This document is a Scope Sheet - Bid Form for an Electrical Trade Package for the Universal Academy Cafeteria Addition project located at 4833 Ogden St, Detroit, Michigan 48210, issued by Cunningham-Limp on 7/14/2025. The scope covers electrical work for a cafeteria addition, with bid references including FA Studio Rev1 Set dated 6/25/2025 and MLP Civil Set dated 7/9/2025. The electrical contractor will be responsible for providing a complete electrical package, including power for rooftop units, electric heaters, exit and emergency lighting, a design-build fire alarm system, and power/wiring for HVAC duct detectors.
The bid form requires contractors to include all necessary energy calculations, raceways for IT, and permit fees, with a standard one-year warranty from substantial project completion. The document leaves spaces for bidders to fill in their company information, base bid amount, alternate pricing, unit costs, and hourly rates. While specific budget details are not completed, the form indicates that the electrical work will be comprehensively scoped, covering everything from lighting and power distribution to fire alarm systems, with the expectation that the contractor will deliver a complete electrical installation meeting all project specifications and local building codes.
View the file
Other files
Show all 14
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SCOPE SHEET - BID FORM
Trade Package
Q Electrical 7/14/2025
Universal Acadmey Cafertiria Addition 4833 Ogden St, Detroit, Michigan 48210
* THIS FORM TO BE COMPETED WITH YES / NO ON EACH LINE ITEM AND ACCOMPANIED WITH YOUR STANDARD FORM OF PROPOSAL. Also provide a written proposal covering this scope and any other items necessary to further qualify your bid including voluntary alternates *
Company:
Estimator:
Office phone:
Cell phone:
Email:
Base Bid $
1. PLANS & SPECS: FA Studio Rev1 Set Dated 6/25/2025 & MLP Civil Set Dated 7/9/2025
2. ANTICIPATED SCHEDULE: Per Cunningham-Limp Instruction to Bidders & General Requirements dated 7/14/2025
3. GENERAL REQUIREMENTS: Per Cunningham-Limp Instruction to Bidders & General Requirements dated 7/14/2025
4. SALES TAX - REQUIRED
5. HOISTING - REQUIRED
6. CONTRACTOR STANDARD WARRANTY - ONE YEAR FROM SUBSTANTINAL COMPLETION OF PROJECT
7. EXTENDED WARRANTIES - PER INDIVIDUAL SPEIFICATION SECTION
8. GENERAL REQUIREMENTS PER DIVISION 1 OF PROJECT MANUAL / SPECIFICATON BOOK
9.
TRADE SCOPE:
Electrical
The scope of work is presented to clarify certain portions of the work to be performed under the specified bid category and shall be supplied and installed unless noted otherwise. The scope of work is not to be construed as a complete itemization of work included in the bid category, nor does it relieve the subcontractor of its responsibility to deliver a complete job in accordance with plans and specifications.
Include (furnish and install uno):
1. All work performed in accordance with referenced drawings above and all applicable notes, details, & specifications related to this scope of work.
2.
3. Contractor to furnish and install a complete electrical package per plans and spec's
4. Contractor is responsible for providing all necessary energy calculations
5. Include all raceways for IT
6. Provide power for all rooftop units
7. Power for electric heaters shall be provided for vestibules and stairwells
8. Provide all exit and emergency lighting as required by code. Backup lighting shall be provided through lay ins where required
9. Provide all lighting per requirements
10. Contractor shall provide a complete design build fire alarm system.
11. Contractor shall be responsible for power and wiring of HVAC contractor supplied duct detectors
12. Include permit fees 13.
14.
Exclude / By Others:
1.
2.
3.
TOTAL BID $ -
Alternates: (Inclusive of labor, materials, and OH&P) $ 1.
2.
3.
BID BREAKDOWN: $
1 Electrical 2 Fire Alarm
Total Bid $ -
UNIT COST(S): (Inclusive of labor, materials, and OH&P) $
HOURLY RATE(S): (inclusive of OH&P) $
GENERAL / TYPICAL SCOPE OF WORK TO INCLUDE: