About this file

This document is a Scope Sheet - Bid Form for a Masonry Trade Package issued by Cunningham-Limp for the Universal Academy Cafeteria Addition project located at 4833 Ogden St, Detroit, Michigan 48210. The project involves masonry work for a cafeteria addition, with bid documents referencing FA Studio architectural plans (Rev1 Set dated 6/25/2025) and MLP Civil plans (dated 7/9/2025). The bid is scheduled for 7/14/2025 and requires comprehensive masonry services including furnishing and installing building and site masonry walls, veneers, CMU, brick, cast stone, flashing, vapor barriers, lintels, bond beams, and related construction elements.

The bid form requires detailed scope compliance, including installation of masonry walls, insulation of exterior wall cavities, installation of hollow metal door frames, caulking of masonry joints, and cleaning of brick and block surfaces. The contractor is expected to provide a standard warranty of one year from substantial project completion, with potential extended warranties per individual specification sections. The document provides space for bidders to submit their total bid price, alternates, unit costs, and hourly rates, with specific requirements for bid submission including accompanying documentation and comprehensive proposal coverage. The project appears to be funded through standard municipal or educational infrastructure development channels, with precise funding details not explicitly outlined in this scope sheet.

View the file

Other files

Show all 14

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SCOPE SHEET - BID FORM

Trade Package

F Masonry 7/14/2025

Universal Acadmey Cafertiria Addition 4833 Ogden St, Detroit, Michigan 48210

* THIS FORM TO BE COMPETED WITH YES / NO ON EACH LINE ITEM AND ACCOMPANIED WITH YOUR STANDARD FORM OF PROPOSAL. Also provide a written proposal covering this scope and any other items necessary to further qualify your bid including voluntary alternates *

Company:

Estimator:

Office phone:

Cell phone:

Email:

Base Bid $

1. PLANS & SPECS: FA Studio Rev1 Set Dated 6/25/2025 & MLP Civil Set Dated 7/9/2025

2. ANTICIPATED SCHEDULE: Per Cunningham-Limp Instruction to Bidders & General Requirements dated 7/14/2025

3. GENERAL REQUIREMENTS: Per Cunningham-Limp Instruction to Bidders & General Requirements dated 7/14/2025

4. SALES TAX - REQUIRED

5. HOISTING - REQUIRED

6. CONTRACTOR STANDARD WARRANTY - ONE YEAR FROM SUBSTANTINAL COMPLETION OF PROJECT

7. EXTENDED WARRANTIES - PER INDIVIDUAL SPEIFICATION SECTION

8. GENERAL REQUIREMENTS PER DIVISION 1 OF PROJECT MANUAL / SPECIFICATON BOOK

9.

TRADE SCOPE:

Masonry

The scope of work is presented to clarify certain portions of the work to be performed under the specified bid category and shall be supplied and installed unless noted otherwise. The scope of work is not to be construed as a complete itemization of work included in the bid category, nor does it relieve the subcontractor of its responsibility to deliver a complete job in accordance with plans and specifications.

Include (furnish and install uno):

1. All work performed in accordance with referenced drawings above and all applicable notes, details, & specifications related to this scope of work.

2.

3. Furnish and install all building and site masonry walls and veneers including CMU, split face units, brick, cast stone, manufactured stone, etc.

4. Provide and install all flashing and vapor barriers in accordance with the Masonry Institute standards.

5. Contractor to supply and install all masonry noted on the drawings per plans and specifications.

6. Rod and grout shall be installed per masonry institute standards.

7. Mortar mix shall be monitored for mix consistency and temperature per appropriate masonry standards / specifications.

8. Supply and install all masonry lintels and bond beams.

9. Contractor shall install all CL supply steel lintels unless otherwise noted.

10. Contractor shall insulate all exterior wall cavities (including behind vertical siding) per plans.

11. Contractor shall install all hollow metal door frames in new and existing masonry walls where indicated

12. Contractor shall caulk all masonry joints, control joins and where masonry abuts dissimilar surfaces.

13. Contractor shall clean / wash all brick and block interior and exterior to CL satisfaction.

14. Cut-in new opening for door 103A in exisitng exterior wall 15.

16.

Exclude / By Others:

1.

2.

3.

TOTAL BID $ -

Alternates: (Inclusive of labor, materials, and OH&P) $ 1.

2.

3.

BID BREAKDOWN: $

1 Masonry

Total Bid $ -

UNIT COST(S): (Inclusive of labor, materials, and OH&P) $

HOURLY RATE(S): (inclusive of OH&P) $

GENERAL / TYPICAL SCOPE OF WORK TO INCLUDE: