This is a Scope Sheet - Bid Form for a Floor Covering trade package issued by Cunningham-Limp for the Universal Academy Cafeteria Addition project located at 4833 Ogden St, Detroit, Michigan 48210. The document outlines the scope of work for floor covering installation, referencing FA Studio Rev1 Set dated 6/25/2025 and MLP Civil Set dated 7/9/2025, with an anticipated project schedule per the contractor's instructions dated 7/14/2025. The scope includes furnishing and installing all soft and hard flooring in indicated areas, with specific requirements such as 10% attic stock, necessary floor preparation, installation of hard surface tiles, waterproofing in wet areas, and ceramic and vinyl base provisions.
The bid form provides a framework for potential contractors to submit their proposals, with sections for base bid, alternates, and bid breakdowns. The trade package specifies a one-year standard contractor warranty from substantial project completion, with additional extended warranties per individual specification sections. The bid includes two primary flooring categories: VCT Flooring and Hard Tile, though specific quantities are not detailed in the document. Bidders are required to complete the form with yes/no responses on each line item and accompany it with a standard proposal form, along with a written proposal covering the scope and any voluntary alternates.
View the file
Other files
Show all 14
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SCOPE SHEET - BID FORM
Trade Package
M Floor Covering
7/14/2025
Universal Acadmey Cafertiria Addition 4833 Ogden St, Detroit, Michigan 48210
* THIS FORM TO BE COMPETED WITH YES / NO ON EACH LINE ITEM AND ACCOMPANIED WITH YOUR STANDARD FORM OF PROPOSAL. Also provide a written proposal covering this scope and any other items necessary to further qualify your bid including voluntary alternates *
Company:
Estimator:
Office phone:
Cell phone:
Email:
Base Bid $
1. PLANS & SPECS: FA Studio Rev1 Set Dated 6/25/2025 & MLP Civil Set Dated 7/9/2025
2. ANTICIPATED SCHEDULE: Per Cunningham-Limp Instruction to Bidders & General Requirements dated 7/14/2025
3. GENERAL REQUIREMENTS: Per Cunningham-Limp Instruction to Bidders & General Requirements dated 7/14/2025
4. SALES TAX - REQUIRED
5. HOISTING - REQUIRED
6. CONTRACTOR STANDARD WARRANTY - ONE YEAR FROM SUBSTANTINAL COMPLETION OF PROJECT
7. EXTENDED WARRANTIES - PER INDIVIDUAL SPEIFICATION SECTION
8. GENERAL REQUIREMENTS PER DIVISION 1 OF PROJECT MANUAL / SPECIFICATON BOOK
9.
TRADE SCOPE:
Floor Covering
The scope of work is presented to clarify certain portions of the work to be performed under the specified bid category and shall be supplied and installed unless noted otherwise. The scope of work is not to be construed as a complete itemization of work included in the bid category, nor does it relieve the subcontractor of its responsibility to deliver a complete job in accordance with plans and specifications.
Include (furnish and install uno):
1. All work performed in accordance with referenced drawings above and all applicable notes, details, & specifications related to this scope of work.
2.
3. Furnish and install all soft and hard flooring in areas as indicated per Finish Plan and Room Schedule.
4. Attic stock of all materials shall be 10%.
5. Flooring installations shall include all necessary floor prep required.
6. Hard surface tile (ceramic, porcelain, quarry, granite, marble ,etc.) shall be installed as indicated.
7. Waterproofing shall be provided under ceramic tile floors and walls in wet areas if noted on drawings.
8. Wall tile 6' high shall be provided at all wet walls unless noted otherwise.
9. All Ceramic and vinyl base shall be provided as indicated or required.
10. Comply with all plans and specifications.
11. Include strips at carpet or VCT to concrete transitions as required.
12.
13.
Exclude / By Others:
1.
2.
3.
TOTAL BID $ -
Alternates: (Inclusive of labor, materials, and OH&P) $ 1.
2.
3.
BID BREAKDOWN: $
1 VCT Flooring 2 Hard Tile
Total Bid $ -
UNIT COST(S): (Inclusive of labor, materials, and OH&P) $
HOURLY RATE(S): (inclusive of OH&P) $
GENERAL / TYPICAL SCOPE OF WORK TO INCLUDE: