Performance Work Statement - PR16088790 -FINAL VERSION.pdf

PDF 726 KB Posted

Attached to
INL Wet scrubber & recirculation water system for Incinerator Project
Solicitation number
PR16088790
Issued by

About this file

This is a Performance Work Statement (PWS) for fabrication and installation services of a Wet Scrubber and Recirculation Water System for an industrial incinerator at OIJ Ciudad Judicial in San José, Costa Rica.

The Contractor is responsible for fabricating and installing a complete wet scrubber gas treatment system, water recirculation and sedimentation tank system, chemical preparation and dosing system (excluding owner-furnished chemical dosing pump), pH/temperature/level monitoring system with alarm integration, removal and disposal of the existing baghouse system, and integration with owner-furnished recircitation pumps and pump house/enclosure. The project is a Firm-Fixed-Price construction contract procured under FAR Part 36 using negotiated procedures and best-value tradeoff source selection per FAR 15.101-1. The solicitation number is PR16129583, with a proposal due date of August 3, 2026, and anticipated award date of August 10, 2026. The period of performance is 60 calendar days from Notice to Proceed. Contracting Officer is Taylor Smith (SmithTS4@state.gov); nominated COR is Mariela Ruiz (RuizM@state.gov). The contract is structured in two CLINs: CLIN 0001 covers fabrication and supply services; CLIN 0002 covers installation, testing, commissioning, and integration services. Progress payments are tied to verified milestone completion at 40%, 80%, and 100% fabrication completion, with final 10% payment withheld until final acceptance. Evaluation factors in descending order of importance are: Technical Expertise and Approach, Key Personnel Qualifications, Past Performance, Resources, and Price. The Contractor must comply with all Costa Rican codes and international standards (ASME, AWS, ASTM, ACI, NACE), provide comprehensive documentation in English and Spanish, maintain a one-year warranty, and supply specified spare parts. Deliverables include as-built drawings, Operations and Maintenance manuals, testing reports, spare parts inventory, and training certification.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Performance Work Statement

(PWS)

Fabrication and Installation

Services

For

Wet Scrubber and Recirculation

Water System

Incinerator Project

OIJ Ciudad Judicial, San José, Costa Rica

Table of Contents

1 SECTION A — SOLICITATION / CONTRACT FORM

2 SECTION B — SUPPLIES OR SERVICES AND PRICES/COSTS

3 SECTION C — DESCRIPTION / SPECIFICATIONS / PERFORMANCE WORK

STATEMENT (PWS)

3.1 C.1 PURPOSE

3.2 C.2 BACKGROUND

3.3 C.3 PERFORMANCE OBJECTIVE AND APPROACH

3.3.1 Fabrication and Installation Overview

3.3.2 Design Responsibility

3.3.3 Government Review Role

3.3.4 Single Point of Responsibility

3.4 C.4 PERFORMANCE STANDARDS AND QUALITY REQUIREMENTS

3.4.1 C.4.1 Wet Scrubber System – Performance Requirements

3.4.2 C.4.2 Water Recirculation and Sedimentation Tank System – Performance

Requirements

3.4.3 C.4.3 Chemical Preparation and Dosing System – Performance Requirements .. 16

3.4.4 C.4.4 pH, Temperature, and Level Monitoring System – Performance

Requirements

3.4.5 C.4.5 Removal and Disposal of Existing Baghouse System – Performance

Requirements

3.4.6 C.4.6 Spare Parts – Performance Requirements

3.5 C.5 PERFORMANCE OUTCOMES AND DELIVERABLES

3.5.1 Site Assessment and Verification

3.5.2 Wet Scrubber and Recirculation System

3.5.3 Chemical Preparation and Monitoring Systems

3.5.4 Baghouse Removal

3.5.5 Integration with Owner-Furnished Equipment

3.5.6 Quality Assurance and Testing

3.5.7 Documentation and Training

3.5.8 Spare Parts

3.5.9 Project Completion

3.6 C.6 APPLICABLE REGULATIONS AND STANDARDS

3.6.1 Costa Rica Codes:

3.6.2 International Codes (where applicable):

3.6.3 Occupational Safety:

3.6.4 Code Compliance Responsibility:

3.6.5 Performance Requirement:

3.7 C.7 NON-PERSONAL SERVICES

3.8 C.8 COORDINATION WITH SITE OPERATIONS

3.9 C.9 MATERIALS AND CORROSION PROTECTION – PERFORMANCE

REQUIREMENTS

3.10 C.10 WORK EXECUTION PERFORMANCE STANDARDS

3.11 C.11 CONTRACTOR EQUIPMENT AND TOOLS – PERFORMANCE

REQUIREMENTS

3.12 C.12 OPERATIONAL CONTINUITY – PERFORMANCE REQUIREMENTS

3.13 C.13 SAFETY AND SECURITY

3.14 C.14 ENVIRONMENTAL PERFORMANCE REQUIREMENTS

3.15 C.15 PERSONNEL REQUIREMENTS

3.16 C.16 INSURANCE

3.17 C.17 QUALITY ASSURANCE / QUALITY CONTROL – PERFORMANCE

REQUIREMENTS

3.18 C.18 DELIVERABLES – PERFORMANCE REQUIREMENTS

3.19 C.19 SCHEDULE PERFORMANCE REQUIREMENTS

3.20 C.20 FINAL ACCEPTANCE CRITERIA – PERFORMANCE VERIFICATION

3.21 C.21 WARRANTY

3.22 C.22 KEY PERSONNEL AND QUALIFICATIONS

3.23 C.23 MEETINGS AND REPORTING

3.24 C.24 CHANGE MANAGEMENT

3.25 C.25 PROPOSAL REQUIREMENTS AND PAYMENT TERMS

3.26 C.26 MATERIALS, SOURCE/NATIONALITY, AND DOMESTIC PREFERENCE 47

3.27 C.27 PLACE AND PERIOD OF PERFORMANCE

3.28 C.28 GOVERNMENT-FURNISHED INFORMATION (GFI)

3.29 C.29 CONTRACTOR SUBMITTALS AND APPROVALS

3.30 C.30 FABRICATION RESPONSIBILITY AND COMPLETENESS CLAUSE

3.31 C.31 CLOSE-OUT

4 SECTION D — PACKAGING AND MARKING

5 SECTION E — INSPECTION AND ACCEPTANCE

6 SECTION F — DELIVERIES OR PERFORMANCE

7 SECTION G — CONTRACT ADMINISTRATION DATA

8 SECTION H — SPECIAL REQUIREMENTS

9 SECTION I — CONTRACT CLAUSES

10 SECTION J — LIST OF ATTACHMENTS

11 SECTION K — REPRESENTATIONS, CERTIFICATIONS & OTHER STATEMENTS . 66

12 SECTION L — INSTRUCTIONS, CONDITIONS, AND NOTICES TO OFFERORS . 67

13 SECTION M — EVALUATION FACTORS FOR AWARD

14 DEFINITIONS

1 SECTION A — SOLICITATION / CONTRACT FORM

Solicitation No.: PR16129583

Title: Fabrication and Installation Services – Wet Scrubber and Recirculation Water System, Incinerator Project, OIJ Ciudad Judicial, San José, Costa Rica

Type: Request for Proposals (RFP) – Firm-Fixed-Price Construction Contract (FAR Part 36), utilizing negotiated procedures authorized under FAR 36.103(b) and conducted in accordance with FAR Part 15. Award will be made using the price-technical tradeoff source selection process defined in FAR 15.101-1 (see Section M).

Issuing Office: INL Costa Rica, U.S. Embassy – San José, Costa Rica

Contracting Officer (CO): Taylor Smith | SmithTS4@state.gov

COR (Nominated): Mariela Ruiz | RuizM@state.gov

Construction Engineer Advisor: Roberto Rivera | RiveraR1@state.gov

Proposal Due: August 3, 2026

Anticipated Award: August 10, 2026

Notice: This acquisition is procured as a Firm-Fixed-Price construction contract for the fabrication, supply, installation, testing, commissioning, and integration of a Wet

Scrubber and Recirculation Water System for an industrial incinerator. Due to the technical complexity of the custom fabrication scope requires evaluation of technical approach, key personnel qualifications, and past performance in addition to price — negotiated procedures under FAR 36.103(b) and FAR Part 15 will be used, with award made on a best-value tradeoff basis per FAR 15.101-1. The Contractor assumes full fabrication and installation responsibility in accordance with the approved engineering design documents.

mailto:SmithTS4@state.gov mailto:RuizM@state.gov mailto:RiveraR1@state.gov

2 SECTION B — SUPPLIES OR SERVICES AND PRICES/COSTS

CLIN Description Type Price

Fabrication and Supply Services – Wet Scrubber, Recirculation Tank, Chemical Preparation and Dosing System, pH/Temperature/Level

Monitoring System, supporting structural steelwork, piping, instrumentation, controls, ancillaries, and spare parts (as identified in

Spare Parts List). Excludes recirculation pumps and pump house/enclosure, which are furnished under a separate INL contract.

FFP $_______

Installation, Testing, Commissioning, and Integration Services – including removal and disposal of existing baghouse system, integration with existing incinerator system and owner-furnished recirculation pumps/pump house, as-built drawings, O&M manuals, and operational narrative

FFP $_______

Cost Summary

Item Description Amount

Subtotal Costs Sum of CLINs 0001–0003 $_______

Overhead/Profit ____% of Subtotal (to be proposed by offeror) $_______

Subtotal (Before VAT) $_______

Value Added Tax (VAT) As applicable per Costa Rica regulations $_______

TOTAL PROJECT COST $_______

CLIN 0001 – Detailed Cost Breakdown

Sub-Category Amount

Engineering and Project Management $_______

Fabrication of equipment $_______

Materials, components, instrumentation, consumables $_______

Chemical preparation and dosing system $_______ pH monitoring and control system $_______

CLIN 0001 SUBTOTAL $_______

CLIN 0002 – Detailed Cost Breakdown

Sub-Category Amount

Engineering and Project Management $_______

Spare parts $_______

Shipping $_______

Installation and on-site assembly $_______

Commissioning and start-up $_______

Integration with existing system $_______

Controls and alarm integration $_______

Existing baghouse removal and disposal $_______

Technical documentation and O&M manuals $_______

CLIN 0002 SUBTOTAL $_______

Notes:

1. Period of Performance: 60 calendar days after NTP for CLINs 0001–0002.

2. Payment Terms: Progress payments per FAR 52.232-5 and FAR 52.232-27 (Section I), tied to verified milestone completion.

3. CLIN Breakdown Rationale:

o CLIN 0001: Covers all fabrication and supply services, including the Wet

Scrubber, Water Recirculation and Sedimentation Tank System, chemical preparation and dosing system (with mechanical agitator), pH/temperature/level monitoring system, supporting structural steelwork, piping, instrumentation, controls, ancillaries, and spare parts as identified in the Spare Parts List. The recirculation pumps and pump house/enclosure (separate from the recirculation tank) shall be furnished by others under a separate INL contract and are excluded from the Contractor's fabrication scope. The chemical dosing pump will also be furnished by others under a separate INL contract and is excluded from the Contractor's supply scope.

o CLIN 0002: Covers on-site installation, integration with the existing incinerator system, coordination and integration with owner-furnished recirculation pumps and pump house (furnished under separate INL contract), removal and disposal of the existing baghouse system, testing, commissioning, as-built drawings, O&M manuals, and operational narrative.

4. Invoicing: Invoices shall reference specific CLIN numbers and sub-categories, and demonstrate progress/completion for each line item. Invoices must be submitted no later than the 15th calendar day of the following month.

5. Firm-Fixed-Price Terms:

o No additional sums payable due to escalation in costs.

o No adjustments for currency exchange rate fluctuations.

o All risks associated with cost increases borne by Contractor.

o Price includes all fabrication, supply, installation, testing, commissioning, integration, documentation, and spare parts within the defined scope.

6. VAT: Calculated and applied in accordance with Costa Rica tax regulations. The

Contractor is responsible for all tax compliance and reporting requirements.

3 SECTION C — DESCRIPTION / SPECIFICATIONS /

PERFORMANCE WORK STATEMENT (PWS)

3.1 C.1 PURPOSE

The purpose of this contract is to provide all fabrication, supply, installation, testing, commissioning, integration, quality control, safety oversight, and supervision necessary to deliver a fully operational Wet Scrubber and Recirculation Water System for the industrial incinerator located at OIJ Ciudad Judicial, San José, Costa Rica. The Contractor shall deliver a safe, code-compliant, fully commissioned system with complete documentation and minimal operational disruption.

3.2 C.2 BACKGROUND

The U.S. Department of State (DoS), through the Bureau of International Narcotics and Law

Enforcement Affairs (INL), assists Costa Rican efforts to effectively address transnational crime through provision of equipment, training, expertise, and law enforcement cooperation.

The existing industrial incinerator (PENNRAM Model C-750, Series 220008, capacity 350 kg/h, manufactured September 2020) at OIJ Ciudad Judicial processes special waste, including psychoactive substances such as marijuana and cocaine. The combustion process generates gases at approximately 940°C containing particulates and acid compounds (HCl, HF, SO₂, NOx) that require treatment prior to emission to comply with applicable environmental regulations.

The existing gas treatment system — comprising an in-line gas scrubber and baghouse filter — is no longer adequate due to deterioration and increased gas flow rates versus the original theoretical design. INL, in cooperation with the Government of Costa Rica, is providing technical assistance for the design, supply, and installation of a replacement Wet Scrubber and

Recirculation Water System to ensure continued environmental compliance and operational effectiveness.

3.3 C.3 PERFORMANCE OBJECTIVE AND APPROACH

This Performance Work Statement is performance-based: the Government describes the required results and measurable performance standards, while allowing the Contractor to propose methods that achieve those outcomes efficiently and safely.

The Contractor shall provide all labor, materials, equipment, fabrication, installation, QA/QC, safety, and supervision necessary to complete the Wet Scrubber and Recirculation Water System at OIJ Ciudad Judicial, delivering a safe, code-compliant, fully commissioned system with complete documentation.

Note: The Government has established performance objectives and quality standards in this PWS. Section C.4 provides minimum performance specifications that contractors must meet or exceed. Contractors are encouraged to propose innovative solutions and methods to achieve these outcomes.

3.3.1 Fabrication and Installation Overview

Under this contract, the Contractor is solely responsible for:

• Conducting all necessary site investigations and assessments;

• Reviewing and verifying all approved engineering design documents prior to fabrication;

• Fabricating all equipment in full conformance with the approved design;

• Performing on-site installation, integration, testing, and commissioning;

• Coordinating with the separate INL contractor supplying recirculation pumps and pump house/enclosure, and providing all necessary interfaces, piping connections, instrumentation interfaces, controls integration, testing, and commissioning activities to achieve a fully operational system;

• Removing and disposing of the existing baghouse system;

• Delivering fully commissioned, operational systems with complete documentation.

The Government provides performance criteria — the required outcomes, functional standards, and quality thresholds — rather than prescriptive fabrication specifications. The Contractor has flexibility to propose solutions that meet or exceed these criteria, subject to INL approval.

3.3.2 Design Responsibility

The engineering design documents have been developed by INCINER8 LATINOAMÉRICA

S.A. and are provided as Government-Furnished Information (GFI). The Contractor assumes full professional responsibility for reviewing the design documents, identifying any discrepancies or constructability concerns prior to fabrication, and fabricating and installing all equipment in strict conformance with the approved design. Fabrication errors, omissions, or non-compliant installations shall be corrected by the Contractor at no additional cost to the Government.

3.3.3 Government Review Role

The Government's review of shop drawings and submittals is for conformance with performance criteria and contract requirements only. Government review and approval does not:

• Transfer fabrication or installation responsibility to the Government;

• Constitute acceptance of the design as structurally or technically adequate;

• Relieve the Contractor of responsibility for errors, omissions, or code non-compliance.

3.3.4 Single Point of Responsibility

The Contractor is the single point of responsibility for all fabrication, supply, installation, testing, commissioning, and integration activities within the defined scope. The Contractor shall manage and coordinate all disciplines, subcontractors, and activities to deliver a complete, integrated, and fully functional system.

The Contractor's role will consist of providing services to include, but not limited to, the fabrication, supply, installation, testing, and commissioning required for the Wet Scrubber and

Recirculation System, to include as-built drawings, Bill of Materials, schedules, operation and maintenance manuals, operational narrative, integration of the new equipment with the existing system, and itemized pricing for each deliverable in accordance with Section B.

The recirculation pumps and pump house/enclosure (separate from the recirculation tank) will be furnished under a separate INL contract by INL. The Contractor shall coordinate with the designated supplier and shall provide all necessary interfaces, piping connections, instrumentation interfaces, controls integration, testing, and commissioning activities required to integrate the supplied equipment into the Wet Scrubber and Recirculation

System.

The Contractor shall provide the necessary controls, instrumentation, and system integration to generate an alarm whenever the new Wet Scrubber and Recirculation System is not operating while the existing system remains operational. The alarm shall be integrated into the existing control system, providing operators with a clear indication of the system's status to prevent operating conditions in which the existing system is running without the required support of the new equipment.

The Contractor shall provide all equipment, instrumentation, controls, supports, and ancillary components required for operation of the chemical preparation system, including the mechanical agitator installed on the chemical preparation tank. The chemical dosing pump will be furnished by others under a separate INL contract and is excluded from the Contractor's supply scope. The Contractor shall provide all necessary tank nozzles, supports, piping connections, isolation valves, instrumentation interfaces, electrical provisions, and physical accommodations required for installation and integration of the owner-furnished chemical dosing pump.

The Contractor will be responsible for storage of tools and equipment required for the performance of this contract. Neither INL nor OIJ will be accountable for any loss of equipment during the period of performance. The Contractor shall bring temporary portable restrooms for their personnel and provide weekly cleaning (Friday afternoon).

The scope of this project consolidates the following into a single procurement and execution effort:

• Fabrication and supply of a centrifugal Wet Scrubber system;

• Fabrication and supply of a Water Recirculation and Sedimentation Tank System;

• Chemical preparation and dosing system for alkaline reagent (excluding owner-furnished chemical dosing pump);

• pH, temperature, and level monitoring and alarm system;

• Removal and disposal of the existing baghouse system;

• Integration with the existing incinerator gas treatment system and owner-furnished recirculation pumps/pump house; and

• Spare parts supply, commissioning, and documentation.

3.4 C.4 PERFORMANCE STANDARDS AND QUALITY REQUIREMENTS

PERFORMANCE-BASED APPROACH: This section establishes the required performance outcomes, quality standards, and acceptance criteria. Contractors shall propose methods, materials, and approaches that meet or exceed these standards.

3.4.1 C.4.1 Wet Scrubber System – Performance Requirements

Performance Objective: Fabricate and install a centrifugal Wet Scrubber capable of neutralizing and removing acid gases (HCl, HF, SO₂, NOx) and particulates from incinerator combustion gases, in full compliance with applicable environmental regulations and the approved engineering design documents.

Minimum Required Outcomes:

• Wet Scrubber shall be fabricated in full conformance with the approved engineering design documents (INCINER8 LATAM Final Design, May 2026, and Annexes, June

2026)

• Combustion gas flow rate handled: 4.3 m³/s at 218.84°C (design conditions)

• Acid gas neutralization via alkaline solution contact (calcium hydroxide or sodium hydroxide as specified)

• 12 spray nozzles (NCS1003 type or approved equivalent), full-cone pattern, 90° spray angle, 10 psi operating pressure, 0.22 in diameter, total water flow 1.2 L/s (18.4 gal/min),

5.8 L/min per nozzle

• Mist eliminator (cortaneblina) installed in the upper section of the scrubber, Ø 1.40 m,

0.20 m height, effective area ≈ 1.54 m², vane-chevron type, stainless steel 316/316L;

removable in sections for maintenance; supported on perimetral ring; no permanent sealing to scrubber body

• Central spray tube (tubo de rociado): 4,271 mm in length

• Disk core breaker (disco rompenúcleo) installed at the base of the spray tube

• Three (3) manholes/access hatches for inspection, cleaning, and nozzle maintenance

• Thermocouples installed at designated locations per design drawings

• Tangential gas inlet duct: 42.7 cm diameter

• Gas outlet: 42.7 cm diameter; reduction from 28" to 18" diameter at scrubber outlet as per design

• All internal and external surfaces in contact with corrosive gases or liquids fabricated in stainless steel (minimum 6 mm thickness for scrubber body; ducting minimum 5 mm;

flanges minimum 1/4")

• Structural support system (floor-mounted metal structure with anchored rings, 3/8" bolts) designed and installed per approved drawings

• System connected to existing horizontal duct downstream of the second spray nozzle and upstream of the induced draft fan, as shown in the design drawings

• The existing spray nozzle system in the horizontal duct section shall be maintained and integrated as part of the overall system; the wet phase shall operate together with the centrifugal scrubber downstream of the relief chimney

• All equipment furnished under this contract shall be designed, fabricated, and arranged to provide safe and practical access for inspection, routine maintenance, calibration, cleaning, repair, removal, and replacement of components throughout the equipment service life

Quality Standards:

• Scrubber body: stainless steel 304 or 316 (ideally 316 for corrosive zones), minimum 6 mm wall thickness

• Welding: TIG (Tungsten Inert Gas) process for all stainless steel components; AWS D1.1 or equivalent; all welds leak-free, full penetration where required

• Nozzle material: metal (carbide or equivalent for high-temperature/abrasion zones at inlet); NCS1003 type or equivalent for spray system

• Alignment tolerances: per approved design drawings

• All equipment: designed and arranged for safe and practical access for inspection, maintenance, calibration, cleaning, repair, and replacement

Acceptance Criteria:

• COR and Fabrication Oversight Consultant approval of shop drawings prior to fabrication

• Material certificates for all stainless steel components provided

• Welder qualification records and welding procedure specifications provided

• Leak testing of all connections and welds completed

• Functional testing of spray nozzles, mist eliminator, and thermocouples completed

• As-built drawings submitted and approved

3.4.2 C.4.2 Water Recirculation and Sedimentation Tank System – Performance Requirements

Performance Objective: Fabricate and install a Water Recirculation and Sedimentation Tank

System capable of continuously supplying treated water to the Wet Scrubber, removing particulates and sludge, and maintaining water quality within operating parameters.

IMPORTANT SCOPE CLARIFICATION: The recirculation pumps and pump house/enclosure (separate from the recirculation tank) shall be furnished by others under a separate INL contract and are excluded from the Contractor's fabrication scope. The Contractor shall provide all necessary tank nozzles, piping tie-ins, instrumentation interfaces, controls integration, testing support, and commissioning activities necessary to achieve a fully operational system upon integration with the owner-furnished pumps and pump house.

Minimum Required Outcomes:

• Tank capacity: 8.7 m³; dimensions: Height 1.5 m × Width 2.0 m × Length 3.0 m;

residence time: 1.0 hour

• Tank constructed in reinforced concrete masonry: concrete block 50 kg/cm², 20×20×40 cm, grouted cells with 4,000 psi concrete; double pin/cell at 20 cm, #4 60K rebar;

compression ring #4 @0.20 m

• Interior waterproofing: SIKA Monotop 101 or approved equivalent epoxy coating;

sanitary curve 2" radius at all interior horizontal and vertical edges

• Exterior finish: cementitious render + oil-based satin paint

• Top slab: 10 cm reinforced concrete with manholes (50 cm × 2 m) with corrugated galvanized steel covers

• Sedimentation chamber and clarification chamber separated by internal curtain/baffle walls

• Drain valve and drainage provisions for sludge removal; drainage to exterior sand trap/desarenadora

• All process piping: stainless steel 304 or 316 (2" supply and return lines); cuello de ganso/siphon-type overflow return

• All required tank nozzles, supports, piping connections, isolation valves, instrumentation interfaces, electrical provisions, and physical accommodations for integration of owner-furnished recirculation pumps and pump house (furnished under separate INL contract)

• Agitators in recirculation tank: optional, depending on neutralizing agent selected; to be confirmed during design review

• All piping supports: floor-mounted metal structure with unistrut rail and 1/2" threaded rod, or ceiling-mounted as applicable per design

Quality Standards:

• Concrete: minimum f'c = 4,000 psi; ACI standards

• Reinforcing steel: ASTM A615 Grade 60

• Interior coating: epoxy-based, fully waterproof, chemically resistant to alkaline solutions

• Stainless steel piping: 304 or 316, welded with TIG process

• All valves: 2" gate or ball valves, stainless steel or compatible material

Acceptance Criteria:

• COR approval of shop drawings prior to fabrication/construction

• Leak testing of tank and all piping connections

• Functional testing of valves and drainage systems

• Integration with owner-furnished pumps and pump house verified

• As-built drawings submitted and approved

3.4.3 C.4.3 Chemical Preparation and Dosing System – Performance Requirements

Performance Objective: Fabricate and install a chemical preparation and storage system for the alkaline reagent (calcium hydroxide or sodium hydroxide) used in the gas neutralization process, including all interfaces for the owner-furnished chemical dosing pump.

IMPORTANT SCOPE CLARIFICATION: The chemical dosing pump will be furnished by others under a separate INL contract and is excluded from the

Contractor's supply scope. The Contractor shall provide all necessary tank nozzles, supports, piping connections, isolation valves, instrumentation interfaces, electrical provisions, and physical accommodations required for installation and integration of the owner-furnished chemical dosing pump.

Minimum Required Outcomes:

• Chemical preparation tank with mechanical agitator/mixer sized to provide adequate mixing of alkaline reagent and prevent solids settling during preparation and storage operations

• All required supports, mounting arrangements, electrical connection points, controls, and ancillary components for proper agitator operation

• All tank nozzles, piping connections, isolation valves, instrumentation interfaces, electrical provisions, and physical accommodations for integration of owner-furnished chemical dosing pump

• Reagent dosing: manually initiated by operator based on pH measurements and operating requirements

• System designed to accommodate calcium hydroxide (3–8% concentration) or sodium hydroxide (1–8% concentration) as selected by INL; recommended concentration per design: 1% for either reagent

• All wetted components: stainless steel or chemically resistant material compatible with alkaline solutions

Quality Standards:

• Agitator: sized for adequate mixing; motor and drive protected against corrosive environment

• All connections: leak-free; isolation valves provided at all interfaces

• Electrical provisions: compliant with applicable codes

Acceptance Criteria:

• Functional testing of agitator and all connections

• Integration with owner-furnished dosing pump verified

• As-built drawings submitted and approved

3.4.4 C.4.4 pH, Temperature, and Level Monitoring System – Performance Requirements

Performance Objective: Supply and commission a continuous monitoring system for recirculation water pH, temperature, and liquid level, integrated with the existing control system, with operator alarms for low pH and low liquid level conditions.

Minimum Required Outcomes:

• Continuous monitoring of recirculation water pH, temperature, and liquid level; all measurements displayed to operators through the control system

• Configurable alarm: low pH (below established operating limit) → operator manually initiates chemical dosing using the owner-furnished dosing pump until required pH range is restored

• Configurable alarm: low liquid level (below established operating limit) → operator manually adds make-up water through the provided water supply valve until required operating level is restored

• Low-level protective functions to prevent equipment damage and unsafe operation

• All measurements, alarms, and status indications integrated into the existing control system and available to operators for monitoring, alarming, trending, and operational awareness

• Alarm integrated into existing control system to notify operators whenever the new Wet

Scrubber and Recirculation System is not operating while the existing system remains operational

• All existing control, monitoring, alarm, status, and interlock signals associated with equipment being removed, replaced, or modified shall be reviewed and addressed;

existing signals shall be terminated, reconfigured, bypassed, or integrated as necessary to ensure continued proper operation of the existing control system and operator control panel without loss of required functionality

Quality Standards:

• pH sensor, pH transmitter, level sensor, differential pressure sensor, flow transmitter (if applicable), and thermocouples: industrial-grade, compatible with alkaline/corrosive environment

• All instrumentation: calibrated prior to commissioning; calibration certificates provided

• Control integration: fully functional with existing operator control panel; no loss of required existing functionality

• Functional testing of all monitoring and alarm functions

• Integration with existing control system verified

• Calibration certificates provided for all instruments

• As-built drawings and control system documentation submitted and approved

3.4.5 C.4.5 Removal and Disposal of Existing Baghouse System – Performance Requirements

Performance Objective: Safely dismantle, remove, and dispose of the existing baghouse system and all associated equipment, supports, accessories, and components, and adjust existing auxiliary systems as necessary to ensure proper integration of the new Wet Scrubber system.

Minimum Required Outcomes:

• Complete removal of existing baghouse system, including all equipment, supports, accessories, and components necessary to facilitate installation of the new Wet Scrubber and Recirculation System

• Proper handling, transportation, and disposal of all removed materials in accordance with applicable environmental regulations and local requirements

• Relocation, modification, reconnection, or adjustment of any existing auxiliary systems, utilities, controls, supports, or interfaces necessary for proper integration of the new equipment following removal of the existing baghouse

• Review and address all control, monitoring, alarm, status, and interlock signals associated with equipment being removed, replaced, or modified; existing signals terminated, reconfigured, bypassed, or integrated as necessary

• Continued proper operation of existing control system and operator control panel without loss of required functionality

Quality Standards:

• Zero environmental violations during removal and disposal

• All waste disposal documented with licensed waste haulers

• No damage to existing facilities, structures, or systems beyond authorized removal scope

Acceptance Criteria:

• COR verification of complete removal and site cleanliness

• Waste disposal documentation provided

• Existing control system functionality verified after removal

3.4.6 C.4.6 Spare Parts – Performance Requirements

Performance Objective: Supply a minimum set of spare parts to support ongoing operation and maintenance of the Wet Scrubber and Recirculation Water System.

Minimum Required Outcomes (per Spare Parts List, Attachment J-6):

Category Spare Part Recommended

Quantity Remarks

Spray System

Spray nozzles, gaskets, and related components

At least 30% of installed nozzles and one complete gasket set

Nozzle specifications shall comply with drawings and process diagrams provided by the designer pH Measurement and Monitoring

System pH Sensor 1 Critical consumable item pH Measurement and Monitoring

System pH Transmitter 1 Critical spare part

Instrumentation Level Sensor 1 Critical spare part

Instrumentation Differential Pressure

Sensor 1 Critical spare part

Instrumentation Flow Transmitter 1 (if applicable)

Mechanical

Integration Flexible Coupling 1 Critical spare part

Valves Repair Kit 1 per critical valve Maintenance spare

Valves Solenoid Valves 2 per model Critical spare part

Chemical Dosing

System

Basic spares: Seal

Kit, diaphragm, check valves

1 per pump For NaOH or other chemical dosing pumps

Category Spare Part Recommended

Quantity Remarks

Electrical and

Control Fuses Complete set Consumable item

Electrical and

Control Relays Complete set Critical spare part

Electrical and

Control Contactors Complete set Critical spare part

Electrical and

Control PLC Power Supply 1 Strategic spare part

Electrical and

Control

PLC I/O Module spare parts 1 Strategic spare part

Recirculation Tank Level Sensor spare parts 1 Critical spare part

Recirculation Tank Drain Valve 1 Critical spare part

Monitoring System Thermocouples 2 Instrumentation spare

Monitoring System Temperature

Transmitters 1 Instrumentation spare

Acceptance Criteria:

• All spare parts delivered, inventoried, and accepted by COR prior to final acceptance

• Spare parts list reconciled with installed equipment

3.5 C.5 PERFORMANCE OUTCOMES AND DELIVERABLES

The Contractor shall achieve the following performance outcomes:

3.5.1 Site Assessment and Verification

• Outcome: Verified site conditions, dimensions, elevations, and interfaces prior to fabrication and installation. All discrepancies between design documents and actual site conditions identified and reported to INL in writing prior to fabrication.

• Deliverable: Written site survey report; comprehensive site survey and concept layout with any proposed options.

3.5.2 Wet Scrubber and Recirculation System

• Outcome: Fully fabricated, installed, and commissioned Wet Scrubber and Recirculation

Water System, operational and compliant with all performance standards in Section C.4 and the approved engineering design documents.

• Deliverable: Commissioned system with as-built drawings, material certificates, welder qualification records, and photographic documentation.

3.5.3 Chemical Preparation and Monitoring Systems

• Outcome: Fully functional chemical preparation system (with mechanical agitator) and pH/temperature/level monitoring system, integrated with the existing control system and owner-furnished chemical dosing pump.

• Deliverable: Completed systems with as-built drawings, manufacturer data sheets, and commissioning reports.

3.5.4 Baghouse Removal

• Outcome: Existing baghouse system fully removed and disposed of; existing control system fully functional.

• Deliverable: Waste disposal documentation; COR verification of removal.

3.5.5 Integration with Owner-Furnished Equipment

• Outcome: New Wet Scrubber and Recirculation System fully integrated with owner-furnished recirculation pumps, pump house/enclosure, and chemical dosing pump (all furnished under separate INL contracts); all interfaces, piping connections, instrumentation interfaces, and controls integration complete and operational.

• Deliverable: Commissioning and integration verification report.

3.5.6 Quality Assurance and Testing

• Outcome: All systems tested, certified, and operating within specified parameters.

• Deliverable: Complete testing documentation and commissioning/performance verification reports.

3.5.7 Documentation and Training

• Outcome: Facility personnel equipped to operate and maintain all installed systems.

• Deliverable: As-built drawings, O&M manuals (English and Spanish), maintenance checklists (English and Spanish), training certificates.

3.5.8 Spare Parts

• Outcome: All required spare parts delivered and accepted.

• Deliverable: Spare parts inventory list signed by COR.

3.5.9 Project Completion

• Outcome: Fully functional Wet Scrubber and Recirculation Water System meeting all performance requirements.

• Deliverable: Final acceptance by COR with all punch-list items resolved.

3.6 C.6 APPLICABLE REGULATIONS AND STANDARDS

The Contractor shall comply with, at minimum:

3.6.1 Costa Rica Codes:

• All applicable Costa Rican construction, mechanical, and environmental codes and regulations

• General Safety in Construction Projects (national regulation)

• CCSS (Caja Costarricense del Seguro Social) registration for all workers

• Work Risk Insurance Policy (Póliza de Riesgos del Trabajo)

• Civil Liability Insurance Policy

• OIJ Safety and Occupational Health guidelines

• All applicable permitting and professional engineering requirements

3.6.2 International Codes (where applicable):

• ASME – pressure vessel and piping codes

• AWS – welding procedures and qualifications

• AISI / ASTM – material specifications

• ACI – for tank concrete works

• NACE International – corrosion protection standards

• Underwriters Laboratories (UL)

• Manufacturer's Operations and Maintenance (O&M) manuals

• National Electrical Code (NEC) or locally applicable electrical codes

3.6.3 Occupational Safety:

• Costa Rican labor and safety regulations

• INL and U.S. Embassy safety policies

• Environmental protection requirements applicable to industrial and chemical works

3.6.4 Code Compliance Responsibility:

In the event of conflicts between standards, the more stringent requirement shall govern, subject to INL approval. If the Contractor identifies any irregularities in the design documents or any non-compliance with applicable regulations, it shall promptly notify the COR. Failure to do so shall preclude the Contractor from later claiming that work was constructed in accordance with the design despite known non-compliance.

3.6.5 Performance Requirement:

The Contractor shall demonstrate compliance with all applicable codes through required permits and inspections, testing and certification documentation, and material certificates.

3.7 C.7 NON-PERSONAL SERVICES

This contract is for non-personal services. Contractor personnel performing work under this contract shall not be considered Government employees for any purpose. The Contractor shall be fully responsible for the management, supervision, direction, and control of its employees and subcontractors. Government personnel shall not exercise direct supervision or control over

Contractor staff. The Contractor is solely responsible for compliance with Costa Rican labor laws, wage requirements, social security contributions, insurance, and any other statutory obligations applicable to its workforce.

3.8 C.8 COORDINATION WITH SITE OPERATIONS

The OIJ Ciudad Judicial facility is an active operational facility. The Contractor shall coordinate all fabrication, installation, and commissioning activities with designated OIJ authorities and INL representatives. Work sequencing, access routes, material storage areas, and temporary facilities shall be approved prior to mobilization. Construction activities shall be planned to minimize interference with daily operations and security protocols.

Normal workdays are Monday through Friday, except Costa Rican National Holidays. Core hours of work are from 0800 to 1600 daily. Extended hours or weekend work require COR approval at least 48 hours in advance.

The Contractor shall provide temporary portable restrooms for their personnel and provide weekly cleaning (Friday afternoon). The Contractor is responsible for storage of all tools and equipment; neither INL nor OIJ will be accountable for any loss of equipment during the period of performance.

Simultaneously with the installation activities under this contract, a separate INL contractor will be performing civil, structural, electrical, hydraulic, pneumatic, and other infrastructure-related work required to support the new equipment. The Contractor shall coordinate its activities with other contractors as necessary to facilitate project execution and successful integration of the equipment. Such coordination shall not relieve the Contractor of its responsibility to complete the work within the scope of this contract.

3.9 C.9 MATERIALS AND CORROSION PROTECTION – PERFORMANCE

REQUIREMENTS

Performance Objective: All materials and equipment shall be new, code-compliant, and capable of meeting the performance standards specified in Section C.4 for the intended service life in a high-temperature, high-humidity, chemically corrosive industrial environment.

General Material Requirements:

• All materials shall be new and free of defects

• Materials shall carry manufacturer's commercial warranty

• Materials shall comply with applicable codes and standards

• Materials shall be suitable for high-temperature, corrosive gas, and alkaline liquid environments

• Contractor shall provide material data sheets demonstrating compliance

Performance-Based Material Standards by System:

A. Wet Scrubber Body and Ducting:

• Performance Requirement: Stainless steel 304 or 316 (ideally 316 for corrosive zones);

minimum 6 mm wall thickness for scrubber body; ducting minimum 5 mm; flanges minimum 1/4"; TIG welding for all stainless steel joints

• Contractor Flexibility: Propose specific products meeting or exceeding performance standards

B. High-Temperature Zones (Zone of Impact/Shock):

• Performance Requirement: Nickel-chromium alloys (Inconel 625 or Hastelloy C-276) where direct, prolonged exposure to temperatures approaching 1,000°C; water cooling jackets required if direct prolonged exposure

• Contractor Flexibility: Propose specific products meeting or exceeding performance standards

C. Spray Nozzles:

• Performance Requirement: Silicon carbide (SiC) or equivalent for inlet zone nozzles;

metal nozzles (NCS1003 type or equivalent, distributed by Acodinsa or approved equivalent) for spray system; 0.22 in diameter; 10 psi operating pressure; full-cone pattern, 90° spray angle; nozzle diameter sized to minimize clogging risk; maintenance access provided for periodic nozzle inspection and replacement (recommended every 15 days or as experience dictates)

• Contractor Flexibility: Propose specific products meeting or exceeding performance standards; consult nozzle distributor for final nozzle selection and confirm exact number and type required to handle 18.4 gal/min at 1.53 gal/min per nozzle

D. Mist Eliminator:

• Performance Requirement: Stainless steel 316/316L; vane-chevron type; Ø 1.40 m; 0.20 m height; removable in sections; supported on perimetral ring; no permanent sealing to scrubber body; wash nozzles provided upstream and/or downstream where solids, salts, or sludge are present

• Contractor Flexibility: Propose specific products meeting or exceeding performance standards; performance to be validated by provider

E. Recirculation Tank:

• Performance Requirement: Reinforced concrete masonry (50 kg/cm² block, 4,000 psi grout); interior epoxy waterproofing (SIKA Monotop 101 or equivalent); stainless steel piping (304 or 316); epoxy-coated or stainless steel fittings and valves; epoxy coating recommended for tank permeabilization given the nature of the water

• Contractor Flexibility: Propose specific products meeting or exceeding performance standards

F. Piping and Supports:

• Performance Requirement: Stainless steel 304 or 316 for all process piping in contact with corrosive gases or alkaline liquids; unistrut rail supports with 1/2" threaded rod or equivalent; floor-mounted metal structure with anchored rings; PVC 180 psi 1" for water supply network (non-process)

• Contractor Flexibility: Propose specific products meeting or exceeding performance standards

Material Approval Process:

• Contractor shall submit material data sheets demonstrating compliance with performance requirements

• Substitutions from reference specifications must demonstrate equal or superior performance

• COR approval required before procurement

• Contractor bears risk of non-compliant material selection

3.10 C.10 WORK EXECUTION PERFORMANCE STANDARDS

Performance Objective: Execute all fabrication, installation, and commissioning work in a professional, safe, and coordinated manner that minimizes disruption to existing OIJ facility operations and delivers quality results.

Minimum Required Outcomes:

A. Pre-Fabrication Phase:

• Site investigation completed and all discrepancies reported to INL prior to fabrication

• Shop drawings approved by INL and Fabrication Oversight Consultant prior to commencement of any fabrication

• All disciplines coordinated to produce an integrated, constructable design

• Submittals made in a timely manner to avoid fabrication or installation delays

• Contractor shall perform a detailed review of all design drawings, specifications, narratives, schedules, and associated project documents prior to start of fabrication; any discrepancies, omissions, ambiguities, conflicts, dimensional inconsistencies, constructability concerns, or apparent errors shall be submitted in writing to the COR and

Fabrication Oversight Consultant for clarification prior to proceeding

B. Coordination and Scheduling:

• All work activities coordinated with INL Costa Rica and OIJ authorities with zero unauthorized disruptions

• Work schedule maintained with ≥ 90% on-time milestone achievement

• Minimum 5 business days advance notice for all access requirements

• Coordination with separate INL contractor performing civil, structural, electrical, hydraulic, and pneumatic infrastructure works, and with separate INL contractor supplying recirculation pumps and pump house

C. Fabrication and Installation Quality:

• All fabrication executed in strict conformance with the approved design documents

• All installations meet or exceed manufacturer specifications and code requirements

• All disturbed surfaces restored to original condition or better

• Sufficient access clearances provided around all equipment requiring periodic maintenance

D. Site Management:

• Work area maintained in clean, safe condition at all times

• Existing facilities and equipment protected from damage (zero damage incidents)

• Debris removed daily; final cleanup within 24 hours of completion

• No discharge of pollutants, chemicals, or waste into the environment

E. Environmental Management:

• Dust, noise, and waste managed per best practices

• All waste disposed legally with documentation

• Zero environmental violations or citations

Acceptance Criteria:

• COR verification of coordination and schedule compliance

• Visual and functional inspection of all installations

• Testing verification of all systems

• Site cleanliness and restoration verified

3.11 C.11 CONTRACTOR EQUIPMENT AND TOOLS – PERFORMANCE

REQUIREMENTS

Performance Objective: The Contractor shall provide all necessary equipment and tools to execute the fabrication, installation, and commissioning work safely, efficiently, and in compliance with manufacturer specifications and code requirements.

Minimum Equipment Capabilities:

• Site investigation: survey equipment, dimensional measurement tools

• Fabrication: TIG welding equipment and certified welders; metal cutting, forming, and finishing equipment; stainless steel fabrication tools; welding facilities with appropriate certifications

• Installation: rigging and lifting equipment; pipe fitting and connection tools; torque wrenches for bolted connections; epoxy injection equipment for anchors

• Electrical and instrumentation: continuity testers, voltage testers, calibration equipment

• Testing: pressure testing equipment, flow measurement equipment, pH/temperature/level calibration equipment

Quality Standards:

• All testing equipment calibrated within past 12 months with certificates provided

• Equipment maintained in good working condition

• Equipment operated by trained, qualified personnel only

• Fabrication facility must have the capacity and equipment to perform TIG welding of stainless steel large-diameter piping and vessels

Acceptance Criteria:

• Calibration certificates provided for all testing equipment

• Equipment demonstrated to be appropriate and functional

• No damage to existing facilities from equipment use

3.12 C.12 OPERATIONAL CONTINUITY – PERFORMANCE

REQUIREMENTS

Performance Objective: Execute all work with minimal disruption to existing OIJ facility operations, coordinating all outages and providing necessary temporary services.

Minimum Required Outcomes:

• Phasing plan that minimizes operational downtime

• All outages coordinated and approved minimum 48 hours in advance

• Temporary services provided as needed to maintain critical operations

• Zero unauthorized disruptions to existing operations

• Coordination with separate INL contractor performing infrastructure works and with separate INL contractor supplying recirculation pumps and pump house

Acceptance Criteria:

• COR approval of phasing plan

• All outages executed within approved windows

• Zero operational disruptions outside approved windows

3.13 C.13 SAFETY AND SECURITY

Safety Performance Objective: Achieve zero lost-time accidents, zero safety violations, and

100% compliance with all safety regulations throughout the project.

Safety Performance Metrics:

• Lost-time accident rate: 0

• Recordable incidents: 0

• Safety violations or citations: 0

• PPE compliance: 100%

• Daily safety briefing completion: 100%

The Contractor shall submit a Site-Specific Safety Plan addressing:

Safety Requirements:

• Hazard analysis for each task

• PPE requirements for all personnel

• Emergency response procedures

• Electrical safety procedures

• Hot work procedures (welding, cutting)

• Confined space procedures (if applicable)

• Chemical handling procedures (alkaline reagents: calcium hydroxide, sodium hydroxide)

• Material handling and storage

• High-temperature work procedures

Personal Protective Equipment (PPE): The Contractor shall provide all necessary PPE for its employees, including:

• Safety goggles and face shields

• Electrical safety gloves

• Chemical-resistant gloves

• Safety footwear

• Dust masks / respirators

• Appropriate clothing such as coveralls

• Hard hats

• Other PPE required to perform tasks effectively and safely

Site Access and Security:

• Compliance with OIJ access, badging, and escort requirements

• The Contractor shall provide full name, identification number, and vehicle license plate number (if applicable) for all personnel requiring access at least five (5) days prior to access

• No personnel may access the site without prior vetting and authorization by OIJ

• OIJ reserves the right to deny site access to any individual

• All personnel must have legal status to work in Costa Rica and must not possess or carry illegal drugs or firearms

3.14 C.14 ENVIRONMENTAL PERFORMANCE REQUIREMENTS

Performance Objective: Achieve zero environmental violations and 100% compliant waste disposal throughout the project. Protect the environment at all times, particularly during removal and disposal of the existing baghouse system.

Minimum Required Outcomes:

• All waste properly segregated, documented, and disposed per Costa Rican regulations

• 100% waste removal within 24 hours of generation

• Zero environmental spills or releases

• No discharge of pollutants, chemicals, or waste into drainage systems or the environment

• Work site maintained clean with proper debris management

Quality Standards:

• Waste disposal documentation for 100% of waste generated

• Licensed waste haulers used for all disposal

• Recycling implemented where feasible

• Immediate containment and reporting of any chemical spills

Acceptance Criteria:

• Complete waste disposal documentation provided

• Zero environmental violations or citations

• COR verification of site cleanliness

• All disturbed surfaces restored

3.15 C.15 PERSONNEL REQUIREMENTS

A. Work Hours

The Contractor's personnel shall…