part_3 RFP B178 HDSS 20200413.pdf
PDF 149 KB Posted
- Attached to
- Building 178 High Density Storage Stacker Federal contract opportunity
- Solicitation number
- N40085-20-B-2540
About this file
This document outlines the requirements for a federal contract to design, procure, and install high density storage systems in Building 178 at Portsmouth Naval Shipyard. The contractor will be responsible for engineering and installing two narrow aisle forklift trucks, forklift chargers, in-floor guide wire systems, and rack systems. Fire suppression and alarm systems must be modified to accommodate the storage systems. Electrical utilities and concrete flooring will also require modifications. The existing stacker unit and office area in the north section of the building will be removed. Additionally, the contractor must provide pricing to design, procure and install one additional narrow aisle forklift truck and one standard forklift truck. The solicitation was issued by the Naval Facilities Engineering Command of the Department of the Navy.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| N40085N40085-20-B-2540 Amendment 0003.pdf | ||
| part_3 RFP B178 HDSS REV 20200717.pdf | ||
| N40085N40085-20-B-2540 Amendment 0002.pdf | ||
| part_1 REV 20200717.pdf | ||
| OF_1419 B178 Stacker.pdf | ||
| 178-362 strutural design loads.pdf | ||
| B178 stacker RFI Set 3.pdf | ||
| B178 High Density Storage System DB BID RFI RTW.pdf | ||
| N40085-20-B-2540 Amendment 0001.pdf | ||
| ASI 002 Fence Gate Change (RFI HDSS 2a).pdf | ||
| 178-420-utility trench detail.pdf | ||
| SEC 10 22 14 INT CHAIN LINK FENCE GATES RFI 1.pdf | ||
| part_6 RFP ATTB EQS B178 HDSS 20200430.pdf | ||
| part_6 RFP ATTA DWG B178 HDSS 20200519.pdf | ||
| part_5 RFP B178 HDSS 20200413.pdf | ||
| part_4 RFP B178 HDSS 20200413.pdf | ||
| part_1 RFP B178 HDSS 20200413.pdf | ||
| Master Scope of Work HDSS 20200506.pdf | ||
| N40085-20-B-2540 Solicitation_B178 Storage Stacker PNSY.pdf | ||
| part_2 RFP B178 HDSS 20200413.pdf | ||
| part_6 RFP B178 HDSS 20200413.pdf |
Show all 21
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
High Density Storage System PNS-B178 Work Order Number Portsmouth Naval Shipyard, Kittery, Maine
SMALL PROJECT TEMPLATE - PART 3 STATEMENT OF WORK / PROJECT PROGRAM - Page 1
Part 3 Statement of Work / Project Program
Table of Contents
CHAPTERS
1. PROJECT DESCRIPTION
2. PROJECT OBJECTIVES
3. SITE ANALYSIS
4. BUILDING REQUIREMENT
5. ROOM REQUIREMENTS
6. ENGINEERING SYSTEMS REQUIREMENTS
A10 Foundations A20 Basement Construction NOT USED B10 Superstructure B20 Exterior Closure NOT USED B30 Roofing NOT USED C10 Interior Construction C20 Stairs NOT USED C30 Interior Finishes D10 Conveying Systems NOT USED D20 Plumbing NOT USED
D30 HVAC NOT USED
D40 Fire Protection Systems D50 Electrical Power and Lighting E10 Equipment E20 Furnishings NOT USED F10 Special Construction NOT USED F20 Selective Building Demolition G10 Site Preparations NOT USED G20 Site Improvements NOT USED G30 Site Mechanical Utilities NOT USED G40 Site Electrical Utilities NOT USED
1.0 PROJECT DESCRIPTION
BUILDING 178 BAY 2, North End, And South End – Prepared Design/Engineering Documents, Procure and Install high-density storage system equipment (Narrow Aisle Rack and Lift Truck Retrieval Systems to optimize storage in these areas). From the existing building systems provide utilities for power, fire suppression, fire alram, and any required building structural modifications for the equipment to meet the UFC, pertaining codes, and equipment manufactures requirements. Existing concrete floor and trenches will need to be repaired and/or modified to meet the flatness requirements of the storage system lift trucks.
Remove the existing stacker and supporting utilities on the north end of Bay 2 to the extent needed to support the installation of the proposed equipment and storage systems.
SMALL PROJECT TEMPLATE - PART 3 STATEMENT OF WORK / PROJECT PROGRAM - Page 2
2.0 PROJECT OBJECTIVES
2.2 SUSTAINABLE DESIGN
Design and construct project per sustainability requirements identified in Section 01 33 29.05 20, Sustainability Reporting for Design-Build. Additional specific sustainability requirements are found in this document.
2.3 STORMWATER MANAGMENT - LOW IMPACT DEVELOPMENT
(LID) – NA
2.4 CYBERSECURITY
All control systems (including systems separate from an energy management control system) must be designed, acquired, and executed in accordance with DoD Instruction 8500.01, DoD Instruction 8510.01, and as required by individual Facilities Engineering Command (FEC) or installation implementation policy.
Incorporate ICS Security Controls located in NIST 800-82, Appendix G, Table G-1.
3.0 SITE ANALYSIS - NA
4.0 BUILDING REQUIREMENTS - NA
5.0 ROOM REQUIREMENTS - NA
6.0 ENGINEERING SYSTEMS REQUIREMENTS (ESR)
A10 Foundations A20 Basement Construction B10 Superstructure B20 Exterior Closure B30 Roofing C10 Interior Construction C20 Stairs C30 Interior Finishes D10 Conveying Systems D20 Plumbing
D30 HVAC
D40 Fire Protection Systems D50 Electrical Power and Lighting E10 Equipment E20 Furnishings F10 Special Construction F20 Selective Building Demo G10 Site Preparations G20 Site Improvements G30 Site Civil/Mechanical Utilities
SMALL PROJECT TEMPLATE - PART 3 STATEMENT OF WORK / PROJECT PROGRAM - Page 3
G40 Site Electrical Utilities
A10 FOUNDATION
Existing soil, rock, and floor conditions are generally described by the included record drawings, SW‐60‐189, and 178‐10‐323 (See Part 6 of the RFP). Note, the actual field conditions could vary from these records. It is the contractor’s responsibility to confirm any conditions that are relevant to the contractor’s design.
A20 BASEMENT CONSTRUCTION - NA
B10 SUPERSTRUCTURE
The structural design of the stacking storage system including the system itself and its connection to the building must meet the provisions of IBC 2018, ASCE 7‐16 as modified by the DoD Building Code, UFC 1‐200‐01. In addition, the stacking storage system must meet the design requirements of
ANSI/RMI MH16.1. Where conflicts occur between these documents, the order of precedence between these documents is a follows: UFC 1‐200‐01 will govern, followed by IBC 2018, followed by
ASCE 7‐16, followed by ANSI/RMI MH16.1.
The Government has no objection to the contractor connecting the stacking storage system into the existing building columns or anchoring the stacking storage system into the existing floor (or a combination thereof) provided that the contractor’s Designer Of Record can show that such a connection will not cause the building to have unsatisfactory performance during wind or seismic events, and provided the connections do not prevent the building or other existing components within the building from functioning as they did prior to the stacker installation.
B20 EXTERIOR ENCLOSURE - NA
B30 ROOFING - NA
C10 INTERIOR CONSTRUCTION - NA
C30 INTERIOR FINISHES
C3020 FLOOR FINISHES
Existing slab is to be the finished floor. This floor must be leveled as necessary to meet the fork truck manufacturer flatness requirements. Some information regarding existing floor flatness has been provided as an aid in bidding, however it is the contractor’s responsibility to perform any needed survey’s, measurements or remediation to ensure the floor flatness meets the chosen fork truck manufacturer’s flatness requirements. These flatness requirements must be met in all areas of fork truck travel as defined on the contract drawings.
Floor Repair: Based on a review of existing conditions, it is anticipated that some localized
SMALL PROJECT TEMPLATE - PART 3 STATEMENT OF WORK / PROJECT PROGRAM - Page 4 concrete floor repair will be required in order to fix spalling or cracked floor. Contractor to anticipate the need to provide 250 sq. ft. of localized floor repair which must be done in a way that meets the flatness requirements discussed above when applicable. For areas outside of the defined area of fork truck travel the repairs must be made such they are flush with the existing floor surface using industry practices for level concrete surfaces. Floor repairs must be made in a way so as to prevent tripping hazards from occurring as a result of the floor repairs.
C3040 INTERIOR COATINGS AND SPECIAL FINISHES - NA
D10 CONVEYING SYSTEMS - NA
D20 PLUMBING - NA
D30 HVAC - NA
D40 FIRE PROTECTION SYSTEMS
D4010 FIRE ALARM AND DETECTION SYSTEMS
Existing fire alarm is a Simplex 4100 addressable fire alarm system.
Provide audio/visual Notification Appliances and circuit wiring as required based on ABA consideration for hearing impaired individuals and equipment layout.
Provide initiation circuits from ASRS system as required per equipment manufacturer’s criteria.
Provide auxiliary control circuits as required by manufacturer from the FACP. (Ex., Automatic equipment shutdown or equipment recall.)
D4020 FIRE SUPPRESSION WATER SUPPLY AND EQUIPMENT
Provide fire protection design and engineering services in accordance with UFC 3-600-01 (Fire
Protection Engineering for Facilities), and UFC 3-601-02 (Operation and Maintenance:
Inspection, Testing, and Maintenance of Fire Protection Systems), as well as all other applicable National Fire Protection Association codes/standards not covered by these references. Provide Sprinkler Protection for the Bldg 178 High Rack Stacker in accordance with NFPA 13 for rack storage for Class IV; unencapsulated commodities stored over 25 feet. Modification of the ceiling level sprinklers will be necessary to comply with the storage requirements of NFPA 13. Locate system risers within weather-protected spaces. Provide hydraulic calculations for the hydraulically most remote area; calculations must account for the flow and pressure demands at each discharge node leading to the system demand at point of connection to available water supply. Fire and life safety requirements must be considered and addressed for facility design.
Confirmation of the fire protection scope must be obtained from the NAVFAC Fire Protection Engineer prior to submitting a fee proposal.
SMALL PROJECT TEMPLATE - PART 3 STATEMENT OF WORK / PROJECT PROGRAM - Page 5
a) Projects that require specifications in Division 21 and/or Division 28 fire alarm/mass notification systems of the UFGS and projects defined by UFC 3-600-01 as a “Major Project” must have a qualified fire protection engineer (QFPE) responsible for the associated design services. The QFPE is responsible for preparing the fire protection design analysis, calculations, specifications, and drawings, including Life Safety Plans, Code Compliance Site Plan, Code Summary Sheet, etc., to complete the fire protection design. A letter of certification must be submitted by the QFPE with the Final Design submission attesting that the fire protection features discussed in the fire protection design analysis have been completely and accurately incorporated into the project’s design for every architect-engineer discipline.
1) For Navy projects, a qualified FPE is defined as a registered professional engineer (P.E.)
who has passed the fire protection engineering written examination administered by the National Council of Examiners for Engineering and Surveys (NCEES).
b) Conduct water flow tests in accordance with NFPA 291 to determine water supply availability and to analyze adequacy of water supply in meeting fire flow and/or fire water demands stipulated in UFC 3-600-01.
d) Fire Detection, Alarm and/or Mass Notification System Plans: Provide performance criteria and depiction of obstructions, elevation changes, ceiling height, ceiling pattern, and type for the construction contractor to layout the detection and initiating devices and notification appliances. Do not layout initiating devices and/or notification appliances on design drawings. Provide sequence of operation and control matrix for system operation
e) Existing Bldg 178 Fire Pump: 2000 GPM, 125 psi, Maximum Pressure 134 psig, 1780 RPM, Size 10 X 8 MH; S/N FP CO 124499, imp diameter 16.500”, Maximum suction 116 psig, Rated BHP 200, Maximum BHP 228.1, 289.0 TDH, counter-clockwise rotation, Suction 125 # flange Discharge -250 # flange
Electric Motor: WEG, M/N 200180P3GFP445TS, S/N 11587751, 460 volts, 230 amps, 1780 RPM, 3 phase, 60 HZ, 1.15 SF, 200 HP, 150 kw (Made in Brazil) 27MA1131019782250, soft start, UL listed 1.15SF, Frame-445TS
Jockey Pump; Patterson Model T51G03364636, 10 GPM, 130 psi, 3450 RPM with 3.00 HP, 3 phase, 60 cycle, 460 volt
Fire Pump installed in 2015
f) Stacker Configuration:
See Attached drawings
g) The Contractor shall provide Record Drawings in accordance with Specification Section 01 01 78 00.00 22.
D4040 SPRINKLERS
SMALL PROJECT TEMPLATE - PART 3 STATEMENT OF WORK / PROJECT PROGRAM - Page 6
Provide wet pipe automatic sprinkler protection for complete coverage throughout the proposed High Density Storage System Equipment.
D4090 OTHER FIRE PROTECTION SYSTEMS
Provide portable fire extinguishers and cabinets as required.
D50 ELECTRICAL
The electrical design must comply with the design criteria specified in UFC 3-501-01, Electrical Engineering, and its referenced documents.
D5010 ELECTRICAL SERVICE & DISTRIBUTION
Power source is 480V, 3Ø, 60 Hz, 3-Wire + Gnd. solidly grounded WYE. Please note that 277 volts is not allowed (neutral prohibited). The electrical source shall originate from LP4M2 in the BLDG 178 Electrical Room. In addition, general lighting, outlet and other appliance circuits shall originate in sub-panel board RP2M2.
Provide an insulated equipment grounding conductor in all raceways for systems operating at greater than 50 volts.
D5020 LIGHTING & BRANCH WIRING
Existing lighting in the high bay area shall be utilized except as modified to ensure adequate illumination around the ASRS per UFC 3-530-01.
Provide lighting and general purpose receptacles throughout all spaces as required from manufacturer recommendations.
D5030 COMMUNICATIONS & SECURITY
Telecommunications Systems
Not Used
Local Area Network (Dedicated).
Not Used
Public Address and Intercommunications Systems
Not Used.
Television Systems
Not Used.
Security Systems
SMALL PROJECT TEMPLATE - PART 3 STATEMENT OF WORK / PROJECT PROGRAM - Page 7
Not Used.
D5090 OTHER ELECTRICAL SERVICES
Provide transient Surge Protective Devices (SPDs) in panel board RP2M2.
Provide additional feeders/branch circuits to serve HVAC loads as required. Source power from
LP4M2/RP2M2.
E10 EQUIPMENT
E1010 COMMERCIAL EQUIPMENT
All specialty equipment will be installed by qualified installers regularly engaged in installing the specialty equipment.
The design and documentation of the equipment will be funded as part of the construction contract. The general contractor must be responsible for coordinating equipment design requirements with the end user, providing equipment specifications, and procurement and installation of equipment. The construction contractor is responsible for the installation of equipment requiring a hard connection (fire protection, hardwire, venting, etc.) to the building and any other modifications to the building to ensure the equipment is installed to specification.
E20 FURNISHINGS - NA
F10 SPECIAL CONSTRUCTION - NA
F20 SELECTIVE BUILDING DEMOLITION
Remove the existing stacker unit and office area in the north section of bay 2 in Building 178.
G10 SITE PREPARATION
NOT USED
G20 SITE IMPROVEMENTS
NOT USED
G30 SITE CIVIL/MECHANICAL UTILITIES
NOT USED
G40 SITE ELECTRICAL UTILITIES - NA
File details come from the government source that posted it. Updated .