PWS Atch 5_QASP.docx
DOCX document 41 KB Posted
- Solicitation number
- N6264926QE025
About this file
This is a Quality Assurance Surveillance Plan (QASP) that establishes performance monitoring procedures and standards for the Oily Wastewater (OWW) Treatment, Recycling, and Disposal Services contract in Sasebo, Japan. The QASP outlines a multi-functional team structure including an on-site Superintendent, Government Technical and Environmental Points of Contact (TPOC/EPOC), and a Contracting Officer, each with defined surveillance and oversight responsibilities. Performance evaluation occurs quarterly using a Contractor Performance Evaluation Sheet (CPES) completed by the Government EPOC, with an annual Contractor Performance Assessment Report (CPAR) submitted by the SRF TPOC.
The QASP establishes ten performance objectives with specific standards and Acceptable Quality Levels (AQLs) covering barge cleanliness, wastewater disposal compliance, license maintenance, environmental protection plan approval, environmental management system training, spill boom deployment, spill notification procedures, treatment process validation, industrial and hazardous waste disposal, and used oil recycling documentation. Contractor performance is rated as "Acceptable" or "Not Acceptable" based on whether AQLs are met, with evaluation methods including weekly no-notice barge inspections, 100% PFAS testing review before discharge, quarterly license and plan reviews, and 100% inspection of transfer operations and waste documentation. Non-conforming performance triggers mandatory corrective action with submission of a Corrective Action Plan within 30 calendar days, while consistently meeting AQLs serves as positive past performance documentation for future contract evaluations.
View the file
Other files
Show all 32
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
QASP (Quality Assurance Surveillance Plan) Ver. 20260707
QUALITY ASSURANCE SURVEILLANCE PLAN (QASP)
1. Introduction:
This QASP is pursuant to the requirements listed in the Performance Work Statement (PWS) entitled Oily Wastewater (OWW) Treatment, Recycling, and Disposal Services. This plan sets forth the procedures and guidelines to ensure that the contractor’s performance achieves the Government’s performance standards and requested service levels. The Government (Govt) reserves the right to make changes to the QASP as necessary.
| 2. | Multi-functional Team Roles/Functions and Responsibility: |
| On-site Superintendent | |
| Ensure the standards of the contract are being fulfilled and advise the Evaluator to evaluate contractor’s performance. |
| Evaluator |
| The Govt Technical Point of Contact (TPOC) and/or the Govt Environmental Point of Contact (EPOC) evaluates contractor’s performance and determines compliance with standard performance objectives. Maintain evaluation records. |
| Contracting Officer |
| Review contractor’s performance documents; resolve all contractual matters between the Government and contractor, and is ultimately responsible for the final determination of the adequacy of the contractor’s performance. |
3. Method of Surveillance:
The following surveillance methods are utilized under this contract.
3.1: Contractor’s Performance Evaluation Sheet (CPES) The Govt EPOC evaluates contractor’s performance using the CPES on a quarterly basis as follows.
Evaluation Period
| 1st Period |
| 2nd Period |
| 3rd Period |
| 4th Period |
| September - November |
| December - February |
| March - May |
| June - August |
The Govt EPOC is responsible for assuring proper Government surveillance of the contractor’s performance. Below table depicts Performance Objective, Performance Standard, Acceptable Quality Level (AQL), and Assessment Method.
| Performance Objective |
| PWS Para. |
| Performance Standard |
| AQL |
| Assessment Method |
| 1 |
| Maintain cleanliness of barges. |
| 4.2.1.f |
| Keep barge decks and containment areas free of visible oily residue, waste, and debris at all times. |
| No more than one validated negative finding per barge, per month. |
| Random, no-notice inspections of all active barges at least weekly, and a formal inspection of 100% of all barges quarterly. |
| 2 |
| Dispose wastewater properly. |
| 4.5.3 |
| Treated wastewater effluent meets all PFAS limits prior to discharge. |
| 100% of all treated wastewater batches must pass PFAS testing (below 50 ppt combined) before discharge. No deviation is permitted. |
| Review of PFAS test results and inspection. |
| 3 |
| Maintain and ensure all licenses are valid. |
| 6.2 |
| Contractor and all subcontractors possess all required licenses to perform the work. |
| 100% of all required Japanese and installation-specific licenses must be valid and current throughout the entire performance period. No lapse is permitted. |
| Periodic Inspection at least quarterly. |
| 4 |
| EPP is updated and approved. |
| 6.3 |
| A current and approved Environmental Protection Plan (EPP) is maintained. |
| The EPP must be approved prior to starting work. All required annual reviews and submissions must be completed on time. No deviation is permitted. |
| Periodic Inspection at least quarterly. |
| 5 |
| Comply with EMS Goals and Policy. |
| 6.4 |
| Comply with EMS Goals, Policy, and training requirements. |
| 100% on-time submission of required EMSAT training certifications and no more than one (1) validated non-conformance finding related to EMS policy. |
| Periodic Inspection at least quarterly. |
| 6 |
| Comply with all environmental protection requirements. |
| 6.5 |
| A spill boom must be correctly deployed, fully encircling the barge(s) with no gaps, during all OWW transfer operations. |
| 95% of all observed transfer actions are compliant. |
| 100% inspection of all observed transfer actions. |
| 7 |
| Provide timely spill notification to the Govt, if any. |
| 6.5.3 |
| All spills are reported immediately in accordance with the PWS. |
| 100% of all spills, regardless of amount, must be reported to the appropriate authorities within the timeframes specified in PWS para 6.5.3. No deviation is permitted. |
| 100% inspection. |
| 8 |
| OWW treatment/purification process is valid. |
| 6.6 |
| Treated effluent meets all JIS testing standards. |
| 100% of all quarterly JIS effluent tests must meet the limits set forth in the JEGS. All associated forms (H and I) must be submitted on time. No deviation is permitted. |
| 100% inspection. |
| 9 |
| Dispose industrial waste and hazardous waste properly. |
| 6.7 |
| All waste generated from treatment operations is properly handled and documented. |
| 100% compliance. All manifests and forms (J, K, L) must be accurate and submitted on time. There shall be zero instances of improper segregation, labeling, or disposal. |
| 100% inspection. |
| 10 |
| Recycle treated used oil properly. |
| 6.8 |
| All recovered used oil is properly recycled and documented. |
| 100% compliance. All required documentation (Customs Declaration, Recycle Certificate, revenue reporting) must be accurate and submitted to the Government on time. No deviation is permitted. |
| 100% inspection. |
The contractor’s performance is evaluated each performance objective and will rate the contractor’s performance as “Acceptable (A)” when the contractor’s performance fulfills the Acceptable Quality Level (AQL) or “Not Acceptable (N)” when the contractor’s performance does not fulfill the AQL. The evaluator’s comment is mandatory.
Based on the performance objectives and comments, the EPOC determines that the contractor’s overall performance is Acceptable or Unacceptable as follows.
| Acceptable |
| The contractor’s performance is considered to have met the stated performance standards. |
| Unacceptable |
| The contractor failed to meet one or more of the stated performance standards. |
3.2. Contractor Performance Assessment Report (CPAR)
The SRF TPOC evaluates contractor’s performance via CPAR on an annual basis. Per the FAR Subpart 42.15 and Navy's CPAR System Guide, CPAR is used for the annual evaluation of overall contract performance. The SRF TPOC evaluates based on CPES and other information. This report may affect future source selections to ensure that the Federal Government only does business with companies that provide quality products and services in support of the agency’s missions.
4. Record of Evaluation:
The Evaluators and Contracting Office maintain evaluation records.
| 5. | Incentive/Decrement: |
| a. | Incentives (Positive Performance) |
The Government will document favorable contractor performance via the Contractor Performance Assessment Reporting System (CPARS) and/or the local Contractor Performance Evaluation System (CPES). Consistently meeting or exceeding the Acceptable Quality Levels (AQLs) will serve as a primary incentive, as these positive past performance records will be utilized by the Government in the evaluation of future contract solicitations.
b. Disincentives (Non-Conforming Services) Disincentives for non-conforming OWW treatment and disposal services will be enforced in accordance with standard commercial contract remedies (e.g., FAR 52.212-4, Contract Terms and Conditions—Commercial Products and Commercial Services). The Government reserves the right to require the Contractor to re-perform any defective or non-conforming service to meet contract requirements at no additional cost to the Government.
c. Mandatory Corrective Action for Unacceptable Performance In the event the Contractor’s overall performance is rated 'Unacceptable' in a CPES and/or CPARS evaluation, the Contractor shall immediately initiate corrective action. The Contractor must rectify all identified deficiencies and submit a Corrective Action Plan (CAP) at no additional cost to the Government within thirty (30) calendar days of receiving the official evaluation report.
(End of QASP)