AND
RETURN GRILLES, ADJUST DAMPERS, AND BALANCE THE SYSTEM TO MATCH THE
ORIGINAL DESIGN FLOW RATES.
EXISTING AHU-3 & AHU-4 DUCTWORK DISTRIBUTION SYSTEMS
NOTES
1. PROVIDE COMPLETE AND PROPERLY FUNCTIONING HVAC SYSTEM FOR THIS PROJECT. VISIT THE PROJECT SITE, EXAMINE THESE PLANS AND ALL EXISTING DRAWINGS RELATING TO THE AREA OF WORK AND REPORT ANY DISCREPANCIES OR OMISSIONS IN THIS PLAN SET TO THE ENGINEER FOR A RESOLUTION AND CLARIFICATION PRIOR TO SUBMISSION FOR BIDS.
2. RISES AND DROPS IN DUCTWORK, ACCESS DOORS, VOLUME DAMPERS, ETC., ARE INDICATED FOR CLARITY FOR A SPECIFIC LOCATION REQUIREMENT AND SHALL NOT BE INTERPRETED AS THE EXTENT OF THE REQUIREMENT FOR THESE ITEMS.
3. ALL DUCT DIMENSIONS, AS SHOWN ON THE DRAWINGS, ARE INTERNAL CLEAR DIMENSIONS AND DUCT SIZE SHALL BE
INCREASED TO COMPENSATE FOR DUCT LINING THICKNESS.
4. PROVIDE ALL 90-DEGREE SQUARE ELBOW WITH DOUBLE RADIUS TURNING VANES UNLESS OTHERWISE INDICATED.
PROVIDE ACCESS DOORS UPSTREAM OF ALL ELBOWS WITH TURNING VANES.
5. LOCATE ALL MECHANICAL EQUIPMENT (RTU'S, RETURN/EXHAUST FANS, DUCTWORK) FOR UNOBSTRUCTED ACCESS TO
UNIT ACCESS PANELS, CONTROLS, AND VALVING.
6. PROVIDE FLEXIBLE CONNECTIONS IN ALL DUCTWORK SYSTEMS (SUPPLY, RETURN, AND EXHAUST) CONNECTED TO AIR HANDLING UNITS , FANS, AND OTHER EQUIPMENT THAT REQUIRE VIBRATION ISOLATION. FLEXIBLE CONNECTIONS SHALL BE
PROVIDED AT THE POINT OF CONNECTION TO THE EQUIPMENT UNLESS OTHERWISE INDICATED.
7. CONTROL WIRING OF SMOKE DETECTORS IS BY THE APPROVED CONTROLS CONTRACTOR.
8. SAFETY DEVICES SHALL BE HARDWIRED TO THE FAN STARTER CIRCUIT, IN ADDITION TO THE DDC SYSTEM.
9. UNLESS OTHERWISE NOTED, ALL DUCTWORK IS OVERHEAD, TIGHT TO THE UNDERSIDE OF AN EXISTING DUCTWORK OR
STRUCTURE, WITH SPACE FOR INSULATION IF REQUIRED.
10. ALL DUCTWORK SHALL BE COORDINATED WITH ALL TRADES INVOLVED. OFFSETS IN DUCTS, INCLUDING DIVIDED DUCTS
AND TRANSITIONS AROUND OBSTRUCTIONS, SHALL BE PROVIDED AT NO ADDITIONAL COST TO THE OWNER.
11. PROVIDE ACCESS DOORS IN DUCTWORK TO PROVIDE ACCESS FOR ALL SMOKE DETECTORS, FIRE DAMPERS, VOLUME
DAMPERS, COILS AND OTHER ITEMS LOCATED IN THE DUCTWORK THAT REQUIRE SERVICE AND/ OR INSPECTION.
12. PROVIDE ACCESS DOORS IN DUCTWORK FOR THE OPERATION, ADJUSTMENT, AND MAINTENANCE OF ALL FANS, VALVES, AND MECHANICAL EQUIPMENT.
13. ALL DUCTS SHALL BE GROUNDED ACROSS FLEXIBLE CONNECTIONS WITH FLEXIBLE COPPER GROUNDING STRAPS.
14. SMOKE DETECTORS SHALL BE FURNISHED AND WIRED BY THE ELECTRICAL CONTRACTOR. THE MECHANICAL
CONTRACTOR SHALL BE RESPONSIBLE FOR MOUNTING THE SMOKE DETECTOR IN DUCTWORK AS SHOWN ON THE
DRAWINGS AND IN ACCORDANCE WITH THE MANUFACTURER'S PRINTED INSTRUCTIONS.
15. SEE SPECIFICATIONS FOR DUCTWORK GAUGES, BRACING, HANGERS, AND OTHER REQUIREMENTS.
16. FIRE ALARM CONTRACTOR SHALL FURNISH FIRE ALARM COMPLIANT SMOKE DETECTOR TO THE SHEET METAL
CONTRACTOR FOR FIELD DUCTWORK INSTALLATION, AS APPLICABLE. DIVISION 16 CONTRACTOR SHALL PROVIDE ALL
SIGNAL AND CONTROL POWER WIRING.
17. SUPPLY AND RETURN AIR DUCTS AND PLENUMS SHALL BE INSULATED WITH NOT LESS THAN R--6 INSULATION WHERE LOCATED IN UNCONDITIONED SPACES AND WHERE LOCATED OUTSIDE THE BUILDING WITH NOT LESS THAN
R-8 INSULATION IN CLIMATE ZONES 1 THROUGH 4.
18. THE CONTRACTOR SHALL PROVIDE CONSTRUCTION DOCUMENTS TO THE BUILDING OWNER WITHIN 90 DAYS OF THE DATE OF RECEIPT OF THE CERTIFICATE OF OCCUPANCY. THOSE DOCUMENTS INCLUDE: DRAWINGS, MANUALS, AND SYSTEM
BALANCING REPORTS.
19. HVAC SYSTEMS SHALL BE BALANCED IN ACCORDANCE WITH GENERALLY ACCEPTED ENGINEERING STANDARDS, AIR AND WATER FLOW RATES SHALL BE MEASURED AND ADJUSTED TO DELIVER FINAL FLOW RATES WITHIN TOLERANCES PROVIDED IN PRODUCT SPECIFICATIONS. TEST AND BALANCING ACTIVITIES SHALL INCLUDE AIR SYSTEM BALANCING.
CONTRACTOR SHALL PROVIDE SIGNED AND SEALED COPY OF TESTING AND BALANCING OF AIR REPORT.
20. THE CONTRACTOR IS TO PROTECT THE FLOOR WITH POLYETHYLENE SHEET OR FILM AND 34" PLYWOOD.
NEW WORK NOTES
This drawing is copyrighted and is subject to copyright protection as an "architectural work" under 17 U. S. C. Sec. 101 et seq. The protection includes but is not limited to the overall form as well as the arrangement and composition of spaces, materials, color and elements in the design. Under such protection, unauthorized use of this drawing may result in the cessation of construction or buildings being seized and/or monetary compensation being awarded to The Robinson Green Beretta Corporation (RGB).
Any reproduction, possession, or use of this drawing or any part thereof without the express written permission of RGB, is prohibited. Violators will be prosecuted to the full extent of the law.
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it. Updated .