About this file

This is a contract change request form from the City of Carmel, Board of Public Works and Safety, related to the 116th Street and Hoover Road Roundabout Construction project in Hamilton County, Indiana. The form provides a standardized template for documenting modifications to the existing construction contract. The document requires specification of the scope of work changes, reasons for the requested modifications, and identification of any supporting attachments. Additionally, the form requests information regarding the timeline impact of proposed changes, including whether additional calendar days will be needed to complete the modified work scope.

The contract change request form includes sections for estimating the approximate cost impact of proposed changes and determining whether additional personnel or specific trades will be required to execute the modified work. The document must be reviewed and approved by appropriate City engineering personnel, with designated spaces for preparer signature, engineer review and recommendation, and secondary review authorization. This form serves as the formal mechanism through which contractors can request adjustments to the original roundabout construction contract, which encompasses HMA pavement, curb and gutter, shared-use path, enclosed storm sewer system, lighting, landscaping, water main relocation, and raised crosswalks at the 116th Street and Hoover Road intersection.

View the file

Other files for this state and local contract opportunity

Other files attached to 116th Street and Hoover Road Roundabout Construction, newest first.
File Type Posted
116th_Street_and_Hoover_Road_Roundabout_Construction.pdf PDF
116th_Street_and_Hoover_Road_Roundabout_Construction.pdf PDF
22-ENG-03_FT_Technical_Specifications.pdf PDF
22-ENG-03_FT_Technical_Specifications.pdf PDF
22-ENG-03_FT_Plans.pdf PDF
22-ENG-03_FT_Plans.pdf PDF
NON_COLLUSION_AFFIDAVIT.pdf PDF
PERFORMANCE_BOND.pdf PDF
SCREENSHOT_INSTRUCTIONS_-_FOR_BIDS.pdf PDF
SUBCONTRACTORS_LIST.pdf PDF
22-ENG-03_FT_Permits.pdf PDF
FIELD_ORDER.pdf PDF
22-ENG-03_FT_Permits.pdf PDF
Exhibit_D_E-Verify-1.PDF PDF
MANUFACTURERS_LIST.pdf PDF
22-ENG-03_FT_Utility_Workplans.pdf PDF
Exhibit_D_E-Verify-1.PDF PDF
MANUFACTURERS_LIST.pdf PDF
PAYMENT_BOND.pdf PDF
WORK_DIRECTIVE_CHANGE.pdf PDF
22-ENG-03_FT_Utility_Workplans.pdf PDF
CONTRACT_CHANGE_ORDER.pdf PDF
FIELD_ORDER.pdf PDF
MAINTENANCE_BOND.pdf PDF
PAYMENT_BOND.pdf PDF
RIGHT_OF_ENTRY.pdf PDF
SAMPLE_AGREEMENT.pdf PDF
CONTRACT_CHANGE_ORDER.pdf PDF
MAINTENANCE_BOND.pdf PDF
PERFORMANCE_BOND.pdf PDF
REQUEST_FOR_PROPOSAL_CHANGE.pdf PDF
SAMPLE_AGREEMENT.pdf PDF
SCREENSHOT_INSTRUCTIONS_-_FOR_BIDS.pdf PDF
SUBCONTRACTORS_LIST.pdf PDF
REQUEST_FOR_PROPOSAL_CHANGE.pdf PDF
SAMPLE_OF_MOU_FOR_E-VERIFY.pdf PDF
WORK_DIRECTIVE_CHANGE.pdf PDF
CONTRACT_CHANGE_REQUEST.pdf PDF
NON_COLLUSION_AFFIDAVIT.pdf PDF
RIGHT_OF_ENTRY.pdf PDF
SAMPLE_OF_MOU_FOR_E-VERIFY.pdf PDF
6._Comprehensive_Set_of_Technical_Specifications_2021-04-28_(V2.7).docx DOCX document
6._Comprehensive_Set_of_Technical_Specifications_2021-04-28_(V2.7).docx DOCX document
Show all 43

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

CITY OF CARMEL

TO: CONTRACT CHANGE REQUEST NO.:

DATE:

PROJECT NAME:

FROM:

IT IS REQUESTED THAT A CONTRACT CHANGE BE MADE TO THE ABOVE

REFERENCED CONTRACT.

1. SCOPE OF WORK (USE ADDITIONAL PAGES IF REQUIRED. ALSO LIST OTHER

CONTRACTS INVOLVED.)

2. REASON FOR CHANGE:

3. APPROXIMATE COST CHANGE TO CONTRACT PRICE: _____________________

4. WILL THE CONTRACT NEED ADDITIONAL CONTRACT TIME TO COMPLETE

THE CHANGE IN WORK SCOPE? _____ -YES _____ -NO _____ -(CALENDAR

DAYS)

5. WILL THE CONTRACTOR NEED ADDITIONAL PERSONNEL TO COMPLETE

THE CHANGE IN WORK SCOPE? _____ -YES _____ -NO

IF NO, TRADE(S): _____________________________________

NO. OF PERSONNEL: _________________________________

DURATION: ______________________________________

6. IDENTIFICATION OF ATTACHMENTS:

DATE: _______________________ DATE: ________________________

PREPARED

REVIEWED BY:____________ REVIEWED BY:____________________________

ENGINEER

Comments and Recommendation:

File details come from the government source that posted it. Updated .