About this file

This is a Request for Proposal Change form issued by the City of Carmel, Indiana, for modifications to an existing contract related to the 116th Street and Hoover Road Roundabout Construction project. The document serves as an official request for contractors to submit proposals detailing any increases, decreases, or no changes to the contract price and/or contract time. Contractors must submit their proposals within fifteen (15) calendar days of the request date, accompanied by four (4) copies of a detailed breakdown including quantities, material costs, equipment, labor, overhead, profit margins, and justification for any additional time requested. The form requires contractors to specify the effect that accepting the proposed change will have on both the project's Substantial Completion date (required by November 16, 2026) and Final Completion date (required by May 1, 2027).

This change request form does not authorize contractors to proceed with the proposed work or to stop previously scheduled work; rather, it serves as a formal inquiry to assess potential modifications. Upon approval by the Engineer and Owner's Representative, a Contract Change Order and Notice to Proceed will be issued. The proposal due date, specification references, drawing references, and other specific details require completion by the responsible parties. Liquidated damages remain applicable at $5,000 per calendar day for any delays beyond the established completion dates, making the timing and cost assessment of any proposed changes critical to the project's financial and scheduling outcomes.

View the file

Other files for this state and local contract opportunity

Other files attached to 116th Street and Hoover Road Roundabout Construction, newest first.
File Type Posted
116th_Street_and_Hoover_Road_Roundabout_Construction.pdf PDF
116th_Street_and_Hoover_Road_Roundabout_Construction.pdf PDF
22-ENG-03_FT_Technical_Specifications.pdf PDF
22-ENG-03_FT_Technical_Specifications.pdf PDF
22-ENG-03_FT_Plans.pdf PDF
22-ENG-03_FT_Plans.pdf PDF
22-ENG-03_FT_Permits.pdf PDF
Exhibit_D_E-Verify-1.PDF PDF
MANUFACTURERS_LIST.pdf PDF
22-ENG-03_FT_Utility_Workplans.pdf PDF
Exhibit_D_E-Verify-1.PDF PDF
MANUFACTURERS_LIST.pdf PDF
PAYMENT_BOND.pdf PDF
WORK_DIRECTIVE_CHANGE.pdf PDF
CONTRACT_CHANGE_REQUEST.pdf PDF
NON_COLLUSION_AFFIDAVIT.pdf PDF
PERFORMANCE_BOND.pdf PDF
SCREENSHOT_INSTRUCTIONS_-_FOR_BIDS.pdf PDF
SUBCONTRACTORS_LIST.pdf PDF
22-ENG-03_FT_Permits.pdf PDF
FIELD_ORDER.pdf PDF
22-ENG-03_FT_Utility_Workplans.pdf PDF
CONTRACT_CHANGE_ORDER.pdf PDF
FIELD_ORDER.pdf PDF
MAINTENANCE_BOND.pdf PDF
PAYMENT_BOND.pdf PDF
RIGHT_OF_ENTRY.pdf PDF
SAMPLE_AGREEMENT.pdf PDF
CONTRACT_CHANGE_ORDER.pdf PDF
MAINTENANCE_BOND.pdf PDF
PERFORMANCE_BOND.pdf PDF
SAMPLE_AGREEMENT.pdf PDF
SCREENSHOT_INSTRUCTIONS_-_FOR_BIDS.pdf PDF
SUBCONTRACTORS_LIST.pdf PDF
REQUEST_FOR_PROPOSAL_CHANGE.pdf PDF
SAMPLE_OF_MOU_FOR_E-VERIFY.pdf PDF
WORK_DIRECTIVE_CHANGE.pdf PDF
CONTRACT_CHANGE_REQUEST.pdf PDF
NON_COLLUSION_AFFIDAVIT.pdf PDF
RIGHT_OF_ENTRY.pdf PDF
SAMPLE_OF_MOU_FOR_E-VERIFY.pdf PDF
6._Comprehensive_Set_of_Technical_Specifications_2021-04-28_(V2.7).docx DOCX document
6._Comprehensive_Set_of_Technical_Specifications_2021-04-28_(V2.7).docx DOCX document
Show all 43

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

CITY OF CARMEL

TO: REQUEST FOR PROPOSAL NO

DATE:

PROJECT NAME:

PROJECT NO.:

Specification Reference:

Drawing Reference: _____________ Drawing Date:____________

Identification of Attachments:

Please submit within fifteen (15) calendar days of this request date a proposal showing increase, decrease or no change in Contract Price and/or Contract Time. Proposal shall be accompanied by four (4) copies of breakdown showing quantities, cost of material, equipment, labor, overhead, profit and basis for the additional time if any.

DESCRIPTION OF PROPOSED CHANGE COVERED BY THIS REQUEST:

REASON FOR CHANGE:

SPECIAL INSTRUCTIONS:

THIS REQUEST DOES NOT AUTHORIZE YOU TO PROCEED WITH THE ABOVE WORK

NOR STOP PREVIOUSLY SCHEDULED WORK. Upon approval a Contract Change Order and a Notice To Proceed will be issued.

Please state in your proposal the effect the acceptance of this Request will have on the Project’s Substantial Completion and Final Completion, if accepted within ___ days of proposal due date.

YOUR PROPOSAL DUE DATE: _____________________________________

By: _____________________________________ _________________ Engineer Date

Approved By: _________________________________ Owners Representative

File details come from the government source that posted it. Updated .