Progress Schedule and Progress Report.xlsx

XLSX spreadsheet 132 KB Posted

Attached to
Replace Foam Fire Suppression System with Water Deluge System Federal contract opportunity
Solicitation number
FA309924R0008
Issued by
Department of the Air Force Air Education and Training Command

About this file

This document appears to be a Progress Schedule and Progress Report related to a federal contract opportunity.

The key details are:

  • The contract is for project number MXDP-1037 titled "Re-Route Arantz & 7th St" with a contract amount of $480,407.79.
  • The period of performance is 150 calendar days from the starting date of 1/25/10 to the completion date of 6/23/10.
  • The contract includes various work elements such as bond, mobilization, design services, testing, traffic control, utility relocation, demolition, road reconstruction, curbs/gutters, sidewalks, pavement markings, signage, landscaping, and project closeout documentation.
  • The document provides a detailed progress schedule and progress report template, with sections for tracking percentage completion of each work element.
  • There are no details provided about the associated federal contract opportunity beyond this specific project.

View the file

Other files for this federal contract opportunity

Other files attached to Replace Foam Fire Suppression System with Water Deluge System, newest first.
File Type Posted
Solicitation Cancelation MFR.pdf PDF
Statement of Work -MXDP22-1013 - Construction.pdf PDF
Attachment B. Wage Determination TX20240186.pdf PDF
Laughlin AFB Division 01 General Specifications.pdf PDF
UFC 3-420-01 Plumbing Systems.pdf PDF
Solicitation - FA309924R0008.pdf PDF
Attachment A. Statement of Work MXDP 22-1013.docx DOCX document
Sundown Policy for Foam Fire Suppression Systems.pdf PDF
Schedule of Submittals.xlsx XLSX spreadsheet
UFC 3-230-01 Water Storage and Distribution.pdf PDF
UFC 3-600-01 Fire Protection Engineering for Facilities.pdf PDF
UFC 4-211-01 Aircraft Maintenance Hangars.pdf PDF
Attachment C. Deluge Liquidated Damages Signed.pdf PDF
E. AETC 47.pdf PDF
F. Financial Institution Reference Sheet.pdf PDF
G. Past Performance Questionnaire.pdf PDF
JandA MONACO.pdf PDF
UFC 3-400-02 Design Engineering Weather Data.pdf PDF
UFC 3-401-01 Mechanical Engineering.pdf PDF
MXDP22-1013_Sub 05_Final Specifications.pdf PDF
Attachment D. Notification of Compliance with Contract Insurance Requirements.pdf PDF
Fire Suppression System Plan Set.pdf PDF
EQ Contractor Tech Specs 2024.pdf PDF
Laughlin_AFB_Installation Facilities Standards.pdf PDF
FM Data Sheet 3-26 Fire Protection for Nonstorage O.pdf PDF
Exemption to UFCs - Sundown Policy - 18JAN22.pdf PDF
UFC 3-410-01 HVAC.pdf PDF
UFC 3-410-02 Direct Digital Control for HVAC Other.pdf PDF
UFC 3-501-01 Electrical Engineering.pdf PDF
Show all 29

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

WORK SHEET

1. CONTRACT NUMBER:
2. STARTING DATE:
3. COMPLETION DATE:
4. PURCHASE REQUEST NO.:
5. PROJECT NUMBER:
6. ACTUAL START DATE:
7. ACTUAL COMPLETION DATE:
8. PROJECT TITLE:
9. SUBMITTED BY:
10. CONTRACT AMOUNT:
TIME CALCULATION
START DATENUMBER OF DAYS GIVENCOMPLETION DATE
31-Dec-99031-Dec-99
NO.WORK ELEMENTSLINE $ AMOUNTPERCENTAGE OF CONTRACT
1ERROR:#DIV/0!
2ERROR:#DIV/0!
3ERROR:#DIV/0!$43,488.12
4ERROR:#DIV/0!
5ERROR:#DIV/0!ERROR:#REF!
6ERROR:#DIV/0!ERROR:#REF!3401.86
7ERROR:#DIV/0!
8ERROR:#DIV/0!
9ERROR:#DIV/0!ERROR:#REF!ERROR:#REF!
10ERROR:#DIV/0!ERROR:#REF!ERROR:#REF!
11ERROR:#DIV/0!ERROR:#REF!ERROR:#REF!
12ERROR:#DIV/0!ERROR:#REF!ERROR:#REF!
13ERROR:#DIV/0!ERROR:#REF!ERROR:#REF!
14ERROR:#DIV/0!ERROR:#REF!ERROR:#REF!
15ERROR:#DIV/0!ERROR:#REF!ERROR:#REF!
16ERROR:#DIV/0!ERROR:#REF!ERROR:#REF!
17ERROR:#DIV/0!
18ERROR:#DIV/0!ERROR:#REF!ERROR:#REF!
19ERROR:#DIV/0!ERROR:#REF!ERROR:#REF!
20ERROR:#DIV/0!ERROR:#REF!ERROR:#REF!
21ERROR:#DIV/0!ERROR:#REF!ERROR:#REF!
22ERROR:#DIV/0!ERROR:#REF!ERROR:#REF!
23ERROR:#DIV/0!ERROR:#REF!ERROR:#REF!
24ERROR:#DIV/0!
25ERROR:#DIV/0!
26ERROR:#DIV/0!
27ERROR:#DIV/0!ERROR:#REF!ERROR:#REF!
28ERROR:#DIV/0!
29ERROR:#DIV/0!
30ERROR:#DIV/0!
31ERROR:#DIV/0!
32ERROR:#DIV/0!
33ERROR:#DIV/0!
34ERROR:#DIV/0!
35ERROR:#DIV/0!
36ERROR:#DIV/0!
37ERROR:#DIV/0!
38ERROR:#DIV/0!
39ERROR:#DIV/0!
40ERROR:#DIV/0!
41ERROR:#DIV/0!
TOTAL WORK0.00ERROR:#DIV/0!

WORK SHEET (2)

1. CONTRACT NUMBER:FA3099-09-D-0001-0002
2. STARTING DATE:25-Jan-10
3. COMPLETION DATE:23-Jun-10
4. PURCHASE REQUEST NO.:
5. PROJECT NUMBER:MXDP-1037
6. ACTUAL START DATE:
7. ACTUAL COMPLETION DATE:
8. PROJECT TITLE:Re-Route Arantz & 7th St
9. SUBMITTED BY:Jody Spear
10. CONTRACT AMOUNT:$480,407.79
TIME CALCULATION
START DATENUMBER OF DAYS GIVENCOMPLETION DATE
25-Jan-1015023-Jun-10
LINE NO.WORK ELEMENTSLINE $ AMOUNTESTIMATED PERCENTAGE OF CONTRACTPERCENTAGE OF CONTRACT
A1.2044090954
1BOND$9,420.001.96%0.00%9420
2MOBILIZATION$13,606.002.83%0.00%$16,387.19
3DESIGN SERVICES$60,000.0012.49%0.00%$72,264.55
4TESTING OF ASBESTOS / LEAD$2,000.000.42%0.00%$2,408.82
5TRAFFIC CONTROL / SAFETY PLAN$11,298.002.35%0.00%$13,607.41
6LOCATE EXISTING UTILITIES$7,500.001.56%0.00%$9,033.07
7RELOCATE EXISTING ELECTRICAL$20,000.004.16%0.00%$24,088.18
8RELOCATE EXISTING GAS$6,200.001.29%0.00%$7,467.34
9RELOCATE EXISTING WATER & FIRE HYDRANT$17,500.003.64%0.00%$21,077.16
10DEMO OF TEMPORARY LIVING FACILITY$16,000.003.33%0.00%$19,270.55
11DEMO OF CONCRETE FOUNDATION/ DRIVEWAYS$13,500.002.81%0.00%$16,259.52
12DEMO OF ROADWAY$19,912.004.14%0.00%$23,982.19
13DEMO OF LANDSCAPING / TREES$11,500.002.39%0.00%$13,850.70
14CLEARING / CLEANING$15,500.003.23%0.00%$18,668.34
15EROSION CONTROL$12,354.002.57%0.00%$14,879.27
16RECONSTRUCT NEW ROAD SUB GRADE$26,896.005.60%0.00%$32,393.79
17RECONSTRUCT OF BASE MATERIAL$12,726.002.65%0.00%$18,327.89
18RECONSTRUCT NEW ASPHALT$66,146.0013.77%0.00%$79,666.84
19RECONSTRUCT OF CURBS / GUTTERS$24,535.005.11%0.00%$29,550.18
20RECONSTRUCT OF NEW SIDE WALKS$12,172.002.53%0.00%$14,660.07
21INSTALL NEW PAVEMENT MARKINGS$4,905.001.02%0.00%$8,079.18
22SIGNAGE$5,000.001.04%0.00%$3,021.47
23PLANT TREES/ SCRUBS$5,000.001.04%0.00%$6,022.05
24GRADING OF TOPSOIL$3,000.000.62%0.00%$3,613.23
25HYDRO MULCH$2,000.000.42%0.00%$533.50
26CLOSE OUT DOCUMENTATION$0.000.00%0.00%$1,875.32
TOTAL WORK$398,670.0082.99%0.00%480407.79040002

PROGRESS SCHEDULE

CONTRACT PROGRESS SCHEDULENOTICE TO PROCEED:
(SEE CONTRACTOR'S INSTRUCTIONS ON REVERSE)
1. CONTRACT NO.8. PROJECT TITLE11. APPROVAL RECOMMENDED BY:
00DATE SIGNEDINSTALLATIONS ENGINEER'S SIGNATURE
2. STARTING DATEDecember 31, 1899
3. COMPLETION DATEDecember 31, 18999. SUBMITTED BY:
4. PURCHASE REQUEST NO.0DATE SIGNED10. CONTRACTOR'S NAME & ADDRESSCONTRACTOR'S SIGNATURE12. APPROVED BY:
5. PROJECT NO.0DATE SIGNEDCONTRACTING OFFICER'S SIGNATURE
6. ACTUAL STARTING DATEDecember 31, 1899
7. ACTUAL COMPLETION DATE
Report ---------->
LINE NO.WORK ELEMENTS%18-Jan1-Feb15-Feb29-Feb14-Mar28-Mar11-Apr25-Apr9-May23-May6-Jun20-Jun4-Jul18-Jul1-Aug15-Aug29-Aug12-Sep26-Sep10-Oct24-Oct7-Nov21-Nov5-Dec19-Dec2-Jan16-Jan30-Jan13-Feb27-Feb13-Mar27-Mar10-Apr24-Apr8-May22-May
ABCD31-Jan14-Feb28-Feb13-Mar27-Mar10-Apr24-Apr8-May22-May5-Jun19-Jun3-Jul17-Jul31-Jul14-Aug28-Aug11-Sep25-Sep9-Oct23-Oct6-Nov20-Nov4-Dec18-Dec1-Jan15-Jan29-Jan12-Feb26-Feb12-Mar26-Mar9-Apr23-Apr7-May21-May4-Jun
10ERROR:#DIV/0!0.00%
0.00%
20ERROR:#DIV/0!0.00%
0.00%
30ERROR:#DIV/0!0.00%
0.00%
40ERROR:#DIV/0!0.00%
0.00%
50ERROR:#DIV/0!0.00%
0.00%
60ERROR:#DIV/0!0.00%
0.00%
70ERROR:#DIV/0!0.00%
0.00%
80ERROR:#DIV/0!0.00%
0.00%
90ERROR:#DIV/0!0.00%
0.00%
100ERROR:#DIV/0!0.00%
0.00%
110ERROR:#DIV/0!0.00%
0.00%
120ERROR:#DIV/0!0.00%
0.00%
130ERROR:#DIV/0!0.00%
0.00%
140ERROR:#DIV/0!0.00%
0.00%
150ERROR:#DIV/0!0.00%
0.00%
160ERROR:#DIV/0!0.00%
0.00%
170ERROR:#DIV/0!0.00%
0.00%
180ERROR:#DIV/0!0.00%
0.00%
190ERROR:#DIV/0!0.00%
0.00%
200ERROR:#DIV/0!0.00%
0.00%
210ERROR:#DIV/0!0.00%
0.00%
220ERROR:#DIV/0!0.00%
0.00%
230ERROR:#DIV/0!0.00%
0.00%
240ERROR:#DIV/0!0.00%
0.00%
250ERROR:#DIV/0!0.00%
0.00%
260ERROR:#DIV/0!0.00%
0.00%
270ERROR:#DIV/0!0.00%
0.00%
280ERROR:#DIV/0!0.00%
0.00%
290ERROR:#DIV/0!0.00%
0.00%
300ERROR:#DIV/0!0.00%
0.00%
310ERROR:#DIV/0!0.00%
0.00%
320ERROR:#DIV/0!0.00%
0.00%
330ERROR:#DIV/0!0.00%
0.00%
340ERROR:#DIV/0!0.00%
0.00%
350ERROR:#DIV/0!0.00%
0.00%
360ERROR:#DIV/0!0.00%
0.00%
370ERROR:#DIV/0!0.00%
0.00%
380ERROR:#DIV/0!0.00%
0.00%
390ERROR:#DIV/0!0.00%
0.00%
400ERROR:#DIV/0!0.00%
0.00%
410ERROR:#DIV/0!0.00%
0.00%
SCHEDULED COMPLETIONWKLY ------------------>ERROR:#DIV/0!0.00%0.00%0.00%0.00%0.00%0.00%0.00%0.00%0.00%0.00%0.00%0.00%0.00%0.00%0.00%0.00%0.00%0.00%0.00%0.00%0.00%0.00%0.00%0.00%0.00%0.00%0.00%0.00%0.00%0.00%0.00%0.00%0.00%0.00%0.00%0.00%0.00%
TOTAL ---------------->0.00%0.00%0.00%0.00%0.00%0.00%0.00%0.00%0.00%0.00%0.00%0.00%0.00%0.00%0.00%0.00%0.00%0.00%0.00%0.00%0.00%0.00%0.00%0.00%0.00%0.00%0.00%0.00%0.00%0.00%0.00%0.00%0.00%0.00%0.00%0.00%
ACTUAL COMPLETIONWKLY ------------------>0.00%
TOTAL ---------------->

PROGRESS CHART

Actual 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 Scheduled 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

PROGRESS REPORT

CONTRACT PROGRESS REPORTPROJECT TITLE:Progress Schedule
0Column
CONTRACTORADDRESSL
REPORTPERIOD COVERED:PROJECT NO.CONTRACT NO.COMPLETION DATE
NO:FROM:TO:0031-Dec-99
31 Last Period1 This Period2 Last Period2 This Period3 Last Period3 This Period4 Last Period4 This Period5 Last Period5 This Period6 Last Period6 This Period7 Last Period7 This Period8 Last Period8 This Period9 Last Period9 This Period10 Last Period10 This Period11 Last Period
NO.WORK ELEMENT% OF TOTAL JOB% LAST PERIOD% THIS PERIODTOTAL % COMPLETEL0L0.00%L0L0.00%L0L0.00%L0L0.00%L0L0.00%L0L0.00%L0L0.00%L0L0.00%L0L0.00%L0L0.00%L
10ERROR:#DIV/0!0.00%0.00%0.00%M0.00%M0.00%M0.00%M0.00%M0.00%M0.00%M0.00%M0.00%M0.00%M0.00%M0.00%M0.00%M0.00%M0.00%M0.00%M0.00%M0.00%M0.00%M0.00%M0.00%M
20ERROR:#DIV/0!0.00%0.00%0.00%N0.00%N0.00%N0.00%N0.00%N0.00%N0.00%N0.00%N0.00%N0.00%N0.00%N0.00%N0.00%N0.00%N0.00%N0.00%N0.00%N0.00%N0.00%N0.00%N0.00%N
30ERROR:#DIV/0!0.00%0.00%0.00%O0.00%O0.00%O0.00%O0.00%O0.00%O0.00%O0.00%O0.00%O0.00%O0.00%O0.00%O0.00%O0.00%O0.00%O0.00%O0.00%O0.00%O0.00%O0.00%O0.00%O
40ERROR:#DIV/0!0.00%0.00%0.00%P0.00%P0.00%P0.00%P0.00%P0.00%P0.00%P0.00%P0.00%P0.00%P0.00%P0.00%P0.00%P0.00%P0.00%P0.00%P0.00%P0.00%P0.00%P0.00%P0.00%P
50ERROR:#DIV/0!0.00%0.00%0.00%Q0.00%Q0.00%Q0.00%Q0.00%Q0.00%Q0.00%Q0.00%Q0.00%Q0.00%Q0.00%Q0.00%Q0.00%Q0.00%Q0.00%Q0.00%Q0.00%Q0.00%Q0.00%Q0.00%Q0.00%Q
60ERROR:#DIV/0!0.00%0.00%0.00%R0.00%R0.00%R0.00%R0.00%R0.00%R0.00%R0.00%R0.00%R0.00%R0.00%R0.00%R0.00%R0.00%R0.00%R0.00%R0.00%R0.00%R0.00%R0.00%R0.00%R
70ERROR:#DIV/0!0.00%0.00%0.00%S0.00%S0.00%S0.00%S0.00%S0.00%S0.00%S0.00%S0.00%S0.00%S0.00%S0.00%S0.00%S0.00%S0.00%S0.00%S0.00%S0.00%S0.00%S0.00%S0.00%S
80ERROR:#DIV/0!0.00%0.00%0.00%T0.00%T0.00%T0.00%T0.00%T0.00%T0.00%T0.00%T0.00%T0.00%T0.00%T0.00%T0.00%T0.00%T0.00%T0.00%T0.00%T0.00%T0.00%T0.00%T0.00%T
90ERROR:#DIV/0!0.00%0.00%0.00%U0.00%U0.00%U0.00%U0.00%U0.00%U0.00%U0.00%U0.00%U0.00%U0.00%U0.00%U0.00%U0.00%U0.00%U0.00%U0.00%U0.00%U0.00%U0.00%U0.00%U
100ERROR:#DIV/0!0.00%0.00%0.00%V0.00%V0.00%V0.00%V0.00%V0.00%V0.00%V0.00%V0.00%V0.00%V0.00%V0.00%V0.00%V0.00%V0.00%V0.00%V0.00%V0.00%V0.00%V0.00%V0.00%V
110ERROR:#DIV/0!0.00%0.00%0.00%W0.00%W0.00%W0.00%W0.00%W0.00%W0.00%W0.00%W0.00%W0.00%W0.00%W0.00%W0.00%W0.00%W0.00%W0.00%W0.00%W0.00%W0.00%W0.00%W0.00%W
120ERROR:#DIV/0!0.00%0.00%0.00%X0.00%X0.00%X0.00%X0.00%X0.00%X0.00%X0.00%X0.00%X0.00%X0.00%X0.00%X0.00%X0.00%X0.00%X0.00%X0.00%X0.00%X0.00%X0.00%X0.00%X
130ERROR:#DIV/0!0.00%0.00%0.00%Y0.00%Y0.00%Y0.00%Y0.00%Y0.00%Y0.00%Y0.00%Y0.00%Y0.00%Y0.00%Y0.00%Y0.00%Y0.00%Y0.00%Y0.00%Y0.00%Y0.00%Y0.00%Y0.00%Y0.00%Y
140ERROR:#DIV/0!0.00%0.00%0.00%Z0.00%Z0.00%Z0.00%Z0.00%Z0.00%Z0.00%Z0.00%Z0.00%Z0.00%Z0.00%Z0.00%Z0.00%Z0.00%Z0.00%Z0.00%Z0.00%Z0.00%Z0.00%Z0.00%Z0.00%Z
150ERROR:#DIV/0!0.00%0.00%0.00%AA0.00%AA0.00%AA0.00%AA0.00%AA0.00%AA0.00%AA0.00%AA0.00%AA0.00%AA0.00%AA0.00%AA0.00%AA0.00%AA0.00%AA0.00%AA0.00%AA0.00%AA0.00%AA0.00%AA0.00%AA
160ERROR:#DIV/0!0.00%0.00%0.00%AB0.00%AB0.00%AB0.00%AB0.00%AB0.00%AB0.00%AB0.00%AB0.00%AB0.00%AB0.00%AB0.00%AB0.00%AB0.00%AB0.00%AB0.00%AB0.00%AB0.00%AB0.00%AB0.00%AB0.00%AB
170ERROR:#DIV/0!0.00%0.00%0.00%AC0.00%AC0.00%AC0.00%AC0.00%AC0.00%AC0.00%AC0.00%AC0.00%AC0.00%AC0.00%AC0.00%AC0.00%AC0.00%AC0.00%AC0.00%AC0.00%AC0.00%AC0.00%AC0.00%AC0.00%AC
180ERROR:#DIV/0!0.00%0.00%0.00%AD0.00%AD0.00%AD0.00%AD0.00%AD0.00%AD0.00%AD0.00%AD0.00%AD0.00%AD0.00%AD0.00%AD0.00%AD0.00%AD0.00%AD0.00%AD0.00%AD0.00%AD0.00%AD0.00%AD0.00%AD
190ERROR:#DIV/0!0.00%0.00%0.00%AE0.00%AE0.00%AE0.00%AE0.00%AE0.00%AE0.00%AE0.00%AE0.00%AE0.00%AE0.00%AE0.00%AE0.00%AE0.00%AE0.00%AE0.00%AE0.00%AE0.00%AE0.00%AE0.00%AE0.00%AE
200ERROR:#DIV/0!0.00%0.00%0.00%AF0.00%AF0.00%AF0.00%AF0.00%AF0.00%AF0.00%AF0.00%AF0.00%AF0.00%AF0.00%AF0.00%AF0.00%AF0.00%AF0.00%AF0.00%AF0.00%AF0.00%AF0.00%AF0.00%AF0.00%AF
210ERROR:#DIV/0!0.00%0.00%0.00%AG0.00%AG0.00%AG0.00%AG0.00%AG0.00%AG0.00%AG0.00%AG0.00%AG0.00%AG0.00%AG0.00%AG0.00%AG0.00%AG0.00%AG0.00%AG0.00%AG0.00%AG0.00%AG0.00%AG0.00%AG
220ERROR:#DIV/0!0.00%0.00%0.00%AH0.00%AH0.00%AH0.00%AH0.00%AH0.00%AH0.00%AH0.00%AH0.00%AH0.00%AH0.00%AH0.00%AH0.00%AH0.00%AH0.00%AH0.00%AH0.00%AH0.00%AH0.00%AH0.00%AH0.00%AH
230ERROR:#DIV/0!0.00%0.00%0.00%AI0.00%AI0.00%AI0.00%AI0.00%AI0.00%AI0.00%AI0.00%AI0.00%AI0.00%AI0.00%AI0.00%AI0.00%AI0.00%AI0.00%AI0.00%AI0.00%AI0.00%AI0.00%AI0.00%AI0.00%AI
240ERROR:#DIV/0!0.00%0.00%0.00%AJ0.00%AJ0.00%AJ0.00%AJ0.00%AJ0.00%AJ0.00%AJ0.00%AJ0.00%AJ0.00%AJ0.00%AJ0.00%AJ0.00%AJ0.00%AJ0.00%AJ0.00%AJ0.00%AJ0.00%AJ0.00%AJ0.00%AJ0.00%AJ
250ERROR:#DIV/0!0.00%0.00%0.00%AK0.00%AK0.00%AK0.00%AK0.00%AK0.00%AK0.00%AK0.00%AK0.00%AK0.00%AK0.00%AK0.00%AK0.00%AK0.00%AK0.00%AK0.00%AK0.00%AK0.00%AK0.00%AK0.00%AK0.00%AK
260ERROR:#DIV/0!0.00%0.00%0.00%AL0.00%AL0.00%AL0.00%AL0.00%AL0.00%AL0.00%AL0.00%AL0.00%AL0.00%AL0.00%AL0.00%AL0.00%AL0.00%AL0.00%AL0.00%AL0.00%AL0.00%AL0.00%AL0.00%AL0.00%AL
270ERROR:#DIV/0!0.00%0.00%0.00%AM0.00%AM0.00%AM0.00%AM0.00%AM0.00%AM0.00%AM0.00%AM0.00%AM0.00%AM0.00%AM0.00%AM0.00%AM0.00%AM0.00%AM0.00%AM0.00%AM0.00%AM0.00%AM0.00%AM0.00%AM
280ERROR:#DIV/0!0.00%0.00%0.00%AN0.00%AN0.00%AN0.00%AN0.00%AN0.00%AN0.00%AN0.00%AN0.00%AN0.00%AN0.00%AN0.00%AN0.00%AN0.00%AN0.00%AN0.00%AN0.00%AN0.00%AN0.00%AN0.00%AN0.00%AN
290ERROR:#DIV/0!0.00%0.00%0.00%AO0.00%AO0.00%AO0.00%AO0.00%AO0.00%AO0.00%AO0.00%AO0.00%AO0.00%AO0.00%AO0.00%AO0.00%AO0.00%AO0.00%AO0.00%AO0.00%AO0.00%AO0.00%AO0.00%AO0.00%AO
300ERROR:#DIV/0!0.00%0.00%0.00%AP0.00%AP0.00%AP0.00%AP0.00%AP0.00%AP0.00%AP0.00%AP0.00%AP0.00%AP0.00%AP0.00%AP0.00%AP0.00%AP0.00%AP0.00%AP0.00%AP0.00%AP0.00%AP0.00%AP0.00%AP
310ERROR:#DIV/0!0.00%0.00%0.00%AQ0.00%AQ0.00%AQ0.00%AQ0.00%AQ0.00%AQ0.00%AQ0.00%AQ0.00%AQ0.00%AQ0.00%AQ0.00%AQ0.00%AQ0.00%AQ0.00%AQ0.00%AQ0.00%AQ0.00%AQ0.00%AQ0.00%AQ0.00%AQ
320ERROR:#DIV/0!0.00%0.00%0.00%AR0.00%AR0.00%AR0.00%AR0.00%AR0.00%AR0.00%AR0.00%AR0.00%AR0.00%AR0.00%AR0.00%AR0.00%AR0.00%AR0.00%AR0.00%AR0.00%AR0.00%AR0.00%AR0.00%AR0.00%AR
330ERROR:#DIV/0!0.00%0.00%0.00%AS0.00%AS0.00%AS0.00%AS0.00%AS0.00%AS0.00%AS0.00%AS0.00%AS0.00%AS0.00%AS0.00%AS0.00%AS0.00%AS0.00%AS0.00%AS0.00%AS0.00%AS0.00%AS0.00%AS0.00%AS
340ERROR:#DIV/0!0.00%0.00%0.00%AT0.00%AT0.00%AT0.00%AT0.00%AT0.00%AT0.00%AT0.00%AT0.00%AT0.00%AT0.00%AT0.00%AT0.00%AT0.00%AT0.00%AT0.00%AT0.00%AT0.00%AT0.00%AT0.00%AT0.00%AT
350ERROR:#DIV/0!0.00%0.00%0.00%AU0.00%AU0.00%AU0.00%AU0.00%AU0.00%AU0.00%AU0.00%AU0.00%AU0.00%AU0.00%AU0.00%AU0.00%AU0.00%AU0.00%AU0.00%AU0.00%AU0.00%AU0.00%AU0.00%AU0.00%AU
360ERROR:#DIV/0!0.00%0.00%0.00%
370ERROR:#DIV/0!0.00%0.00%0.00%
380ERROR:#DIV/0!0.00%0.00%0.00%
390ERROR:#DIV/0!0.00%0.00%0.00%
400ERROR:#DIV/0!0.00%0.00%0.00%
410ERROR:#DIV/0!0.00%0.00%0.00%
TOTALERROR:#DIV/0!0.00%0.00%0.00%
REMARKS
Scheduled0.00%Actual0.00%
At the Contracting Officer's discretion and according to the payments clause of the contract, the information provided on this form may be
used for computing progress payments.
PROGRESS OR COMPLETION CERTIFICATE
I hereby certify that the contractor has satisfactory completed the indicated percentage of the contract per contract specifications.
SUBMITTED BY OR FOR
CONTRACTOR
TYPE NAME AND TITLESIGNATUREDATE
BASE CIVIL ENGINEER
TYPE NAME AND TITLESIGNATUREDATE
REVIEWED BY OR CONTRACTING OFFICER
TYPE NAME AND TITLESIGNATUREDATE