This document is a Scope Sheet - Bid Form for Trade Package L (Millwork) issued by Cunningham-Limp for the Universal Academy Cafeteria Addition project located at 4833 Ogden St, Detroit, Michigan 48210. The project involves millwork-related work to be performed based on FA Studio Rev1 Set dated 6/25/2025 and MLP Civil Set dated 7/9/2025, with an anticipated completion date of 7/14/2025. The scope of work includes furnishing and installing solid surface countertops and backsplashes in restrooms, P. lam sills at windows, and requires the submission of shop drawings for approvals.
The bid form outlines standard requirements including a one-year contractor warranty, sales tax, and hoisting provisions. The document is structured for potential bidders to complete, with sections for total bid amount, alternates, bid breakdown, unit costs, and hourly rates. No specific pricing details are filled in, leaving room for contractors to provide their own cost proposals. The project appears to be part of a cafeteria addition construction project, with this specific trade package focused exclusively on millwork-related installations and requirements.
View the file
Other files
Show all 14
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SCOPE SHEET - BID FORM
Trade Package
L Millwork 7/14/2025
Universal Acadmey Cafertiria Addition 4833 Ogden St, Detroit, Michigan 48210
* THIS FORM TO BE COMPETED WITH YES / NO ON EACH LINE ITEM AND ACCOMPANIED WITH YOUR STANDARD FORM OF PROPOSAL. Also provide a written proposal covering this scope and any other items necessary to further qualify your bid including voluntary alternates *
Company:
Estimator:
Office phone:
Cell phone:
Email:
Base Bid $
1. PLANS & SPECS: FA Studio Rev1 Set Dated 6/25/2025 & MLP Civil Set Dated 7/9/2025
2. ANTICIPATED SCHEDULE: Per Cunningham-Limp Instruction to Bidders & General Requirements dated 7/14/2025
3. GENERAL REQUIREMENTS: Per Cunningham-Limp Instruction to Bidders & General Requirements dated 7/14/2025
4. SALES TAX - REQUIRED
5. HOISTING - REQUIRED
6. CONTRACTOR STANDARD WARRANTY - ONE YEAR FROM SUBSTANTINAL COMPLETION OF PROJECT
7. EXTENDED WARRANTIES - PER INDIVIDUAL SPEIFICATION SECTION
8. GENERAL REQUIREMENTS PER DIVISION 1 OF PROJECT MANUAL / SPECIFICATON BOOK
9.
TRADE SCOPE:
Millwork
The scope of work is presented to clarify certain portions of the work to be performed under the specified bid category and shall be supplied and installed unless noted otherwise. The scope of work is not to be construed as a complete itemization of work included in the bid category, nor does it relieve the subcontractor of its responsibility to deliver a complete job in accordance with plans and specifications.
Include (furnish and install uno):
1. All work performed in accordance with referenced drawings above and all applicable notes, details, & specifications related to this scope of work.
2.
3. Furnish and Install Soild surface countertop and backsplash in each restroom
4. Furnish and install p. lam sills at the windows
5. Provide shop drawings for approvals 6.
7.
8.
Exclude / By Others:
1.
2.
3.
TOTAL BID $ -
Alternates: (Inclusive of labor, materials, and OH&P) $ 1.
2.
3.
BID BREAKDOWN: $
1 Millwork
Total Bid $ -
UNIT COST(S): (Inclusive of labor, materials, and OH&P) $
HOURLY RATE(S): (inclusive of OH&P) $
GENERAL / TYPICAL SCOPE OF WORK TO INCLUDE: