Attachment C. Deluge Liquidated Damages Signed.pdf
PDF 298 KB Posted
- Attached to
- Replace Foam Fire Suppression System with Water Deluge System Federal contract opportunity
- Solicitation number
- FA309924R0008
About this file
This document is a Determination and Findings for the inclusion of FAR Clause 52.211-12, Liquidated Damages, in Solicitation Number FA309924R0008 for the replacement of the foam fire suppression system with a water deluge system in Building 50 at Laughlin AFB.
The key details are: This will be a firm-fixed-price construction contract. Timely performance is critical, and the government may reasonably expect to suffer damages if delivery or performance is delinquent. Liquidated damages have been calculated based on the costs of inspection and administration, and are considered fair and reasonable. The solicitation has a 245-calendar day period of performance, with two Notices to Proceed - 63 days for pre-construction submittals and 182 days for construction. The acquisition is a total small business set-aside with NAICS code 238220. The government anticipates awarding a firm-fixed-price contract.
View the file
Other files for this federal contract opportunity
Show all 29
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
DETERMINATION AND FINDINGS
TO
INCLUDE FAR CLAUSE 52.211-12
Solicitation Number: FA309924R0008 Solicitation Title: Replace Foam Fire Suppression System with Water Deluge System, B50 Date: 7 September 2021
FINDINGS:
1. This will be executed as a Firm-Fixed-Price Contract for construction work related to removal and replacement of the existing foam fire suppression system with a compliant Water Deluge system in building 50 on Laughlin AFB. The work is required in support of the 47th Civil Engineering Squadron.
2. The time of delivery or timely performance is so important that the Government may reasonably expect to suffer damage if the delivery or performance is delinquent, and the extent or amount of such damage would be difficult or impossible to estimate accurately or prove.
3. The contractor has complete control over the pace of work.
4. Use of liquidated damages in construction contracts is a normal trade practice; therefore, use of administrative liquidated damages on this project will not increase pricing on the contract nor affect competition.
5. The costs of inspection and administration are included in the liquidated damages computations attached for the requiring activity, base contracting, and base legal office, are the minimum necessary to adequately survey the contractor's performance and do not constitute a penalty.
DETERMINATION:
The costs of liquidated damages have been determined as follows:
Liquidated Damages Itemization
MXDP 22-1013 Replace Foam Fire System with Water Deluge System, B50
0.5 hr per day @ $ 54.23 /hr $ 27.12
1.0 hr per day @ $ 41.84 /hr $ 41.84
1.0 hr per day @ $ 43.10 /hr $ 43.10
1.0 hr per day @ $ 43.10 /hr $ 43.10
2.0 hr per day @ $ 29.44 /hr $ 58.88
2.0 hr per day @ $ 21.44 /hr $ 42.88
2.0 hr per day @ $ 29.26 /hr $ 58.52
Base Civil Engineer
Chief, Engineering Flight
Chief, Project Management Element
Chief, Portfolio Optimization Element
Senior Project Manager
Construction Inspector
Contract Officer Admin
Contract Specialist Admin 2.0 hr per day @ $ 29.26 /hr $ 58.52
Total Per Day $ 373.96
6. The amount annotated above is the standard charge for liquidated damages per calendar day of delay. The amount noted includes only applicable contractual administration charges. Should equipment, facility charges or any other type of charges other than administration be included, the amount of liquidated damages will be increased to cover those costs to the Government and shall be indicated in the individual delivery order.
7. Based on the calculated charges to be assessed as liquidated damages, the above charges are considered fair and reasonable as to actual damages the government would incur in the event the subject contract is not completed in the allotted time set for the project as the completed date.
KATHERINE H. WELLS, SSgt, USAF Contracting Officer
| 2024-08-22T11:24:23-0500 | |
| WELLS.KATHERINE.HOPE.1160922784 |